Joshua Mcmahan
- Listed as
- attorney, authorized agent-others, engineer
- Firm
- Glumac Engineers
- Based in
- San Francisco
- On San Francisco permits
- Jun 2000 to May 2026
83 permits since 2000 (engineer on 81 permits, attorney on 1 permit, authorized agent-others on 1 permit): 50 completed, 4 in progress, 20 never finaled, 9 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 18, 2026 | In progress filed May 2026, not yet issued | 2 Harrison St | B N Builders Inc | floors 3,4,5: revision to permit 202512302985. added employee cafeteria with no prep qnd mk storage on 5/f. made various minor design changes throughout. add 3 phone booths on 3/f. mep included.Details
floors 3,4,5: revision to permit 202512302985. added employee cafeteria with no prep qnd mk storage on 5/f. made various minor design changes throughout. add 3 phone booths on 3/f. mep included. | |
| Dec 11, 2025 | In progress issued Sep 2026 | 345 Spear St | Devcon Construction | 1/fl- ti of commerical kitchen at kills plaza. work includes construction of non bearing parititons, finishes, doors, frames and hardwareDetails
1/fl- ti of commerical kitchen at kills plaza. work includes construction of non bearing parititons, finishes, doors, frames and hardware | $240,000 |
| Sep 11, 2025 | In progress issued Oct 2025 | 4 Embarcadero Center | Skyline Construction | 13/f: mep. new ducts, heating cooling, lighting, power and plumbing. ref permit 202508112754.Details
13/f: mep. new ducts, heating cooling, lighting, power and plumbing. ref permit 202508112754. | $1,200,000 |
| Jun 16, 2025 | Completed final sign-off Jan 2026 | 300 Clay St | Matrix Hg Inc | add (3) overhead electric heaters in an existing outdoor dining area for an existing restaurant.Details
add (3) overhead electric heaters in an existing outdoor dining area for an existing restaurant. | $36,789 |
| Jan 2, 2024 | Completed final sign-off Jun 2024 | 345 Spear St | Bcci Construction Company | 7th fl electrical to replace existing light fixtures and revise/add power outletsDetails
7th fl electrical to replace existing light fixtures and revise/add power outlets | $20,000 |
| Dec 22, 2023 | In progress issued Feb 2024 | 1201 Bryant St | Skyline Construction | 3rd floor: installations of racks associated mep system and required structural anchorages in the hil lab space. roof-install vrf and package roof toop units.Details
3rd floor: installations of racks associated mep system and required structural anchorages in the hil lab space. roof-install vrf and package roof toop units. | $250,000 |
| Sep 8, 2023 | Completed final sign-off Jul 2024 | 345 Spear St | Bcci Construction Company | 4th fl: mep deferred 202211287247. revise hvac & associated ductwork configeration & layoutDetails
4th fl: mep deferred 202211287247. revise hvac & associated ductwork configeration & layout | |
| Aug 24, 2023 | Completed final sign-off Jan 2024 | 2 Harrison St | Novo Construction Inc | 5th fl: mechanical & electrical work on 5th fl for t.i.. ref arch pa# 202308144301.Details
5th fl: mechanical & electrical work on 5th fl for t.i.. ref arch pa# 202308144301. | $25,000 |
| Aug 24, 2023 | Completed final sign-off Feb 2024 | 2 Harrison St | Novo Construction Inc | 4th fl: mechanical & electrical work on 4th fl for t.i.. ref arch pa# 202308144314.Details
4th fl: mechanical & electrical work on 4th fl for t.i.. ref arch pa# 202308144314. | $25,000 |
| Aug 24, 2023 | Completed final sign-off Jan 2024 | 2 Harrison St | Novo Construction Inc | 2nd fl: mechanical & electrical work on 2nd fl for t.i.. ref arch pa# 202308144326.Details
2nd fl: mechanical & electrical work on 2nd fl for t.i.. ref arch pa# 202308144326. | $30,000 |
| Apr 11, 2023 | Completed final sign-off Jul 2023 | 1 Market St | Paganini Electric Corp(See Signatories) | 39th flr - furnish and install 2 fire life safety 2-way communication call stations. ref 201605258242.Details
39th flr - furnish and install 2 fire life safety 2-way communication call stations. ref 201605258242. | $23,000 |
| Feb 2, 2023 | Never finaled issued Feb 2023, no final | 1 Market St | Paganini Electric Corp(See Signatories) | add 2 way communication call station on the 17th flDetails
add 2 way communication call station on the 17th fl | $22,500 |
| Aug 25, 2022 | Completed final sign-off Apr 2024 | 188 The Embarcadero | Novo Construction Inc | deferred mep for pa 202207279366Details
deferred mep for pa 202207279366 | $400,000 |
| Aug 23, 2022 | Completed final sign-off Mar 2023 | 188 The Embarcadero | Novo Construction Inc | 7/f: deferred mep for bpa#202207067840Details
7/f: deferred mep for bpa#202207067840 | $400,000 |
| Dec 10, 2021 | Completed final sign-off Aug 2022 | 1 Market St | Gci, Inc | 10/f: interior t.i.: selective demo and construction of non-structural partitions, doors and sidelights, ceilings, lighting, power, millwork and finishes. no change in occupancy, use or area.Details
10/f: interior t.i.: selective demo and construction of non-structural partitions, doors and sidelights, ceilings, lighting, power, millwork and finishes. no change in occupancy, use or area. | $966,899 |
| Aug 12, 2021 | Never finaled issued Jan 2022, no final | 199 Fremont St | Skyline Construction | flr 8,9,11,12,14-18: revision to pa 202102255357 to add bike storage at basement level 1, replace toilets on 8,9,11,12,15. remove previously approved relocation of toilet on 8,9,11,12, and 14-18.Details
flr 8,9,11,12,14-18: revision to pa 202102255357 to add bike storage at basement level 1, replace toilets on 8,9,11,12,15. remove previously approved relocation of toilet on 8,9,11,12, and 14-18. | $20,000 |
| Jun 15, 2021 | Completed final sign-off May 2022 | 250 Clay St | Bcci Construction Company | ground floor, electrical only: new panel to serve loads in the storage, new lighting and controls, and recepticles for bike charging. ref bpa 202106102134Details
ground floor, electrical only: new panel to serve loads in the storage, new lighting and controls, and recepticles for bike charging. ref bpa 202106102134 | $10,000 |
| Jan 22, 2021 | Never finaled issued Feb 2021, no final | 1 Market St | Paganini Electric Corp(See Signatories) | 18/19th floors: addition of 4 new two-way communication call stations. 2 per floor at freight & main elevator lobbies. connect stations to (e) backbones. ref t.i. pa 201912190043 & 201912190040.Details
18/19th floors: addition of 4 new two-way communication call stations. 2 per floor at freight & main elevator lobbies. connect stations to (e) backbones. ref t.i. pa 201912190043 & 201912190040. | $40,000 |
| Sep 26, 2020 | Completed final sign-off Mar 2021 | 211 Main St | Dome Construction Corp | 16/f: t.i.: non-structural partitions, millwork, finishes, lighting & associated mep. ada upgrades to restrooms. maher n/a.Details
16/f: t.i.: non-structural partitions, millwork, finishes, lighting & associated mep. ada upgrades to restrooms. maher n/a. | $2,597,000 |
| Sep 26, 2020 | Expired or cancelled withdrawn Oct 2021 | 800 Market St | 3/f: t.i: non-structural partitions, flooring, finisehs, fixturse. memorialize cua 2019-014033 to change from m to b occupancy.Details
3/f: t.i: non-structural partitions, flooring, finisehs, fixturse. memorialize cua 2019-014033 to change from m to b occupancy. | $556,768 | |
| Jul 6, 2020 | Completed final sign-off Jun 2021 | 945 Bryant St | Field Construction Inc. | 1/f: demo of (e) partitions & associated power/data floor finishes, ceiling, lighting, construction of (n) partions doors, power & tele/data, lighting, millwork & finishes, all work to occur on the 1st floor of a 3-story bldg. tenant suite is currently vacant. mep, life safety & sprinkler deferred.Details
1/f: demo of (e) partitions & associated power/data floor finishes, ceiling, lighting, construction of (n) partions doors, power & tele/data, lighting, millwork & finishes, all work to occur on the 1st floor of a 3-story bldg. tenant suite is currently vacant. mep, life safety & sprinkler deferred. | $1,500,000 |
| Mar 9, 2020 | Expired or cancelled cancelled Nov 2024 | 340 Bryant St | interior ti of 2nd & 4th. non-structural ti to include, but not limited to partitions, flooring, ceilings, furnishings & finishes. no change to other floors in building or (e) egress path to street. no food/beverage or third party catering to be provided by employerDetails
interior ti of 2nd & 4th. non-structural ti to include, but not limited to partitions, flooring, ceilings, furnishings & finishes. no change to other floors in building or (e) egress path to street. no food/beverage or third party catering to be provided by employer | $1,200,000 | |
| Feb 20, 2020 | Completed final sign-off Sep 2021 | 1 Market St | Level 10 Construction Lp | ref pa# 201906113076; tenant remodel to add sandwich cafe to office building new hvac, exhaust, lighting, controls and power outlets, this is the deferred submittal for mepDetails
ref pa# 201906113076; tenant remodel to add sandwich cafe to office building new hvac, exhaust, lighting, controls and power outlets, this is the deferred submittal for mep | |
| Jan 21, 2020 | Completed final sign-off Oct 2020 | 1 Market St | Paganini Electric Corp(See Signatories) | steuart tower fls 20, 21, 22: installation of 2-way communicatoin call station at elevator lobbies. connecting them to building existing backbone system.Details
steuart tower fls 20, 21, 22: installation of 2-way communicatoin call station at elevator lobbies. connecting them to building existing backbone system. | $20,000 |
| Jan 3, 2020 | Completed final sign-off Sep 2021 | 345 Spear St | Bcci Construction Company | ref pa# 201912230295; 1st fl. elctrical only. permit to support appoved arch set for security turnstiles, new power and communication connections added//vif complaince with cfc 1010.3.2 -this section speaks to turnstiles and that they shall remain open upon fire alarm acuationDetails
ref pa# 201912230295; 1st fl. elctrical only. permit to support appoved arch set for security turnstiles, new power and communication connections added//vif complaince with cfc 1010.3.2 -this section speaks to turnstiles and that they shall remain open upon fire alarm acuation | $20,000 |
| Dec 18, 2019 | Completed final sign-off Feb 2021 | 211 Main St | Dome Construction Corp | 6th fl: commercial ti to include new conference storefronts, offices, breakroom, finishes, and ada upgrades in restrooms. new lighting throughout.Details
6th fl: commercial ti to include new conference storefronts, offices, breakroom, finishes, and ada upgrades in restrooms. new lighting throughout. | $1,200,000 |
| Nov 18, 2019 | Expired or cancelled withdrawn Nov 2020 | 28 02nd St | 5th fl - new ti of (e) office space. new floor & ceiling finishes, new non-bearing partitions, new millwork & fixtures, new electrical & lighting fixtures, & update mechanical and plumbing.Details
5th fl - new ti of (e) office space. new floor & ceiling finishes, new non-bearing partitions, new millwork & fixtures, new electrical & lighting fixtures, & update mechanical and plumbing. | $100,000 | |
| Nov 18, 2019 | Expired or cancelled withdrawn Nov 2020 | 28 02nd St | 7th fl - new ti of (e) office space. new floor & ceiling finishes, new non-bearing partitions, new millwork & fixtures, new electrical & lighting fixtures, & update mechanical and plumbing.Details
7th fl - new ti of (e) office space. new floor & ceiling finishes, new non-bearing partitions, new millwork & fixtures, new electrical & lighting fixtures, & update mechanical and plumbing. | $150,000 | |
| Nov 18, 2019 | Expired or cancelled withdrawn Nov 2020 | 28 02nd St | 6th fl - new ti of (e) office space. new floor & ceiling finishes, new non-bearing partitions, new millwork & fixtures, new electrical & lighting fixtures, & update mechanical and plumbing.Details
6th fl - new ti of (e) office space. new floor & ceiling finishes, new non-bearing partitions, new millwork & fixtures, new electrical & lighting fixtures, & update mechanical and plumbing. | $150,000 | |
| Nov 18, 2019 | Expired or cancelled withdrawn Nov 2020 | 28 02nd St | 4th fl - new ti of (e) office space. new floor & ceiling finishes, new non-bearing partitions, new millwork & fixtures, new electrical & lighting fixtures, & update mechanical and plumbing.Details
4th fl - new ti of (e) office space. new floor & ceiling finishes, new non-bearing partitions, new millwork & fixtures, new electrical & lighting fixtures, & update mechanical and plumbing. | $150,000 | |
| Oct 25, 2019 | Completed final sign-off Nov 2020 | 50 Beale St | Field Construction Inc. | addition of ventilation fan to existing as meter room in basementDetails
addition of ventilation fan to existing as meter room in basement | $50,000 |
| Oct 25, 2019 | Completed final sign-off Nov 2020 | 50 Beale St | Field Construction Inc. | mechanical alterations to e basement gas room. work includes new mech louvers at gr level facade/glazing.Details
mechanical alterations to e basement gas room. work includes new mech louvers at gr level facade/glazing. | $5,000 |
| Sep 18, 2019 | Never finaled issued Sep 2019, no final | 50 Beale St | Paganini Electric Corp(See Signatories) | add emergency 2-way communication system call stations to new riser to serve future tenants locked elevator lobby locations per cbc 1008.1.9.12 item 5. maher naDetails
add emergency 2-way communication system call stations to new riser to serve future tenants locked elevator lobby locations per cbc 1008.1.9.12 item 5. maher na | $100,000 |
| Aug 28, 2019 | Completed final sign-off Oct 2019 | 1 Market St | Paganini Electric Corp(See Signatories) | install of (3) 2-way communications call stations, connect to (e) backbone. work to occur on 24th floor only.Details
install of (3) 2-way communications call stations, connect to (e) backbone. work to occur on 24th floor only. | $15,000 |
| Jul 22, 2019 | Completed final sign-off Mar 2022 | 1 Market St | Source Planning And Construction Inc | 20th flr - ti reconfiguragtimg (e) space. defferred permit for life safety (mech/ele included)Details
20th flr - ti reconfiguragtimg (e) space. defferred permit for life safety (mech/ele included) | $600,000 |
| Mar 6, 2019 | Expired or cancelled expired Nov 2025 | 1 Embarcadero Center | Acco Engineered Systems Inc. Dba Acco En | replacement of existing boilers,cooling towers, chillers, associated pumps. reconfigure power distribution based on new equipment electrical requirements. *maher n/a**Details
replacement of existing boilers,cooling towers, chillers, associated pumps. reconfigure power distribution based on new equipment electrical requirements. *maher n/a** | $5,000,000 |
| Feb 7, 2019 | Completed final sign-off Jun 2019 | 50 Beale St | Cahill Contractors Llc. | interior renovation of level 4, including light demo. and minor lalyout changes of office spaces and new lighting maher n/aDetails
interior renovation of level 4, including light demo. and minor lalyout changes of office spaces and new lighting maher n/a | $100,000 |
| Sep 28, 2018 | Never finaled issued Nov 2018, no final | 50 Beale St | Gci, Inc | interior tenant improvement lobby remodel, including all new finishes & lighting. no structural. no exterior work. maher naDetails
interior tenant improvement lobby remodel, including all new finishes & lighting. no structural. no exterior work. maher na | $1,519,200 |
| Dec 20, 2017 | Completed final sign-off Dec 2018 | 1 Market St | Dpr Construction | 12th fl amep ti full floor. no structural, soft demo under separate pa #201712085901, new office, meeting rooms, new restrooms. no changes to bldg core. 2-hr horizontal exit . n/a maher ordinance.Details
12th fl amep ti full floor. no structural, soft demo under separate pa #201712085901, new office, meeting rooms, new restrooms. no changes to bldg core. 2-hr horizontal exit . n/a maher ordinance. | $3,200,000 |
| Oct 20, 2017 | Never finaled issued Nov 2017, no final | 335 Powell St | Cw Horton General Contractor | mep - for general remoedl of guestroom corridor w/replacement of light fixtures. limited remodel of guest room bath rooms. ref arch #201709259458. maher na. floors 3-12 onlyDetails
mep - for general remoedl of guestroom corridor w/replacement of light fixtures. limited remodel of guest room bath rooms. ref arch #201709259458. maher na. floors 3-12 only | |
| Oct 17, 2017 | Completed final sign-off Jan 2018 | 101 California St | Swinerton Builders | partial 17th flr t.i. - demolition of (e) offices. new construction is converting offices into open office area & converting conference rooms into new offices, includign partition, doors, millwork, mechanical, electrical & plumbing. no structural work to be performed. n/a maher ordinanceDetails
partial 17th flr t.i. - demolition of (e) offices. new construction is converting offices into open office area & converting conference rooms into new offices, includign partition, doors, millwork, mechanical, electrical & plumbing. no structural work to be performed. n/a maher ordinance | $150,000 |
| Sep 25, 2017 | Never finaled issued Oct 2017, no final | 335 Powell St | Cw Horton General Contractor | remodel main corridors & guestroom baths. corridor: new portals, chandeliers, signage & wall sconces. guest baths: replace plumbing fixtures in 600 rooms. move walls/fixtures in 102 rooms. no changes to occupancy/hvac/fire life 0n/a maherDetails
remodel main corridors & guestroom baths. corridor: new portals, chandeliers, signage & wall sconces. guest baths: replace plumbing fixtures in 600 rooms. move walls/fixtures in 102 rooms. no changes to occupancy/hvac/fire life 0n/a maher | $3,000,000 |
| Sep 15, 2017 | Completed final sign-off May 2018 | 315 Montgomery St | G Swanson Constr. Inc. | 1/f- t.i. modifications to include relocated access ramp and stairs, new financial and client advisor rooms & client meeting rooms, new ceilings. (e) restrooms and breakrooms to remain. new furniture and finishes. n/a ordinance #155-13Details
1/f- t.i. modifications to include relocated access ramp and stairs, new financial and client advisor rooms & client meeting rooms, new ceilings. (e) restrooms and breakrooms to remain. new furniture and finishes. n/a ordinance #155-13 | $700,000 |
| Aug 8, 2017 | Completed final sign-off Sep 2017 | 1 Market St | West Coast Electric Service Company Inc | 37/f, 38/f- revision to pa#2016-12-15-5015 and 2016-05-25-8242. add emergency two way communicatin call boxes to floors 37 and 38. total (4) boxes/ tie into existing. n/a ordinance #155-13Details
37/f, 38/f- revision to pa#2016-12-15-5015 and 2016-05-25-8242. add emergency two way communicatin call boxes to floors 37 and 38. total (4) boxes/ tie into existing. n/a ordinance #155-13 | $2,400 |
| Jun 20, 2017 | Never finaled issued Jun 2017, no final | 211 Main St | Hathaway Dinwiddie Co. | 15th fl: revision to #2017-0417-4089. electrical drawings have been revised to remove the title 24 power distribution forms and controlled power outlet.s no other updates. maher naDetails
15th fl: revision to #2017-0417-4089. electrical drawings have been revised to remove the title 24 power distribution forms and controlled power outlet.s no other updates. maher na | |
| Jun 20, 2017 | Never finaled issued Jun 2017, no final | 211 Main St | Hathaway Dinwiddie Co. | 14th fl: revision to #2017-0417-4086. electrical drawings have been revised to remove the title 24 power distribution forms and controlled power outlet.s no other updates. maher naDetails
14th fl: revision to #2017-0417-4086. electrical drawings have been revised to remove the title 24 power distribution forms and controlled power outlet.s no other updates. maher na | |
| Jun 15, 2017 | Never finaled issued Jun 2017, no final | 300 Clay St | Gci, Inc | 14th fl: tenant improvement demolition and construction of mech, ele, plumbing. no structural to be performed. life safety deferred. ref 2017-0526-7759.Details
14th fl: tenant improvement demolition and construction of mech, ele, plumbing. no structural to be performed. life safety deferred. ref 2017-0526-7759. | $329,000 |
| Jun 12, 2017 | Never finaled issued Jul 2017, no final | 580 California St | Richlen Construction | 4/f- demolition of select interior partitions and millwork, construction of new conference rooms, new millwork, power/data, finishes throughout. space currently unoccupied . sprinkler system modification under sep permit maher not reqDetails
4/f- demolition of select interior partitions and millwork, construction of new conference rooms, new millwork, power/data, finishes throughout. space currently unoccupied . sprinkler system modification under sep permit maher not req | $800,000 |
| Jun 2, 2017 | Completed final sign-off Jun 2018 | 215 Fremont St | Skyline Construction | 7/f & 7m- replacement of selected lighting, power outlets and hvac, new plumbing connection to break room and restroom. ref. to t.i. pa#2017-0524-7575. n/a ordinance #155-13. fire alarm/sprinklers deferred.Details
7/f & 7m- replacement of selected lighting, power outlets and hvac, new plumbing connection to break room and restroom. ref. to t.i. pa#2017-0524-7575. n/a ordinance #155-13. fire alarm/sprinklers deferred. | |
| May 3, 2017 | Completed final sign-off Jun 2018 | 215 Fremont St | Skyline Construction | 6/f- interior demolition of non-structural elements including but not limited to partition, doors, lighting and ceiling. construct of new offices, conference, break area and new finish. life safety, fire alarm and sprinkler are under separate permit. n/a ordinance #155-13 incuding mep.Details
6/f- interior demolition of non-structural elements including but not limited to partition, doors, lighting and ceiling. construct of new offices, conference, break area and new finish. life safety, fire alarm and sprinkler are under separate permit. n/a ordinance #155-13 incuding mep. | $3,000,000 |
| Apr 17, 2017 | Never finaled issued Apr 2017, no final | 211 Main St | Hathaway Dinwiddie Co. | 15th floor commercial tenant improvement to include new private offices & upgrades to exisitng offices, conference rooms & break area. new led lighting throughout. new ada upgrades in restrooms. n/a maher ordinanceDetails
15th floor commercial tenant improvement to include new private offices & upgrades to exisitng offices, conference rooms & break area. new led lighting throughout. new ada upgrades in restrooms. n/a maher ordinance | $50,000 |
| Apr 17, 2017 | Never finaled issued Apr 2017, no final | 211 Main St | Hathaway Dinwiddie Co. | 14th floor commercial tenant improvement to include new private offices & upgrades to exisitng offices, conference rooms & break area. new led lighting throughout. new ada upgrades in restrooms. n/a maher ordinanceDetails
14th floor commercial tenant improvement to include new private offices & upgrades to exisitng offices, conference rooms & break area. new led lighting throughout. new ada upgrades in restrooms. n/a maher ordinance | $50,000 |
| Mar 22, 2017 | Completed final sign-off Mar 2018 | 2 Embarcadero Center | Fisher Development Inc | 1,2,3/f-interior renovation to (e) gym include: demo (e) lighting, plumbing, hvac terminals & vav boxes,(e) casework-desks,lockers,storage,flooring, acoustic ceiling & limited non bearing partitions. new lighting,plumbing,hvac fixtures,floor,wall finishes,acoustic ceiling & non bearing partitions.Details
1,2,3/f-interior renovation to (e) gym include: demo (e) lighting, plumbing, hvac terminals & vav boxes,(e) casework-desks,lockers,storage,flooring, acoustic ceiling & limited non bearing partitions. new lighting,plumbing,hvac fixtures,floor,wall finishes,acoustic ceiling & non bearing partitions. | $175,000 |
| Oct 14, 2016 | Never finaled issued Nov 2016, no final | 601 Montgomery St | High Level Construction Co | commercial tenant improvement which includes demo of non-structural partitions, lighting, and finshes. construction of non-structural partitions. includes mep.Details
commercial tenant improvement which includes demo of non-structural partitions, lighting, and finshes. construction of non-structural partitions. includes mep. | $375,600 |
| Sep 27, 2016 | Never finaled issued Oct 2016, no final | 601 Montgomery St | Rossi Builders Inc. | #800- commercial t.i. includes demolition of non structural partitions, lighting and finishes, construction of non structural partitions includes mechanical, electrical and plumbing. n/a ordinance #155-13Details
#800- commercial t.i. includes demolition of non structural partitions, lighting and finishes, construction of non structural partitions includes mechanical, electrical and plumbing. n/a ordinance #155-13 | $300,000 |
| Aug 10, 2016 | Completed final sign-off Apr 2017 | 580 California St | Richlen Construction | #175- demolition of interior partitions, doors, frames, hardware & finishes. space is currently unoccupied. construction of new conference room, bike storage, pantry & office. new finishes throughout. sprinkler/life safety under separate permit. maher naDetails
#175- demolition of interior partitions, doors, frames, hardware & finishes. space is currently unoccupied. construction of new conference room, bike storage, pantry & office. new finishes throughout. sprinkler/life safety under separate permit. maher na | $350,000 |
| Jun 8, 2016 | Completed final sign-off May 2017 | 2200 Chestnut St | G Swanson Constr. Inc. | demo of (e) partitions, finishes, hvac, elec. ti with new partitions, finishes, associated hvac, electrical and upgrade (e) restrooms to accessibility code.Details
demo of (e) partitions, finishes, hvac, elec. ti with new partitions, finishes, associated hvac, electrical and upgrade (e) restrooms to accessibility code. | $750,000 |
| Jun 8, 2016 | Completed final sign-off Mar 2017 | 188 The Embarcadero | Dpr Construction | basement & roof- m.e.p. work - new lighting fixtures, controls, power & signal outlets for central plant upgrades, replace existing mechanical equipment. ref pa #201505126148. n/a meher ordinanceDetails
basement & roof- m.e.p. work - new lighting fixtures, controls, power & signal outlets for central plant upgrades, replace existing mechanical equipment. ref pa #201505126148. n/a meher ordinance | $3,500,000 |
| May 19, 2016 | Completed final sign-off Dec 2016 | 1 Market St | Dpr Construction | spear tower: selective interior non-structural demolition, (n) non-structural partitions, doors, ceiling, lights, millwork, finishes, electrical and hvac. no change in occupancy, use or floor area. n/a ordinance #155-13Details
spear tower: selective interior non-structural demolition, (n) non-structural partitions, doors, ceiling, lights, millwork, finishes, electrical and hvac. no change in occupancy, use or floor area. n/a ordinance #155-13 | $131,040 |
| May 12, 2016 | Completed final sign-off Oct 2016 | 335 Powell St | Cw Horton General Contractor | revision to pa#2016-0422-5497, to remodel existing corridor on 11/f change out lights, (n) wall coverings carpet, paint, 2 (n) fire/life safety, seperate permit. n/a ordinance #155-13Details
revision to pa#2016-0422-5497, to remodel existing corridor on 11/f change out lights, (n) wall coverings carpet, paint, 2 (n) fire/life safety, seperate permit. n/a ordinance #155-13 | $15,000 |
| Apr 14, 2016 | Completed final sign-off Jan 2019 | 505 Howard St | Skanska Usa Building Inc | revision to mep pa#201601207450 to revise lan room layout and restroom cores. arch. & structural under pa#201512185489. mep pa#201601207450. n/a ordinance #155-13Details
revision to mep pa#201601207450 to revise lan room layout and restroom cores. arch. & structural under pa#201512185489. mep pa#201601207450. n/a ordinance #155-13 | |
| Feb 5, 2016 | Completed final sign-off Sep 2016 | 1 Market St | Dpr Construction | 15th floor - selective interior non-structural demolitoin, new non-structural partitoins, doors, ceiling, lights, millwork finishes, electrical , plumbing & hvac. no change in occupancy or use or change in floor area.Details
15th floor - selective interior non-structural demolitoin, new non-structural partitoins, doors, ceiling, lights, millwork finishes, electrical , plumbing & hvac. no change in occupancy or use or change in floor area. | $537,360 |
| Jan 28, 2016 | Never finaled issued Jan 2016, no final | 180 Golden Gate Av | Bcci Construction Company | revision to appl #201509217519 to revise electrical panel schedule. n/a maher ordinanceDetails
revision to appl #201509217519 to revise electrical panel schedule. n/a maher ordinance | |
| Jan 27, 2016 | Completed final sign-off Jan 2019 | 505 Howard St | Skanska Usa Building Inc | new mep for 1st time tenant improvement to levels 7 & partial 8/f. arch. t.i. pa# 201601086655. n/a ordinance #155-13Details
new mep for 1st time tenant improvement to levels 7 & partial 8/f. arch. t.i. pa# 201601086655. n/a ordinance #155-13 | $1,785,000 |
| Jan 22, 2016 | Completed final sign-off Apr 2016 | 601 Montgomery St | Clune Construction Company L P | #1400 -commercial t.i. includes demolition, new non-structural partitions, lighting, electrical, millwork and finishes. f/a sprinkler under separate permit. n/a ordinance #155-13Details
#1400 -commercial t.i. includes demolition, new non-structural partitions, lighting, electrical, millwork and finishes. f/a sprinkler under separate permit. n/a ordinance #155-13 | $762,841 |
| Jan 20, 2016 | Completed final sign-off Jan 2019 | 505 Howard St | Skanska Usa Building Inc | first time ti to level 6 inlcuding new mep. addition of rooftop equipment. architectural structural under separate permit. ref pa 2015-1218-5489. n/a for maher ordinance no.155-13Details
first time ti to level 6 inlcuding new mep. addition of rooftop equipment. architectural structural under separate permit. ref pa 2015-1218-5489. n/a for maher ordinance no.155-13 | $2,000,000 |
| Dec 28, 2015 | Completed final sign-off Oct 2017 | 345 Spear St | Bcci Construction Company | 5th flr: partial floor t.i. including minor demolition,new partitions,finishes & associated mep, fire ls under separate permit; maher n/aDetails
5th flr: partial floor t.i. including minor demolition,new partitions,finishes & associated mep, fire ls under separate permit; maher n/a | $795,000 |
| Dec 22, 2015 | Completed final sign-off Jun 2017 | 1155 Market St | Dpr Construction | floors 10 & 11 - lighting revision to pa #201507020526.Details
floors 10 & 11 - lighting revision to pa #201507020526. | |
| Nov 10, 2015 | Completed final sign-off Jul 2016 | 215 Fremont St | Dome Construction Corp | floors 3-7&7a: add new wall with door and card readers to secure each elevator lobby in order to subtenant the floors. add card reader to doors within elevator lobby as well as within the stairwell at each level. new finishes and lighting at elevator lobby. n/a ordinance #155-13Details
floors 3-7&7a: add new wall with door and card readers to secure each elevator lobby in order to subtenant the floors. add card reader to doors within elevator lobby as well as within the stairwell at each level. new finishes and lighting at elevator lobby. n/a ordinance #155-13 | $1,000,000 |
| Sep 11, 2015 | Never finaled issued Sep 2015, no final | 188 The Embarcadero | Dpr Construction | 2nd floor: ti - addition of conference rooms and open office seating. mep & electrical included. maher naDetails
2nd floor: ti - addition of conference rooms and open office seating. mep & electrical included. maher na | $2,500,000 |
| Jul 28, 2015 | Completed final sign-off Feb 2016 | 188 The Embarcadero | Dpr Construction | revision to pa#201506048095 re-arranging some conference room walls. n/a ordinance #155-13.Details
revision to pa#201506048095 re-arranging some conference room walls. n/a ordinance #155-13. | |
| Jul 28, 2015 | Completed final sign-off Aug 2017 | 1155 Market St | Dpr Construction | new mechanical, electrical and plumbing in the area of work in pa#201503191356. sprinklers and life safety under deferred submittal.Details
new mechanical, electrical and plumbing in the area of work in pa#201503191356. sprinklers and life safety under deferred submittal. | $455,800 |
| Jul 1, 2015 | Never finaled issued Aug 2015, no final | 3 Embarcadero Center | Principal Builders Inc. | title 24 mep. - to install new fixtures and equipment on 10/f. t.i. pa#201505277277. n/a ordinance #155-13Details
title 24 mep. - to install new fixtures and equipment on 10/f. t.i. pa#201505277277. n/a ordinance #155-13 | $450,000 |
| Jun 11, 2015 | Never finaled issued Jun 2015, no final | 3 Embarcadero Center | Principal Builders Inc. | 9th floor: mechanical electrical, plumbing. t.i. to install new equipment and fixtures. ref. t.i. appl. #2015.05277.7275. maher n/a.Details
9th floor: mechanical electrical, plumbing. t.i. to install new equipment and fixtures. ref. t.i. appl. #2015.05277.7275. maher n/a. | $450,000 |
| Jun 3, 2015 | Never finaled issued Jun 2015, no final | 3 Embarcadero Center | Principal Builders Inc. | 8th floor: mechanical, electrical, plumbing to install new equipment and fixtures. ref app#201505206826 for t.i. work. n/a for maherDetails
8th floor: mechanical, electrical, plumbing to install new equipment and fixtures. ref app#201505206826 for t.i. work. n/a for maher | $1,800,000 |
| Mar 17, 2015 | Completed final sign-off Oct 2016 | 345 Spear St | Bcci Construction Company | 7th floor: mep work associated with pa#201501236545 including new lighting & hvac. life safety under seperate permit. n/a ordinance #155-13Details
7th floor: mep work associated with pa#201501236545 including new lighting & hvac. life safety under seperate permit. n/a ordinance #155-13 | $875,000 |
| Jul 7, 2014 | Expired or cancelled cancelled Oct 2015 | 470 Pacific Av | Northern Sun Associates | 2nd floor. hvac, electrical and add restroom & shower for tenant improvement work.Details
2nd floor. hvac, electrical and add restroom & shower for tenant improvement work. | $10,000 |
| Jun 24, 2014 | Completed final sign-off Dec 2014 | 1 Market St | Dpr Construction | 2/f annex- mep scope for tenant improvement to 2/f annex for pa# 201406168417, life safety and srpinkler under seperate permit.Details
2/f annex- mep scope for tenant improvement to 2/f annex for pa# 201406168417, life safety and srpinkler under seperate permit. | $133,637 |
| Jun 20, 2014 | Completed final sign-off Oct 2014 | 1 Market St | Dpr Construction | 2nd floor steuart spear tenant improvement - provide new lighting & controls, power & signal & vav's duct work & controls. ref #2014.0507.5102. sprinkler & life safety under separate permit. n/a maher ordinanceDetails
2nd floor steuart spear tenant improvement - provide new lighting & controls, power & signal & vav's duct work & controls. ref #2014.0507.5102. sprinkler & life safety under separate permit. n/a maher ordinance | $2,134,450 |
| Oct 30, 2013 | Expired or cancelled withdrawn Nov 2013 | 1075 California St | t.i. to guestrooms, including plumbing & elecrical upgrades. guestroom count reduced from 147 rooms to 134 rooms.Details
t.i. to guestrooms, including plumbing & elecrical upgrades. guestroom count reduced from 147 rooms to 134 rooms. | $4,700,000 | |
| Apr 17, 2012 | Completed final sign-off Oct 2012 | 400 Post St | Lorentz Bruun Co., Inc. | rev to pa# 2011/11/01/8054. 3539 sqft interior t.i for a retail banking center, this project was previously approved/permited, but client asked gensler to redesign. project includes 24 hr atm vestiblue, sliding glass nanwall system, lobby, hospitality area for customers, teller line, offices,Details
rev to pa# 2011/11/01/8054. 3539 sqft interior t.i for a retail banking center, this project was previously approved/permited, but client asked gensler to redesign. project includes 24 hr atm vestiblue, sliding glass nanwall system, lobby, hospitality area for customers, teller line, offices, | |
| Sep 23, 2010 | Completed final sign-off Nov 2010 | 50 Fremont St | C B 2 Builders Incorporated | 24th fl, mep for architectural permit 201009010009Details
24th fl, mep for architectural permit 201009010009 | $10,000 |
| Jun 15, 2000 | Completed final sign-off Sep 2000 | 1 Embarcadero Center | fire alarmDetails
fire alarm | $8,500 |