Permit 202106152467
250 Clay St
ground floor, electrical only: new panel to serve loads in the storage, new lighting and controls, and recepticles for bike charging. ref bpa 202106102134
- Outcome
- Completed (city status: complete, May 23, 2022)
- Filed
- Jun 15, 2021
- Permit issued
- Jul 19, 2021
- Final sign-off
- May 23, 2022
- Declared cost
- $10,000
- Building use
- prkng garage/public
- Neighborhood
- Financial District/South Beach
- Contractor
- Bcci Construction Company (license 492944)
- Property
- All permits at this address (block 0204, lot 023)