How long do building permits take in San Francisco's Financial District/South Beach neighborhood?

In the Financial District/South Beach neighborhood of San Francisco, of the 2,182 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 6 days, up from 3 days a year earlier. Of the 1,631 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 99 days of being issued, down from 107 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's FinancialDistrict/South Beach neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/financial-district-south-beach · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 20262,182 issued62,400 issued3
Permit issued to final sign-offOctober 2023 through September 20241,631 finished991,609 finished107

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q454144500too recent
2026-Q35634086356028530too recent
2026-Q2566530961218651220too recent
2026-Q1596558439358771720too recent
2025-Q4731686566470912330too recent
2025-Q3708669656496842500too recent
2025-Q2675654257494893000too recent
2025-Q1588576256468933500too recent
2024-Q4521501261399942440too recent
2024-Q3565533361421963410yes
2024-Q2602578262451954090yes
2024-Q1511489153386903180yes
2023-Q44914713763741203682yes
2023-Q351949435639411934799yes
2023-Q257153537642484415109yes
2023-Q1462436170330102332101yes
2022-Q4647584296465117386134yes
2022-Q3712667378539116408142yes
2022-Q2741686268549105374150yes
2022-Q1633602184499116447103yes
2021-Q4637611370483124457128yes
2021-Q3599569190458112463122yes
2021-Q262459826100493126405103yes
2021-Q15755373513641083418137yes
2020-Q473068845155543112456148yes
2020-Q381074821138557114413219yes
2020-Q22242024016013011648289yes
2020-Q19068220112565185485270yes
2019-Q41,1911,104270775194623337yes
2019-Q31,2951,236150846138577373yes
2019-Q21,2521,192140842140650356yes
2019-Q11,2041,138149777126706366yes
2018-Q41,1761,130263802130714311yes
2018-Q31,3041,249355854120628381yes
2018-Q21,2891,219265892127734327yes
2018-Q11,1851,113255812128568304yes
2017-Q41,0491,006166742125571252yes
2017-Q31,029977148661101484303yes
2017-Q21,0521,013160720121457286yes
2017-Q196492905067381405252yes
2016-Q41,0531,015156735104440281yes
2016-Q31,04499115470499424289yes
2016-Q21,1221,080162775106423302yes
2016-Q11,1991,138156822110507317yes
2015-Q41,2551,184176845122511333yes
2015-Q31,2721,199257884148477305yes
2015-Q21,1301,077161774139482294yes
2015-Q1974939156667124506268yes
2014-Q495290015964498529248yes
2014-Q391486604659884505255yes
2014-Q21,1991,127374820118452305yes
2014-Q185581504261483379196yes
2013-Q41,0671,02015877487476243yes
2013-Q395991914466295420248yes
2013-Q2960921156683114514231yes
2013-Q182577614054895346223yes
2012-Q487082415757588440236yes
2012-Q3967919159608104426289yes
2012-Q295691016463996351253yes
2012-Q188884905160679380229yes
2011-Q486080814561574358184yes
2011-Q388384404062482393204yes
2011-Q2763723044521107372194yes
2011-Q171268404352391375156yes
2010-Q4841810138607119404183yes
2010-Q3754716138488105354218yes
2010-Q265662803746097356144yes
2010-Q157755302237690350155yes
2009-Q455553603038094269133yes
2009-Q3678660026492109344145yes
2009-Q282280302162190291163yes
2009-Q180578301558976337171yes
2008-Q4776750019522113349203yes
2008-Q3937905014613136301235yes
2008-Q2960926012638126336211yes
2008-Q1899862020593101356192yes
2007-Q41,022989021651120360190yes
2007-Q31,017989011657134307185yes
2007-Q21,0721,057028706127333215yes
2007-Q1881868040580126317131yes
2006-Q4868858041527126337119yes
2006-Q3980949051572128312115yes
2006-Q2909898043524126351101yes
2006-Q189988504351799316119yes
2005-Q4955932047553118349150yes
2005-Q31,013994047573131400156yes
2005-Q2996972052627118268145yes
2005-Q1834812054553111296110yes
2004-Q4783756054488128291126yes
2004-Q3893873056561108349134yes
2004-Q21,001971061669117351105yes
2004-Q1769753057465124316108yes
2003-Q4850835105353212836393yes
2003-Q38218071055501114387111yes
2003-Q27267137524649835769yes
2003-Q17267016434389026973yes
2002-Q4669643116339210027683yes
2002-Q372969404241310830349yes
2002-Q267765705638010831855yes
2002-Q16035760503069931625yes
2001-Q471467985536812325728yes
2001-Q374071046837214138616yes
2001-Q290786265544914333116yes
2001-Q195890786947212639121yes
2000-Q490085675645415640415yes
2000-Q31,0601,01086352917239510yes
2000-Q21,2891,221127261022249620yes
2000-Q11,2361,167146554421753920yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

17,053 of the 91,987 building permits filed since 2000 (19%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Financial District/South Beach neighborhood

Shown apart, with their own page here: kitchen remodel (3,060 filed, 2,343 finished; contractors); bathroom remodel (2,943 filed, 2,280 finished; contractors); stairs (1,642 filed, 1,122 finished; contractors); deck (176 filed, 96 finished; contractors); roof deck (108 filed, 65 finished; contractors); pergola or trellis (62 filed, 30 finished; contractors). Other types: 85,930 permits.

Nearby neighborhoods

Chinatown, Nob Hill, Tenderloin; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.