Permit GraphShortlistSan Francisco building permits since 2000

How long do building permits take in San Francisco's Chinatown neighborhood?

In the Chinatown neighborhood of San Francisco, of the 329 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 5 days, the same as a year earlier. Of the 375 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 101 days of being issued, down from 152 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's ChinatownneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/chinatown · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026329 issued5386 issued5
Permit issued to final sign-offOctober 2023 through September 2024375 finished101324 finished152

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q48400too recent
2026-Q3102744341622560too recent
2026-Q287754462749970too recent
2026-Q1897847345481680too recent
2025-Q412210279552362370too recent
2025-Q3139132269951342300too recent
2025-Q21079610104761163220too recent
2025-Q18478710155602660too recent
2024-Q4838048761992790too recent
2024-Q3117104412382923290yes
2024-Q2189177342143933860yes
2024-Q110086111068763170yes
2023-Q4113102478821444291yes
2023-Q312511371268412628224yes
2023-Q212210961358517449320yes
2023-Q11099461927218346818yes
2022-Q412511281648315858224yes
2022-Q3898641526615149219yes
2022-Q2108934837114160123yes
2022-Q1103976857514392524yes
2021-Q4816981305610038318yes
2021-Q394897906716438422yes
2021-Q28173281585714842914yes
2021-Q16761302165015886012yes
2020-Q48678502146612271812yes
2020-Q3806822163426833330yes
2020-Q2343126233177063916yes
2020-Q113212801717116146954yes
2019-Q418216301079517358067yes
2019-Q320919505111211148983yes
2019-Q21571430858610051656yes
2019-Q116115304310110032451yes
2018-Q4186172090999657375yes
2018-Q319718817811313444575yes
2018-Q2171162516710614441558yes
2018-Q11611500621008359551yes
2017-Q418317308710511154565yes
2017-Q319818404011012045469yes
2017-Q21761640459313654471yes
2017-Q1136132042859542643yes
2016-Q41801650708410752479yes
2016-Q317615921149512051360yes
2016-Q21451320367210643662yes
2016-Q118616904210310447465yes
2015-Q41661520859513262960yes
2015-Q31691510418011043971yes
2015-Q21941830351088843275yes
2015-Q114414012910012034439yes
2014-Q4145138030859830051yes
2014-Q3171158036968735461yes
2014-Q220119403413310858755yes
2014-Q11481380209210076142yes
2013-Q418316706611310533552yes
2013-Q32132060261218537282yes
2013-Q224823002113310543994yes
2013-Q11311270507811290348yes
2012-Q4157152043918974959yes
2012-Q31651580427811066680yes
2012-Q216315603810311244053yes
2012-Q1121112030737026938yes
2011-Q41481400211008224938yes
2011-Q3135131016709269255yes
2011-Q2126117021639887053yes
2011-Q1147139010977134938yes
2010-Q41371210327012554448yes
2010-Q31571470487711165260yes
2010-Q21311230286215455657yes
2010-Q11141120267210434136yes
2009-Q4153143014867227052yes
2009-Q31321250507511365546yes
2009-Q218117501410411428160yes
2009-Q1121116018619139049yes
2008-Q4169161015859133558yes
2008-Q3160157067911933770yes
2008-Q2174164010997435955yes
2008-Q118117301111311032642yes
2007-Q41921860228913934669yes
2007-Q3162148076616043251yes
2007-Q21431420117817743433yes
2007-Q11341320279612644824yes
2006-Q41351310768217430228yes
2006-Q3127127046589041536yes
2006-Q21591570278410945348yes
2006-Q1148148018647838742yes
2005-Q41621550517110831455yes
2005-Q31661650578614730355yes
2005-Q21881850679616034859yes
2005-Q1166160027779431252yes
2004-Q4148145042679336750yes
2004-Q3148147069618455857yes
2004-Q21911860549511674365yes
2004-Q11161150675110537546yes
2003-Q41281240525813039440yes
2003-Q3121116033538735038yes
2003-Q2151148069717825839yes
2003-Q1108105062539835022yes
2002-Q4139136072578028840yes
2002-Q31391350427611641131yes
2002-Q21801750141599337019yes
2002-Q11511500965912655214yes
2001-Q4198190052661216047yes
2001-Q31091060100451223202yes
2001-Q2163158067751555771yes
2001-Q118317913281741409183yes
2000-Q4140134090671335682yes
2000-Q3142141055462247791yes
2000-Q2133126050532664150yes
2000-Q1186177561682566243yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

4,170 of the 15,521 building permits filed since 2000 (27%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Chinatown neighborhood

Shown apart, with their own page here: bathroom remodel (823 filed, 547 finished; contractors); kitchen remodel (802 filed, 556 finished; contractors); stairs (431 filed, 289 finished; contractors); roof deck (63 filed, 35 finished; contractors); deck (61 filed, 38 finished; contractors). Other types: 13,839 permits.

Nearby neighborhoods

Financial District/South Beach, North Beach, Nob Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.