How long do kitchen remodel permits take in San Francisco's Chinatown neighborhood?

In the Chinatown neighborhood of San Francisco, of the 26 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 2 days a year earlier. Of the 22 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 136 days of being issued, down from 266 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco'sChinatown neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/chinatown/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202626 issued014 issued2
Permit issued to final sign-offOctober 2023 through September 202422 finished13623 finished266

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41100too recent
2026-Q311901110too recent
2026-Q210835620too recent
2026-Q15501310too recent
2025-Q44420too recent
2025-Q33320too recent
2025-Q23320too recent
2025-Q12210too recent
2024-Q466210451103670too recent
2024-Q3760226842270yes
2024-Q26668861422640yes
2024-Q199021161383280yes
2023-Q44440yes
2023-Q365722741yes
2023-Q24440yes
2023-Q111100992924822yes
2022-Q4882930963326281yes
2022-Q366711725873551yes
2022-Q2111179572888763yes
2022-Q15514251433870yes
2021-Q410985981703951yes
2021-Q3119619972235713yes
2021-Q27705261192731yes
2021-Q176011262278220yes
2020-Q411901139846581yes
2020-Q33220yes
2020-Q23321yes
2020-Q13330yes
2019-Q4762515451735991yes
2019-Q3121079661343045yes
2019-Q26655832yes
2019-Q1662223261902520yes
2018-Q41097998865711yes
2018-Q3880352467062yes
2018-Q215141227132163311yes
2018-Q1131201012602800yes
2017-Q4971318361264181yes
2017-Q3763412862544820yes
2017-Q2107010351387062yes
2017-Q19903682043491yes
2016-Q47702661162201yes
2016-Q39842645yes
2016-Q28708852004142yes
2016-Q1131203492024943yes
2015-Q41413413112976093yes
2015-Q316161394142306512yes
2015-Q21514220111633423yes
2015-Q177122371122400yes
2014-Q49932392112970yes
2014-Q39925245yes
2014-Q29904482505321yes
2014-Q11090381713791yes
2013-Q4121005391656450yes
2013-Q3990256781593yes
2013-Q21414025122615402yes
2013-Q1101002991463291yes
2012-Q4991524572947271yes
2012-Q39801151171801yes
2012-Q212110391373992yes
2012-Q110100268925742yes
2011-Q410921172093701yes
2011-Q3121201311782860yes
2011-Q2650141yes
2011-Q113120310802191yes
2010-Q49946981865870yes
2010-Q31413252761204980yes
2010-Q28702433yes
2010-Q1101029391446191yes
2009-Q45532252654820yes
2009-Q3661248051885220yes
2009-Q210721,01244yes
2009-Q1101016671472771yes
2008-Q4111101892143751yes
2008-Q313120091081631yes
2008-Q2980262063540yes
2008-Q19901152703831yes
2007-Q4880822yes
2007-Q3101004561093861yes
2007-Q24430yes
2007-Q1880296961551yes
2006-Q44410yes
2006-Q34430yes
2006-Q2101001462784662yes
2006-Q155042140yes
2005-Q48801862064922yes
2005-Q33320yes
2005-Q21313007821903yes
2005-Q11100yes
2004-Q42210yes
2004-Q34420yes
2004-Q23330yes
2003-Q43310yes
2003-Q3660030yes
2003-Q2660042yes
2003-Q11110yes
2002-Q47716140yes
2002-Q35501140yes
2002-Q21100yes
2002-Q14430yes
2001-Q43310yes
2001-Q32210yes
2001-Q276019730yes
2001-Q12210yes
2000-Q42210yes
2000-Q31110yes
2000-Q2770010yes
2000-Q13320yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

97 of the 802 kitchen remodel permits filed since 2000 (12%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Chinatown neighborhood

Shown apart, with their own page here: bathroom remodel (823 filed, 547 finished; contractors); kitchen remodel (802 filed, 556 finished; contractors); stairs (431 filed, 289 finished; contractors); roof deck (63 filed, 35 finished; contractors); deck (61 filed, 38 finished; contractors). Other types: 13,839 permits. All permits in San Francisco's Chinatown neighborhood

Nearby neighborhoods

Financial District/South Beach, North Beach, Nob Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.