How long do bathroom remodel permits take in San Francisco's Chinatown neighborhood?

In the Chinatown neighborhood of San Francisco, of the 33 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 4 days a year earlier. Of the 16 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 226 days of being issued, up from 150 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sChinatown neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/chinatown/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202633 issued016 issued4
Permit issued to final sign-offOctober 2023 through September 202416 finished22616 finished150

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41100too recent
2026-Q3161401800too recent
2026-Q2770320too recent
2026-Q16601010too recent
2025-Q4661112310too recent
2025-Q388217551122340too recent
2025-Q23200too recent
2025-Q12210too recent
2024-Q44420too recent
2024-Q35440yes
2024-Q266327052793330yes
2024-Q12210yes
2023-Q411907262083160yes
2023-Q355121031yes
2023-Q2552211441yes
2023-Q15502741yes
2022-Q487136051274932yes
2022-Q3663616241yes
2022-Q2121122681267733yes
2022-Q1111111791244042yes
2021-Q4119197782383951yes
2021-Q36606142yes
2021-Q26605051694291yes
2021-Q111104811393261,0791yes
2020-Q48611520064065961yes
2020-Q37501142yes
2020-Q23321yes
2020-Q13330yes
2019-Q4884046871743511yes
2019-Q3131101491693812yes
2019-Q21010910071442902yes
2019-Q1774324371913220yes
2018-Q4995114861344613yes
2018-Q3121201882207473yes
2018-Q212111306111903350yes
2018-Q188018662940yes
2017-Q4880671161331yes
2017-Q3763850652118411yes
2017-Q2108226044yes
2017-Q1660242yes
2016-Q466016151272931yes
2016-Q31513546192712964yes
2016-Q2981737935341yes
2016-Q1161401594316214yes
2015-Q4121032583668004yes
2015-Q32119188161485883yes
2015-Q213110107532434yes
2015-Q199102381062581yes
2014-Q41211342101982330yes
2014-Q3171705492691,0298yes
2014-Q21211014210247030yes
2014-Q11412013111304381yes
2013-Q498410562077382yes
2013-Q3191802113866235yes
2013-Q23131028281365393yes
2013-Q1101002291563601yes
2012-Q45432yes
2012-Q3131211193226932yes
2012-Q28823851594193yes
2012-Q13321yes
2011-Q46601062004360yes
2011-Q3660040yes
2011-Q2750141yes
2011-Q188038942690yes
2010-Q47703962044660yes
2010-Q31817252892465830yes
2010-Q29823152905321yes
2010-Q11111223101923811yes
2009-Q45523141yes
2009-Q3661243452675220yes
2009-Q28626961361972yes
2009-Q17709351472910yes
2008-Q41212016101093661yes
2008-Q317160012961931yes
2008-Q27700532920yes
2008-Q1770231yes
2007-Q4880721yes
2007-Q37703340yes
2007-Q2660852733760yes
2007-Q188010261183181yes
2006-Q43330yes
2006-Q377019640yes
2006-Q2990051353924yes
2006-Q17705330yes
2005-Q41010017372515001yes
2005-Q31110yes
2005-Q2770022yes
2005-Q188024030yes
2004-Q42210yes
2004-Q33310yes
2004-Q24430yes
2004-Q11101yes
2003-Q43310yes
2003-Q3550040yes
2003-Q24440yes
2003-Q13320yes
2002-Q33320yes
2002-Q24420yes
2001-Q42200yes
2001-Q33310yes
2001-Q24410yes
2001-Q14420yes
2000-Q43320yes
2000-Q31110yes
2000-Q24400yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

108 of the 823 bathroom remodel permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Chinatown neighborhood

Shown apart, with their own page here: bathroom remodel (823 filed, 547 finished; contractors); kitchen remodel (802 filed, 556 finished; contractors); stairs (431 filed, 289 finished; contractors); roof deck (63 filed, 35 finished; contractors); deck (61 filed, 38 finished; contractors). Other types: 13,839 permits. All permits in San Francisco's Chinatown neighborhood

Nearby neighborhoods

Financial District/South Beach, North Beach, Nob Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.