Permit GraphShortlistSan Francisco building permits since 2000

How long do building permits take in each San Francisco neighborhood?

In San Francisco, of the 19,390 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 17,331 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 99 days of being issued, down from 123 days the year before. The city as a whole.

From the city’s permit records, by the quarter each permit was filed. Data as of 22 November 2026. Each neighborhood’s page has the quarter-by-quarter record, a chart to embed and downloads. How this is calculated.

NeighborhoodPermits issued
filed October 2025 through September 2026
Median days to issueA year earlierReached final
filed October 2023 through September 2024
Median days issue to finalThe year beforeNever finaled
since 2000
San Francisco (all)19,3900017,3319912326%
Bayview Hunters Point489045961278521%
Bernal Heights64400593959425%
Castro/Upper Market7060062110313429%
Excelsior42100502689824%
Glen Park277002778013822%
Haight Ashbury4070040610013033%
Hayes Valley352013089012433%
Inner Richmond500004668611330%
Inner Sunset7000062211011727%
Lone Mountain/USF317002649213428%
Marina7220067511614029%
Mission1,077008629211031%
Nob Hill4650040111315835%
Noe Valley795006809814127%
Oceanview/Merced/Ingleside353003586911221%
Outer Mission301002737412122%
Outer Richmond9300087010412526%
Pacific Heights6890061310812732%
Portola21400213639824%
Presidio100433%
Presidio Heights3960029710918431%
Russian Hill4430040910414232%
Seacliff1280012817215123%
Sunset/Parkside1,520001,5658410823%
Twin Peaks2040021210211821%
Visitacion Valley16800146709623%
West of Twin Peaks1,312001,2379913120%
Western Addition307002321029828%
North Beach3261122910613730%
Potrero Hill4241032310713726%
Tenderloin225122399015431%
South of Market4303636313714728%
Chinatown3517537610215227%
Financial District/South Beach2,276731,6339910719%
Japantown10298639110029%
Mission Bay2079616613913223%
Treasure Island2519252020627031%
Lakeshore17028861958827%
Golden Gate Park111104031%
Lincoln Park20318%
McLaren Park33101277123%

A blank median means fewer than 5 permits in the window. “Reached final” counts the permits filed in those quarters that have a final sign-off; the median is measured from the day the permit was issued. 803 of 803,269 permits since 2000 name no neighborhood and are in the city row only.

How this is calculated

Approved means the city issued the permit. On this site “issued” and “approved” mean the same thing: the permit record’s issue date. It is not a final inspection. The first stage counts the days from the filing date to the issue date, over the permits filed in the last four complete quarters, against the four before them.

Final sign-off means the city’s own status for the permit is “complete”, with its completion date. The second stage counts the days from the issue date to the completion date, over permits filed in the last four quarters that ended two or more years ago, so that most have had time to finish. Inspection records are not yet included.

The median is the middle permit: half took less, half more. A median needs at least 5 permits behind it, or it is left blank.

Never finaled is no final sign-off three years after the permit was issued (or filed, if never issued), for a permit that has not expired, been cancelled, withdrawn, revoked, disapproved, denied or suspended. Those permits are in the counts and not in the medians, which therefore understate the real wait.

A permit’s neighborhood is the Analysis Neighborhood the city writes on it. Each neighborhood’s page carries the full note.

For example, permit 202605121139, as the city’s record read in October 2026, was filed on May 12, 2026 and issued on June 12, 2026: 31 days to issue. Its final sign-off is dated September 1, 2026: 81 days from issue to final. Filing to final is not one stage here; the two are counted apart.

How to read these records.