How long do building permits take in each San Francisco neighborhood?
In San Francisco, of the 19,390 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 17,331 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 99 days of being issued, down from 123 days the year before. The city as a whole.
From the city’s permit records, by the quarter each permit was filed. Data as of 22 November 2026. Each neighborhood’s page has the quarter-by-quarter record, a chart to embed and downloads. How this is calculated.
| Neighborhood | Permits issued filed October 2025 through September 2026 | Median days to issue | A year earlier | Reached final filed October 2023 through September 2024 | Median days issue to final | The year before | Never finaled since 2000 |
|---|---|---|---|---|---|---|---|
| San Francisco (all) | 19,390 | 0 | 0 | 17,331 | 99 | 123 | 26% |
| Bayview Hunters Point | 489 | 0 | 4 | 596 | 127 | 85 | 21% |
| Bernal Heights | 644 | 0 | 0 | 593 | 95 | 94 | 25% |
| Castro/Upper Market | 706 | 0 | 0 | 621 | 103 | 134 | 29% |
| Excelsior | 421 | 0 | 0 | 502 | 68 | 98 | 24% |
| Glen Park | 277 | 0 | 0 | 277 | 80 | 138 | 22% |
| Haight Ashbury | 407 | 0 | 0 | 406 | 100 | 130 | 33% |
| Hayes Valley | 352 | 0 | 1 | 308 | 90 | 124 | 33% |
| Inner Richmond | 500 | 0 | 0 | 466 | 86 | 113 | 30% |
| Inner Sunset | 700 | 0 | 0 | 622 | 110 | 117 | 27% |
| Lone Mountain/USF | 317 | 0 | 0 | 264 | 92 | 134 | 28% |
| Marina | 722 | 0 | 0 | 675 | 116 | 140 | 29% |
| Mission | 1,077 | 0 | 0 | 862 | 92 | 110 | 31% |
| Nob Hill | 465 | 0 | 0 | 401 | 113 | 158 | 35% |
| Noe Valley | 795 | 0 | 0 | 680 | 98 | 141 | 27% |
| Oceanview/Merced/Ingleside | 353 | 0 | 0 | 358 | 69 | 112 | 21% |
| Outer Mission | 301 | 0 | 0 | 273 | 74 | 121 | 22% |
| Outer Richmond | 930 | 0 | 0 | 870 | 104 | 125 | 26% |
| Pacific Heights | 689 | 0 | 0 | 613 | 108 | 127 | 32% |
| Portola | 214 | 0 | 0 | 213 | 63 | 98 | 24% |
| Presidio | 10 | 0 | 4 | 33% | |||
| Presidio Heights | 396 | 0 | 0 | 297 | 109 | 184 | 31% |
| Russian Hill | 443 | 0 | 0 | 409 | 104 | 142 | 32% |
| Seacliff | 128 | 0 | 0 | 128 | 172 | 151 | 23% |
| Sunset/Parkside | 1,520 | 0 | 0 | 1,565 | 84 | 108 | 23% |
| Twin Peaks | 204 | 0 | 0 | 212 | 102 | 118 | 21% |
| Visitacion Valley | 168 | 0 | 0 | 146 | 70 | 96 | 23% |
| West of Twin Peaks | 1,312 | 0 | 0 | 1,237 | 99 | 131 | 20% |
| Western Addition | 307 | 0 | 0 | 232 | 102 | 98 | 28% |
| North Beach | 326 | 1 | 1 | 229 | 106 | 137 | 30% |
| Potrero Hill | 424 | 1 | 0 | 323 | 107 | 137 | 26% |
| Tenderloin | 225 | 1 | 2 | 239 | 90 | 154 | 31% |
| South of Market | 430 | 3 | 6 | 363 | 137 | 147 | 28% |
| Chinatown | 351 | 7 | 5 | 376 | 102 | 152 | 27% |
| Financial District/South Beach | 2,276 | 7 | 3 | 1,633 | 99 | 107 | 19% |
| Japantown | 102 | 9 | 8 | 63 | 91 | 100 | 29% |
| Mission Bay | 207 | 9 | 6 | 166 | 139 | 132 | 23% |
| Treasure Island | 25 | 19 | 25 | 20 | 206 | 270 | 31% |
| Lakeshore | 170 | 28 | 8 | 61 | 95 | 88 | 27% |
| Golden Gate Park | 1 | 11 | 10 | 40 | 31% | ||
| Lincoln Park | 2 | 0 | 3 | 18% | |||
| McLaren Park | 3 | 3 | 10 | 127 | 71 | 23% |
A blank median means fewer than 5 permits in the window. “Reached final” counts the permits filed in those quarters that have a final sign-off; the median is measured from the day the permit was issued. 803 of 803,269 permits since 2000 name no neighborhood and are in the city row only.
How this is calculated
Approved means the city issued the permit. On this site “issued” and “approved” mean the same thing: the permit record’s issue date. It is not a final inspection. The first stage counts the days from the filing date to the issue date, over the permits filed in the last four complete quarters, against the four before them.
Final sign-off means the city’s own status for the permit is “complete”, with its completion date. The second stage counts the days from the issue date to the completion date, over permits filed in the last four quarters that ended two or more years ago, so that most have had time to finish. Inspection records are not yet included.
The median is the middle permit: half took less, half more. A median needs at least 5 permits behind it, or it is left blank.
Never finaled is no final sign-off three years after the permit was issued (or filed, if never issued), for a permit that has not expired, been cancelled, withdrawn, revoked, disapproved, denied or suspended. Those permits are in the counts and not in the medians, which therefore understate the real wait.
A permit’s neighborhood is the Analysis Neighborhood the city writes on it. Each neighborhood’s page carries the full note.
For example, permit 202605121139, as the city’s record read in October 2026, was filed on May 12, 2026 and issued on June 12, 2026: 31 days to issue. Its final sign-off is dated September 1, 2026: 81 days from issue to final. Filing to final is not one stage here; the two are counted apart.