How long do building permits take in San Francisco's Russian Hill neighborhood?

In the Russian Hill neighborhood of San Francisco, of the 433 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 408 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 104 days of being issued, down from 142 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's Russian HillneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/russian-hill · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026433 issued0486 issued0
Permit issued to final sign-offOctober 2023 through September 2024408 finished104438 finished142

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q45100too recent
2026-Q3108790151625340too recent
2026-Q21281070405121960too recent
2026-Q111310602677541750too recent
2025-Q415314109780842530too recent
2025-Q311810808271842850too recent
2025-Q214113306395613260too recent
2025-Q1134124053101942760too recent
2024-Q4129121079911123300too recent
2024-Q312311603698973420yes
2024-Q21571470451121083630yes
2024-Q114413301241041063290yes
2023-Q413912707094904285yes
2023-Q317215802813112335233yes
2023-Q215714416411313734827yes
2023-Q11271201919515363920yes
2022-Q415113131639918867324yes
2022-Q311910401188815255315yes
2022-Q214714218511817258917yes
2022-Q1149131011010917356918yes
2021-Q41341242829415569724yes
2021-Q314913907110616673025yes
2021-Q2158147213810818072737yes
2021-Q11621521212311218061435yes
2020-Q413812131618416258940yes
2020-Q3182161612610217863363yes
2020-Q2776851373414639437yes
2020-Q121319701639718270196yes
2019-Q4271256067129237802117yes
2019-Q3279268074117135629146yes
2019-Q2262246054120143654130yes
2019-Q1222214072107166716106yes
2018-Q4226214056104114620104yes
2018-Q33113030101170166688125yes
2018-Q23062890105153165657132yes
2018-Q1267254032123205686132yes
2017-Q4247233080101155744131yes
2017-Q33483320475188183668140yes
2017-Q22702550140144167601105yes
2017-Q120519405488133542104yes
2016-Q420819501729019281499yes
2016-Q32802660244143167792122yes
2016-Q2246233061125177661102yes
2016-Q119919508910618887883yes
2015-Q4238225082123163765100yes
2015-Q3275259058142150581109yes
2015-Q225624508114419661593yes
2015-Q1232222072115136785103yes
2014-Q422921806412212469893yes
2014-Q321621106911515357092yes
2014-Q222522006112613668890yes
2014-Q1173167021979836867yes
2013-Q42051980369811953993yes
2013-Q32192120696109350102yes
2013-Q21971910241109447374yes
2013-Q11831790121147835862yes
2012-Q420519401111211855373yes
2012-Q321320605411915372681yes
2012-Q21991910561249952056yes
2012-Q118017402711910259546yes
2011-Q417817401010610054055yes
2011-Q32162120711911047678yes
2011-Q22162080911114146876yes
2011-Q11571530299611950648yes
2010-Q413313207679840644yes
2010-Q31891820128110556983yes
2010-Q22102010239811453193yes
2010-Q11611530237910345267yes
2009-Q416816408789528972yes
2009-Q317016507628836583yes
2009-Q2169162025896941565yes
2009-Q117216608889035260yes
2008-Q4198192013949434674yes
2008-Q32422330298144286102yes
2008-Q2215206058410334786yes
2008-Q12031970229510133880yes
2007-Q42332250910310034997yes
2007-Q32442360410112226098yes
2007-Q22202150010010338689yes
2007-Q1192190028011230676yes
2006-Q4157150006511834760yes
2006-Q3192189017811843682yes
2006-Q22192090010210430479yes
2006-Q1156150017819226251yes
2005-Q41591580396811429162yes
2005-Q32062000010012134274yes
2005-Q2185184019410035465yes
2005-Q11751710397813336263yes
2004-Q419218703939047367yes
2004-Q324323500929027798yes
2004-Q2196193071038434963yes
2004-Q1144138006110433947yes
2003-Q41511480827311927951yes
2003-Q3190186029810833648yes
2003-Q2161153060808330942yes
2003-Q1161157032789534729yes
2002-Q41471430605411041839yes
2002-Q31681620168410033134yes
2002-Q21311310345911228517yes
2002-Q114513506852913045yes
2001-Q4159149065721005976yes
2001-Q3158156071731234574yes
2001-Q215414903473963342yes
2001-Q112712106956963224yes
2000-Q4150137076581366494yes
2000-Q313913006451263540yes
2000-Q21751690120631224252yes
2000-Q1148142049491395420yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

6,352 of the 19,993 building permits filed since 2000 (32%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Russian Hill neighborhood

Shown apart, with their own page here: bathroom remodel (3,069 filed, 2,224 finished; contractors); kitchen remodel (3,022 filed, 2,219 finished; contractors); stairs (887 filed, 594 finished; contractors); deck (425 filed, 281 finished; contractors); roof deck (310 filed, 176 finished; contractors). Other types: 14,642 permits.

Nearby neighborhoods

Nob Hill, North Beach, Chinatown; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.