How long do building permits take in San Francisco's Bernal Heights neighborhood?

In the Bernal Heights neighborhood of San Francisco, of the 644 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 593 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 95 days of being issued, up from 94 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 23 November 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's BernalHeights neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/bernal-heights · Data as of 23 November 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026644 issued0728 issued0
Permit issued to final sign-offOctober 2023 through September 2024593 finished95528 finished94

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 99 days from issue to final over the same quarters. See every quarter since 2000.

Every quarter since 2000 (108 quarters)

One row for each quarter in which permits were filed, newest first. To see whether permits are getting faster or slower, read the two median columns down the page; “too recent” quarters have not had time to finish, so their medians run low.

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q471410205250too recent
2026-Q31501180283135700too recent
2026-Q218115904475311250too recent
2026-Q1192173048113361700too recent
2025-Q4212194085121472010too recent
2025-Q3191181044133592290too recent
2025-Q2183173072131703110too recent
2025-Q1216205055154822810too recent
2024-Q4177169025127893520too recent
2024-Q31991880571521123920yes
2024-Q2195181036155953230yes
2024-Q1190176031145863830yes
2023-Q420719401081418743322yes
2023-Q32242040411485241160yes
2023-Q221619816315512648143yes
2023-Q116715303711511351137yes
2022-Q418315813791109037041yes
2022-Q318117501291259258341yes
2022-Q218117007912312466138yes
2022-Q1216188014014911041841yes
2021-Q4179166014212714854537yes
2021-Q321119706615815155934yes
2021-Q2205183011014212954933yes
2021-Q1195177027212714769147yes
2020-Q42061741220313613263536yes
2020-Q3229203420514015471769yes
2020-Q2101916765210843542yes
2020-Q122520509612013968285yes
2019-Q42932730286144210800120yes
2019-Q33273060118154163702143yes
2019-Q2317301084176132613124yes
2019-Q1271257057152115636105yes
2018-Q42752580137149175807102yes
2018-Q3338321069192168682122yes
2018-Q2281266050150149495107yes
2018-Q13012760114146142553129yes
2017-Q4268252013015017166992yes
2017-Q3320299052189160530104yes
2017-Q2297283056175111544100yes
2017-Q123422707912014849895yes
2016-Q4289272018716717659697yes
2016-Q3311299059174158607119yes
2016-Q2304289053173148510104yes
2016-Q128026601591711421,08791yes
2015-Q425624609715112948287yes
2015-Q327426203115191368107yes
2015-Q2298283023517511950199yes
2015-Q125624804916710537278yes
2014-Q4253238020115713673179yes
2014-Q3263244010314714560093yes
2014-Q224223508614412248382yes
2014-Q125424406316513053774yes
2013-Q423422606214110350581yes
2013-Q32332260161319433589yes
2013-Q22462370431589056270yes
2013-Q12132050161376835655yes
2012-Q416115301610410231445yes
2012-Q32342220151389838679yes
2012-Q22252160761336940280yes
2012-Q118818106312111544855yes
2011-Q41841770291249241149yes
2011-Q32031960201227323562yes
2011-Q2228217071395235771yes
2011-Q12001860141319136347yes
2010-Q422821602615711234652yes
2010-Q32372280301529341464yes
2010-Q22142070451386542261yes
2010-Q1181175091149637041yes
2009-Q42142060161446837549yes
2009-Q32342300181407035873yes
2009-Q2226221051495637253yes
2009-Q119519001510910739470yes
2008-Q4266259071537734779yes
2008-Q3261252051586635570yes
2008-Q22802670121497736482yes
2008-Q1238227071219133577yes
2007-Q427826801612711538480yes
2007-Q3248238051128233593yes
2007-Q2231226011079127677yes
2007-Q12542480151209826971yes
2006-Q4251248001308433772yes
2006-Q330028902614010431761yes
2006-Q226926404613312343474yes
2006-Q124524204312210835763yes
2005-Q422722204110212035253yes
2005-Q32752700011510936575yes
2005-Q2235225010111010436751yes
2005-Q12292210221109040942yes
2004-Q4235227001129427955yes
2004-Q3305297001698430158yes
2004-Q22232200541359734650yes
2004-Q12402390291049641956yes
2003-Q428828408311090365110yes
2003-Q32552520013810626639yes
2003-Q2246244011277434055yes
2003-Q123623203210510048046yes
2002-Q4300295041117106387100yes
2002-Q333132404717211934746yes
2002-Q22692520811439844917yes
2002-Q12112050501101262907yes
2001-Q419819107385673056yes
2001-Q3198191021921084361yes
2001-Q223422601497973224yes
2001-Q12202110118112804125yes
2000-Q4208201053871013564yes
2000-Q3211206038951493660yes
2000-Q22192090951071834665yes
2000-Q12041860558411352912yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

6,201 of the 25,281 building permits filed since 2000 (25%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 803 of 803,269 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Bernal Heights neighborhood

Shown apart, with their own page here: bathroom remodel (3,713 filed, 2,616 finished; contractors); kitchen remodel (3,003 filed, 2,091 finished; contractors); stairs (2,255 filed, 1,512 finished; contractors); deck (1,276 filed, 825 finished; contractors); roof deck (214 filed, 133 finished; contractors). Other types: 17,993 permits.

What was filed here, by building use

Of 3,840 permits filed in the Bernal Heights neighborhood of San Francisco from October 2021 through September 2026, the largest building uses were single-family homes (56.1%), two-family buildings (27.9%) and apartment buildings (8.0%); 0.3% had no use on record.

What was filed in San Francisco's Bernal Heights neighborhood,by building useSingle-family homes: 2,156 permits (56.1%)Two-family buildings: 1,073 permits (27.9%)Apartment buildings: 309 permits (8.0%)Retail and services: 68 permits (1.8%)Food and drink: 59 permits (1.5%)Health, schools and assembly: 58 permits (1.5%)Everything else: 117 permits (3.0%)Single-family homes2,156 · 56.1%Two-family buildings1,073 · 27.9%Apartment buildings309 · 8.0%Retail and services68 · 1.8%Food and drink59 · 1.5%Health, schools and assembly58 · 1.5%Everything else117 · 3.0%Source: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/bernal-heights · Data as of 23 November 20263,840 permits filed October 2021 through September 2026, by the building use the city wrote on the permit. Withnone, the assessor's class for the parcel where it names a home; otherwise "No use on record".

This chart as an image (SVG) and the numbers as CSV, with the source and date, free to reuse under CC BY 4.0. The sentence names the largest groups that have a name; the table also lists the catch-all groups. The building use is the one the city wrote on the permit; with none, the assessor’s class for the parcel where it names a home. Residential hotels are counted with hotels.

Building usePermits filedShare
Single-family homes2,15656.1%
Two-family buildings1,07327.9%
Apartment buildings3098.0%
Retail and services681.8%
Food and drink591.5%
Health, schools and assembly581.5%
Offices431.1%
Industrial and storage320.8%
Parking and vacant lots180.5%
No use on record130.3%
Other uses110.3%

What was filed here, by project type

Of 3,840 permits filed in the Bernal Heights neighborhood of San Francisco from October 2021 through September 2026, 68.4% matched none of the project types this site names. The most common types were bathroom remodel (8.1% of all permits), stairs (4.7%) and kitchen remodel (4.5%); 11.4% matched more than one type.

What was filed in San Francisco's Bernal Heights neighborhood,by project typeMore than one typeMore than one type: 439 permits (11.4%)439 · 11.4%Bathroom remodelBathroom remodel: 310 permits (8.1%)310 · 8.1%StairsStairs: 179 permits (4.7%)179 · 4.7%Kitchen remodelKitchen remodel: 172 permits (4.5%)172 · 4.5%DeckDeck: 91 permits (2.4%)91 · 2.4%Roof deckRoof deck: 20 permits (0.5%)20 · 0.5%Other typesOther types: 2 permits (0.1%)2 · 0.1%2,627 of 3,840 permits (68.4%) matched none of the project types this site names; they are not drawn as a bar.Source: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/bernal-heights · Data as of 23 November 20263,840 permits filed October 2021 through September 2026, by the project type the site's keyword rules read inthe permit's description. A permit with several types is one bar, "More than one type".

This chart as an image (SVG) and the numbers as CSV, with the source and date, free to reuse under CC BY 4.0. The sentence names the largest groups that have a name; the table also lists the catch-all groups. The project type is what this site’s keyword rules read in the permit’s description, so most permits match none of the types named here; a permit that matches several is counted once, as “more than one type”.

Project typePermits filedShare
No type matched2,62768.4%
More than one type43911.4%
Bathroom remodel3108.1%
Stairs1794.7%
Kitchen remodel1724.5%
Deck912.4%
Roof deck200.5%
Other types20.1%

Nearby neighborhoods

Glen Park, Noe Valley, Portola; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed.

Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. It shows how long a typical permit took: half of the permits that finished did so faster, and a few that took years do not pull it up the way they would an average. It leaves out permits that never finished, so treat it as a floor, not a promise. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.