How long do building permits take in San Francisco's Portola neighborhood?

In the Portola neighborhood of San Francisco, of the 209 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 213 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 63 days of being issued, down from 98 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's PortolaneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/portola · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026209 issued0248 issued0
Permit issued to final sign-offOctober 2023 through September 2024213 finished63192 finished98

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q34534221724400too recent
2026-Q266570930391130too recent
2026-Q1605403532481780too recent
2025-Q4686403842402030too recent
2025-Q3958708362422460too recent
2025-Q2625503046823090too recent
2025-Q1555305739231310too recent
2024-Q4555303646423140too recent
2024-Q3797501359462850yes
2024-Q2766903652423160yes
2024-Q170690953603270yes
2023-Q4645904549915121yes
2023-Q372680349446431818yes
2023-Q274660795510823215yes
2023-Q1616022548962818yes
2022-Q4706301264512734919yes
2022-Q37166048468034217yes
2022-Q25451035397834814yes
2022-Q1114580413914049770yes
2021-Q449450246341283847yes
2021-Q362580304437335913yes
2021-Q2605502894112632213yes
2021-Q162560198368449622yes
2020-Q4817402294810863820yes
2020-Q370634237431201,04619yes
2020-Q21917637311932375yes
2020-Q1646101743321767626yes
2019-Q486790485813640925yes
2019-Q390850404811752130yes
2019-Q286770964914452826yes
2019-Q1807801095612033221yes
2018-Q465590623911943818yes
2018-Q3817501234211048533yes
2018-Q287820645510668923yes
2018-Q165590172328426725yes
2017-Q451460231277039416yes
2017-Q397920163569480835yes
2017-Q275720113389265930yes
2017-Q1787301875115351523yes
2016-Q482760168437736924yes
2016-Q3737001764310545725yes
2016-Q261590923310235620yes
2016-Q174710214613031619yes
2015-Q478750294911234322yes
2015-Q365620554413945615yes
2015-Q2635601003314338320yes
2015-Q162590883414142821yes
2014-Q470560963416837824yes
2014-Q365650209406432121yes
2014-Q253510523313359917yes
2014-Q1535208386048011yes
2013-Q452510224010538411yes
2013-Q36563043412826727yes
2013-Q267650143713147524yes
2013-Q1494904268032422yes
2012-Q455540473210049821yes
2012-Q36260014339771,23618yes
2012-Q25149037319154017yes
2012-Q1444305334912297yes
2011-Q440390122510320513yes
2011-Q35452029276735321yes
2011-Q26059015338029023yes
2011-Q1605706398429217yes
2010-Q411110402,851701491,72133yes
2010-Q3746708524636815yes
2010-Q264630163710034925yes
2010-Q16867012479135218yes
2009-Q45754018355140918yes
2009-Q3676501064112252921yes
2009-Q2807707417229732yes
2009-Q1828004365752842yes
2008-Q412111801484632967yes
2008-Q3797603015016431424yes
2008-Q28280050517125124yes
2008-Q1575405307527220yes
2007-Q4807803465525626yes
2007-Q3868402438919034yes
2007-Q2767200408423923yes
2007-Q1484800249628913yes
2006-Q4736900428023720yes
2006-Q3767401074310436215yes
2006-Q27165003410024619yes
2006-Q16463002710622122yes
2005-Q46261003610431418yes
2005-Q39391060627921516yes
2005-Q280760134111425915yes
2005-Q181770334515331418yes
2004-Q470680169329840620yes
2004-Q384810110367536327yes
2004-Q2777502614910937918yes
2004-Q1585707347725516yes
2003-Q4747200419122318yes
2003-Q37268072377722319yes
2003-Q2676701163611039613yes
2003-Q15858040279824514yes
2002-Q47270023458132715yes
2002-Q3605600318428115yes
2002-Q2838005143553709yes
2002-Q175710384352399342yes
2001-Q4878600401103991yes
2001-Q358550027911650yes
2001-Q27573083461604352yes
2001-Q1696701931742841yes
2000-Q45956069291255822yes
2000-Q3828101452542381yes
2000-Q2848303247653080yes
2000-Q18080032371193440yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

1,823 of the 7,454 building permits filed since 2000 (24%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Portola neighborhood

Shown apart, with their own page here: bathroom remodel (1,260 filed, 951 finished; contractors); kitchen remodel (823 filed, 589 finished; contractors); stairs (364 filed, 246 finished; contractors); deck (327 filed, 234 finished; contractors). Other types: 5,440 permits.

Nearby neighborhoods

McLaren Park, Visitacion Valley, Bayview Hunters Point; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.