How long do building permits take in San Francisco's Bayview Hunters Point neighborhood?

In the Bayview Hunters Point neighborhood of San Francisco, of the 477 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 4 days a year earlier. Of the 595 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 127 days of being issued, up from 84 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's BayviewHunters Point neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/bayview-hunters-point · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026477 issued0869 issued4
Permit issued to final sign-offOctober 2023 through September 2024595 finished127474 finished84

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41260200too recent
2026-Q3108760292010250too recent
2026-Q21681360366829980too recent
2026-Q112210304266401500too recent
2025-Q418116207691672440too recent
2025-Q32001850133120362910too recent
2025-Q22722467315167803760too recent
2025-Q1278267213982061403560too recent
2024-Q4187171170107692850too recent
2024-Q327525810622221182640yes
2024-Q2235228231751862065440yes
2024-Q113011708390914120yes
2023-Q4164140013497844363yes
2023-Q31811640721148841648yes
2023-Q22101951731567240841yes
2023-Q114212601509711761129yes
2022-Q419516503011077028260yes
2022-Q3218168119712519957944yes
2022-Q2186154130611513147347yes
2022-Q1163137018110114944748yes
2021-Q414312761839915152037yes
2021-Q3160149016011112861733yes
2021-Q21671531515310916863746yes
2021-Q11751424331710120484344yes
2020-Q4180156364199917478460yes
2020-Q3183160243441049458458yes
2020-Q2595393253611035315yes
2020-Q118316202158215566576yes
2019-Q42781970291114138858129yes
2019-Q3314275010117913149299yes
2019-Q2247213018314214255375yes
2019-Q123721801331369473673yes
2018-Q424422501611447240566yes
2018-Q326524101131409861091yes
2018-Q2279251012917114652671yes
2018-Q1261237020315311843577yes
2017-Q433130745921021273595yes
2017-Q3261235011115010255385yes
2017-Q2237225013515012449872yes
2017-Q1207188015911913766064yes
2016-Q4213197015012414456667yes
2016-Q3218211132414210355861yes
2016-Q221420009712317074269yes
2016-Q1225210140314710560361yes
2015-Q435733073032504261,13480yes
2015-Q3202183012612415460855yes
2015-Q2196180017512218691550yes
2015-Q1207198126313118689956yes
2014-Q4200187012813513886944yes
2014-Q3205196026911811275262yes
2014-Q2218194013612313042958yes
2014-Q119318505410910146856yes
2013-Q4184175015011112565253yes
2013-Q323222606514312596367yes
2013-Q22192110431478541553yes
2013-Q12001940581398344143yes
2012-Q42212050491309743665yes
2012-Q322621706214510246262yes
2012-Q21791740441178636247yes
2012-Q1253248340109132829117yes
2011-Q4180177010411812654238yes
2011-Q31961870531219251947yes
2011-Q2137132011798536341yes
2011-Q11741660629414097751yes
2010-Q4148138082847472543yes
2010-Q3175161057989578544yes
2010-Q22041880331098138860yes
2010-Q11561450519714669933yes
2009-Q41531470261981551,26036yes
2009-Q3183174010110511248650yes
2009-Q21701570539510536344yes
2009-Q1147139010907836031yes
2008-Q432932106123116380163yes
2008-Q323022404311412254882yes
2008-Q221120001512018839352yes
2008-Q1193179029868638868yes
2007-Q43483330685122369223yes
2007-Q3201194093908447565yes
2007-Q231130104617816057866yes
2007-Q121720804512518946348yes
2006-Q42011900207987657541yes
2006-Q322822006310510443039yes
2006-Q221120007810911131645yes
2006-Q12021920431089047531yes
2005-Q421620501,03111919247236yes
2005-Q3228218024211618846332yes
2005-Q222221701313810830819yes
2005-Q115715501036915137735yes
2004-Q4238197090711120893736yes
2004-Q3182178020987233436yes
2004-Q22122090202949344738yes
2004-Q1156149099858438215yes
2003-Q4189185069949236326yes
2003-Q31891850811069041327yes
2003-Q223522607013910438622yes
2003-Q124624202414511928424yes
2002-Q423421801171297830919yes
2002-Q320920103211118934032yes
2002-Q225324007114710029516yes
2002-Q1238231042119634336yes
2001-Q4425415013255622204yes
2001-Q3336324077152944591yes
2001-Q21701610350821245752yes
2001-Q12212050131781103385yes
2000-Q41941830144721303821yes
2000-Q32812710891201193212yes
2000-Q22101970107911334260yes
2000-Q12712490851131474490yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

4,787 of the 22,817 building permits filed since 2000 (21%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Bayview Hunters Point neighborhood

Shown apart, with their own page here: bathroom remodel (2,453 filed, 1,694 finished; contractors); kitchen remodel (1,911 filed, 1,279 finished; contractors); stairs (1,180 filed, 748 finished; contractors); deck (707 filed, 429 finished; contractors). Other types: 18,226 permits.

Nearby neighborhoods

Portola, Bernal Heights, Visitacion Valley; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.