How long do building permits take in San Francisco's Presidio Heights neighborhood?

In the Presidio Heights neighborhood of San Francisco, of the 387 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 297 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 109 days of being issued, down from 182 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's PresidioHeights neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/presidio-heights · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026387 issued0420 issued0
Permit issued to final sign-offOctober 2023 through September 2024297 finished109298 finished182

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q44000too recent
2026-Q310267055138250too recent
2026-Q21189605239301080too recent
2026-Q111210408052461730too recent
2025-Q412612006084601980too recent
2025-Q313412805485742420too recent
2025-Q2112107084651223380too recent
2025-Q1100911109651232950too recent
2024-Q41019407569853170too recent
2024-Q3107100064761313890yes
2024-Q21211140108821023650yes
2024-Q1979503170874760yes
2023-Q49686074691756322yes
2023-Q31029321126720365630yes
2023-Q212912201469213660718yes
2023-Q17264025611896474yes
2022-Q411911242237823963425yes
2022-Q393880617016760013yes
2022-Q211210711057921878124yes
2022-Q112110901989319770317yes
2021-Q41231131759218466418yes
2021-Q312511832249022277518yes
2021-Q211911041708219573326yes
2021-Q111611131628531786722yes
2020-Q4107100261457614377423yes
2020-Q31089442055814060444yes
2020-Q265526671814140441yes
2020-Q115414801328216256962yes
2019-Q423118809495238906116yes
2019-Q3215207010992188975114yes
2019-Q2225216017102130782111yes
2019-Q11361270226414077763yes
2018-Q41791710497921987487yes
2018-Q31901860609618483183yes
2018-Q21861780288312178193yes
2018-Q11751710457916574184yes
2017-Q42001890359917572089yes
2017-Q3229216029412616974287yes
2017-Q219218406310717561372yes
2017-Q11471420196914466772yes
2016-Q417416701028612056477yes
2016-Q321320807210916161492yes
2016-Q219318603210016043584yes
2016-Q11491420917716868665yes
2015-Q41931850578416071398yes
2015-Q321420707010714075289yes
2015-Q21821730389715366066yes
2015-Q117516907010019460760yes
2014-Q41881750919222662275yes
2014-Q317216603610115672858yes
2014-Q2212203010312115865972yes
2014-Q1146138063808266153yes
2013-Q41591530428912741260yes
2013-Q319619102011115456972yes
2013-Q21631590268912558965yes
2013-Q11351330676812656564yes
2012-Q41561490388818846760yes
2012-Q31721690459716255861yes
2012-Q21471430477618453158yes
2012-Q11361330968313868450yes
2011-Q4110106024556270348yes
2011-Q31611570308814549763yes
2011-Q21761710498912956173yes
2011-Q116415602510116157456yes
2010-Q41591560338513746268yes
2010-Q31651580158714837669yes
2010-Q21771730639912849171yes
2010-Q11301280487313444246yes
2009-Q412412209698440447yes
2009-Q316115606899139459yes
2009-Q2141136013785937643yes
2009-Q1128123012718457446yes
2008-Q4154149097510247263yes
2008-Q3205196029511174486yes
2008-Q21921870148410829484yes
2008-Q11771650138012030370yes
2007-Q4152147065599846974yes
2007-Q3184175014829735482yes
2007-Q218918601809839682yes
2007-Q1165162007812750070yes
2006-Q4165159007213440170yes
2006-Q31941920279412443683yes
2006-Q21741730208610637466yes
2006-Q115815701248711136748yes
2005-Q4171168008810238249yes
2005-Q320520000888828662yes
2005-Q2181179007510538966yes
2005-Q115915500689422656yes
2004-Q416416200838640851yes
2004-Q3192189038912338750yes
2004-Q2193188012938126645yes
2004-Q1148146067717025536yes
2003-Q4151148036636620545yes
2003-Q32072050239819628768yes
2003-Q21811780431039332337yes
2003-Q1111110056559431028yes
2002-Q4109107058509823843yes
2002-Q31461400175618231434yes
2002-Q2150148057729835010yes
2002-Q1126124048619235612yes
2001-Q4112111045531324842yes
2001-Q3118116045581643194yes
2001-Q21371330124861123264yes
2001-Q1103100068641112843yes
2000-Q4122118070721384111yes
2000-Q3134128040671163671yes
2000-Q22011890321231613851yes
2000-Q1187177083832104372yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

5,114 of the 16,388 building permits filed since 2000 (31%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Presidio Heights neighborhood

Shown apart, with their own page here: bathroom remodel (2,186 filed, 1,601 finished; contractors); kitchen remodel (1,790 filed, 1,292 finished; contractors); stairs (954 filed, 639 finished; contractors); deck (617 filed, 395 finished; contractors); roof deck (172 filed, 112 finished; contractors). Other types: 12,277 permits.

Nearby neighborhoods

Presidio, Lone Mountain/USF, Inner Richmond; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.