How long do kitchen remodel permits take in San Francisco's Presidio Heights neighborhood?

In the Presidio Heights neighborhood of San Francisco, of the 50 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 2 days a year earlier. Of the 39 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 258 days of being issued, up from 172 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco'sPresidio Heights neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/presidio-heights/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202650 issued064 issued2
Permit issued to final sign-offOctober 2023 through September 202439 finished25840 finished172

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q3141215010too recent
2026-Q2161504340too recent
2026-Q1121102151281760too recent
2025-Q4121209481082240too recent
2025-Q3121103262062220too recent
2025-Q2171736161783160too recent
2025-Q1141454782113040too recent
2024-Q422222159122483120too recent
2024-Q3161511122132444240yes
2024-Q2101066081763720yes
2024-Q116160125123546420yes
2023-Q488021064056020yes
2023-Q38707564227332yes
2023-Q21717099141112042yes
2023-Q11311020111954461yes
2022-Q41414322791613524yes
2022-Q31312052101603823yes
2022-Q21211113491483121yes
2022-Q115154247152727010yes
2021-Q42020835182355552yes
2021-Q31919365123106293yes
2021-Q21212061102224562yes
2021-Q126250166203665864yes
2020-Q4232238145172709784yes
2020-Q315152168131663422yes
2020-Q28861161964501yes
2020-Q1111133394207492yes
2019-Q426256532222809673yes
2019-Q31715038111211,0015yes
2019-Q22020027181887282yes
2019-Q1161408111433153yes
2018-Q41615262132408311yes
2018-Q317171322161908051yes
2018-Q21616086152107371yes
2018-Q115150144112227003yes
2017-Q41414081121603800yes
2017-Q32424022202106701yes
2017-Q221210349172726873yes
2017-Q118150124141422741yes
2016-Q421190217152457462yes
2016-Q31818080122186473yes
2016-Q22019027151596924yes
2016-Q116150197141276010yes
2015-Q41615018111866202yes
2015-Q32323192142361,0404yes
2015-Q226262276221657281yes
2015-Q1212122341182786261yes
2014-Q41717092152345870yes
2014-Q31818065172931,0451yes
2014-Q22828189242106443yes
2014-Q1121183372387212yes
2013-Q41616056151583111yes
2013-Q32625029222508892yes
2013-Q22424076183007305yes
2013-Q113131150122786291yes
2012-Q427261122242305893yes
2012-Q319190102171884381yes
2012-Q219186160122765075yes
2012-Q119190172172217752yes
2011-Q4660251983611yes
2011-Q32219058171683132yes
2011-Q22121021161263603yes
2011-Q11918034171395331yes
2010-Q42019070152068553yes
2010-Q31616053141503341yes
2010-Q222224180192625242yes
2010-Q11919036143044732yes
2009-Q48808261444122yes
2009-Q31615067112543944yes
2009-Q21211036071534952yes
2009-Q11414316111308402yes
2008-Q42020366144645680yes
2008-Q3262604151533214yes
2008-Q22020016102523512yes
2008-Q118170288131263362yes
2007-Q4161514192103896130yes
2007-Q31818020132533363yes
2007-Q2202001121313984yes
2007-Q1181700111234500yes
2006-Q41919062122664053yes
2006-Q3222200113115395yes
2006-Q2202000181364102yes
2006-Q188012042yes
2005-Q4181800121833581yes
2005-Q31919058111552793yes
2005-Q215150091404830yes
2005-Q1151504691662544yes
2004-Q415150166112454091yes
2004-Q322220115131534523yes
2004-Q2161600102223061yes
2004-Q1141402191312270yes
2003-Q4101006161953562yes
2003-Q31616028141371981yes
2003-Q222220401151815023yes
2003-Q116160081962822yes
2002-Q4990342yes
2002-Q3131208861372932yes
2002-Q2101002771732821yes
2002-Q114140091713211yes
2001-Q4101004261582080yes
2001-Q3990051711950yes
2001-Q211110091963521yes
2001-Q112120103111152410yes
2000-Q41110011872393100yes
2000-Q31313011352167850yes
2000-Q22323047191643130yes
2000-Q1222100131943861yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

181 of the 1,790 kitchen remodel permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Presidio Heights neighborhood

Shown apart, with their own page here: bathroom remodel (2,186 filed, 1,601 finished; contractors); kitchen remodel (1,790 filed, 1,292 finished; contractors); stairs (954 filed, 639 finished; contractors); deck (617 filed, 395 finished; contractors); roof deck (172 filed, 112 finished; contractors). Other types: 12,277 permits. All permits in San Francisco's Presidio Heights neighborhood

Nearby neighborhoods

Presidio, Lone Mountain/USF, Inner Richmond; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.