How long do bathroom remodel permits take in San Francisco's Presidio Heights neighborhood?

In the Presidio Heights neighborhood of San Francisco, of the 61 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 1 day a year earlier. Of the 49 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 250 days of being issued, up from 161 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sPresidio Heights neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/presidio-heights/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202661 issued084 issued1
Permit issued to final sign-offOctober 2023 through September 202449 finished25052 finished161

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q3211603510too recent
2026-Q222180477651010too recent
2026-Q113120751281760too recent
2025-Q41515710391072650too recent
2025-Q3181703872132420too recent
2025-Q22423226141233220too recent
2025-Q12323167142062770too recent
2024-Q421214147122673140too recent
2024-Q321201174172504150yes
2024-Q21714315381784630yes
2024-Q118180100172505960yes
2023-Q41111423473986760yes
2023-Q31514257101894605yes
2023-Q22121039201056260yes
2023-Q11311112111954461yes
2022-Q418177298112545114yes
2022-Q31514030133005122yes
2022-Q22219673141925604yes
2022-Q124242231212586632yes
2021-Q42727027252355822yes
2021-Q322221126153256023yes
2021-Q215150115141724491yes
2021-Q127260158213615675yes
2020-Q420200145153061,0034yes
2020-Q3252513309201594634yes
2020-Q2886485874312yes
2020-Q12322232172406165yes
2019-Q430280192272507341yes
2019-Q325232112213011,0652yes
2019-Q22019056161617162yes
2019-Q11614016131467701yes
2018-Q42221187193438741yes
2018-Q32323065202075472yes
2018-Q22727088241506602yes
2018-Q130302452192637268yes
2017-Q414146135123024581yes
2017-Q325244158202187620yes
2017-Q22323092192197713yes
2017-Q12017014141423853yes
2016-Q430291120242496862yes
2016-Q32323192172126473yes
2016-Q22827049201625087yes
2016-Q119180428161741,0371yes
2015-Q42423051191606622yes
2015-Q32727092211854053yes
2015-Q23937084301716273yes
2015-Q124234220172896343yes
2014-Q43130030262426282yes
2014-Q33129062282138851yes
2014-Q235340250312596902yes
2014-Q1201918202142386584yes
2013-Q42727118231615013yes
2013-Q33534025282366855yes
2013-Q2262609201787025yes
2013-Q12121015619696252yes
2012-Q428271148252405723yes
2012-Q31918035152001,1492yes
2012-Q220205159162765642yes
2012-Q12020080182127692yes
2011-Q41414468101606683yes
2011-Q32725138211483233yes
2011-Q22726084212323602yes
2011-Q1272506241745672yes
2010-Q420190156132389406yes
2010-Q32423178211734102yes
2010-Q23030186251916142yes
2010-Q12323033162404104yes
2009-Q4101004081863601yes
2009-Q32221069161783164yes
2009-Q2161512261121965912yes
2009-Q11111849101888400yes
2008-Q41616566134555580yes
2008-Q3272408152215734yes
2008-Q222220163142704571yes
2008-Q12422029162083402yes
2007-Q422200111133306111yes
2007-Q32120017172463580yes
2007-Q22323026181893974yes
2007-Q1181700111496581yes
2006-Q418180092404504yes
2006-Q3292900212135393yes
2006-Q2212100151113732yes
2006-Q114140109122486430yes
2005-Q4202000121613573yes
2005-Q3222200151192612yes
2005-Q2141400111423481yes
2005-Q12020076151582704yes
2004-Q41616032121924520yes
2004-Q3242400181283582yes
2004-Q2171702681123752yes
2004-Q113130061773361yes
2003-Q413130061722743yes
2003-Q3161600131672931yes
2003-Q225250316151445851yes
2003-Q113130081862302yes
2002-Q4880061061371yes
2002-Q314140091123150yes
2002-Q2151500102062771yes
2002-Q1151506491674421yes
2001-Q49904531yes
2001-Q388027440yes
2001-Q21312011981803091yes
2001-Q17701151742600yes
2000-Q41413062112113960yes
2000-Q3772815861843760yes
2000-Q2151306873003970yes
2000-Q1201800123233911yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

208 of the 2,186 bathroom remodel permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Presidio Heights neighborhood

Shown apart, with their own page here: bathroom remodel (2,186 filed, 1,601 finished; contractors); kitchen remodel (1,790 filed, 1,292 finished; contractors); stairs (954 filed, 639 finished; contractors); deck (617 filed, 395 finished; contractors); roof deck (172 filed, 112 finished; contractors). Other types: 12,277 permits. All permits in San Francisco's Presidio Heights neighborhood

Nearby neighborhoods

Presidio, Lone Mountain/USF, Inner Richmond; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.