How long do building permits take in San Francisco's Lakeshore neighborhood?

In the Lakeshore neighborhood of San Francisco, of the 170 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 28 days, up from 8 days a year earlier. Of the 61 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 95 days of being issued, up from 88 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 23 November 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's LakeshoreneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005006002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/lakeshore · Data as of 23 November 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026170 issued28116 issued8
Permit issued to final sign-offOctober 2023 through September 202461 finished9566 finished88

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 99 days from issue to final over the same quarters. See every quarter since 2000.

Every quarter since 2000 (108 quarters)

One row for each quarter in which permits were filed, newest first. To see whether permits are getting faster or slower, read the two median columns down the page; “too recent” quarters have not had time to finish, so their medians run low.

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q410501810too recent
2026-Q328232857626900too recent
2026-Q240372291620690too recent
2026-Q1272527019231780too recent
2025-Q49985129183371242060too recent
2025-Q35957932539741600too recent
2025-Q2302713104251012340too recent
2025-Q11514047101041690too recent
2024-Q4181838176141822400too recent
2024-Q3242202418403200yes
2024-Q22323134161292660yes
2024-Q12118586131303260yes
2023-Q42020521614732422yes
2023-Q32524619016802746yes
2023-Q2272725720742087yes
2023-Q126251791513443910yes
2022-Q43428102251510327716yes
2022-Q3232362041314140910yes
2022-Q220192194121102347yes
2022-Q1141472569101765012yes
2021-Q41513054101484373yes
2021-Q32827033191364228yes
2021-Q2353432591812330916yes
2021-Q1323066364133425518yes
2020-Q43533492172215139911yes
2020-Q3332940183221803837yes
2020-Q22726371141557667710yes
2020-Q1222082291020062410yes
2019-Q424225482202398552yes
2019-Q321202196151766574yes
2019-Q22625112119904856yes
2019-Q1343214213271439986yes
2018-Q416165429923147yes
2018-Q3302921150201435078yes
2018-Q2323006923733277yes
2018-Q138371269184851519yes
2017-Q419190130141739164yes
2017-Q3262354115926547yes
2017-Q2242101371220235011yes
2017-Q142422532111641520yes
2016-Q4444071002314726317yes
2016-Q37272420318034141yes
2016-Q27774141044728840626yes
2016-Q154520612930656022yes
2015-Q4968514914337568448yes
2015-Q3413971811426466623yes
2015-Q2103101121297030042728yes
2015-Q11071056756225736843yes
2014-Q44949259257618724yes
2014-Q34744059278023417yes
2014-Q26459312454725030813yes
2014-Q135312179177635614yes
2013-Q445414113268031415yes
2013-Q341390219286230811yes
2013-Q25856032427218514yes
2013-Q125242928816883027yes
2012-Q426250831650947yes
2012-Q353500391379945210yes
2012-Q254491554154966yes
2012-Q1292908919721288yes
2011-Q415142391248901yes
2011-Q3171714810501465yes
2011-Q2191805312631272yes
2011-Q1252101417501773yes
2010-Q42624113314643118yes
2010-Q3333106021531627yes
2010-Q22523084133513210yes
2010-Q13329030178124911yes
2009-Q4272504515702409yes
2009-Q32726211517421228yes
2009-Q23938013248426313yes
2009-Q1272702916762926yes
2008-Q42626042021614yes
2008-Q3252205816431285yes
2008-Q24039051249616012yes
2008-Q13636032111223913yes
2007-Q443431272912433710yes
2007-Q348460120326224911yes
2007-Q227270313591237yes
2007-Q1323202617714955yes
2006-Q412412497987920939236yes
2006-Q3222005011993293yes
2006-Q22828085156315512yes
2006-Q1262502711439810yes
2005-Q41616001044906yes
2005-Q32823021451725yes
2005-Q22121028818499yes
2005-Q1141402118608785yes
2004-Q41090551102452yes
2004-Q3222203388711012yes
2004-Q229290381011023112yes
2004-Q13535067157917913yes
2003-Q422210769882177yes
2003-Q33131049155913211yes
2003-Q230270311415824011yes
2003-Q1212146186171063513yes
2002-Q424240258142483645yes
2002-Q31515012082063356yes
2002-Q225250016671713yes
2002-Q1343303521602082yes
2001-Q45944094277121212yes
2001-Q33232027191433810yes
2001-Q24141064241782681yes
2001-Q129290119123104481yes
2000-Q418180111113734032yes
2000-Q321200128721181yes
2000-Q2343304119993232yes
2000-Q1282609817592171yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

981 of the 3,691 building permits filed since 2000 (27%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 803 of 803,269 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Lakeshore neighborhood

Shown apart, with their own page here: kitchen remodel (120 filed, 80 finished; contractors); bathroom remodel (79 filed, 58 finished; contractors); stairs (52 filed, 35 finished; contractors). Other types: 3,464 permits.

What was filed here, by building use

Of 588 permits filed in the Lakeshore neighborhood of San Francisco from October 2021 through September 2026, the largest building uses were retail and services (31.3%), apartment buildings (15.3%) and food and drink (14.8%); 1.0% had no use on record.

What was filed in San Francisco's Lakeshore neighborhood, bybuilding useRetail and services: 184 permits (31.3%)Apartment buildings: 90 permits (15.3%)Food and drink: 87 permits (14.8%)Single-family homes: 78 permits (13.3%)Health, schools and assembly: 63 permits (10.7%)Two-family buildings: 38 permits (6.5%)Everything else: 48 permits (8.2%)Retail and services184 · 31.3%Apartment buildings90 · 15.3%Food and drink87 · 14.8%Single-family homes78 · 13.3%Health, schools and assembly63 · 10.7%Two-family buildings38 · 6.5%Everything else48 · 8.2%Source: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/lakeshore · Data as of 23 November 2026588 permits filed October 2021 through September 2026, by the building use the city wrote on the permit. Withnone, the assessor's class for the parcel where it names a home; otherwise "No use on record".

This chart as an image (SVG) and the numbers as CSV, with the source and date, free to reuse under CC BY 4.0. The sentence names the largest groups that have a name; the table also lists the catch-all groups. The building use is the one the city wrote on the permit; with none, the assessor’s class for the parcel where it names a home. Residential hotels are counted with hotels.

Building usePermits filedShare
Retail and services18431.3%
Apartment buildings9015.3%
Food and drink8714.8%
Single-family homes7813.3%
Health, schools and assembly6310.7%
Two-family buildings386.5%
Other uses223.7%
Offices81.4%
Parking and vacant lots71.2%
No use on record61.0%
Industrial and storage50.9%

What was filed here, by project type

Of 588 permits filed in the Lakeshore neighborhood of San Francisco from October 2021 through September 2026, 93.0% matched none of the project types this site names. The most common types were kitchen remodel (3.1% of all permits), bathroom remodel (1.4%) and stairs (1.2%); 0.7% matched more than one type.

What was filed in San Francisco's Lakeshore neighborhood, byproject typeKitchen remodelKitchen remodel: 18 permits (3.1%)18 · 3.1%Bathroom remodelBathroom remodel: 8 permits (1.4%)8 · 1.4%StairsStairs: 7 permits (1.2%)7 · 1.2%More than one typeMore than one type: 4 permits (0.7%)4 · 0.7%Other typesOther types: 4 permits (0.7%)4 · 0.7%547 of 588 permits (93.0%) matched none of the project types this site names; they are not drawn as a bar.Source: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/lakeshore · Data as of 23 November 2026588 permits filed October 2021 through September 2026, by the project type the site's keyword rules read in thepermit's description. A permit with several types is one bar, "More than one type".

This chart as an image (SVG) and the numbers as CSV, with the source and date, free to reuse under CC BY 4.0. The sentence names the largest groups that have a name; the table also lists the catch-all groups. The project type is what this site’s keyword rules read in the permit’s description, so most permits match none of the types named here; a permit that matches several is counted once, as “more than one type”.

Project typePermits filedShare
No type matched54793.0%
Kitchen remodel183.1%
Bathroom remodel81.4%
Stairs71.2%
More than one type40.7%
Other types40.7%

Nearby neighborhoods

Oceanview/Merced/Ingleside, West of Twin Peaks, Sunset/Parkside; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed.

Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. It shows how long a typical permit took: half of the permits that finished did so faster, and a few that took years do not pull it up the way they would an average. It leaves out permits that never finished, so treat it as a floor, not a promise. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.