Permit GraphShortlistSan Francisco building permits since 2000

How long do building permits take in San Francisco's Oceanview/Merced/Ingleside neighborhood?

In the Oceanview/Merced/Ingleside neighborhood of San Francisco, of the 345 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 357 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 69 days of being issued, down from 112 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco'sOceanview/Merced/Ingleside neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/oceanview-merced-ingleside · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026345 issued0499 issued0
Permit issued to final sign-offOctober 2023 through September 2024357 finished69314 finished112

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q48200too recent
2026-Q376470181125490too recent
2026-Q298850234128840too recent
2026-Q1998806060421610too recent
2025-Q413812502788622390too recent
2025-Q312611505584582160too recent
2025-Q214113304997472380too recent
2025-Q1130126038103472410too recent
2024-Q413412505196623140too recent
2024-Q3151140036105683170yes
2024-Q213112305095413200yes
2024-Q1112106014831114290yes
2023-Q410810106274483112yes
2023-Q311711102857910940326yes
2023-Q214112908210312652231yes
2023-Q19385035589463126yes
2022-Q41101010837411260021yes
2022-Q395830105608731022yes
2022-Q2988801016211248423yes
2022-Q112110201047612257032yes
2021-Q41221100668513249628yes
2021-Q312911701068410858225yes
2021-Q2928203605311851425yes
2021-Q180680233587560214yes
2020-Q4938201776011066419yes
2020-Q3113100190678346430yes
2020-Q246404832916641010yes
2020-Q11149702736115347030yes
2019-Q41361210806523775947yes
2019-Q316415301739011662857yes
2019-Q214312901758215469344yes
2019-Q1119106042708665434yes
2018-Q411710401407313141232yes
2018-Q3152133037767647159yes
2018-Q21501390648513134256yes
2018-Q1142131067788439851yes
2017-Q413012301168212552939yes
2017-Q31561480369010247556yes
2017-Q21371300200767640050yes
2017-Q1112105044618334934yes
2016-Q4144133048769334051yes
2016-Q314013601288412067048yes
2016-Q211010501127311150836yes
2016-Q1928801405810966626yes
2015-Q41391300607711053643yes
2015-Q3134134042809052252yes
2015-Q21431330897510545749yes
2015-Q11211120515512748354yes
2014-Q41201160476812437943yes
2014-Q31461400136898351343yes
2014-Q21241190888310237935yes
2014-Q11141100418014865225yes
2013-Q4152150050310813254440yes
2013-Q31161110188310435325yes
2013-Q27975024539341019yes
2013-Q19593016649639427yes
2012-Q413613403141041001,10624yes
2012-Q3106105023727837527yes
2012-Q210499012717136426yes
2012-Q19594026706432918yes
2011-Q411011003707430632yes
2011-Q311511004767827023yes
2011-Q2119115039787827231yes
2011-Q19492071689226922yes
2010-Q4737106514936414yes
2010-Q3106104053726032722yes
2010-Q2116110011788835929yes
2010-Q1127124015837635527yes
2009-Q412011304687252342yes
2009-Q312111708847229827yes
2009-Q212111805637520844yes
2009-Q112612002505824162yes
2008-Q410410306678933228yes
2008-Q315414804879730048yes
2008-Q214914003958721334yes
2008-Q1121119066910242034yes
2007-Q414214008898538246yes
2007-Q316115703898731152yes
2007-Q213413301779755939yes
2007-Q1115109036586039230yes
2006-Q412011800716418224yes
2006-Q315714600858340029yes
2006-Q213413300818226333yes
2006-Q11311310130817829431yes
2005-Q41181130123579832139yes
2005-Q314714401968310639331yes
2005-Q2149142032948029423yes
2005-Q112312000767024820yes
2004-Q4134128047911630720yes
2004-Q3184182031236226628yes
2004-Q2228228091696022114yes
2004-Q1197194011284217028yes
2003-Q420720402061555028221yes
2003-Q317517201301078035019yes
2003-Q2212207011425029928yes
2003-Q11771700141158328320yes
2002-Q41651560251029237326yes
2002-Q313612904138310035818yes
2002-Q215314905861102685yes
2002-Q11251250181731133765yes
2001-Q41251210157541464265yes
2001-Q312211806758944313yes
2001-Q21111060180491684990yes
2001-Q18885048421433611yes
2000-Q41091060154421203661yes
2000-Q31341320159521565991yes
2000-Q211011001653863170yes
2000-Q1109105043301265390yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

2,793 of the 13,592 building permits filed since 2000 (21%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Oceanview/Merced/Ingleside neighborhood

Shown apart, with their own page here: bathroom remodel (2,842 filed, 2,115 finished; contractors); kitchen remodel (2,071 filed, 1,499 finished; contractors); stairs (917 filed, 606 finished; contractors); deck (605 filed, 389 finished; contractors). Other types: 9,103 permits.

Nearby neighborhoods

Outer Mission, Lakeshore, West of Twin Peaks; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.