How long do bathroom remodel permits take in San Francisco's Oceanview/Merced/Ingleside neighborhood?

In the Oceanview/Merced/Ingleside neighborhood of San Francisco, of the 82 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 4 days, down from 9 days a year earlier. Of the 55 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 190 days of being issued, down from 218 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sOceanview/Merced/Ingleside neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/oceanview-merced-ingleside/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202682 issued489 issued9
Permit issued to final sign-offOctober 2023 through September 202455 finished19066 finished218

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42000too recent
2026-Q3301441900too recent
2026-Q2211924040too recent
2026-Q12622156012941840too recent
2025-Q43027155201632840too recent
2025-Q32725071161562830too recent
2025-Q2252216112142123500too recent
2025-Q119188144131063030too recent
2024-Q427241740212013870too recent
2024-Q3282513192162064000yes
2024-Q2201714167142025580yes
2024-Q122179187151905820yes
2023-Q4121106210903291yes
2023-Q321191110152685053yes
2023-Q22926877222453837yes
2023-Q12319071131946826yes
2022-Q423193114161986864yes
2022-Q329250303171573334yes
2022-Q218167170121624533yes
2022-Q12520242181814466yes
2021-Q42725574222666604yes
2021-Q332306282212026827yes
2021-Q224233577151743885yes
2021-Q1151365430114198543yes
2020-Q4242249322162637805yes
2020-Q3262212304132459137yes
2020-Q216144122132364251yes
2020-Q128258439191804654yes
2019-Q433304117213858053yes
2019-Q3262316769193548443yes
2019-Q2413611254252577448yes
2019-Q12316120131688085yes
2018-Q424195169172324572yes
2018-Q3312614120212313654yes
2018-Q241350210322063704yes
2018-Q13732616627973794yes
2017-Q4302914301271566750yes
2017-Q333331202251733537yes
2017-Q233315430232104136yes
2017-Q1272222225161743486yes
2016-Q433325326241574515yes
2016-Q331314137242347067yes
2016-Q224227281202506044yes
2016-Q128265292192607855yes
2015-Q42525378202521,0063yes
2015-Q32828239222645654yes
2015-Q231306251242819435yes
2015-Q130265204191941,1185yes
2014-Q438371177281624336yes
2014-Q333303307231307675yes
2014-Q22927141232173594yes
2014-Q13936248302366744yes
2013-Q43736162291484147yes
2013-Q32828427221733396yes
2013-Q229272168231027822yes
2013-Q11818130161222202yes
2012-Q4272711425994352yes
2012-Q32222121201443842yes
2012-Q23431111281043313yes
2012-Q12929129261064003yes
2011-Q42727025211142961yes
2011-Q3222106191251941yes
2011-Q22421014191413271yes
2011-Q12121122191202832yes
2010-Q410901693245280yes
2010-Q3242338617942511yes
2010-Q235352146351182900yes
2010-Q126262132191183583yes
2009-Q42928111221546864yes
2009-Q3212118181042682yes
2009-Q2323207241181885yes
2009-Q1121104101692681yes
2008-Q41616090151333111yes
2008-Q3282708201572762yes
2008-Q2272504221362231yes
2008-Q12726026171834453yes
2007-Q4323005251333175yes
2007-Q3221900141522653yes
2007-Q2202005171543191yes
2007-Q112100647713022yes
2006-Q4191800121362662yes
2006-Q3222100152585791yes
2006-Q2242303920992571yes
2006-Q12727049211212821yes
2005-Q41313045101603101yes
2005-Q326260282181513973yes
2005-Q2252500201413702yes
2005-Q114140247122045291yes
2004-Q4252400191393012yes
2004-Q358580055632802yes
2004-Q274740069621251yes
2004-Q146450042571621yes
2003-Q465650160311831yes
2003-Q333330027701781yes
2003-Q277760173492281yes
2003-Q142420036852112yes
2002-Q42928024251132301yes
2002-Q318170353131763681yes
2002-Q22424018171622472yes
2002-Q11111007771900yes
2001-Q41110016481804060yes
2001-Q31917023101703091yes
2001-Q2141405681531800yes
2001-Q18803562283260yes
2000-Q47702320yes
2000-Q31312013361582581yes
2000-Q27701451474150yes
2000-Q13310yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

274 of the 2,842 bathroom remodel permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Oceanview/Merced/Ingleside neighborhood

Shown apart, with their own page here: bathroom remodel (2,842 filed, 2,115 finished; contractors); kitchen remodel (2,071 filed, 1,499 finished; contractors); stairs (917 filed, 606 finished; contractors); deck (605 filed, 389 finished; contractors). Other types: 9,103 permits. All permits in San Francisco's Oceanview/Merced/Ingleside neighborhood

Nearby neighborhoods

Outer Mission, Lakeshore, West of Twin Peaks; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.