Permit GraphShortlistSan Francisco building permits since 2000

How long do building permits take in San Francisco's Treasure Island neighborhood?

In the Treasure Island neighborhood of San Francisco, of the 23 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 19 days, down from 26 days a year earlier. Of the 20 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 206 days of being issued, down from 270 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's TreasureIsland neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02505007501000125015002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/treasure-island · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202623 issued1920 issued26
Permit issued to final sign-offOctober 2023 through September 202420 finished20634 finished270

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q385142200too recent
2026-Q286146010too recent
2026-Q198244210too recent
2025-Q46440too recent
2025-Q387724520too recent
2025-Q25420too recent
2025-Q14400too recent
2024-Q455168330too recent
2024-Q33320yes
2024-Q2982711381683180yes
2024-Q1211501940yes
2023-Q487215862064000yes
2023-Q317158120632055810yes
2023-Q2242276407142925489yes
2023-Q1668216842yes
2022-Q4201933246102966768yes
2022-Q317141120985781,0608yes
2022-Q2282563181204128455yes
2022-Q1762814333yes
2021-Q41414119261536468yes
2021-Q3129257129yes
2021-Q26610215233yes
2021-Q15441yes
2020-Q45331yes
2020-Q34431yes
2020-Q2161695514131341343yes
2020-Q13312yes
2019-Q4131030171351,1331,1627yes
2019-Q32220yes
2019-Q213447yes
2019-Q1135272753153156yes
2018-Q46615216261,4261,5760yes
2018-Q34322yes
2018-Q22111yes
2018-Q15431yes
2017-Q46441yes
2017-Q33321yes
2017-Q2656027541yes
2017-Q11101yes
2016-Q44420yes
2016-Q31101yes
2016-Q24312yes
2016-Q17450yes
2015-Q487025744yes
2015-Q32211yes
2015-Q25422yes
2015-Q12202yes
2014-Q43312yes
2014-Q32111yes
2014-Q255098532yes
2014-Q13321yes
2013-Q47702116yes
2013-Q35553241yes
2013-Q22220yes
2013-Q11110yes
2012-Q22101yes
2011-Q31001yes
2011-Q12000yes
2010-Q3555541yes
2010-Q21101yes
2009-Q31101yes
2009-Q21101yes
2008-Q31101yes
2004-Q41110yes
2002-Q21100yes
2002-Q12200yes
2001-Q41100yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

133 of the 432 building permits filed since 2000 (31%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Treasure Island neighborhood

No project type has 30 or more finished permits here, so the types are not shown apart. Citywide, by type: roof deck, pergola or trellis, deck, stairs, kitchen remodel, bathroom remodel.

Nearby neighborhoods

North Beach, Chinatown, Financial District/South Beach; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.