Permit GraphShortlistSan Francisco building permits since 2000

How long do building permits take in San Francisco's Mission Bay neighborhood?

In the Mission Bay neighborhood of San Francisco, of the 207 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 9 days, up from 6 days a year earlier. Of the 166 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 139 days of being issued, up from 132 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 23 November 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's Mission BayneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002503002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/mission-bay · Data as of 23 November 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026207 issued9284 issued6
Permit issued to final sign-offOctober 2023 through September 2024166 finished139152 finished132

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 99 days from issue to final over the same quarters. See every quarter since 2000.

Every quarter since 2000 (108 quarters)

One row for each quarter in which permits were filed, newest first. To see whether permits are getting faster or slower, read the two median columns down the page; “too recent” quarters have not had time to finish, so their medians run low.

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q4201402310too recent
2026-Q34331436541590too recent
2026-Q2464012761440720too recent
2026-Q1615579025821580too recent
2025-Q4908114183411172670too recent
2025-Q37976456551343230too recent
2025-Q2847812121501123590too recent
2025-Q16463576411314350too recent
2024-Q47367494481113320too recent
2024-Q379751469631162630yes
2024-Q2363119113301633810yes
2024-Q158475120331193750yes
2023-Q4694802394013433419yes
2023-Q366595924313146519yes
2023-Q26154141164116639814yes
2023-Q148430195321266758yes
2022-Q45950111243613379817yes
2022-Q3796861264913152427yes
2022-Q287732805613072621yes
2022-Q168657735114639013yes
2021-Q483751426412149916yes
2021-Q31141040728516748523yes
2021-Q28173311226414232010yes
2021-Q19383342206317676025yes
2020-Q4114105472388013551526yes
2020-Q3134117431578920454030yes
2020-Q2373766184281566039yes
2020-Q113913302077623443459yes
2019-Q4196182212111926770865yes
2019-Q3248230410014021468288yes
2019-Q2194184211211625682569yes
2019-Q118016737110813373858yes
2018-Q41641591759112689266yes
2018-Q316615828810715889251yes
2018-Q213512211937314894649yes
2018-Q11281233616318082061yes
2017-Q41251220797016094251yes
2017-Q31041021786716984036yes
2017-Q21221130636615179546yes
2017-Q11121070647711145530yes
2016-Q41231160668610893629yes
2016-Q310510061016215286038yes
2016-Q21201133167731521,20042yes
2016-Q11281210568211845739yes
2015-Q4145134160851371,11350yes
2015-Q31009631286712692329yes
2015-Q21271184807423156546yes
2015-Q194900336017679529yes
2014-Q496923113582101,15534yes
2014-Q31211122718311265728yes
2014-Q21191091728410045425yes
2014-Q1888741266110361523yes
2013-Q4959261077014476322yes
2013-Q3888441086118382223yes
2013-Q268655114471411,01116yes
2013-Q18681221599861321yes
2012-Q461591584010185217yes
2012-Q364600573911480220yes
2012-Q279771435311381323yes
2012-Q17978034497493922yes
2011-Q45755270371401,31418yes
2011-Q38986080669057821yes
2011-Q2504701639663305yes
2011-Q16967013578461810yes
2010-Q486811515310520827yes
2010-Q3555133442827496yes
2010-Q27368393479720815yes
2010-Q164600694610234210yes
2009-Q4626111156342093yes
2009-Q35353141428531610yes
2009-Q26864036531062389yes
2009-Q17667039448434123yes
2008-Q482790196511533313yes
2008-Q384820635411344818yes
2008-Q21161110238012434527yes
2008-Q184820325010952316yes
2007-Q469681693220662022yes
2007-Q39592022549046527yes
2007-Q272720583811927923yes
2007-Q1807901064119646018yes
2006-Q41101080445919335919yes
2006-Q312312101444918274632yes
2006-Q21039501074320252321yes
2006-Q179760473227478118yes
2005-Q47572057376898619yes
2005-Q3127126040988736918yes
2005-Q21411400408910663131yes
2005-Q17473076419664716yes
2004-Q475730975010877510yes
2004-Q31071010666714541519yes
2004-Q258570473415232211yes
2004-Q16261077391284978yes
2003-Q447450177261064968yes
2003-Q361560102421163085yes
2003-Q26665098408740610yes
2003-Q19494044565830024yes
2002-Q45046074311783983yes
2002-Q37675064539170412yes
2002-Q26765050421623433yes
2002-Q150470140233087671yes
2001-Q45855262271543545yes
2001-Q35649495252555192yes
2001-Q2737113147292377214yes
2001-Q162540112261847041yes
2000-Q474701080361881,5673yes
2000-Q375734123273168473yes
2000-Q2867430101453502,1443yes
2000-Q15550012895711,7511yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

2,213 of the 9,593 building permits filed since 2000 (23%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 803 of 803,269 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Mission Bay neighborhood

Shown apart, with their own page here: bathroom remodel (505 filed, 382 finished; contractors); kitchen remodel (469 filed, 354 finished; contractors); stairs (168 filed, 125 finished; contractors). Other types: 8,716 permits.

What was filed here, by building use

Of 1,333 permits filed in the Mission Bay neighborhood of San Francisco from October 2021 through September 2026, the largest building uses were offices (47.6%), apartment buildings (15.2%) and food and drink (10.1%); 1.4% had no use on record.

What was filed in San Francisco's Mission Bay neighborhood, bybuilding useOffices: 634 permits (47.6%)Apartment buildings: 203 permits (15.2%)Food and drink: 134 permits (10.1%)Retail and services: 112 permits (8.4%)Health, schools and assembly: 111 permits (8.3%)Other uses: 44 permits (3.3%)Everything else: 95 permits (7.1%)Offices634 · 47.6%Apartment buildings203 · 15.2%Food and drink134 · 10.1%Retail and services112 · 8.4%Health, schools and assembly111 · 8.3%Other uses44 · 3.3%Everything else95 · 7.1%Source: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/mission-bay · Data as of 23 November 20261,333 permits filed October 2021 through September 2026, by the building use the city wrote on the permit. Withnone, the assessor's class for the parcel where it names a home; otherwise "No use on record".

This chart as an image (SVG) and the numbers as CSV, with the source and date, free to reuse under CC BY 4.0. The sentence names the largest groups that have a name; the table also lists the catch-all groups. The building use is the one the city wrote on the permit; with none, the assessor’s class for the parcel where it names a home. Residential hotels are counted with hotels.

Building usePermits filedShare
Offices63447.6%
Apartment buildings20315.2%
Food and drink13410.1%
Retail and services1128.4%
Health, schools and assembly1118.3%
Other uses443.3%
Industrial and storage403.0%
Parking and vacant lots251.9%
No use on record191.4%
Hotels110.8%

What was filed here, by project type

Of 1,333 permits filed in the Mission Bay neighborhood of San Francisco from October 2021 through September 2026, 88.1% matched none of the project types this site names. The most common types were bathroom remodel (3.4% of all permits), kitchen remodel (3.3%) and stairs (1.7%); 2.7% matched more than one type.

What was filed in San Francisco's Mission Bay neighborhood, byproject typeBathroom remodelBathroom remodel: 45 permits (3.4%)45 · 3.4%Kitchen remodelKitchen remodel: 44 permits (3.3%)44 · 3.3%More than one typeMore than one type: 36 permits (2.7%)36 · 2.7%StairsStairs: 23 permits (1.7%)23 · 1.7%Other typesOther types: 11 permits (0.8%)11 · 0.8%1,174 of 1,333 permits (88.1%) matched none of the project types this site names; they are not drawn as a bar.Source: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.www.permitgraph.org/neighborhoods/mission-bay · Data as of 23 November 20261,333 permits filed October 2021 through September 2026, by the project type the site's keyword rules read inthe permit's description. A permit with several types is one bar, "More than one type".

This chart as an image (SVG) and the numbers as CSV, with the source and date, free to reuse under CC BY 4.0. The sentence names the largest groups that have a name; the table also lists the catch-all groups. The project type is what this site’s keyword rules read in the permit’s description, so most permits match none of the types named here; a permit that matches several is counted once, as “more than one type”.

Project typePermits filedShare
No type matched1,17488.1%
Bathroom remodel453.4%
Kitchen remodel443.3%
More than one type362.7%
Stairs231.7%
Other types110.8%

Nearby neighborhoods

South of Market, Potrero Hill, Financial District/South Beach; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed.

Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. It shows how long a typical permit took: half of the permits that finished did so faster, and a few that took years do not pull it up the way they would an average. It leaves out permits that never finished, so treat it as a floor, not a promise. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.