How long do bathroom remodel permits take in San Francisco's Mission Bay neighborhood?

In the Mission Bay neighborhood of San Francisco, of the 13 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 12 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 150 days of being issued, up from 26 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sMission Bay neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002503002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/mission-bay/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202613 issued09 issued0
Permit issued to final sign-offOctober 2023 through September 202412 finished15014 finished26

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41100too recent
2026-Q36511020too recent
2026-Q24320too recent
2026-Q11110too recent
2025-Q44420too recent
2025-Q33220too recent
2025-Q24320too recent
2025-Q14420too recent
2024-Q31110yes
2024-Q22220yes
2024-Q13330yes
2023-Q477154261533020yes
2023-Q33321yes
2023-Q23330yes
2023-Q16503841yes
2022-Q47618451071191yes
2022-Q3880681015230yes
2022-Q23330yes
2022-Q11110yes
2021-Q4660242yes
2021-Q3550051673450yes
2021-Q23321yes
2021-Q1550041yes
2020-Q41110yes
2020-Q34321yes
2020-Q255203741yes
2020-Q13312yes
2019-Q44422yes
2019-Q325250016141668yes
2019-Q2262400132210011yes
2019-Q13030002920991yes
2018-Q413120172121086080yes
2018-Q3101049082669872yes
2018-Q24440yes
2018-Q16602242yes
2017-Q44431yes
2017-Q34422yes
2017-Q2660661863140yes
2017-Q1550925702440yes
2016-Q44312yes
2016-Q36602452184811yes
2016-Q2770951173602yes
2016-Q111110010572391yes
2015-Q41110yes
2015-Q32220yes
2015-Q23330yes
2015-Q1550552475810yes
2014-Q43330yes
2014-Q33320yes
2014-Q266085731381yes
2014-Q13320yes
2013-Q45554941yes
2013-Q32220yes
2013-Q22220yes
2013-Q12220yes
2012-Q44440yes
2012-Q32220yes
2012-Q24431yes
2012-Q15504031yes
2011-Q45505841yes
2011-Q22220yes
2011-Q17701377904670yes
2010-Q42110yes
2010-Q32220yes
2010-Q24440yes
2010-Q12220yes
2009-Q41110yes
2009-Q32220yes
2009-Q21110yes
2009-Q12220yes
2008-Q42220yes
2008-Q33330yes
2008-Q11110yes
2007-Q43330yes
2007-Q34431yes
2007-Q23311yes
2007-Q11110yes
2006-Q4550020yes
2006-Q32210yes
2006-Q2550020yes
2006-Q1990710yes
2005-Q41110yes
2005-Q349493342861237yes
2005-Q2424100311001259yes
2005-Q12220yes
2004-Q42210yes
2004-Q31110yes
2004-Q21110yes
2004-Q12210yes
2003-Q41110yes
2003-Q31110yes
2003-Q24421yes
2002-Q41110yes
2002-Q32211yes
2002-Q22220yes
2001-Q41110yes
2001-Q11110yes
2000-Q21000yes
2000-Q12100yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

71 of the 504 bathroom remodel permits filed since 2000 (14%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Mission Bay neighborhood

Shown apart, with their own page here: bathroom remodel (504 filed, 382 finished; contractors); kitchen remodel (469 filed, 353 finished; contractors); stairs (168 filed, 125 finished; contractors). Other types: 8,702 permits. All permits in San Francisco's Mission Bay neighborhood

Nearby neighborhoods

South of Market, Potrero Hill, Financial District/South Beach; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.