How long do building permits take in San Francisco's Inner Sunset neighborhood?

In the Inner Sunset neighborhood of San Francisco, of the 685 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 621 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 110 days of being issued, down from 117 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's Inner SunsetneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/inner-sunset · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026685 issued0829 issued0
Permit issued to final sign-offOctober 2023 through September 2024621 finished110503 finished117

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q48410too recent
2026-Q31611180231822550too recent
2026-Q21941630428234960too recent
2026-Q1202191039132491590too recent
2025-Q4231213043150661980too recent
2025-Q3201193043143461970too recent
2025-Q2238235035190722330too recent
2025-Q1220209040171782960too recent
2024-Q4201192051147872680too recent
2024-Q3237227047171993390yes
2024-Q2207198041154923180yes
2024-Q12021910351631233830yes
2023-Q417216401481331304784yes
2023-Q31961890371519437427yes
2023-Q219117909313810849031yes
2023-Q117316005610911750445yes
2022-Q4159143013510517849832yes
2022-Q3162159012713114360920yes
2022-Q219018006813413243640yes
2022-Q1203190012214717374337yes
2021-Q418016203912813046934yes
2021-Q319718307112811858549yes
2021-Q2180167011012715371434yes
2021-Q1175168014212011641246yes
2020-Q4176161021212815253232yes
2020-Q3194169518510911868767yes
2020-Q28976462507143934yes
2020-Q1225210014211318468888yes
2019-Q42792420119129167625123yes
2019-Q333431203815898565140yes
2019-Q2296284019154100570127yes
2019-Q1256245079131221813109yes
2018-Q4265249086144124850100yes
2018-Q3277259051139107474113yes
2018-Q22902780143140118433126yes
2018-Q12372260103120150595103yes
2017-Q42942850122171105571109yes
2017-Q33583420302208178838120yes
2017-Q22972870115179127509102yes
2017-Q1231220012612611155786yes
2016-Q42802660104156134524104yes
2016-Q33113040105176133758117yes
2016-Q2311302049184112596108yes
2016-Q123222007413311374381yes
2015-Q4263257037133143512113yes
2015-Q3283268011316815258497yes
2015-Q2264247010215710140190yes
2015-Q126325304515312446399yes
2014-Q421721003913214352972yes
2014-Q325424303415612254581yes
2014-Q223522504515111365470yes
2014-Q12041960221349737357yes
2013-Q423623002613711438282yes
2013-Q32332260191429238574yes
2013-Q2255251071589740880yes
2013-Q120620201012510742767yes
2012-Q42102090241357735066yes
2012-Q32302220101569839455yes
2012-Q2220218071448842968yes
2012-Q11761720121207635343yes
2011-Q4228226081337036577yes
2011-Q32642610161618335789yes
2011-Q22081980261377735550yes
2011-Q11971920101215632259yes
2010-Q42092030151269035168yes
2010-Q32612560201419636897yes
2010-Q22722660413571291111yes
2010-Q1198190071265642656yes
2009-Q42162130191438032757yes
2009-Q3248243061405034987yes
2009-Q21851800391016742168yes
2009-Q1211205071108034487yes
2008-Q4227219071279332476yes
2008-Q32932820314487316111yes
2008-Q22612590121456826394yes
2008-Q12332230111218335092yes
2007-Q426725001010598311128yes
2007-Q33143060513980380131yes
2007-Q23073020015886376108yes
2007-Q12962900221688037085yes
2006-Q4244239001348234952yes
2006-Q3292287001608624860yes
2006-Q22812770441529031253yes
2006-Q1236234001277127069yes
2005-Q4230225001219027976yes
2005-Q3294292001628426890yes
2005-Q22692660014511429590yes
2005-Q1228225001289226573yes
2004-Q425224502112411437786yes
2004-Q3272269001369829393yes
2004-Q225824805714411837885yes
2004-Q1206203011167030464yes
2003-Q42212150111610240280yes
2003-Q3255249031468425990yes
2003-Q2251244021367825191yes
2003-Q12702650811662244134yes
2002-Q42072050661199035062yes
2002-Q3245237001457935469yes
2002-Q22382310211299128331yes
2002-Q11911890206103753367yes
2001-Q4187182085106942347yes
2001-Q318417604097823275yes
2001-Q21691640321081013203yes
2001-Q1176172027102952783yes
2000-Q4209197056101993544yes
2000-Q3217207014112882582yes
2000-Q22702580301321162852yes
2000-Q1230217070791764453yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

6,817 of the 24,938 building permits filed since 2000 (27%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Inner Sunset neighborhood

Shown apart, with their own page here: bathroom remodel (3,920 filed, 2,888 finished; contractors); kitchen remodel (3,224 filed, 2,313 finished; contractors); stairs (1,621 filed, 1,088 finished; contractors); deck (1,328 filed, 890 finished; contractors); roof deck (157 filed, 91 finished; contractors). Other types: 17,714 permits.

Nearby neighborhoods

Golden Gate Park, Twin Peaks, Haight Ashbury; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.