How long do stairs permits take in San Francisco's Financial District/South Beach neighborhood?

In the Financial District/South Beach neighborhood of San Francisco, of the 60 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 24 days, up from 22 days a year earlier. Of the 34 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 132 days of being issued, down from 245 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's FinancialDistrict/South Beach neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02004006008002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/financial-district-south-beach/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202660 issued2449 issued22
Permit issued to final sign-offOctober 2023 through September 202434 finished13220 finished245

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42000too recent
2026-Q32916123120too recent
2026-Q21414357400too recent
2026-Q114123523151231380too recent
2025-Q419182612491001990too recent
2025-Q318172139101922640too recent
2025-Q2161521107121331780too recent
2025-Q11010146891263680too recent
2024-Q4878530851922160too recent
2024-Q312123015981232940yes
2024-Q212112543101382540yes
2024-Q17620236782620yes
2023-Q414132064102625160yes
2023-Q34313yes
2023-Q2161418193124447321yes
2023-Q17542833yes
2022-Q44440yes
2022-Q3141356108114816462yes
2022-Q299287094427520yes
2022-Q1131217128101224643yes
2021-Q41110224664248334yes
2021-Q32019514916984524yes
2021-Q2767617662864190yes
2021-Q111106820961616335yes
2020-Q4868813063867610yes
2020-Q3221892294152305963yes
2020-Q277774135282872yes
2020-Q1131272179112284581yes
2019-Q4272349299205829555yes
2019-Q3262535170215777863yes
2019-Q2201828123145188324yes
2019-Q1262521103223407693yes
2018-Q420201936153079424yes
2018-Q3373418115263859347yes
2018-Q2474523103362311,0928yes
2018-Q1414128158354081,1605yes
2017-Q4232237130206441,2432yes
2017-Q3161610120134011,2333yes
2017-Q2181741100104738897yes
2017-Q119191362132745514yes
2016-Q420201270162324514yes
2016-Q323221487212526661yes
2016-Q216166124122224154yes
2016-Q127242580211524063yes
2015-Q4181719131103344847yes
2015-Q3262423176193486086yes
2015-Q2212038175133976947yes
2015-Q120201672122507338yes
2014-Q41714437111305653yes
2014-Q3252324104192021,2442yes
2014-Q2272638126172777289yes
2014-Q119191890172535012yes
2013-Q414141866132385821yes
2013-Q3262525151221985363yes
2013-Q2161638230142144652yes
2013-Q1151519126133167962yes
2012-Q417171577131645334yes
2012-Q3232017129152186235yes
2012-Q2171424170112673754yes
2012-Q1161617118133236343yes
2011-Q415152083131212082yes
2011-Q313131079101183293yes
2011-Q213138101121743021yes
2011-Q11413710581224715yes
2010-Q4131342382344475yes
2010-Q316151186112286884yes
2010-Q26683651883180yes
2010-Q1771587913950yes
2009-Q43330yes
2009-Q3111143492153311yes
2009-Q21414829142103570yes
2009-Q11010149292315031yes
2008-Q4111126492574012yes
2008-Q32221221152004403yes
2008-Q22221263162104683yes
2008-Q1171728114112664296yes
2007-Q41918897131564433yes
2007-Q31616040101983203yes
2007-Q2970152503251yes
2007-Q1997928652177292yes
2006-Q488011951552630yes
2006-Q313108223772315871yes
2006-Q21717040102144090yes
2006-Q11413012573286810yes
2005-Q41918010351913256yes
2005-Q388174931yes
2005-Q210102014062165461yes
2005-Q11212287752385031yes
2004-Q4121103571534311yes
2004-Q310105221872123711yes
2004-Q213135676102784560yes
2004-Q112125817382705741yes
2003-Q49905382354150yes
2003-Q31414090141605630yes
2003-Q26602830yes
2003-Q1773014361203880yes
2002-Q4109269061061321yes
2002-Q388247961666341yes
2002-Q21211010040yes
2002-Q177294521yes
2001-Q477299451613061yes
2001-Q3994617432yes
2001-Q2872832652763661yes
2001-Q11098428352195840yes
2000-Q4141331116103504230yes
2000-Q31817714782606860yes
2000-Q215152913852403230yes
2000-Q1161406751554410yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

231 of the 1,642 stairs permits filed since 2000 (14%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Financial District/South Beach neighborhood

Shown apart, with their own page here: kitchen remodel (3,060 filed, 2,343 finished; contractors); bathroom remodel (2,943 filed, 2,280 finished; contractors); stairs (1,642 filed, 1,122 finished; contractors); deck (176 filed, 96 finished; contractors); roof deck (108 filed, 65 finished; contractors); pergola or trellis (62 filed, 30 finished; contractors). Other types: 85,930 permits. All permits in San Francisco's Financial District/South Beach neighborhood

Nearby neighborhoods

Chinatown, Nob Hill, Tenderloin; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.