Block 0231, lot 023
201 Clay St
- City’s use
- Commercial Office
- Built
- 1974
- Stories
- 35
- Building
- 725,000 sq ft
- Lot
- 75,625 sq ft
- Zoning
- C3O
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
The 200 most recent permits filed for this property.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 14, 2026 | In progress issued Sep 2026 | 2 Embarcadero Center | Peacock Construction | 28/f: deferred submittal for pa # 202608116388Details
28/f: deferred submittal for pa # 202608116388 | $69,641 |
| Sep 14, 2026 | In progress issued Sep 2026 | 2 Embarcadero Center | Peacock Construction | 26/f: deferred submittal for pa # 202608116389Details
26/f: deferred submittal for pa # 202608116389 | $60,400 |
| Aug 11, 2026 | In progress issued Sep 2026 | 2 Embarcadero Center | Peacock Construction | 28th floor: t.i.demo of a partition of existing pantry and adding one all gender restroom. new non-structural partitions doors, lighting, millwork minor electrical and fixtures.Details
28th floor: t.i.demo of a partition of existing pantry and adding one all gender restroom. new non-structural partitions doors, lighting, millwork minor electrical and fixtures. | $185,000 |
| Aug 11, 2026 | In progress issued Sep 2026 | 2 Embarcadero Center | Peacock Construction | 26th floor: t.i.demo of a non-structural partition, millwork, doors, finishes.Details
26th floor: t.i.demo of a non-structural partition, millwork, doors, finishes. | $185,000 |
| Jul 17, 2026 | In progress issued Aug 2026 | 2 Embarcadero Center | Vulcan Construction Inc | 22nd fl, ste 2220 construction of a new demising wall to divide an existing vacant office suite into 2 vacant office suitesDetails
22nd fl, ste 2220 construction of a new demising wall to divide an existing vacant office suite into 2 vacant office suites | $6,800 |
| Jul 2, 2026 | In progress filed Jul 2026, not yet issued | 2 Embarcadero Center | construction of new security gates and screens to the existing stairways. interior exit.Details
construction of new security gates and screens to the existing stairways. interior exit. | $31,500 | |
| Jun 26, 2026 | In progress issued Jun 2026 | 2 Embarcadero Center | Field Construction Inc. | 18/f: mechanical and electrical for bpa# 202605141295Details
18/f: mechanical and electrical for bpa# 202605141295 | $545,000 |
| Jun 22, 2026 | In progress issued Jun 2026 | 2 Embarcadero Center | Bilcor Inc | 18/fl - install (1) call station 2400-808nspm with mushroom button for lock . elevator lobby- 2 way ecs permanent backbone infrastructrue permit 202008313022. install 1 call station. 2 way call statoin to intergrate with building 2 way emergency comm system. arch ref 202605141295.Details
18/fl - install (1) call station 2400-808nspm with mushroom button for lock . elevator lobby- 2 way ecs permanent backbone infrastructrue permit 202008313022. install 1 call station. 2 way call statoin to intergrate with building 2 way emergency comm system. arch ref 202605141295. | $1,000 |
| May 28, 2026 | Completed final sign-off Aug 2026 | 2 Embarcadero Center | Peacock Construction | 16/f: suites 1660/1680: title 24 electrical spec suite office tenant retrofit: lighting fixtures & assocated circuiting / controls, power & signal devices & associated wiring.Details
16/f: suites 1660/1680: title 24 electrical spec suite office tenant retrofit: lighting fixtures & assocated circuiting / controls, power & signal devices & associated wiring. | $150,000 |
| May 28, 2026 | Completed final sign-off Sep 2026 | 2 Embarcadero Center | Peacock Construction | ref. 202601224294, mechanical-rework of low side air distribution.Details
ref. 202601224294, mechanical-rework of low side air distribution. | $150,000 |
| May 14, 2026 | In progress issued May 2026 | 2 Embarcadero Center | Field Construction Inc. | 18/f: interior ti improvement - demo of non-structural partitions, finishes, fixtures, and lighting. restroom ada upgrades. mep, fire safety under separate permit.Details
18/f: interior ti improvement - demo of non-structural partitions, finishes, fixtures, and lighting. restroom ada upgrades. mep, fire safety under separate permit. | $1,150,000 |
| Mar 11, 2026 | In progress issued Aug 2026 | 2 Embarcadero Center | Silverado Contractors Inc | 11/f: selective demolition of non-load-bearing partitions. removal of power and data outlets, lighting, switches, and associated electrical devices including removal of suspended ceiling tiles, grid, and related ceiling mounted devices, except smoke control devices as well as removal of (e)Details
11/f: selective demolition of non-load-bearing partitions. removal of power and data outlets, lighting, switches, and associated electrical devices including removal of suspended ceiling tiles, grid, and related ceiling mounted devices, except smoke control devices as well as removal of (e) | $300,000 |
| Feb 6, 2026 | In progress issued Feb 2026 | 2 Embarcadero Center | Siemens Industry, Inc. | 18/19th fl - fire only work to document the systems relocation sequence due to the tenant stairwell infill between floors nd 19. no parts added. ref pa 202410152915Details
18/19th fl - fire only work to document the systems relocation sequence due to the tenant stairwell infill between floors nd 19. no parts added. ref pa 202410152915 | |
| Feb 3, 2026 | In progress filed Feb 2026, not yet issued | 2 Embarcadero Center | M C S Construction Services | revision to pa #2025-0414-4331: removing deferred mechanicalDetails
revision to pa #2025-0414-4331: removing deferred mechanical | |
| Jan 22, 2026 | Completed final sign-off Sep 2026 | 2 Embarcadero Center | Peacock Construction | 16/fl- ti to (e) tenant space to provide spec suite. include non structrual demo of (e) ti and build out of (e) with non structrural partitions doors and sidelites, suspend ceilings, casework and finishesDetails
16/fl- ti to (e) tenant space to provide spec suite. include non structrual demo of (e) ti and build out of (e) with non structrural partitions doors and sidelites, suspend ceilings, casework and finishes | $500,000 |
| Dec 4, 2025 | Completed final sign-off Dec 2025 | 2 Embarcadero Center | Siemens Industry, Inc. | 23rd fl, ste 2350 - remodel done under pa 202509266161 additions are 9 speakers, 4 speaker/strobes, and 3 strobesDetails
23rd fl, ste 2350 - remodel done under pa 202509266161 additions are 9 speakers, 4 speaker/strobes, and 3 strobes | $12,865 |
| Dec 3, 2025 | Completed final sign-off Jan 2026 | 2 Embarcadero Center | M C S Construction Services | 23rd fl suite 2350 ref pa #202509266161: deferred electrical permit. light fixtures & associated circuiting/controls, power and signal devices & associated wiring.Details
23rd fl suite 2350 ref pa #202509266161: deferred electrical permit. light fixtures & associated circuiting/controls, power and signal devices & associated wiring. | $100,000 |
| Nov 6, 2025 | Completed final sign-off Mar 2026 | 2 Embarcadero Center | Bay City Mechanical Inc | 3rd floor: hvac work including installation of 4 fan coil units and 1 supply for the atrium area(front) of the 3rd floor. this will include new electrical under different permit/contrators) not moving existing walls, no seismic retrofit, accessible entrance and legalizing a unit.ref# 202403188032Details
3rd floor: hvac work including installation of 4 fan coil units and 1 supply for the atrium area(front) of the 3rd floor. this will include new electrical under different permit/contrators) not moving existing walls, no seismic retrofit, accessible entrance and legalizing a unit.ref# 202403188032 | $55,009 |
| Sep 26, 2025 | Completed final sign-off Jan 2026 | 2 Embarcadero Center | M C S Construction Services | 23rd flr/suite 2350. t.i. includes demo of non-structure partitions, doors, bldg of new non str partions. doors and finishes. all new or revised meps, life safety work will be design-build and submitted for permit separately bldging is fully sprinkled.Details
23rd flr/suite 2350. t.i. includes demo of non-structure partitions, doors, bldg of new non str partions. doors and finishes. all new or revised meps, life safety work will be design-build and submitted for permit separately bldging is fully sprinkled. | $200,000 |
| Aug 13, 2025 | In progress issued Aug 2025 | 2 Embarcadero Center | M C S Construction Services | 22nd fl, ste 2210 revision to pa 202504144331 includes additional 410 sq ft of ti w/selective demo of non structural partitions, lights, finishes; construction of non-structural partitions, lights, doors, windows and finishesDetails
22nd fl, ste 2210 revision to pa 202504144331 includes additional 410 sq ft of ti w/selective demo of non structural partitions, lights, finishes; construction of non-structural partitions, lights, doors, windows and finishes | $35,000 |
| Jul 15, 2025 | Completed final sign-off Jul 2025 | 2 Embarcadero Center | Siemens Industry, Inc. | 1st fl - fire only work for the security center remodel done under pa 202405242925, and the network interface additions for section monitoring and microphone cabability from 2 embarcadero center (ec), 1 ec, 3 ec, and 4 ec. the security center job adds 6 speaker/strobes and 1 strobeDetails
1st fl - fire only work for the security center remodel done under pa 202405242925, and the network interface additions for section monitoring and microphone cabability from 2 embarcadero center (ec), 1 ec, 3 ec, and 4 ec. the security center job adds 6 speaker/strobes and 1 strobe | $70,000 |
| Jun 13, 2025 | In progress issued Jun 2025 | 2 Embarcadero Center | Mc Millan Electric | electrical work for new security operations center on level lobby. deferred electrical submittal ref#: 202405242925Details
electrical work for new security operations center on level lobby. deferred electrical submittal ref#: 202405242925 | $56,450 |
| May 30, 2025 | Completed final sign-off Jul 2025 | 2 Embarcadero Center | Siemens Industry, Inc. | 19th fl - fire only work for the conferenc room remodel. ref pa 202503263060. 1 speaker/strobe and 1 are addedDetails
19th fl - fire only work for the conferenc room remodel. ref pa 202503263060. 1 speaker/strobe and 1 are added | $1,561 |
| May 20, 2025 | Completed final sign-off Jun 2025 | 2 Embarcadero Center | Siemens Industry, Inc. | 22nd/fl: fire only work fore suite 2210 remodel on the 22nd floor. under pa#202504144331. 1 speaker/strobe is added and 1 speaker/strobe is relocated.Details
22nd/fl: fire only work fore suite 2210 remodel on the 22nd floor. under pa#202504144331. 1 speaker/strobe is added and 1 speaker/strobe is relocated. | $1,922 |
| May 20, 2025 | Completed final sign-off Jun 2025 | 2 Embarcadero Center | Golden Gate Fire Protection Inc | 22nd floor ref pa # 2025-0414-4331: fire sprinkler t.i. relocate 3 pendents.Details
22nd floor ref pa # 2025-0414-4331: fire sprinkler t.i. relocate 3 pendents. | $750 |
| May 13, 2025 | In progress issued May 2025 | 2 Embarcadero Center | R L H Fire Protection Inc | 19th fl ref pa # 2025-0326-3060: fire sprinkler permit relocate 4 and delete 2 pendent sprinklersDetails
19th fl ref pa # 2025-0326-3060: fire sprinkler permit relocate 4 and delete 2 pendent sprinklers | $1,200 |
| Apr 25, 2025 | In progress issued Apr 2025 | 2 Embarcadero Center | Acco Engineered Systems Inc. Dba Acco En | rev to pa# 2025-0409-4014: revise title 24 acceptance testDetails
rev to pa# 2025-0409-4014: revise title 24 acceptance test | |
| Apr 14, 2025 | Completed final sign-off Jul 2025 | 2 Embarcadero Center | Pioneer Fire Inc. | suite 2210 and 2211: relocate 25 pendent (uk302) heads, converting 7 upright uk306 heads, remove 2 pendent heads, add 1 pendent uk302 head. ref 202405242925Details
suite 2210 and 2211: relocate 25 pendent (uk302) heads, converting 7 upright uk306 heads, remove 2 pendent heads, add 1 pendent uk302 head. ref 202405242925 | $11,500 |
| Apr 14, 2025 | In progress issued Apr 2025 | 2 Embarcadero Center | M C S Construction Services | tenant improvement of suite 2210 on the 22nd fl includes: selective demo of non structural partitions, lights, finishes. construction of non structural partitions, lights, doors, windows, finishes. no change in occupancy use or area.Details
tenant improvement of suite 2210 on the 22nd fl includes: selective demo of non structural partitions, lights, finishes. construction of non structural partitions, lights, doors, windows, finishes. no change in occupancy use or area. | $75,424 |
| Apr 9, 2025 | In progress issued Apr 2025 | 2 Embarcadero Center | Acco Engineered Systems Inc. Dba Acco En | deferred mechanical for permit 202405242925. lobby level / suite 2210-2211: ti change of use from retail to office. mechanical on 2nd level and rooftop: demo out existing fan coils chilled and heater water piping, new vrf systems, new fans for ventilation air, bathroom exhaustDetails
deferred mechanical for permit 202405242925. lobby level / suite 2210-2211: ti change of use from retail to office. mechanical on 2nd level and rooftop: demo out existing fan coils chilled and heater water piping, new vrf systems, new fans for ventilation air, bathroom exhaust | $300,000 |
| Mar 26, 2025 | Completed final sign-off Aug 2025 | 2 Embarcadero Center | Hathaway Dinwiddie Co. | 19/flr- demo of non load bearing partitions, finishes, ceilings construction of (n) full height partitions, doors, glazing, assoocated electrical power lighting, associates mechanical system distribution and finishes.Details
19/flr- demo of non load bearing partitions, finishes, ceilings construction of (n) full height partitions, doors, glazing, assoocated electrical power lighting, associates mechanical system distribution and finishes. | $400,000 |
| Mar 10, 2025 | Completed final sign-off Mar 2025 | 2 Embarcadero Center | Siemens Industry, Inc. | 16th fl - fire only work, ste 1630 remodel done under pa 202502079849. additions are 7 speaker/strobes and 3 strobes, as well as the relocation of 1 smoke detectorDetails
16th fl - fire only work, ste 1630 remodel done under pa 202502079849. additions are 7 speaker/strobes and 3 strobes, as well as the relocation of 1 smoke detector | $9,310 |
| Mar 6, 2025 | Completed final sign-off Mar 2025 | 2 Embarcadero Center | R L H Fire Protection Inc | fire sprinkler relocate 19, add 4 and delete 4 sprinklers on the 16th fl ti 202502079849Details
fire sprinkler relocate 19, add 4 and delete 4 sprinklers on the 16th fl ti 202502079849 | $7,500 |
| Mar 4, 2025 | Completed final sign-off May 2025 | 2 Embarcadero Center | M C S Construction Services | suite 1630: deferred mechanical & electrical permit ref pa 202502079849 mech- mech modifications to accommodate arch layout changes, new dual duct rav box & new ductwork as needed. reconfigure of (e) ductwork & air dist. electrical- new power & signal devices throughout space new title 24.Details
suite 1630: deferred mechanical & electrical permit ref pa 202502079849 mech- mech modifications to accommodate arch layout changes, new dual duct rav box & new ductwork as needed. reconfigure of (e) ductwork & air dist. electrical- new power & signal devices throughout space new title 24. | $100,000 |
| Feb 7, 2025 | Completed final sign-off May 2025 | 2 Embarcadero Center | M C S Construction Services | ste 1630: selective demo of millwork, non structural walls, power outlets, & finishes. construction of non structural partitions, doors/ store-fronts, electrical, millwork & finishes. no change in occupancy, use in area. mep deferredDetails
ste 1630: selective demo of millwork, non structural walls, power outlets, & finishes. construction of non structural partitions, doors/ store-fronts, electrical, millwork & finishes. no change in occupancy, use in area. mep deferred | $498,278 |
| Dec 9, 2024 | Completed final sign-off Dec 2024 | 2 Embarcadero Center | Siemens Industry, Inc. | fire only for partial remodel on floor 19. additions are 2 speaker/strobes, 1 strobe, 1 moudule, and the relocation of 1 speaker stobe. ref 202409170925Details
fire only for partial remodel on floor 19. additions are 2 speaker/strobes, 1 strobe, 1 moudule, and the relocation of 1 speaker stobe. ref 202409170925 | $4,105 |
| Oct 31, 2024 | In progress issued Nov 2024 | 2 Embarcadero Center | R L H Fire Protection Inc | 19/f: fire sprinkler: relocate 16, add 5, delete 3 sprinklers on 19/f. ref t.i. pa 202409170925Details
19/f: fire sprinkler: relocate 16, add 5, delete 3 sprinklers on 19/f. ref t.i. pa 202409170925 | $7,000 |
| Oct 15, 2024 | Completed final sign-off Mar 2025 | 2 Embarcadero Center | M C S Construction Services | 19/fl-ref 202409170925- to infill of (e) stair openingDetails
19/fl-ref 202409170925- to infill of (e) stair opening | $50,000 |
| Sep 17, 2024 | Completed final sign-off Mar 2025 | 2 Embarcadero Center | Hathaway Dinwiddie Co. | 19th/f: demo of non-load bearing partitions, finishes & ceiling. construction of new full height partitions, interior finishes, associated electrical power/lighting distribution. mech & plumbingDetails
19th/f: demo of non-load bearing partitions, finishes & ceiling. construction of new full height partitions, interior finishes, associated electrical power/lighting distribution. mech & plumbing | $600,000 |
| Aug 9, 2024 | Completed final sign-off Oct 2024 | 2 Embarcadero Center | Bilcor Inc | install 1 call station, 1 call station signage, ref to t.i.202403188032. ref to f/a 202406204812Details
install 1 call station, 1 call station signage, ref to t.i.202403188032. ref to f/a 202406204812 | $1,332 |
| Jul 31, 2024 | Completed final sign-off Oct 2024 | 2 Embarcadero Center | M C S Construction Services | 23rd flr - deferred electrical permit. permit ref# 2024-0621-4954. lighting fixtures + associated circuitung/controls, power + signal devices + associated wiringDetails
23rd flr - deferred electrical permit. permit ref# 2024-0621-4954. lighting fixtures + associated circuitung/controls, power + signal devices + associated wiring | $50,000 |
| Jul 16, 2024 | Expired or cancelled cancelled Aug 2024 | 2 Embarcadero Center | Pioneer Fire Inc. | 23rd floor: relocate 6 pendents.Details
23rd floor: relocate 6 pendents. | $4,800 |
| Jul 11, 2024 | Completed final sign-off Jul 2024 | 2 Embarcadero Center | Anderson, Rowe & Buckley, Inc. | 3/f suite 300: tenant improvement to existing fire sprinkler system add 14 and relocate 204 sprinklers ti 2024-0318-8032Details
3/f suite 300: tenant improvement to existing fire sprinkler system add 14 and relocate 204 sprinklers ti 2024-0318-8032 | $138,000 |
| Jun 21, 2024 | Completed final sign-off Oct 2024 | 2 Embarcadero Center | M C S Construction Services | 23rd floor- demo of ceiling and finishes in common area as well as restrooms . new wall and floor finsihes celings, lights as well as restroom fixtures, accessories and associated finishes. no change in use or occupancyDetails
23rd floor- demo of ceiling and finishes in common area as well as restrooms . new wall and floor finsihes celings, lights as well as restroom fixtures, accessories and associated finishes. no change in use or occupancy | $465,334 |
| Jun 20, 2024 | Completed final sign-off Oct 2024 | 2 Embarcadero Center | Siemens Industry, Inc. | fire only: work for bxp remodel on floor 3: additions and replacement are 19 smoke detectors, 14 duct detectors, 6 modules, 2 pull stations, 31 speakers, 39 speaker/ strobes, and 4 strobes. permit ref# 202403188032.Details
fire only: work for bxp remodel on floor 3: additions and replacement are 19 smoke detectors, 14 duct detectors, 6 modules, 2 pull stations, 31 speakers, 39 speaker/ strobes, and 4 strobes. permit ref# 202403188032. | $125,000 |
| Jun 5, 2024 | Completed final sign-off Jul 2024 | 2 Embarcadero Center | M C S Construction Services | suite 480: permit ref# 2024-0426-08255: deferred electrical permit: office tenant retrofit: new power receptacles, tele data outlets, and associated wiring in an existing to remain office suite.Details
suite 480: permit ref# 2024-0426-08255: deferred electrical permit: office tenant retrofit: new power receptacles, tele data outlets, and associated wiring in an existing to remain office suite. | $30,000 |
| May 24, 2024 | In progress issued Mar 2025 | 2 Embarcadero Center | lobby level/ suite 2210-2211: change of use from retail to office. t.i. includes the demo of no str partitions and building new non-str partitions. all new or revised meps, life safety work and sprinklers will be design build and submitted for permit. separately. (bldg is fully sprinklers)Details
lobby level/ suite 2210-2211: change of use from retail to office. t.i. includes the demo of no str partitions and building new non-str partitions. all new or revised meps, life safety work and sprinklers will be design build and submitted for permit. separately. (bldg is fully sprinklers) | $397,884 | |
| May 15, 2024 | Completed final sign-off Aug 2024 | 2 Embarcadero Center | Peacock Construction | g/f suite r2118: no change of use or occupant loads. demo of (e) millwork, paint walls and ceilings, flooring maintenance. install of wine dispensing machines, glass washer, accessible signage and retrofit of accessible bar counter. no work to fa. fs to remain. mep under separate permit.Details
g/f suite r2118: no change of use or occupant loads. demo of (e) millwork, paint walls and ceilings, flooring maintenance. install of wine dispensing machines, glass washer, accessible signage and retrofit of accessible bar counter. no work to fa. fs to remain. mep under separate permit. | $52,000 |
| Apr 26, 2024 | Completed final sign-off Jul 2024 | 2 Embarcadero Center | M C S Construction Services | 4th fl selective demolition of millwork, non structural walls, power outlets and finishes. construction of non structural partitions, door/stovefronts, electrical, millwork finishes. no change in occupancy, use or areaDetails
4th fl selective demolition of millwork, non structural walls, power outlets and finishes. construction of non structural partitions, door/stovefronts, electrical, millwork finishes. no change in occupancy, use or area | $363,520 |
| Apr 26, 2024 | Completed final sign-off May 2024 | 2 Embarcadero Center | Golden Gate Fire Protection Inc | add 2 pendent sprinkers on the 16/f ste 1670. ref ti pa# 202403157877Details
add 2 pendent sprinkers on the 16/f ste 1670. ref ti pa# 202403157877 | $1,200 |
| Apr 19, 2024 | In progress issued Apr 2024 | 2 Embarcadero Center | Peacock Construction | hvac modification to support t.i. add 2 return grilles, new power & lighting. ref 202403157877Details
hvac modification to support t.i. add 2 return grilles, new power & lighting. ref 202403157877 | $25,000 |
| Apr 18, 2024 | Completed final sign-off May 2024 | 2 Embarcadero Center | Siemens Industry, Inc. | 1 speaker strobe added and one speaker relocated. ref permit 2024-0315-7877Details
1 speaker strobe added and one speaker relocated. ref permit 2024-0315-7877 | $961 |
| Mar 18, 2024 | Completed final sign-off Jan 2025 | 2 Embarcadero Center | Principal Builders Inc. | 3/f. ste 300. ti demo of non stru partitions and build (n) non str partitions. mep included. fire alarm and sprinklers under sep permit. bldg is fully sprinkled.Details
3/f. ste 300. ti demo of non stru partitions and build (n) non str partitions. mep included. fire alarm and sprinklers under sep permit. bldg is fully sprinkled. | $1,600,000 |
| Mar 15, 2024 | Completed final sign-off Jul 2024 | 2 Embarcadero Center | Peacock Construction | selective demolition of non structural ceilings, lights, electrical millwork and finishes. construction of non structural partitions, lights, doors/windows, ele milwork finishes. no change in occupancy. use or areaDetails
selective demolition of non structural ceilings, lights, electrical millwork and finishes. construction of non structural partitions, lights, doors/windows, ele milwork finishes. no change in occupancy. use or area | $130,000 |
| Jan 11, 2024 | Completed final sign-off Feb 2024 | 2 Embarcadero Center | Siemens Industry, Inc. | 22nd fl - fire only work to add 4 strobes for phone booths ref pa 202312263071Details
22nd fl - fire only work to add 4 strobes for phone booths ref pa 202312263071 | $2,484 |
| Jan 9, 2024 | Completed final sign-off Jan 2024 | 2 Embarcadero Center | Pioneer Fire Inc. | 22nd fl - add (4) pendents ref pa 2023-1226-3071Details
22nd fl - add (4) pendents ref pa 2023-1226-3071 | $400 |
| Dec 26, 2023 | Completed final sign-off Mar 2024 | 2 Embarcadero Center | Gci, Inc | project is located on the 22nd fl. consist of addition of four pre-fab phone booths no change of occupancy, use or areaDetails
project is located on the 22nd fl. consist of addition of four pre-fab phone booths no change of occupancy, use or area | $82,500 |
| Sep 28, 2023 | Completed final sign-off Feb 2024 | 2 Embarcadero Center | Peacock Construction | lobby lighting & controls ref pa 2023-0613-9939Details
lobby lighting & controls ref pa 2023-0613-9939 | $10,000 |
| Aug 1, 2023 | Completed final sign-off Dec 2023 | 2 Embarcadero Center | Gci, Inc | unit 2200: mechanical & electrical properties work for t.i. to consist of new ducktwork, grilles & diffusers, new lighting & controls, power & signal. ref pa 202305117552Details
unit 2200: mechanical & electrical properties work for t.i. to consist of new ducktwork, grilles & diffusers, new lighting & controls, power & signal. ref pa 202305117552 | $20,000 |
| Jul 11, 2023 | Completed final sign-off Oct 2023 | 2 Embarcadero Center | Golden Gate Fire Protection Inc | fire sprinklers: relocate 2 concelaled pendents on 1st fl and relocate 6 concealed pendents on 2nd fl. as-built to pa# 202305238382.Details
fire sprinklers: relocate 2 concelaled pendents on 1st fl and relocate 6 concealed pendents on 2nd fl. as-built to pa# 202305238382. | $1,000 |
| Jun 30, 2023 | Never finaled issued Jul 2023, no final | 2 Embarcadero Center | Siemens Industry, Inc. | fire only work for the suite 2200 remodel on fl 22. additoins are 2 smoke detectors, 18 speaker strobes, 3 strobes, ref 202305117552Details
fire only work for the suite 2200 remodel on fl 22. additoins are 2 smoke detectors, 18 speaker strobes, 3 strobes, ref 202305117552 | $20,601 |
| Jun 30, 2023 | Never finaled issued Jul 2023, no final | 2 Embarcadero Center | Pioneer Fire Inc. | relocate 106 pendent heads, add 3 uprights, convert 16 sprinklers to uprights, ref pa# 202305117552.Details
relocate 106 pendent heads, add 3 uprights, convert 16 sprinklers to uprights, ref pa# 202305117552. | $13,120 |
| Jun 13, 2023 | Completed final sign-off Feb 2024 | 2 Embarcadero Center | Peacock Construction | demo of (e) retail suite @ ground floor (01) and lobby floor (02) including removal of (e) storefront. patch back of ceiling, walls, floor. utilities to be cut back and capped as described. sprinkler under separate permit.Details
demo of (e) retail suite @ ground floor (01) and lobby floor (02) including removal of (e) storefront. patch back of ceiling, walls, floor. utilities to be cut back and capped as described. sprinkler under separate permit. | $140,000 |
| Jun 12, 2023 | Completed final sign-off Jun 2023 | 2 Embarcadero Center | Bilcor Inc | install 1 new call station with mushroom button flush mount backbone ref 202008111563. fa 202302172155Details
install 1 new call station with mushroom button flush mount backbone ref 202008111563. fa 202302172155 | $1,300 |
| May 23, 2023 | Completed final sign-off Oct 2023 | 2 Embarcadero Center | Golden Gate Fire Protection Inc | 1st & 2nd fl: fire sprinklers. relocate 4 uprights on 1st fl, and relocate 8 uprights on 2nd fl.Details
1st & 2nd fl: fire sprinklers. relocate 4 uprights on 1st fl, and relocate 8 uprights on 2nd fl. | $7,440 |
| May 11, 2023 | Completed final sign-off Feb 2024 | 2 Embarcadero Center | Gci, Inc | ste 2200, 22nd fl - interior ccommercial ti of (e) tenant space includes non-structural demo of (e) ti and build out of new including non-structural partitions, doors and sidelites, suspended ceilings, casework and finishes. mep and life safety systems are design build under a separate permitDetails
ste 2200, 22nd fl - interior ccommercial ti of (e) tenant space includes non-structural demo of (e) ti and build out of new including non-structural partitions, doors and sidelites, suspended ceilings, casework and finishes. mep and life safety systems are design build under a separate permit | $948,383 |
| Mar 16, 2023 | Expired or cancelled cancelled Jan 2026 | 2 Embarcadero Center | install 8 prefab phone booths on floors 17 & 30Details
install 8 prefab phone booths on floors 17 & 30 | $21,000 | |
| Feb 28, 2023 | Completed final sign-off Nov 2023 | 2 Embarcadero Center | Hathaway Dinwiddie Co. | this project implements no. 2022009016 prj. demolition of extg architectural concrete battered wall at clay street facade at lobby level (level 2).Details
this project implements no. 2022009016 prj. demolition of extg architectural concrete battered wall at clay street facade at lobby level (level 2). | $170,000 |
| Feb 27, 2023 | Never finaled issued Feb 2023, no final | 2 Embarcadero Center | Bilcor Inc | 12th fl - install new call station rath 2400808nspm w/mushroom button (flush mount); ref pa 2020-0831-3022 and fa ref 2023-0217-2155Details
12th fl - install new call station rath 2400808nspm w/mushroom button (flush mount); ref pa 2020-0831-3022 and fa ref 2023-0217-2155 | $1,400 |
| Feb 17, 2023 | Never finaled issued Feb 2023, no final | 2 Embarcadero Center | Siemens Industry, Inc. | 12/f: add a module for monitoring 2 fault points from the existing 20way communicator system (per sffd)Details
12/f: add a module for monitoring 2 fault points from the existing 20way communicator system (per sffd) | $600 |
| Jan 10, 2023 | Completed final sign-off Feb 2023 | 2 Embarcadero Center | M C S Construction Services | deferred electrical permit, pa# 2022-1031-5542Details
deferred electrical permit, pa# 2022-1031-5542 | $50,000 |
| Jan 3, 2023 | Completed final sign-off Feb 2023 | 2 Embarcadero Center | Siemens Industry, Inc. | 23rd fl, ste 2320 remodel; addition of 1 smoke detector and the relocation of 2 speakers and 1 strobe. ref pa 2022-1031-5542Details
23rd fl, ste 2320 remodel; addition of 1 smoke detector and the relocation of 2 speakers and 1 strobe. ref pa 2022-1031-5542 | $1,270 |
| Jan 3, 2023 | Completed final sign-off Jan 2023 | 2 Embarcadero Center | Golden Gate Fire Protection Inc | fire sprinklers relocate 49 pendents in ste. ref pa 2022-0708-8028. ste 2320Details
fire sprinklers relocate 49 pendents in ste. ref pa 2022-0708-8028. ste 2320 | $25,725 |
| Oct 31, 2022 | Completed final sign-off Feb 2023 | 2 Embarcadero Center | M C S Construction Services | 23rd floor: suite 2320; t.i. includes demo of non str. partitions and doors and the build of new non-str partitions, doors and finishes. all new or rvised meps life safty/fire alarm and sprinkler will be design build and submitted seperately if needed. bldg is fully spriklered.Details
23rd floor: suite 2320; t.i. includes demo of non str. partitions and doors and the build of new non-str partitions, doors and finishes. all new or rvised meps life safty/fire alarm and sprinkler will be design build and submitted seperately if needed. bldg is fully spriklered. | $150,000 |
| Oct 24, 2022 | Completed final sign-off Dec 2024 | 2 Embarcadero Center | Cccs, Inc | to comply with access business entrnace, abe #201811072374. replacement of entry door for ada compliance.Details
to comply with access business entrnace, abe #201811072374. replacement of entry door for ada compliance. | $15,000 |
| Sep 22, 2022 | Completed final sign-off Mar 2023 | 2 Embarcadero Center | Source Planning And Construction Inc | 16th fl - revision to pa 2021-0211-4453 reduce scope delete mep scopeDetails
16th fl - revision to pa 2021-0211-4453 reduce scope delete mep scope | |
| Aug 29, 2022 | Completed final sign-off Oct 2022 | 2 Embarcadero Center | Siemens Industry, Inc. | fire only work to add 1 strobe for the siute 2700 remodel on fl 27 (ref pa# 202207088028)Details
fire only work to add 1 strobe for the siute 2700 remodel on fl 27 (ref pa# 202207088028) | $550 |
| Aug 25, 2022 | Expired or cancelled withdrawn Feb 2023 | 2 Embarcadero Center | Hathaway Dinwiddie Co. | demolition of portions of existing architectural concrete battered wall at clay street facade at lobby level(level 02)Details
demolition of portions of existing architectural concrete battered wall at clay street facade at lobby level(level 02) | $170,000 |
| Aug 18, 2022 | Completed final sign-off Sep 2022 | 2 Embarcadero Center | Siemens Industry, Inc. | fire only work for the "corner stone" partial-areas remodel floor 21; additions are 3 speaker/strobe and 9 strobes. as well as relocations of 3 spearkers and 2 strobes ref permit app 202009114001Details
fire only work for the "corner stone" partial-areas remodel floor 21; additions are 3 speaker/strobe and 9 strobes. as well as relocations of 3 spearkers and 2 strobes ref permit app 202009114001 | $7,700 |
| Aug 18, 2022 | Completed final sign-off Sep 2022 | 2 Embarcadero Center | Siemens Industry, Inc. | fire only work for the "corner stone" partial-areas remodel floor 20; additions are 1 speaker/strobe and 12 strobes. ref permit app 202009114001Details
fire only work for the "corner stone" partial-areas remodel floor 20; additions are 1 speaker/strobe and 12 strobes. ref permit app 202009114001 | $7,250 |
| Jul 8, 2022 | Completed final sign-off Mar 2023 | 2 Embarcadero Center | Peacock Construction | suite 2700: interior t.i.: demo of (e) office & adding 1 all gender restroom. new non-structural partitions, door, lighting, plumbing fixtures, fittings & finishes.Details
suite 2700: interior t.i.: demo of (e) office & adding 1 all gender restroom. new non-structural partitions, door, lighting, plumbing fixtures, fittings & finishes. | $200,934 |
| Jun 21, 2022 | Never finaled issued Jun 2022, no final | 2 Embarcadero Center | Siemens Industry, Inc. | 12th fl ste 1200: fire only work. partial floor remodel. additions are 1 strobe and 3 speaker/strobes. ref pa# 202204202592.Details
12th fl ste 1200: fire only work. partial floor remodel. additions are 1 strobe and 3 speaker/strobes. ref pa# 202204202592. | $2,450 |
| May 10, 2022 | Never finaled issued Jun 2022, no final | 2 Embarcadero Center | Anderson, Rowe & Buckley, Inc. | suite 1200: fire sprinkler only: relocate 20 pendents for rbc refresh on the 12th floor. ref t.i. pa202204202592.Details
suite 1200: fire sprinkler only: relocate 20 pendents for rbc refresh on the 12th floor. ref t.i. pa202204202592. | $10,000 |
| Apr 25, 2022 | Completed final sign-off Aug 2022 | 2 Embarcadero Center | Pioneer Fire Inc. | 21/f: add (2) pendent sprinkler heads. ref bpa#202202017099Details
21/f: add (2) pendent sprinkler heads. ref bpa#202202017099 | $500 |
| Apr 20, 2022 | Completed final sign-off Jun 2023 | 2 Embarcadero Center | Peacock Construction | ste 1200: interior t.i. - demo non-structural partitions, doors, millwork. construction of new walls, doors, millwork, power, finishes. new mech,elec, & plum.Details
ste 1200: interior t.i. - demo non-structural partitions, doors, millwork. construction of new walls, doors, millwork, power, finishes. new mech,elec, & plum. | $694,000 |
| Apr 20, 2022 | Never finaled issued May 2022, no final | 2 Embarcadero Center | Clune Construction Company L P | revision to pa 202009114001 includes (n) return grilles for area on level 20x 21 (n) lighting fixtures and receptacles in various areas.Details
revision to pa 202009114001 includes (n) return grilles for area on level 20x 21 (n) lighting fixtures and receptacles in various areas. | |
| Mar 31, 2022 | Expired or cancelled withdrawn Oct 2022 | 2 Embarcadero Center | 25th fl/ste 2510 t.i. modules demo of non structural paritions and building new non str partitions. new or revised meps life safely and sprinklers will be design build under seperate permit.Details
25th fl/ste 2510 t.i. modules demo of non structural paritions and building new non str partitions. new or revised meps life safely and sprinklers will be design build under seperate permit. | $190,000 | |
| Mar 21, 2022 | Completed final sign-off Apr 2022 | 2 Embarcadero Center | Pioneer Fire Inc. | 20th fl: relocate 18 pendent heads, remove 5 pendent heads. ref ti pa# 202202017099.Details
20th fl: relocate 18 pendent heads, remove 5 pendent heads. ref ti pa# 202202017099. | $4,500 |
| Feb 1, 2022 | Never finaled issued Feb 2022, no final | 2 Embarcadero Center | Clune Construction Company L P | revision to pa 2020-0911-4001 20th & 21st fl mnor revision to replace (e) non-structural partitions with new glass walls per planDetails
revision to pa 2020-0911-4001 20th & 21st fl mnor revision to replace (e) non-structural partitions with new glass walls per plan | |
| Oct 22, 2021 | Never finaled issued Oct 2021, no final | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm work to obtain an "as-built" permit for the life safety on the "jams sfo" remodels on floors 14 and 15; the revision reflect that no new or relocated detectors were part of the work initially under permit 202104269366.Details
fire alarm work to obtain an "as-built" permit for the life safety on the "jams sfo" remodels on floors 14 and 15; the revision reflect that no new or relocated detectors were part of the work initially under permit 202104269366. | |
| Sep 24, 2021 | Completed final sign-off Mar 2022 | 2 Embarcadero Center | Specialized Graphics Inc | 4 evacuation maps on 15th floor.Details
4 evacuation maps on 15th floor. | $800 |
| May 13, 2021 | Completed final sign-off Oct 2021 | 2 Embarcadero Center | M C S Construction Services | deferred mep ref 2019-1101-6189Details
deferred mep ref 2019-1101-6189 | $50,000 |
| Apr 29, 2021 | Completed final sign-off Jun 2021 | 2 Embarcadero Center | Siemens Industry, Inc. | fire only work for the "suite 460" remodel on floor 4; additions are 8 speaker/strobes and 2 speakers. ref permit app# 2019 1101 6189Details
fire only work for the "suite 460" remodel on floor 4; additions are 8 speaker/strobes and 2 speakers. ref permit app# 2019 1101 6189 | $6,350 |
| Apr 26, 2021 | Never finaled issued Jun 2021, no final | 2 Embarcadero Center | Siemens Industry, Inc. | fire work only for the "jams sfo" remodels on floors 14 and 15; additions are 1 smoke detector, 18 modules, 1 strobe power supply, 14 speakers, 40 speaker/strobes, 10 strobes, as well as the replacement of 27 smoke detectors and 6 duct detectors. ref. permit app # 2021-0114-2680 (fl 14) and 2021-011Details
fire work only for the "jams sfo" remodels on floors 14 and 15; additions are 1 smoke detector, 18 modules, 1 strobe power supply, 14 speakers, 40 speaker/strobes, 10 strobes, as well as the replacement of 27 smoke detectors and 6 duct detectors. ref. permit app # 2021-0114-2680 (fl 14) and 2021-011 | $64,800 |
| Apr 15, 2021 | Completed final sign-off Jun 2021 | 2 Embarcadero Center | Ayoob & Peery Plumbing Co Inc | 4th floor: add (3) and remove (5) sprinklers per t.i. ref # : 2019-1101-6189Details
4th floor: add (3) and remove (5) sprinklers per t.i. ref # : 2019-1101-6189 | $2,700 |
| Apr 13, 2021 | Completed final sign-off Jul 2021 | 2 Embarcadero Center | R L H Fire Protection Inc | fire sprinkler permit. relocate 79, add 22 and delete 7 sprinklers on the 15th floor. t.i. # 2021-0114-2691Details
fire sprinkler permit. relocate 79, add 22 and delete 7 sprinklers on the 15th floor. t.i. # 2021-0114-2691 | $27,000 |
| Apr 13, 2021 | Completed final sign-off Jul 2021 | 2 Embarcadero Center | R L H Fire Protection Inc | fire sprinkler permit. relocate 52, add 3 and delete 25 sprinklers on the 14th floor. t.i. # 2021-0114-2680Details
fire sprinkler permit. relocate 52, add 3 and delete 25 sprinklers on the 14th floor. t.i. # 2021-0114-2680 | $12,000 |
| Apr 9, 2021 | Completed final sign-off Feb 2022 | 2 Embarcadero Center | mep for tenant improvement pa# 2021-0114-2691Details
mep for tenant improvement pa# 2021-0114-2691 | $640,000 | |
| Apr 7, 2021 | Completed final sign-off Feb 2022 | 2 Embarcadero Center | Vulcan Construction Inc | suite 1400: mep for t.i under permit 202101142680Details
suite 1400: mep for t.i under permit 202101142680 | $390,000 |
| Apr 1, 2021 | Completed final sign-off Jan 2022 | 2 Embarcadero Center | Msr Mechanical Llc | replace 2 (e) water-cooled chillers in kind.Details
replace 2 (e) water-cooled chillers in kind. | $850,000 |
| Feb 11, 2021 | Completed final sign-off Mar 2023 | 2 Embarcadero Center | Source Planning And Construction Inc | 16th fl: non-structural demo. (n) non-structutal partitions, finishes, plumbing, fixtures & accessories. no change in area, occupancy or use. mep, l/s, fire sprinklers under separate permit.Details
16th fl: non-structural demo. (n) non-structutal partitions, finishes, plumbing, fixtures & accessories. no change in area, occupancy or use. mep, l/s, fire sprinklers under separate permit. | $157,000 |
| Jan 14, 2021 | Completed final sign-off Feb 2022 | 2 Embarcadero Center | Vulcan Construction Inc | suite 1500:t.i.: selective demo & construction of non-load bearing partitions, new celings & light fixtures, new electrical, new office doors & frames, newmillwork & new finshes. mep is deferred. maher n/aDetails
suite 1500:t.i.: selective demo & construction of non-load bearing partitions, new celings & light fixtures, new electrical, new office doors & frames, newmillwork & new finshes. mep is deferred. maher n/a | $395,476 |
| Jan 14, 2021 | Never finaled issued Mar 2021, no final | 2 Embarcadero Center | Vulcan Construction Inc | suite 1400: t.i.: selective demo & construction of non-load bearing partitions, new celings & light fixtures, new electrical, new office doors & frames, new millwork & new finshes. mep is deferred. maher n/aDetails
suite 1400: t.i.: selective demo & construction of non-load bearing partitions, new celings & light fixtures, new electrical, new office doors & frames, new millwork & new finshes. mep is deferred. maher n/a | $126,490 |
| Jan 4, 2021 | Completed final sign-off Mar 2021 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm work for floor 2 restrooms remodel; additions are 2 duct detectors and 8 strobes. ref. permit app # 2020-0918-4477.Details
fire alarm work for floor 2 restrooms remodel; additions are 2 duct detectors and 8 strobes. ref. permit app # 2020-0918-4477. | $7,570 |
| Dec 18, 2020 | Completed final sign-off Dec 2022 | 2 Embarcadero Center | Hathaway Dinwiddie Co. | deferred submital for novum strucures & concrete works(exterior skin) in lobby improvement area. ref pa# 201910033419.Details
deferred submital for novum strucures & concrete works(exterior skin) in lobby improvement area. ref pa# 201910033419. | |
| Dec 10, 2020 | Completed final sign-off Apr 2021 | 2 Embarcadero Center | R L H Fire Protection Inc | fire sprinkler permit. relocate 35 and add 11 sprinklers for lobby renovation t.i. # 2019-1003-3419Details
fire sprinkler permit. relocate 35 and add 11 sprinklers for lobby renovation t.i. # 2019-1003-3419 | $15,000 |
| Nov 30, 2020 | Completed final sign-off Mar 2021 | 2 Embarcadero Center | Gci, Inc | 2nd fl: mechanical - demo existing duct & hvac equipment. install (2) new fire/smoke dampers, install low pressure ductwork. electrical - lighting, power & signal. ref ti pa# 202009184477Details
2nd fl: mechanical - demo existing duct & hvac equipment. install (2) new fire/smoke dampers, install low pressure ductwork. electrical - lighting, power & signal. ref ti pa# 202009184477 | |
| Oct 28, 2020 | Completed final sign-off Sep 2021 | 2 Embarcadero Center | Pioneer Fire Inc. | relocate (8) pendents, lower (3) pendents. gc ti#Details
relocate (8) pendents, lower (3) pendents. gc ti# | $4,500 |
| Oct 28, 2020 | Completed final sign-off Dec 2021 | 2 Embarcadero Center | Siemens Industry, Inc. | fire only work for the lobby renovation remodel; additions are 6smoke detectors, 3 duct detectors, 1 module, and 5 speaker/strobes. ref #2019-1003-3419.Details
fire only work for the lobby renovation remodel; additions are 6smoke detectors, 3 duct detectors, 1 module, and 5 speaker/strobes. ref #2019-1003-3419. | $12,070 |
| Oct 6, 2020 | Completed final sign-off Jan 2021 | 2 Embarcadero Center | Source Planning And Construction Inc | revision to pa #2020 0722 0710. existing tile & grid to be remained, existing lights to be relamped, existing signs & strobes to remain. new havc grillesDetails
revision to pa #2020 0722 0710. existing tile & grid to be remained, existing lights to be relamped, existing signs & strobes to remain. new havc grilles | |
| Sep 18, 2020 | Completed final sign-off Mar 2021 | 2 Embarcadero Center | Gci, Inc | 2nd fl: renovation of existing restroom & elevator lobby, restroom, include replacing existing light & plumbing fixtures, new finishes. elevator lobby includes new finishes. no work on elevators. deferred mep.Details
2nd fl: renovation of existing restroom & elevator lobby, restroom, include replacing existing light & plumbing fixtures, new finishes. elevator lobby includes new finishes. no work on elevators. deferred mep. | $600,000 |
| Sep 11, 2020 | Never finaled issued Mar 2021, no final | 2 Embarcadero Center | 20th & 21st flr: interior ti to include non-structural demo. new non-structural partitions, lighting, glazing, & finishes.Details
20th & 21st flr: interior ti to include non-structural demo. new non-structural partitions, lighting, glazing, & finishes. | $3,213,162 | |
| Aug 31, 2020 | Completed final sign-off Dec 2020 | 2 Embarcadero Center | Bilcor Inc | fire life safety: install 1 command center, 1 distributionboard, 1 command center system supervior, 1 power supply/ups backup, 4 backup batteries for ups, 1 power supply monitor, and 1 dual monitor module.Details
fire life safety: install 1 command center, 1 distributionboard, 1 command center system supervior, 1 power supply/ups backup, 4 backup batteries for ups, 1 power supply monitor, and 1 dual monitor module. | $6,600 |
| Jul 22, 2020 | Completed final sign-off Jan 2021 | 2 Embarcadero Center | Source Planning And Construction Inc | 22/f: nonstructural demo, upgrade toilet room to be fully accessible, new finishes in toilet rooms, elevator lobby & corr. no change in occupancy, use or area. mep, life safety, sprinklers under seperate permit.Details
22/f: nonstructural demo, upgrade toilet room to be fully accessible, new finishes in toilet rooms, elevator lobby & corr. no change in occupancy, use or area. mep, life safety, sprinklers under seperate permit. | $150,000 |
| Jul 20, 2020 | Never finaled issued Aug 2020, no final | 201 Clay St | street spaceDetails
street space | ||
| Jul 13, 2020 | Completed final sign-off Sep 2020 | 2 Embarcadero Center | selective demolition scope for ste 1630 and 1670 including wall and power/data removal in existing office spaces.Details
selective demolition scope for ste 1630 and 1670 including wall and power/data removal in existing office spaces. | $5,000 | |
| Feb 10, 2020 | Completed final sign-off Apr 2020 | 2 Embarcadero Center | Siemens Industry, Inc. | 16th fl - fire alarm work for the "evercore" remodel. additions are 1 smoke detector, 2 speakers, 1 speaker/strobe, 6 strobes and the relocation of 1 speaker. ref pa 2019-1220-0104Details
16th fl - fire alarm work for the "evercore" remodel. additions are 1 smoke detector, 2 speakers, 1 speaker/strobe, 6 strobes and the relocation of 1 speaker. ref pa 2019-1220-0104 | $5,840 |
| Feb 5, 2020 | Completed final sign-off Apr 2020 | 2 Embarcadero Center | Golden Gate Fire Protection Inc | fire sprinkler. relocate 2 pendents on the 16th floor.Details
fire sprinkler. relocate 2 pendents on the 16th floor. | $1,000 |
| Feb 5, 2020 | Completed final sign-off Apr 2020 | 2 Embarcadero Center | Siemens Industry, Inc. | 16th fl - fire alarm work for the "blue cross" remodel. additions are 2 speakers/strobes and 1 strobe. ref pa 2019-1220-0104Details
16th fl - fire alarm work for the "blue cross" remodel. additions are 2 speakers/strobes and 1 strobe. ref pa 2019-1220-0104 | $1,820 |
| Jan 23, 2020 | Completed final sign-off Jun 2020 | 2 Embarcadero Center | M C S Construction Services | deferral mep permit for building permit 201912200104; minor hvac modifications to accomodate new offices new title 24 lighting and work stations powerDetails
deferral mep permit for building permit 201912200104; minor hvac modifications to accomodate new offices new title 24 lighting and work stations power | $75,000 |
| Jan 21, 2020 | Completed final sign-off Apr 2020 | 2 Embarcadero Center | R L H Fire Protection Inc | 16/f: fire sprinkler permit: relocate 10 pendents and remove 2 sprinklers on the 16th fl. ref ti #201912200104.Details
16/f: fire sprinkler permit: relocate 10 pendents and remove 2 sprinklers on the 16th fl. ref ti #201912200104. | $2,000 |
| Jan 7, 2020 | Never finaled issued Jan 2020, no final | 2 Embarcadero Center | street space w/mtaDetails
street space w/mta | ||
| Dec 23, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Skyline Construction | suite 1630: interior fit out on 16th fl to include construction of non load bearing parition and door in existing office space. all existing, door,Details
suite 1630: interior fit out on 16th fl to include construction of non load bearing parition and door in existing office space. all existing, door, | $200,000 |
| Dec 20, 2019 | Completed final sign-off Jun 2020 | 2 Embarcadero Center | M C S Construction Services | 16/f: new non structural partitons, ceiling, lighting, finishes elec. no change in area occupancy use. mep, ls, sprklr sep permit. maher n/a.Details
16/f: new non structural partitons, ceiling, lighting, finishes elec. no change in area occupancy use. mep, ls, sprklr sep permit. maher n/a. | $281,260 |
| Nov 1, 2019 | Completed final sign-off Oct 2021 | 2 Embarcadero Center | M C S Construction Services | 4th floor: non-structural demo, new non-structural partitions, doors, frames, hardware, lighting, millwork, finishes. no change in occupancy or area,or use. mep, life safty, sprinklers under seperate permit. n/a for maherDetails
4th floor: non-structural demo, new non-structural partitions, doors, frames, hardware, lighting, millwork, finishes. no change in occupancy or area,or use. mep, life safty, sprinklers under seperate permit. n/a for maher | $251,084 |
| Oct 15, 2019 | Completed final sign-off Oct 2019 | 2 Embarcadero Center | Golden Gate Fire Protection Inc | 26th, 27th and 28th flrs, fire sprinklers. relocate 6 pendents on the 26th flr. relocate 7 pendents on the 27th flr. relocate 2 pendents on the 28th flr. ref t.i 201907166007 - 28th flr, 201907166006 - 27th flr, 201907166005 - 26th flrDetails
26th, 27th and 28th flrs, fire sprinklers. relocate 6 pendents on the 26th flr. relocate 7 pendents on the 27th flr. relocate 2 pendents on the 28th flr. ref t.i 201907166007 - 28th flr, 201907166006 - 27th flr, 201907166005 - 26th flr | $7,500 |
| Oct 7, 2019 | Expired or cancelled withdrawn Oct 2019 | 2 Embarcadero Center | temporary staging of "dyson" vacuum(s) tech. tour 2019. from october 11, 2019. to oct 14, 2019. no permanent attachment,Details
temporary staging of "dyson" vacuum(s) tech. tour 2019. from october 11, 2019. to oct 14, 2019. no permanent attachment, | $10,000 | |
| Oct 3, 2019 | Completed final sign-off Dec 2022 | 2 Embarcadero Center | Hathaway Dinwiddie Co. | lobby improvement includes new curtain wall, minor slab infill, ceilings, partitions & associated steel structure fl wall, elevator cab finishes & mep. replacement of glass canopy @ podium courtyard & addition of (n) stair from lobby to promenade level.**maher n/a**Details
lobby improvement includes new curtain wall, minor slab infill, ceilings, partitions & associated steel structure fl wall, elevator cab finishes & mep. replacement of glass canopy @ podium courtyard & addition of (n) stair from lobby to promenade level.**maher n/a** | $2,250,000 |
| Oct 3, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Cosco Fire Protection Inc. | replace damaged fire pump w/like diesel fire pump. replace 2 jockey pumps & controllers for all 3 pumpsDetails
replace damaged fire pump w/like diesel fire pump. replace 2 jockey pumps & controllers for all 3 pumps | $28,500 |
| Sep 24, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Peacock Construction | t-24 mechanical for work under pa# 201907166005Details
t-24 mechanical for work under pa# 201907166005 | |
| Sep 24, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Peacock Construction | 26th fl. t-24 mechanical for work under pa# 201907166007.Details
26th fl. t-24 mechanical for work under pa# 201907166007. | |
| Sep 24, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Peacock Construction | 28th fl. t-24 electrical for work under pa's 201907166005, 201907166006 & 201907166007.Details
28th fl. t-24 electrical for work under pa's 201907166005, 201907166006 & 201907166007. | |
| Sep 24, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Peacock Construction | 27th fl. t-24 mechanical for work under pa# 201907166006Details
27th fl. t-24 mechanical for work under pa# 201907166006 | |
| Sep 20, 2019 | Completed final sign-off Feb 2025 | 2 Embarcadero Center | Dome Construction Corp | suite r2308/promenade level: new door opening within (e) buildingDetails
suite r2308/promenade level: new door opening within (e) building | $11,000 |
| Sep 17, 2019 | Never finaled issued Sep 2019, no final | 2 Embarcadero Center | Bcci Construction Company | revision to app#2019 0617 3593. title 24 revision only to void hers inspections, nrch-mch-04-h. n/a for maherDetails
revision to app#2019 0617 3593. title 24 revision only to void hers inspections, nrch-mch-04-h. n/a for maher | |
| Aug 21, 2019 | Completed final sign-off Aug 2020 | 2 Embarcadero Center | Dome Construction Corp | rev to pa# 201907095363; revision of power/data plan, furring out of core walls, removed opening n/a maherDetails
rev to pa# 201907095363; revision of power/data plan, furring out of core walls, removed opening n/a maher | |
| Jul 30, 2019 | Completed final sign-off Jan 2020 | 2 Embarcadero Center | Peacock Construction | install hvac unit on roof, replace 1 piece of glass at skylight, no change in occupancy, use or atrea, sprinklers & life sagety under sep permitDetails
install hvac unit on roof, replace 1 piece of glass at skylight, no change in occupancy, use or atrea, sprinklers & life sagety under sep permit | $150,170 |
| Jul 26, 2019 | Completed final sign-off Sep 2020 | 2 Embarcadero Center | Peacock Construction | work in parking garage - provide floor drains in car wash bay. provide power & water connections for car wash equipment (hand held hose with spray nozzle). no public access to project areaDetails
work in parking garage - provide floor drains in car wash bay. provide power & water connections for car wash equipment (hand held hose with spray nozzle). no public access to project area | $10,000 |
| Jul 23, 2019 | Completed final sign-off Mar 2021 | 2 Embarcadero Center | Hathaway Dinwiddie Co. | new bridge walkways at lobby level w/ glass guardrails.Details
new bridge walkways at lobby level w/ glass guardrails. | $400,000 |
| Jul 16, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Peacock Construction | 27th flr. demo select furniture. new non-structural partitions, doors, frames, glass, ceiling, grid and tile. sprinklers, mep, life-safety under separate permit. maher n/a.Details
27th flr. demo select furniture. new non-structural partitions, doors, frames, glass, ceiling, grid and tile. sprinklers, mep, life-safety under separate permit. maher n/a. | $67,240 |
| Jul 16, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Peacock Construction | 28th flr. demo select furniture. new non-structural partitions, doors, frames, glass, ceiling, grid and tile. sprinklers, mep, life-safety under separate permitDetails
28th flr. demo select furniture. new non-structural partitions, doors, frames, glass, ceiling, grid and tile. sprinklers, mep, life-safety under separate permit | $24,600 |
| Jul 16, 2019 | Completed final sign-off Mar 2020 | 2 Embarcadero Center | Peacock Construction | 26th flr. demo select furniture. new non-structural partitions, doors, frames, glass, ceiling, grid and tile. sprinklers, mep, life-safety under separate permitDetails
26th flr. demo select furniture. new non-structural partitions, doors, frames, glass, ceiling, grid and tile. sprinklers, mep, life-safety under separate permit | $67,240 |
| Jul 9, 2019 | Completed final sign-off Aug 2020 | 2 Embarcadero Center | Dome Construction Corp | ec 2, promenade level, suite r2308. interior build-out of (e) building incl demo, (n) finishes, (n) plumbing, minor electrical and partitions. (e) mech, electrical, plumb and sprinkler system modification is under separate permitDetails
ec 2, promenade level, suite r2308. interior build-out of (e) building incl demo, (n) finishes, (n) plumbing, minor electrical and partitions. (e) mech, electrical, plumb and sprinkler system modification is under separate permit | $500,000 |
| Jun 17, 2019 | Never finaled issued Jun 2019, no final | 2 Embarcadero Center | Bcci Construction Company | 1st fl - revision to pa 2019-0222-3624 architectural revisions only - revised consult room; breakroom configuration, updated ceiling heits, revised power and data locations; revised furniture and equipment locations; lovver attachment detailDetails
1st fl - revision to pa 2019-0222-3624 architectural revisions only - revised consult room; breakroom configuration, updated ceiling heits, revised power and data locations; revised furniture and equipment locations; lovver attachment detail | |
| Jun 12, 2019 | Completed final sign-off Jul 2019 | 2 Embarcadero Center | Golden Gate Fire Protection Inc | lobby level, fire sprinklers. 23 pendent srpinklers and 5 uprights. ti#201902223624Details
lobby level, fire sprinklers. 23 pendent srpinklers and 5 uprights. ti#201902223624 | $40,950 |
| May 23, 2019 | Completed final sign-off Aug 2019 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm work for 1 medical remodel on lobby level, additions are 1 smoke detector, 1 speaker, 11 speaker/strobes, 17 strobes. n/a for maher.Details
fire alarm work for 1 medical remodel on lobby level, additions are 1 smoke detector, 1 speaker, 11 speaker/strobes, 17 strobes. n/a for maher. | $18,220 |
| Apr 8, 2019 | Never finaled issued Apr 2019, no final | 2 Embarcadero Center | Golden Gate Fire Protection Inc | 16th fl - relocate 62 sprinkler pendents; add 7 pendents, relocate 20 uprights, add 2 plug 21 for millenium. ref pa 2018-1130-7087Details
16th fl - relocate 62 sprinkler pendents; add 7 pendents, relocate 20 uprights, add 2 plug 21 for millenium. ref pa 2018-1130-7087 | $45,500 |
| Feb 25, 2019 | Completed final sign-off May 2019 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm work for the "millenium" remodel on floor 16; additions are 1 smk det, 1 module, 3 speakers, 17 speakers/strobes and 5 strobes. maher naDetails
fire alarm work for the "millenium" remodel on floor 16; additions are 1 smk det, 1 module, 3 speakers, 17 speakers/strobes and 5 strobes. maher na | $10,910 |
| Feb 22, 2019 | Completed final sign-off Nov 2019 | 2 Embarcadero Center | Bcci Construction Company | above ground flr - office ti of new non structural partitions, ceiling, casework, finishes, mechanical, electrical and plumbing work maher naDetails
above ground flr - office ti of new non structural partitions, ceiling, casework, finishes, mechanical, electrical and plumbing work maher na | $495,000 |
| Feb 11, 2019 | Completed final sign-off Jun 2019 | 2 Embarcadero Center | Bcci Construction Company | 16th fl mech,elec, plumbing to support apprvd arch. in stall 4 new wshps and 4 new vav boxes. ref 201901140263Details
16th fl mech,elec, plumbing to support apprvd arch. in stall 4 new wshps and 4 new vav boxes. ref 201901140263 | $60,000 |
| Jan 14, 2019 | Completed final sign-off Jun 2019 | 2 Embarcadero Center | Bcci Construction Company | 16th flr - partial floor ti construction of non structural walls, ceiling lightinf and finishes mep deferred maher na.Details
16th flr - partial floor ti construction of non structural walls, ceiling lightinf and finishes mep deferred maher na. | $1,077,796 |
| Nov 30, 2018 | Never finaled issued Nov 2018, no final | 2 Embarcadero Center | Golden Gate Fire Protection Inc | 16th floor sprinkler demo: relocate 79 sprinklers from pendent to upright in prep for future ti, east side partial floor, plug off 11Details
16th floor sprinkler demo: relocate 79 sprinklers from pendent to upright in prep for future ti, east side partial floor, plug off 11 | $39,500 |
| Nov 28, 2018 | Expired or cancelled cancelled Jan 2026 | 2 Embarcadero Center | installation of floor data and power box for existing floor fixtures, electrical onlyDetails
installation of floor data and power box for existing floor fixtures, electrical only | $67,741 | |
| Nov 26, 2018 | Never finaled issued Nov 2018, no final | 2 Embarcadero Center | Dome Construction Corp | revision to 201806283245. correct green form to include arch infoDetails
revision to 201806283245. correct green form to include arch info | |
| Nov 21, 2018 | Completed final sign-off Jun 2019 | 2 Embarcadero Center | Bcci Construction Company | 16th fl - demo of partitions, ceiling system, power/data, and flooring. demo of existing ductwork. per ab-017 ada deferred. relocation of sprinklers from pendent to upright because of removal of lower ceiling under pa 2018-1130-7087Details
16th fl - demo of partitions, ceiling system, power/data, and flooring. demo of existing ductwork. per ab-017 ada deferred. relocation of sprinklers from pendent to upright because of removal of lower ceiling under pa 2018-1130-7087 | $35,000 |
| Nov 8, 2018 | Completed final sign-off Apr 2019 | 2 Embarcadero Center | Peacock Construction | 22nd floor: t-24 mechanical for work under app#201809261406 and 201811024830. n/a maherDetails
22nd floor: t-24 mechanical for work under app#201809261406 and 201811024830. n/a maher | |
| Nov 8, 2018 | Completed final sign-off Apr 2019 | 2 Embarcadero Center | Peacock Construction | 22/f: t24 elec for work under t.i. pa#201809261406 and 201811024830. maher n/a.Details
22/f: t24 elec for work under t.i. pa#201809261406 and 201811024830. maher n/a. | $2,500 |
| Nov 2, 2018 | Completed final sign-off Apr 2019 | 2 Embarcadero Center | Peacock Construction | ti 22nd floor-revision to 201809261406 non struct demo, new millwork, lighting. ele, door, no change in occup, use or area. mep/fire/life safety under sep permit maher naaDetails
ti 22nd floor-revision to 201809261406 non struct demo, new millwork, lighting. ele, door, no change in occup, use or area. mep/fire/life safety under sep permit maher naa | $20,000 |
| Oct 24, 2018 | Completed final sign-off Oct 2019 | 2 Embarcadero Center | Peacock Construction | escalator replacementDetails
escalator replacement | $200,000 |
| Oct 23, 2018 | Completed final sign-off Dec 2018 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm work for the "wework" remodels on floors 29th and 30th; additions are 9 smoke detectors, 4 pull stations, 2 strobe power supplies, 4 modules, 42 speaker/strobes, and 12 strobes. ref pa 2018-0628-3245. n/a for maher.Details
fire alarm work for the "wework" remodels on floors 29th and 30th; additions are 9 smoke detectors, 4 pull stations, 2 strobe power supplies, 4 modules, 42 speaker/strobes, and 12 strobes. ref pa 2018-0628-3245. n/a for maher. | $46,500 |
| Oct 17, 2018 | Completed final sign-off Nov 2018 | 2 Embarcadero Center | R L H Fire Protection Inc | 22nd flr. fire sprinkler ti, relocate 1 and add 1 pendent head at (n) phone rooms. ref pa 201809261406. maher n/a.Details
22nd flr. fire sprinkler ti, relocate 1 and add 1 pendent head at (n) phone rooms. ref pa 201809261406. maher n/a. | $2,500 |
| Sep 26, 2018 | Completed final sign-off Apr 2019 | 2 Embarcadero Center | Peacock Construction | 22nd fl: non-structural dmeo., (n) non-structural partitions, doors, lighting, electrical, finishes. no change in occupancy, use or area. mep, life safety, sprinkler under sep permit. maher naDetails
22nd fl: non-structural dmeo., (n) non-structural partitions, doors, lighting, electrical, finishes. no change in occupancy, use or area. mep, life safety, sprinkler under sep permit. maher na | $89,910 |
| Aug 1, 2018 | Completed final sign-off Nov 2018 | 201 Clay St | R L H Fire Protection Inc | sprinklers ti on 29th and 30th. ref pa# 201806283245; delete 5 pendents and relocate (102) pendent turned upright, add (2) pendent sprinklers. hydro required.Details
sprinklers ti on 29th and 30th. ref pa# 201806283245; delete 5 pendents and relocate (102) pendent turned upright, add (2) pendent sprinklers. hydro required. | $38,841 |
| Jul 24, 2018 | Completed final sign-off Jan 2019 | 2 Embarcadero Center | Dpr Construction | 7th flr. removal of 1 urinal, removal of 1 urinal partition. add 1 wc, add 1 stall door at men's restroom. occupancy remains type b. ref original ba# 201607283557Details
7th flr. removal of 1 urinal, removal of 1 urinal partition. add 1 wc, add 1 stall door at men's restroom. occupancy remains type b. ref original ba# 201607283557 | $10,000 |
| Jul 17, 2018 | Completed final sign-off Jan 2019 | 2 Embarcadero Center | Dpr Construction | 8th flr. removal of 1 urinal at men's restrm, removal of urinal partition at men's restrm. addition of 1 wc at men's restrm, addition aof (1) stall w/door @ men's room; original permit #201607283557Details
8th flr. removal of 1 urinal at men's restrm, removal of urinal partition at men's restrm. addition of 1 wc at men's restrm, addition aof (1) stall w/door @ men's room; original permit #201607283557 | $10,000 |
| Jun 28, 2018 | Completed final sign-off Jun 2019 | 2 Embarcadero Center | Dome Construction Corp | 29th & 30th floors - 10,442 interior remodel - ti for office top (2) floors of 30 story bldg. mep, interior wall partitions, interior storefront, ceiling & floor finishes. maher naDetails
29th & 30th floors - 10,442 interior remodel - ti for office top (2) floors of 30 story bldg. mep, interior wall partitions, interior storefront, ceiling & floor finishes. maher na | $1,300,000 |
| Jun 4, 2018 | Never finaled issued Jun 2018, no final | 2 Embarcadero Center | Golden Gate Fire Protection Inc | lobby - fire sprinklers only relocate 20 pendents for bridal galleria on the lobby areaDetails
lobby - fire sprinklers only relocate 20 pendents for bridal galleria on the lobby area | $5,000 |
| Jun 4, 2018 | Completed final sign-off Jul 2018 | 2 Embarcadero Center | Siemens Industry, Inc. | 13th flr - fire alarm suite 1300 remodel add 4 smk det at electrically locked doors per sffd. maher na. ref#201805240117. (f/a pa#201802282412)Details
13th flr - fire alarm suite 1300 remodel add 4 smk det at electrically locked doors per sffd. maher na. ref#201805240117. (f/a pa#201802282412) | $2,540 |
| May 31, 2018 | Never finaled issued Jun 2018, no final | 201 Clay St | Dome Construction Corp | 29/30 flr - interior demo. remove of interior partition walls, interior storefront, ceiling and floor finishes. bathroom fixtures, ceiling & flooring to be removed. lights, switching controls, conductors, cabling & raceways to panels mech systems back to duct main. n/a for maher.Details
29/30 flr - interior demo. remove of interior partition walls, interior storefront, ceiling and floor finishes. bathroom fixtures, ceiling & flooring to be removed. lights, switching controls, conductors, cabling & raceways to panels mech systems back to duct main. n/a for maher. | $78,805 |
| May 24, 2018 | Never finaled issued May 2018, no final | 2 Embarcadero Center | Principal Builders Inc. | 13/f: revision to 201801249940 to add push to exit button security add signage at elevator lobby doorDetails
13/f: revision to 201801249940 to add push to exit button security add signage at elevator lobby door | $100 |
| May 24, 2018 | Completed final sign-off Nov 2018 | 2 Embarcadero Center | Peacock Construction | title 24 electrical only 1st floor . ref app#201804196806Details
title 24 electrical only 1st floor . ref app#201804196806 | $15,000 |
| May 14, 2018 | Completed final sign-off Jul 2018 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm lobby - add 5 speaker/strobes maher naDetails
fire alarm lobby - add 5 speaker/strobes maher na | $3,200 |
| Apr 19, 2018 | Completed final sign-off Nov 2018 | 2 Embarcadero Center | Peacock Construction | minor demolition, and new non-structural partitions, finishes and millwork. reuse and new lighting. relocate hvac ducts, and grilles, relocate sprinklers to accomodate new layout on separate permits.Details
minor demolition, and new non-structural partitions, finishes and millwork. reuse and new lighting. relocate hvac ducts, and grilles, relocate sprinklers to accomodate new layout on separate permits. | $200,000 |
| Apr 12, 2018 | Completed final sign-off Jul 2018 | 2 Embarcadero Center | A S F Electric Inc | 2nd & ground floors - fa as builts ref 201711103734 mahern aDetails
2nd & ground floors - fa as builts ref 201711103734 mahern a | |
| Apr 12, 2018 | Completed final sign-off Apr 2018 | 2 Embarcadero Center | Ayoob & Peery Plumbing Co Inc | as builts for 201802221920 - 13th flr - add 3, reloate 41 amd plug 14 sprinkler to conform with new new wall/ceiling layout of the ti maher naDetails
as builts for 201802221920 - 13th flr - add 3, reloate 41 amd plug 14 sprinkler to conform with new new wall/ceiling layout of the ti maher na | |
| Mar 5, 2018 | Completed final sign-off Mar 2018 | 2 Embarcadero Center | Siemens Industry, Inc. | 4th flr - fire alarm - add 2 strobes, 2 (e) strobes are being relocated. ref 201801037734 maher naDetails
4th flr - fire alarm - add 2 strobes, 2 (e) strobes are being relocated. ref 201801037734 maher na | $1,200 |
| Feb 28, 2018 | Never finaled issued Feb 2018, no final | 2 Embarcadero Center | Siemens Industry, Inc. | 13th flr, suite 1300 -fire alarm, add 3 speakers and 11 speaker/strobes replace 2 speaker/strobes maher na. ref pa# 201801249440Details
13th flr, suite 1300 -fire alarm, add 3 speakers and 11 speaker/strobes replace 2 speaker/strobes maher na. ref pa# 201801249440 | $8,820 |
| Feb 23, 2018 | Never finaled issued Feb 2018, no final | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm as-built permit for the addition of 2 duct detectors and update to the existing sequence of operation per the sffd testing inspector. the work was done for the "wework" remodels on floor 17. ref. permit app #201707101404Details
fire alarm as-built permit for the addition of 2 duct detectors and update to the existing sequence of operation per the sffd testing inspector. the work was done for the "wework" remodels on floor 17. ref. permit app #201707101404 | $3,170 |
| Feb 22, 2018 | Completed final sign-off Apr 2018 | 2 Embarcadero Center | Ayoob & Peery Plumbing Co Inc | 13th floor: t.i. to relocate 35 and plug 15 sprinklers to conform to the new wall/ceiling layout of the t.i. ref app#201801249440. n/a for maher.Details
13th floor: t.i. to relocate 35 and plug 15 sprinklers to conform to the new wall/ceiling layout of the t.i. ref app#201801249440. n/a for maher. | $7,875 |
| Jan 31, 2018 | Completed final sign-off Feb 2018 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm work for the "suite 470" remodel on floor 4; additions are 1 smoke detector and 1 strobe, as well as the relocation of 1 strobe. ref pa 2018-0103-7734. maher naDetails
fire alarm work for the "suite 470" remodel on floor 4; additions are 1 smoke detector and 1 strobe, as well as the relocation of 1 strobe. ref pa 2018-0103-7734. maher na | $1,500 |
| Jan 24, 2018 | Completed final sign-off Jul 2018 | 2 Embarcadero Center | Principal Builders Inc. | t.i. to demo and construct new partitions, doors, millwork, ceiling, finishes and mep systems in existing tenant space. fire alarms and sprinkler on separate permit. maher n/aDetails
t.i. to demo and construct new partitions, doors, millwork, ceiling, finishes and mep systems in existing tenant space. fire alarms and sprinkler on separate permit. maher n/a | $778,238 |
| Jan 11, 2018 | Completed final sign-off Jan 2018 | 2 Embarcadero Center | R L H Fire Protection Inc | ground floor: fire sprinkler t.i. 3 relocated sprinkler, 1 added sprinkler, & 2 demo sprinkler. ref app#201711103734. n/a for maherDetails
ground floor: fire sprinkler t.i. 3 relocated sprinkler, 1 added sprinkler, & 2 demo sprinkler. ref app#201711103734. n/a for maher | $1,300 |
| Jan 3, 2018 | Completed final sign-off Oct 2018 | 2 Embarcadero Center | Source Planning And Construction Inc | 4th fl - non structural, demo. (n) non-structural partitions, lighting, doors, electrical, finishes. no change in occupancy, use or area. mep, life safety, sprinklers under sep permit. maher n/aDetails
4th fl - non structural, demo. (n) non-structural partitions, lighting, doors, electrical, finishes. no change in occupancy, use or area. mep, life safety, sprinklers under sep permit. maher n/a | $146,172 |
| Dec 22, 2017 | Never finaled issued Jan 2018, no final | 2 Embarcadero Center | Acco Engineered Systems Inc. Dba Acco En | suite 1200 install a 3 ton ac unit to serve as backup to an e ac unit in a server rmDetails
suite 1200 install a 3 ton ac unit to serve as backup to an e ac unit in a server rm | $42,000 |
| Dec 13, 2017 | Expired or cancelled cancelled Jan 2026 | 2 Embarcadero Center | 2nd flr: non structural demo, new non structural partitions, doors, glazing, finishes, no change in occupancy use, or area, mep, life safety & sprinkler under sep permit maheer naDetails
2nd flr: non structural demo, new non structural partitions, doors, glazing, finishes, no change in occupancy use, or area, mep, life safety & sprinkler under sep permit maheer na | $61,074 | |
| Nov 29, 2017 | Never finaled issued Nov 2017, no final | 2 Embarcadero Center | Golden Gate Fire Protection Inc | 11th flr: fire sprinkler only, relocate 12 pendents; maher naDetails
11th flr: fire sprinkler only, relocate 12 pendents; maher na | $3,000 |
| Nov 21, 2017 | Completed final sign-off Dec 2017 | 2 Embarcadero Center | Siemens Industry, Inc. | floor 16: fire alarm work for the blue cross remodel (2017090209050). add 1 smoke detector, 1 speaker, 5 speaker/strobes and 2 strobers maher naDetails
floor 16: fire alarm work for the blue cross remodel (2017090209050). add 1 smoke detector, 1 speaker, 5 speaker/strobes and 2 strobers maher na | $5,715 |
| Nov 10, 2017 | Completed final sign-off Jul 2018 | 2 Embarcadero Center | Gray West Construction Inc | ground floor - convert partial stock room into fitting rm/closet, reconfigure cabinet wall in sales area. creat ada fitting rm; 2nd fl - convert closet into pos niche, reconfigure cabinet wall in sales area, install atachere display window, add ada toilet rm sign dual gender. convert w/ada hcfr dimsDetails
ground floor - convert partial stock room into fitting rm/closet, reconfigure cabinet wall in sales area. creat ada fitting rm; 2nd fl - convert closet into pos niche, reconfigure cabinet wall in sales area, install atachere display window, add ada toilet rm sign dual gender. convert w/ada hcfr dims | $185,667 |
| Nov 9, 2017 | Completed final sign-off Feb 2018 | 2 Embarcadero Center | Skyline Construction | 16th floor: admin permit for mechanical. ref app#201709209050. n/a for maherDetails
16th floor: admin permit for mechanical. ref app#201709209050. n/a for maher | $90,000 |
| Nov 8, 2017 | Completed final sign-off Nov 2017 | 2 Embarcadero Center | R L H Fire Protection Inc | 16/f- fire sprinkler permit, relocate 6, add 1 amd delete 1 pendent sprinklers. t.i. pa#201709209050. n/a ordinance #155-13Details
16/f- fire sprinkler permit, relocate 6, add 1 amd delete 1 pendent sprinklers. t.i. pa#201709209050. n/a ordinance #155-13 | $2,000 |
| Nov 7, 2017 | Completed final sign-off Dec 2017 | 2 Embarcadero Center | Potter Fire Protection | ground floor: relocate 9 and demo 1 fire sprinkler. ref app#201709067108. n/a for maher. space r2106.Details
ground floor: relocate 9 and demo 1 fire sprinkler. ref app#201709067108. n/a for maher. space r2106. | $4,500 |
| Oct 23, 2017 | Never finaled issued Oct 2017, no final | 2 Embarcadero Center | Skyline Construction | electrical work for ti on the 16th fl. ref pa 2017-0920-9050. maher naDetails
electrical work for ti on the 16th fl. ref pa 2017-0920-9050. maher na | $10,000 |
| Oct 20, 2017 | Completed final sign-off Jan 2018 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm work for the "restroom upgrade: remodel on floor 11. additions are 2 duct detectors, 2 speaker/strobes and 1 strobe. ref pa 2017-1006-0581. maher naDetails
fire alarm work for the "restroom upgrade: remodel on floor 11. additions are 2 duct detectors, 2 speaker/strobes and 1 strobe. ref pa 2017-1006-0581. maher na | $2,750 |
| Oct 20, 2017 | Completed final sign-off Dec 2017 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alarm work for the "proper foods" remodel on floor 1; additions are 3 speaker/strobes. ref pa 2017-0906-7108. maher naDetails
fire alarm work for the "proper foods" remodel on floor 1; additions are 3 speaker/strobes. ref pa 2017-0906-7108. maher na | $1,530 |
| Oct 6, 2017 | Completed final sign-off Mar 2018 | 2 Embarcadero Center | Peacock Construction | 11th fl: renovate existing restrooms, add 1 unisex restroom, new non rated partitions, lighting, ceilings, door and frame. power and communication. sprinkler/alarm deferred. n/a for maher.Details
11th fl: renovate existing restrooms, add 1 unisex restroom, new non rated partitions, lighting, ceilings, door and frame. power and communication. sprinkler/alarm deferred. n/a for maher. | $63,000 |
| Sep 20, 2017 | Completed final sign-off Feb 2018 | 2 Embarcadero Center | Skyline Construction | non strucutral demo non struct partitoins, ceiling, lights, doors, millwork, finishes. no change in occupancy, use or area mep sep permit. n/a maherDetails
non strucutral demo non struct partitoins, ceiling, lights, doors, millwork, finishes. no change in occupancy, use or area mep sep permit. n/a maher | $189,852 |
| Sep 6, 2017 | Completed final sign-off Dec 2017 | 2 Embarcadero Center | Northern Sun Associates | r2106:gr fl ti food service to food service. new work includes non bearing partiton, casework, lighting, plumbing, elec, finishes. no seating or eat in dining. all food prepacked and prepared offsite with no req for additional food prep. reuse of mechanical maher not reqDetails
r2106:gr fl ti food service to food service. new work includes non bearing partiton, casework, lighting, plumbing, elec, finishes. no seating or eat in dining. all food prepacked and prepared offsite with no req for additional food prep. reuse of mechanical maher not req | $100,000 |
| Aug 30, 2017 | Never finaled issued Aug 2017, no final | 2 Embarcadero Center | Peacock Construction | t-24 electrical for work done under pa 2017-0602-8212Details
t-24 electrical for work done under pa 2017-0602-8212 | $4,000 |
| Aug 23, 2017 | Completed final sign-off Sep 2017 | 2 Embarcadero Center | Siemens Industry, Inc. | fire alrm work for the "crosslink capital" remodel on floor 22; additions are 1 speaker, 3 speaker/strobes and 3 strobes. ref pa 2017-0630-0789. maher naDetails
fire alrm work for the "crosslink capital" remodel on floor 22; additions are 1 speaker, 3 speaker/strobes and 3 strobes. ref pa 2017-0630-0789. maher na | $3,570 |
| Aug 21, 2017 | Never finaled issued Aug 2017, no final | 2 Embarcadero Center | Siemens Industry, Inc. | 2nd floor fire alarm work for the "macquerie" tenant meeting room. the addition of 1 speaker/strobe. ref pa #201706068502. maher naDetails
2nd floor fire alarm work for the "macquerie" tenant meeting room. the addition of 1 speaker/strobe. ref pa #201706068502. maher na | $510 |
Find contractors for work like this