15 permits since 2000 (engineer on 15 permits): 6 completed, 7 in progress, 2 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 21, 2026 | In progress issued Sep 2026 | 236 King St | Jdl Build Group Dba Jdl Construction | interior t.i. for new fitness center. demolition of non-load partitions. new non-load bearing partitions, new mep and finishesDetails
interior t.i. for new fitness center. demolition of non-load partitions. new non-load bearing partitions, new mep and finishes | $300,000 |
| Sep 10, 2026 | In progress filed Sep 2026, not yet issued | 2435 Ocean Av | mechanical and electrical permit. refer to 202510076895Details
mechanical and electrical permit. refer to 202510076895 | $10,000 | |
| Jun 3, 2026 | In progress issued Jun 2026 | 663 San Jose Av | Topview Construction Group Inc | revision to 202504235073. children restroom relocation, washer/dryer installation, sink, dishwasher connection. one door at infant nap room revision, and addition of one outdoor deck for childcare use.Details
revision to 202504235073. children restroom relocation, washer/dryer installation, sink, dishwasher connection. one door at infant nap room revision, and addition of one outdoor deck for childcare use. | $20,000 |
| Jan 30, 2026 | In progress issued Mar 2026 | 1273 Jackson St | Cogent Llc, S L Construction Co | to comply with nov 202423124 fire repair damaged 4 unit; upgrade to code where required build in kind; fire reapair @ laundromat storage and wash closet value @ 12kDetails
to comply with nov 202423124 fire repair damaged 4 unit; upgrade to code where required build in kind; fire reapair @ laundromat storage and wash closet value @ 12k | $850,000 |
| Jan 26, 2026 | Completed final sign-off May 2026 | 619 Post St | D & K Construction &Painting Company Inc | mep submittal for t.i. 202510278164. provide n) receptacles & gfi/wp receptacles, as indicated in plan, install interial lighting fixture & controls to comply w/ ca energy code req. provide nfs disconnection for e) mech equipment, remove/replace e) panal a with new a1Details
mep submittal for t.i. 202510278164. provide n) receptacles & gfi/wp receptacles, as indicated in plan, install interial lighting fixture & controls to comply w/ ca energy code req. provide nfs disconnection for e) mech equipment, remove/replace e) panal a with new a1 | $30,000 |
| Dec 30, 2025 | In progress filed Dec 2025, not yet issued | 1944 Ocean Av | ref 202502059741- (n) lighting and outletsDetails
ref 202502059741- (n) lighting and outlets | $34,000 | |
| Nov 17, 2025 | In progress issued Nov 2025 | 508 Balboa St | Rsb Construction Group Inc | revision to pa # 2025-0804-2231: change storage to restroom. revise ada restroom layout. revised kitchenette cabinet & sink layout.Details
revision to pa # 2025-0804-2231: change storage to restroom. revise ada restroom layout. revised kitchenette cabinet & sink layout. | $100 |
| Nov 10, 2025 | Completed final sign-off Feb 2026 | 146 Geary St | C C I Commercial Construction & Improv | revision to pa # 2025-0530-7632: comprising below scopes. all changes have been clouded #2. demo removal on non structural partitions & finishes. removal of (e) retail stair finishes. a: (n) retail space & back of house ti improvement. mep (n) mep system for retaul & back of houseDetails
revision to pa # 2025-0530-7632: comprising below scopes. all changes have been clouded #2. demo removal on non structural partitions & finishes. removal of (e) retail stair finishes. a: (n) retail space & back of house ti improvement. mep (n) mep system for retaul & back of house | |
| Jun 23, 2025 | In progress issued Apr 2026 | 663 San Jose Av | Topview Construction Group Inc | prop h:tenant improvements for a licensed child care center. scope of work include non-structural interior demolition. installation of new partition walls. upgrades to restrooms to meet child care and ada requirements. new flooring, finishes, electrical, and plumbing as needed. (change of use)Details
prop h:tenant improvements for a licensed child care center. scope of work include non-structural interior demolition. installation of new partition walls. upgrades to restrooms to meet child care and ada requirements. new flooring, finishes, electrical, and plumbing as needed. (change of use) | $150,000 |
| May 30, 2025 | Completed final sign-off Feb 2026 | 146 Geary St | C C I Commercial Construction & Improv | basement, 1st & 2nd fl t.i. demo non structural partitions/finishes, removal e) retail stairs finishes. new retail space & back of house non structural paritions, ceiling finishes, casement, retail stair enclosure, guardrail, restrooms & b.of n rms w/ada complianct, water fountain. e)elevator remainDetails
basement, 1st & 2nd fl t.i. demo non structural partitions/finishes, removal e) retail stairs finishes. new retail space & back of house non structural paritions, ceiling finishes, casement, retail stair enclosure, guardrail, restrooms & b.of n rms w/ada complianct, water fountain. e)elevator remain | $200,000 |
| Oct 17, 2023 | Completed final sign-off Aug 2025 | 180 Sansome St | Bay City Mechanical Inc | replacing fusible link smoke dampers with new automated fire smoke dampers.Details
replacing fusible link smoke dampers with new automated fire smoke dampers. | $369,000 |
| Oct 3, 2023 | Never finaled filed Oct 2023, never issued | 1800 Owens St | new condenser water unit & new vfd's on sector 1 roof with associated structural support. chilled water piping from new condenser unit will run in an existing shaft down to level 1. no architectural work proposed. all work is mep w/ structural.Details
new condenser water unit & new vfd's on sector 1 roof with associated structural support. chilled water piping from new condenser unit will run in an existing shaft down to level 1. no architectural work proposed. all work is mep w/ structural. | $200,000 | |
| Apr 20, 2022 | Never finaled issued May 2022, no final | 2 Embarcadero Center | Clune Construction Company L P | revision to pa 202009114001 includes (n) return grilles for area on level 20x 21 (n) lighting fixtures and receptacles in various areas.Details
revision to pa 202009114001 includes (n) return grilles for area on level 20x 21 (n) lighting fixtures and receptacles in various areas. | |
| Apr 7, 2022 | Completed final sign-off Oct 2022 | 222 Sansome St | Cw Horton General Contractor | revision to pa# 201907186324. to document change in designated accessible mobility guestrooms.Details
revision to pa# 201907186324. to document change in designated accessible mobility guestrooms. | |
| Feb 23, 2022 | Completed final sign-off Apr 2024 | 140 New Montgomery St | 13th fl: mep deferred submittal to support approved arch drawings. ref/rev pa# 202202017102. architectural revDetails
13th fl: mep deferred submittal to support approved arch drawings. ref/rev pa# 202202017102. architectural rev | $300,000 |