Cw Horton General Contractor
- Based in
- Hayward
- On San Francisco permits
- Nov 2006 to Apr 2022
- Last 24 months
- 0 permits filed
55 permits since 2000: 24 completed, 14 never finaled, 17 expired or cancelled.
Of the 14 never-finaled permits, 1 is 3 to 5 years old, 10 are 5 to 10 years old, 3 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Apr 7, 2022 | Completed final sign-off Oct 2022 | 222 Sansome St | revision to pa# 201907186324. to document change in designated accessible mobility guestrooms.Details
revision to pa# 201907186324. to document change in designated accessible mobility guestrooms. | |
| Oct 15, 2021 | Never finaled issued Nov 2021, no final | 222 Sansome St | revision to app#201911187527. electrical scope only per inspector request.Details
revision to app#201911187527. electrical scope only per inspector request. | $5,000 |
| Jul 1, 2020 | Never finaled issued Jul 2020, no final | 222 Sansome St | new livng wall structural at bldg exterior, scope includes new structural framing, plumbing, electrical and lighting.Details
new livng wall structural at bldg exterior, scope includes new structural framing, plumbing, electrical and lighting. | $60,000 |
| Nov 18, 2019 | Never finaled issued Feb 2020, no final | 222 Sansome St | no change to building area or room count. accessible path of travel upgrades/barrier removal exterior & hotel entry. non-structural demo & repair of (e) materials.new lighting at select areas in elevator lobby & restaurant. 3rd floor corridor new finishes & decorative lighting. new entry at lobby.Details
no change to building area or room count. accessible path of travel upgrades/barrier removal exterior & hotel entry. non-structural demo & repair of (e) materials.new lighting at select areas in elevator lobby & restaurant. 3rd floor corridor new finishes & decorative lighting. new entry at lobby. | $300,000 |
| Oct 4, 2019 | Completed final sign-off Feb 2022 | 222 Sansome St | 3rd fl - inteior remodel of health club and unisex restroom scope include new floor and wall finishes, fitness equipment. existing unisex restroom to be upgrade to comply with current codes with no change in fixture counts. work consist of finishes only and barrier removal.Details
3rd fl - inteior remodel of health club and unisex restroom scope include new floor and wall finishes, fitness equipment. existing unisex restroom to be upgrade to comply with current codes with no change in fixture counts. work consist of finishes only and barrier removal. | $17,000 |
| Jul 18, 2019 | Completed final sign-off Oct 2022 | 222 Sansome St | 38th-48th flrs. renovation of guestrooms and corridors including (n) finishes, plumbing fixtures and flooringDetails
38th-48th flrs. renovation of guestrooms and corridors including (n) finishes, plumbing fixtures and flooring | $2,900,000 |
| Jul 9, 2019 | Completed final sign-off Oct 2021 | 181 03rd St | demo of (e) spa & convert to guestrooms & small office use. renovation of guestrooms, corridors & elevator lobbies for 4th fl includes non-structural upgrade to interior partitions & fee upgrades.Details
demo of (e) spa & convert to guestrooms & small office use. renovation of guestrooms, corridors & elevator lobbies for 4th fl includes non-structural upgrade to interior partitions & fee upgrades. | $615,132 |
| Sep 11, 2018 | Never finaled issued Nov 2018, no final | 2500 Mason St | revision to pa #201711284910. these revisions remove new guest rooms, new offices out of scope, keep existing fitness room and also adjust ceiling in the lobby/dining areas.Details
revision to pa #201711284910. these revisions remove new guest rooms, new offices out of scope, keep existing fitness room and also adjust ceiling in the lobby/dining areas. | |
| Aug 31, 2018 | Completed final sign-off Oct 2018 | 2500 Mason St | revision to 201711164128 to shear wall modifications to rooms 4424 & 4625. maher n/aDetails
revision to 201711164128 to shear wall modifications to rooms 4424 & 4625. maher n/a | $10,000 |
| Mar 1, 2018 | Expired or cancelled cancelled Jan 2026 | 335 Powell St | revision to pa #201709259458: change standpipe access to inside shower stall through swing door glass panel in bathroom (type 11), n/a for maherDetails
revision to pa #201709259458: change standpipe access to inside shower stall through swing door glass panel in bathroom (type 11), n/a for maher | |
| Feb 20, 2018 | Completed final sign-off Jan 2020 | 181 03rd St | renovation of guest rooms, corridors & suites from 5th to 31st floors. work includes (n) showers, casework, finishes, int.signage, mep upgrades. guest room count to be revised from 414 to 401. no exterior work.Details
renovation of guest rooms, corridors & suites from 5th to 31st floors. work includes (n) showers, casework, finishes, int.signage, mep upgrades. guest room count to be revised from 414 to 401. no exterior work. | $7,500,000 |
| Jan 23, 2018 | Expired or cancelled withdrawn Jul 2022 | 405 Taylor St | revision to (e) permit oringinal permit included renovation of hotel fitness room. revised permit includes changes to the proposed lighting plan. ref pa 201708215379 maher naDetails
revision to (e) permit oringinal permit included renovation of hotel fitness room. revised permit includes changes to the proposed lighting plan. ref pa 201708215379 maher na | |
| Oct 20, 2017 | Never finaled issued Nov 2017, no final | 335 Powell St | mep - for general remoedl of guestroom corridor w/replacement of light fixtures. limited remodel of guest room bath rooms. ref arch #201709259458. maher na. floors 3-12 onlyDetails
mep - for general remoedl of guestroom corridor w/replacement of light fixtures. limited remodel of guest room bath rooms. ref arch #201709259458. maher na. floors 3-12 only | |
| Oct 13, 2017 | Never finaled issued Oct 2017, no final | 335 Powell St | revision to pa #201709259458. construction of decorative elements adjacent to stair enclosure floors 3 thru 12. maher naDetails
revision to pa #201709259458. construction of decorative elements adjacent to stair enclosure floors 3 thru 12. maher na | |
| Sep 25, 2017 | Never finaled issued Oct 2017, no final | 335 Powell St | remodel main corridors & guestroom baths. corridor: new portals, chandeliers, signage & wall sconces. guest baths: replace plumbing fixtures in 600 rooms. move walls/fixtures in 102 rooms. no changes to occupancy/hvac/fire life 0n/a maherDetails
remodel main corridors & guestroom baths. corridor: new portals, chandeliers, signage & wall sconces. guest baths: replace plumbing fixtures in 600 rooms. move walls/fixtures in 102 rooms. no changes to occupancy/hvac/fire life 0n/a maher | $3,000,000 |
| Sep 25, 2017 | Never finaled issued Oct 2017, no final | 335 Powell St | remodel 7 accessible guest rooms w/mobility features, accessible bedroom area update to 2016 guidelines, renovate (e) accessible baths with new tub or roll-in shower. work conjunction with future permit for renovate approx. 102 guest rooms. no changes to occupancy/hvac/fire life safety. n/a maherDetails
remodel 7 accessible guest rooms w/mobility features, accessible bedroom area update to 2016 guidelines, renovate (e) accessible baths with new tub or roll-in shower. work conjunction with future permit for renovate approx. 102 guest rooms. no changes to occupancy/hvac/fire life safety. n/a maher | $150,000 |
| Aug 21, 2017 | Expired or cancelled expired Sep 2022 | 405 Taylor St | the project scope consists of the renovation of public spaces in a 16-story hotel on the basement & mezz fl. specific work will include the select demo & construction of walls, ceiling, fixtures and finishes, no change to egress. no exterior work in this permit, no work in the historic lobby.Details
the project scope consists of the renovation of public spaces in a 16-story hotel on the basement & mezz fl. specific work will include the select demo & construction of walls, ceiling, fixtures and finishes, no change to egress. no exterior work in this permit, no work in the historic lobby. | $125,000 |
| Aug 9, 2017 | Completed final sign-off Apr 2018 | 333 Ofarrell St | 8th floor - conversion of office space, which was originally guest rooms back to guest rooms. no additional quantity of rooms being added. mep & life safety separate permit. n/a maher ordinance. work in rooms 831, 832, 8/f, tower 3Details
8th floor - conversion of office space, which was originally guest rooms back to guest rooms. no additional quantity of rooms being added. mep & life safety separate permit. n/a maher ordinance. work in rooms 831, 832, 8/f, tower 3 | $157,007 |
| Aug 8, 2017 | Completed final sign-off Feb 2018 | 333 Ofarrell St | floors 5,8,9,10,11,12,14 - replacement of (e) guest room & back of house doors. n/a maher ordinanceDetails
floors 5,8,9,10,11,12,14 - replacement of (e) guest room & back of house doors. n/a maher ordinance | $991,007 |
| Aug 7, 2017 | Expired or cancelled expired Sep 2022 | 405 Taylor St | accesible rooms ref bpa#201706300767. renovation of non-accessible guestrooms in a 16 story hotel. work on floors 2-17. includes select demolition and construction of walls, ceilings, fixtures and finishes. no change in egress.Details
accesible rooms ref bpa#201706300767. renovation of non-accessible guestrooms in a 16 story hotel. work on floors 2-17. includes select demolition and construction of walls, ceilings, fixtures and finishes. no change in egress. | $1,100,000 |
| Jun 30, 2017 | Expired or cancelled expired Sep 2022 | 405 Taylor St | barrier removal only. scope consists of 10 guestrooms to current accessibility code req. accessible rooms levels 2-11. additional 17 guestrooms updated with communication features. no exterior work. fire life safety under separate permitDetails
barrier removal only. scope consists of 10 guestrooms to current accessibility code req. accessible rooms levels 2-11. additional 17 guestrooms updated with communication features. no exterior work. fire life safety under separate permit | $225,000 |
| Jun 29, 2017 | Never finaled issued Jul 2017, no final | 335 Powell St | renovation of (e) 4 suites on 3rd, 4th, 6th and 12th floors. all areas of work will receive replacement or relocation of (e) plumbing & electrical fixtures, new millwork, new floor, wall, ceiling finishes, minor reconfiguration of interior walls (non-structural). new or replacement doors & frames.Details
renovation of (e) 4 suites on 3rd, 4th, 6th and 12th floors. all areas of work will receive replacement or relocation of (e) plumbing & electrical fixtures, new millwork, new floor, wall, ceiling finishes, minor reconfiguration of interior walls (non-structural). new or replacement doors & frames. | $520,000 |
| May 16, 2017 | Completed final sign-off Aug 2023 | 405 Taylor St | project scope consists of the select demolition & renovation of public space areas. hotel lobby, work includes demolition & construction of walls, ceilings, floors, fixtures & finishes. no exterior work. no change in egress. no plumbing work perform on this permit.Details
project scope consists of the select demolition & renovation of public space areas. hotel lobby, work includes demolition & construction of walls, ceilings, floors, fixtures & finishes. no exterior work. no change in egress. no plumbing work perform on this permit. | $260,500 |
| Jan 23, 2017 | Never finaled issued May 2017, no final | 333 Ofarrell St | barrier removal. general renovation of existing parking level and accessibility upgrade along the path of travel. work inclues accessible parking spot restriping to bring up to cook. work tower 111 on floor 1, 6, 7,8, 9, 10, 11Details
barrier removal. general renovation of existing parking level and accessibility upgrade along the path of travel. work inclues accessible parking spot restriping to bring up to cook. work tower 111 on floor 1, 6, 7,8, 9, 10, 11 | $62,000 |
| Jan 5, 2017 | Completed final sign-off Jul 2017 | 1250 Columbus Av | barrier removal to provide ada access to lower level of extg fitness center for hotel guests use only. scope includes removing a bathroom.Details
barrier removal to provide ada access to lower level of extg fitness center for hotel guests use only. scope includes removing a bathroom. | $150,000 |
| Jul 14, 2016 | Completed final sign-off Oct 2017 | 1250 Columbus Av | renovate 285 (e) guestrooms include tub to shower pluming conversion. new fl & wall finishes & new ff & e. upgrade 10 (e) guestrm for accessiblity req. conversion of 17 (e) guestrm to communication rm. renovate (e) cordidors include replace decorative light fixture in kind. new led light in elevatoDetails
renovate 285 (e) guestrooms include tub to shower pluming conversion. new fl & wall finishes & new ff & e. upgrade 10 (e) guestrm for accessiblity req. conversion of 17 (e) guestrm to communication rm. renovate (e) cordidors include replace decorative light fixture in kind. new led light in elevato | $900,000 |
| May 12, 2016 | Completed final sign-off Oct 2016 | 335 Powell St | revision to pa#2016-0422-5497, to remodel existing corridor on 11/f change out lights, (n) wall coverings carpet, paint, 2 (n) fire/life safety, seperate permit. n/a ordinance #155-13Details
revision to pa#2016-0422-5497, to remodel existing corridor on 11/f change out lights, (n) wall coverings carpet, paint, 2 (n) fire/life safety, seperate permit. n/a ordinance #155-13 | $15,000 |
| May 5, 2016 | Completed final sign-off Aug 2016 | 335 Powell St | remodel of extg men and women's restroom(32nd floor). new finishes, plumbing fixtures, and accessories to replace extg. no lighting fixts. n/a for maherDetails
remodel of extg men and women's restroom(32nd floor). new finishes, plumbing fixtures, and accessories to replace extg. no lighting fixts. n/a for maher | $45,000 |
| Apr 22, 2016 | Completed final sign-off Oct 2016 | 335 Powell St | 11th floor-main bldg-guestrms #1109 & #1172. build (2) model rooms & baths in (e) guestrms/baths. cosmetic remodel. work includes (2) new showers, plbg fixtures, replacement of selected light fixtures w/new, no hvac, no ext. work. n/a maher ordDetails
11th floor-main bldg-guestrms #1109 & #1172. build (2) model rooms & baths in (e) guestrms/baths. cosmetic remodel. work includes (2) new showers, plbg fixtures, replacement of selected light fixtures w/new, no hvac, no ext. work. n/a maher ord | $45,000 |
| Apr 18, 2016 | Never finaled issued Nov 2016, no final | 333 Ofarrell St | new plumbing and finishes for 389 guestroms in tower 2 on floor 7-23. n/a for maher ordinance no.155-13.Details
new plumbing and finishes for 389 guestroms in tower 2 on floor 7-23. n/a for maher ordinance no.155-13. | $4,862,415 |
| Mar 3, 2016 | Completed final sign-off Dec 2016 | 333 Ofarrell St | interior renovation ground floor promenade, tower 1 elevator lobby, and executive conference center. ti includes new finishes, lighting, furniture, and millwork. no mech and elec maher not reqDetails
interior renovation ground floor promenade, tower 1 elevator lobby, and executive conference center. ti includes new finishes, lighting, furniture, and millwork. no mech and elec maher not req | $353,457 |
| Jul 29, 2015 | Never finaled issued Aug 2015, no final | 335 Powell St | mezz. below 2/f- cosmetic renovation of (2) meeting rooms, work includes capret, paint & wall coverings. new light fixtures to replace existing, new lighting controls. no exterior work. n/a ordinance #155-13Details
mezz. below 2/f- cosmetic renovation of (2) meeting rooms, work includes capret, paint & wall coverings. new light fixtures to replace existing, new lighting controls. no exterior work. n/a ordinance #155-13 | $350,000 |
| Jul 24, 2015 | Expired or cancelled cancelled Nov 2024 | 335 Powell St | mezz below 2nd & 2nd flr; cosmetic renovation of (5) existing meeting/convention rooms, work includes carpet, paint wall covering & replacement of (e) light fixtures with new light fix & controls;maher n/aDetails
mezz below 2nd & 2nd flr; cosmetic renovation of (5) existing meeting/convention rooms, work includes carpet, paint wall covering & replacement of (e) light fixtures with new light fix & controls;maher n/a | $600,000 |
| Oct 28, 2013 | Completed final sign-off Apr 2014 | 335 Powell St | voluntary barrier removal and widening doors. replacing 5 bathrtubs with 5 roll in showers in extg accessable guest rooms.Details
voluntary barrier removal and widening doors. replacing 5 bathrtubs with 5 roll in showers in extg accessable guest rooms. | $250,000 |
| Oct 17, 2013 | Never finaled issued Nov 2013, no final | 333 Ofarrell St | commercial tenant improvement to (e) lobby cafe, no mechanical of plumbing, new casework & finishes.Details
commercial tenant improvement to (e) lobby cafe, no mechanical of plumbing, new casework & finishes. | $20,000 |
| May 24, 2013 | Completed final sign-off Jan 2014 | 55 04th St | revision to pa 201209270830. disable access voluntary upgrades to public spaces or hotel - omit partial slope to 4th street bar and grill. add men and women's dry sauna modifications. - add mission a2.5 sheetDetails
revision to pa 201209270830. disable access voluntary upgrades to public spaces or hotel - omit partial slope to 4th street bar and grill. add men and women's dry sauna modifications. - add mission a2.5 sheet | |
| Jan 4, 2013 | Completed final sign-off Dec 2013 | 55 04th St | revision to app#201209270830. new added scope is to install new disabled access pool lifts(2) to extg indoor pool and spa located on 5th level of hotel.Details
revision to app#201209270830. new added scope is to install new disabled access pool lifts(2) to extg indoor pool and spa located on 5th level of hotel. | $8,000 |
| Sep 27, 2012 | Completed final sign-off Jan 2014 | 55 04th St | disabled access voluntary upgrades to public spaces of hotelDetails
disabled access voluntary upgrades to public spaces of hotel | $95,000 |
| Feb 23, 2012 | Completed final sign-off Jul 2013 | 55 04th St | 40 guestroom ada modifications; remodel to conciege lounge & pantry guestroom bathroom backlit mirrors (electrical work - 1500 rooms).Details
40 guestroom ada modifications; remodel to conciege lounge & pantry guestroom bathroom backlit mirrors (electrical work - 1500 rooms). | $650,000 |
| Nov 12, 2009 | Never finaled issued Nov 2009, no final | 335 Powell St | construct new guest accessible ice machine room of public corridor-31st floor, tower. new 1 hr non structural partitions and 30 min door/closer, wall, ceiling & floor finishes. plumb & elect in connection with relocation of (e) ice machine. fire/life safety and fire sprinkler under seperate permit.Details
construct new guest accessible ice machine room of public corridor-31st floor, tower. new 1 hr non structural partitions and 30 min door/closer, wall, ceiling & floor finishes. plumb & elect in connection with relocation of (e) ice machine. fire/life safety and fire sprinkler under seperate permit. | $10,000 |
| Oct 19, 2009 | Completed final sign-off Apr 2010 | 335 Powell St | st francis hotel. remodel reception lobby and tower elevator lobby. voluntary accessibility upgrade of geray st entry doors located approx. 25 feet from street. wall finishes change. paint clgs, new ltg to replace less than 50% existing at reception lobby. new power operated doors at geary entryDetails
st francis hotel. remodel reception lobby and tower elevator lobby. voluntary accessibility upgrade of geray st entry doors located approx. 25 feet from street. wall finishes change. paint clgs, new ltg to replace less than 50% existing at reception lobby. new power operated doors at geary entry | $200,000 |
| Mar 3, 2009 | Completed final sign-off Mar 2009 | 2500 Mason St | to obtain final inspection for work approved under pa#200710125325. all work has been completedDetails
to obtain final inspection for work approved under pa#200710125325. all work has been completed | |
| Mar 3, 2009 | Expired or cancelled expired Nov 2010 | 2500 Mason St | to obtain final inspection for work approved under pa#200704178948. all work has been completedDetails
to obtain final inspection for work approved under pa#200704178948. all work has been completed | |
| Mar 3, 2009 | Expired or cancelled expired Nov 2010 | 2500 Mason St | to obtain final inspection for work approved under pa#200704178933. all work has been completedDetails
to obtain final inspection for work approved under pa#200704178933. all work has been completed | |
| Nov 17, 2008 | Completed final sign-off Jun 2009 | 335 Powell St | cosmetic remodel of 4 (e) public toilet rms.on mezzanine &2nd fl. main bldg. -st.francis hotel.new lav counter tops, faucets,stone flrs, wainscots flrs, (n) fluorescent lights fixt.paint & wall covering.no alts to fire alarm or fire sprinkler system. no hvac or water heater system alteration.Details
cosmetic remodel of 4 (e) public toilet rms.on mezzanine &2nd fl. main bldg. -st.francis hotel.new lav counter tops, faucets,stone flrs, wainscots flrs, (n) fluorescent lights fixt.paint & wall covering.no alts to fire alarm or fire sprinkler system. no hvac or water heater system alteration. | $175,000 |
| Sep 5, 2008 | Completed final sign-off Jun 2009 | 335 Powell St | remodel 6 suites-31st flr (tower) except for some major work in (e) h.c accessible guestroom bath (3180), other work is cosmetic in nature, new wall coverings, paint, carpet, light fixtures, stone finishes, counters in bathrooms, etc. no alteration to hvac or hot water systems, fire, life safety sepDetails
remodel 6 suites-31st flr (tower) except for some major work in (e) h.c accessible guestroom bath (3180), other work is cosmetic in nature, new wall coverings, paint, carpet, light fixtures, stone finishes, counters in bathrooms, etc. no alteration to hvac or hot water systems, fire, life safety sep | $900,000 |
| Jan 28, 2008 | Expired or cancelled expired Jan 2012 | 181 03rd St | guest room suites renovation to 9 suites total. 6 jr. suites - floor 23-28. 3 extreme suites - floor 31. under separate permit: fire protection/fire alarm, sprinkler, hvac, electrical plumbing.Details
guest room suites renovation to 9 suites total. 6 jr. suites - floor 23-28. 3 extreme suites - floor 31. under separate permit: fire protection/fire alarm, sprinkler, hvac, electrical plumbing. | $180,000 |
| Dec 6, 2007 | Expired or cancelled expired Mar 2009 | 2500 Mason St | conversion of e hotel fitness center to 2 guest rooms and a portion of e breezeway and meeting room to n fitness center. revision to 200611077123,200611066930. mech included. fire safety and sprinkler under seperate permit. replace e stairs with new planter boxes.Details
conversion of e hotel fitness center to 2 guest rooms and a portion of e breezeway and meeting room to n fitness center. revision to 200611077123,200611066930. mech included. fire safety and sprinkler under seperate permit. replace e stairs with new planter boxes. | $233,910 |
| Oct 12, 2007 | Expired or cancelled expired Mar 2009 | 2500 Mason St | revision to pa# 2006/11/07/7123. change is the revised accessable path of travel from north point st. sidewalk shown on original permit is incorrect. existing condition is not accessable. one accessible path of travel from beach st. is provided.Details
revision to pa# 2006/11/07/7123. change is the revised accessable path of travel from north point st. sidewalk shown on original permit is incorrect. existing condition is not accessable. one accessible path of travel from beach st. is provided. | |
| Apr 6, 2007 | Expired or cancelled expired Jan 2010 | 2500 Mason St | upgrade 2 public restrms to full ada accessibility compliance.r/r ramp to meet ada accessibility req&cosmetic upgrades to meeting spaces incl replacement of carpet,trim,wall covering& ceiling tiles. this is the 2nd of a 2-phase remodel to the hotel public area.visual alarm shall be under sep permit.Details
upgrade 2 public restrms to full ada accessibility compliance.r/r ramp to meet ada accessibility req&cosmetic upgrades to meeting spaces incl replacement of carpet,trim,wall covering& ceiling tiles. this is the 2nd of a 2-phase remodel to the hotel public area.visual alarm shall be under sep permit. | $300,000 |
| Mar 28, 2007 | Expired or cancelled expired Mar 2009 | 2500 Mason St | specific landscape improvement of new trellis and canopy structures from bldg to structural slab. ref#20061166930Details
specific landscape improvement of new trellis and canopy structures from bldg to structural slab. ref#20061166930 | $100,000 |
| Mar 14, 2007 | Expired or cancelled expired Jan 2010 | 2500 Mason St | ref.appl#200611066930 landscape & ext.improvements incl.outdoor lightingplanting & irrigation renovation, new replacement st.tree @ northpoint,replace paving,steel treelis,canvas awnings,new deck repalcement,glass concrete wall renovation,outdoor gas illumination devices,new flagpoles & sign replaceDetails
ref.appl#200611066930 landscape & ext.improvements incl.outdoor lightingplanting & irrigation renovation, new replacement st.tree @ northpoint,replace paving,steel treelis,canvas awnings,new deck repalcement,glass concrete wall renovation,outdoor gas illumination devices,new flagpoles & sign replace | $1,000,000 |
| Mar 7, 2007 | Expired or cancelled expired Jan 2010 | 2500 Mason St | 2nd phrase of multi-phrase remodel incl flrs 1 to 4 of building 4, 5, 6 of guest rooms & guest flr corridors. remodel incl replacement of carpet, wall covering, sink, vanity counter, selected bathroom flr & wall tile, all required accessibility upgrades.this is 1 building composed of 6 wings.Details
2nd phrase of multi-phrase remodel incl flrs 1 to 4 of building 4, 5, 6 of guest rooms & guest flr corridors. remodel incl replacement of carpet, wall covering, sink, vanity counter, selected bathroom flr & wall tile, all required accessibility upgrades.this is 1 building composed of 6 wings. | $975,000 |
| Nov 7, 2006 | Expired or cancelled expired Jan 2010 | 2500 Mason St | remodel (e) public areas at 1/f including lobby & meeting spaces,phase 1, buiding 2 1/f, public areas. convert restaurant space into meeting room & eating area. sprinklers & life safety seperate permit. remodel male & female public restrooms. sffd assembly permit required.Details
remodel (e) public areas at 1/f including lobby & meeting spaces,phase 1, buiding 2 1/f, public areas. convert restaurant space into meeting room & eating area. sprinklers & life safety seperate permit. remodel male & female public restrooms. sffd assembly permit required. | $1,100,000 |
| Nov 6, 2006 | Expired or cancelled expired Mar 2009 | 2500 Mason St | remodel (e) guestrooms, phase 1, building 1, 2 and 3, sprinkler and life safety under separate permit.Details
remodel (e) guestrooms, phase 1, building 1, 2 and 3, sprinkler and life safety under separate permit. | $975,000 |