Jason A Sayner
- Listed as
- architect, authorized agent-others
- Firm
- Huntsman Ag
- Based in
- Sf
- On San Francisco permits
- Apr 2017 to Jun 2024
29 permits since 2000 (architect on 27 permits, authorized agent-others on 2 permits): 24 completed, 2 in progress, 2 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 13, 2024 | In progress issued Jul 2024 | 4 Embarcadero Center | Gci, Inc | 10/f: demo, non structural partitions. construction of new non structural partitions & finishes. mechanical & electricalDetails
10/f: demo, non structural partitions. construction of new non structural partitions & finishes. mechanical & electrical | $1,000,000 |
| Apr 29, 2024 | In progress issued May 2024 | 4 Embarcadero Center | Gci, Inc | 23rd fl - new non-structural partitions including new millwork & finishes. mechanical - new exhaust fans, ductwork & air distribution, ddc controls & air balance. power, lighting & signalDetails
23rd fl - new non-structural partitions including new millwork & finishes. mechanical - new exhaust fans, ductwork & air distribution, ddc controls & air balance. power, lighting & signal | $1,273,322 |
| Apr 22, 2024 | Completed final sign-off Jan 2025 | 415 Mission St | Hathaway Dinwiddie Co. | 4/f: conversion of an (e) it provisioning room into bt lab work room. relocation of selective furniture, selective relocation of lighting fixtures, upgrades of (e) partitions to the 1hr fire rating and door replacement, minor structural and hvac work included. no chang of occupant load or egressDetails
4/f: conversion of an (e) it provisioning room into bt lab work room. relocation of selective furniture, selective relocation of lighting fixtures, upgrades of (e) partitions to the 1hr fire rating and door replacement, minor structural and hvac work included. no chang of occupant load or egress | $1,350,000 |
| Mar 20, 2024 | Completed final sign-off Jan 2025 | 535 Mission St | Skyline Construction | 25th fl - interior tenant improvement of existing office; demolition of existing walls and ceilings (minor demo); deferred mep on separate permitDetails
25th fl - interior tenant improvement of existing office; demolition of existing walls and ceilings (minor demo); deferred mep on separate permit | $1,500,000 |
| Mar 15, 2024 | Completed final sign-off Jul 2024 | 2 Embarcadero Center | Peacock Construction | selective demolition of non structural ceilings, lights, electrical millwork and finishes. construction of non structural partitions, lights, doors/windows, ele milwork finishes. no change in occupancy. use or areaDetails
selective demolition of non structural ceilings, lights, electrical millwork and finishes. construction of non structural partitions, lights, doors/windows, ele milwork finishes. no change in occupancy. use or area | $130,000 |
| Mar 6, 2024 | Completed final sign-off Apr 2024 | 3 Embarcadero Center | M C S Construction Services | 11/f suite 1120: revision to permit 202401123863. removal and reconfiguration of 2 offices, addition of pocket door, and reconfiguration of support it space.Details
11/f suite 1120: revision to permit 202401123863. removal and reconfiguration of 2 offices, addition of pocket door, and reconfiguration of support it space. | |
| Mar 4, 2024 | Completed final sign-off Oct 2024 | 4 Embarcadero Center | M C S Construction Services | selective demo of non struct ceilings, lights elect, millwork and finishes construction of non struct partitions lights, doors windows, elec, mill work and finishes no change in occupancy, use or areaDetails
selective demo of non struct ceilings, lights elect, millwork and finishes construction of non struct partitions lights, doors windows, elec, mill work and finishes no change in occupancy, use or area | $737,208 |
| Feb 28, 2024 | Completed final sign-off Apr 2024 | 3 Embarcadero Center | M C S Construction Services | 11th fl, ste 1120 - deferred mech & elect. pa 202401123863 & 202403067187 mech. demo & replacement of grilles, registers & diffusers for office refresh. demo & install new dual duct vav boxes. electrical lighting fixtures & associated circuiting/controls. power & signal devices & associated wiringDetails
11th fl, ste 1120 - deferred mech & elect. pa 202401123863 & 202403067187 mech. demo & replacement of grilles, registers & diffusers for office refresh. demo & install new dual duct vav boxes. electrical lighting fixtures & associated circuiting/controls. power & signal devices & associated wiring | $150,000 |
| Jan 22, 2024 | Completed final sign-off Dec 2024 | 4 Embarcadero Center | Gci, Inc | 31/f: new phone booth added to the area of work. no channge in occupancy use or area.Details
31/f: new phone booth added to the area of work. no channge in occupancy use or area. | $30,000 |
| Jan 12, 2024 | Completed final sign-off Apr 2024 | 3 Embarcadero Center | M C S Construction Services | 11th fl, ste 1120 project is located scope consists of removal of non-strucutral partitions, glazing, doors, millwork, lighting, wall and floor finishes throughout. construction of (n) non-structural demising partition and internal suite partitions. (n) inferior glazing, doors, lights, millwork andDetails
11th fl, ste 1120 project is located scope consists of removal of non-strucutral partitions, glazing, doors, millwork, lighting, wall and floor finishes throughout. construction of (n) non-structural demising partition and internal suite partitions. (n) inferior glazing, doors, lights, millwork and | $450,000 |
| Dec 26, 2023 | Completed final sign-off Mar 2024 | 2 Embarcadero Center | Gci, Inc | project is located on the 22nd fl. consist of addition of four pre-fab phone booths no change of occupancy, use or areaDetails
project is located on the 22nd fl. consist of addition of four pre-fab phone booths no change of occupancy, use or area | $82,500 |
| Dec 13, 2023 | Completed final sign-off Dec 2024 | 4 Embarcadero Center | Gci, Inc | removal of interconnecting staircase and infill slab between floors 31 and 32. no change of occupancy or use.Details
removal of interconnecting staircase and infill slab between floors 31 and 32. no change of occupancy or use. | $65,481 |
| Dec 6, 2023 | Completed final sign-off Dec 2024 | 4 Embarcadero Center | Gci, Inc | 31st fl, ste 3100 - demo of non structural partitions, glazing, doors, millwork, wall & floor finishes throughout & selective demo of light fixtures; construction of (n) non-structural demizing partition & internal suite partitions; (n) glazing, doors, lights, millwork and finishesDetails
31st fl, ste 3100 - demo of non structural partitions, glazing, doors, millwork, wall & floor finishes throughout & selective demo of light fixtures; construction of (n) non-structural demizing partition & internal suite partitions; (n) glazing, doors, lights, millwork and finishes | $417,252 |
| Sep 1, 2023 | Completed final sign-off May 2024 | 535 Mission St | Gci, Inc | 11th fl: t.i includes the demo of non-str partitions and building new non-structural partitions. all new or revised hvac electrical, plumbing and life safety/prinkler work will be design build and submitted for permit separately. building is fully sprinklered.Details
11th fl: t.i includes the demo of non-str partitions and building new non-structural partitions. all new or revised hvac electrical, plumbing and life safety/prinkler work will be design build and submitted for permit separately. building is fully sprinklered. | $1,273,134 |
| Aug 7, 2023 | Completed final sign-off Feb 2024 | 1 Embarcadero Center | M C S Construction Services | 25/f: revision to pa# 202303163759, revising hallway doors/partitions only to be non-rated. no change in occupancy or use.Details
25/f: revision to pa# 202303163759, revising hallway doors/partitions only to be non-rated. no change in occupancy or use. | |
| Jun 23, 2023 | Completed final sign-off Nov 2023 | 1 Embarcadero Center | M C S Construction Services | 11th fl. design build ti. demo noin struct partioins, doors, glazing, lighting, plumbing,finishes. replace removed fireproofing w new to maintain e fire ratings. construct new non structural partitions. e ceilig grid to remain. replace damaged parts, new act, lighting, millwork, finishes throughout.Details
11th fl. design build ti. demo noin struct partioins, doors, glazing, lighting, plumbing,finishes. replace removed fireproofing w new to maintain e fire ratings. construct new non structural partitions. e ceilig grid to remain. replace damaged parts, new act, lighting, millwork, finishes throughout. | $431,538 |
| Jun 14, 2023 | Never finaled issued Jun 2023, no final | 291 Geary St | Reinhardt Construction Solutions Llc | #510: revision to pa# 202306059229. frame thickness (metal studs). wall attachments.Details
#510: revision to pa# 202306059229. frame thickness (metal studs). wall attachments. | |
| Jun 8, 2023 | Completed final sign-off Jan 2024 | 1 Embarcadero Center | M C S Construction Services | 41/f: design build t.i., rr/lobby remodel, demo of nonstructural partitions, doors, glazing, plumbing, vinishes, replace removed fire proofing w/new to match (e)fire ratings, new nonstruc partitions. (e) ceiling grid to remain, new act tiles, lighting, millwork, finishesDetails
41/f: design build t.i., rr/lobby remodel, demo of nonstructural partitions, doors, glazing, plumbing, vinishes, replace removed fire proofing w/new to match (e)fire ratings, new nonstruc partitions. (e) ceiling grid to remain, new act tiles, lighting, millwork, finishes | $870,830 |
| Jun 5, 2023 | Never finaled issued Jun 2023, no final | 291 Geary St | Reinhardt Construction Solutions Llc | unit 510: build partition walls (4) glass fronted offices, install new lights/plugs, install data/routers, sheetrock walls, wood painted doorsDetails
unit 510: build partition walls (4) glass fronted offices, install new lights/plugs, install data/routers, sheetrock walls, wood painted doors | $110,000 |
| May 30, 2023 | Completed final sign-off Oct 2023 | 4 Embarcadero Center | M C S Construction Services | ste 710 - interior commercial ti of existing tenant space. includes non-structural demolition of existing ti and build out of new including non-structural partitions, doors and sidelites, suspended ceiling, casework, and finishes. mep and life safety systems are design-build under a separate permiDetails
ste 710 - interior commercial ti of existing tenant space. includes non-structural demolition of existing ti and build out of new including non-structural partitions, doors and sidelites, suspended ceiling, casework, and finishes. mep and life safety systems are design-build under a separate permi | $495,000 |
| May 22, 2023 | Completed final sign-off Nov 2024 | 1 Embarcadero Center | Skyline Construction | 25/f: t.i work includes non-structural partitions, ceiling and finishes. mep deferred.Details
25/f: t.i work includes non-structural partitions, ceiling and finishes. mep deferred. | $750,000 |
| May 11, 2023 | Completed final sign-off Feb 2024 | 3 Embarcadero Center | Gci, Inc | ste 1480: interior commercial t.i. of (e) space. non-structural demo of (e) t.i. and build-out of new including non-structural partitions, doors, & sidelites, suspended ceilings, casework, & finishes. mep & life safety systems are design-build under separate permit.Details
ste 1480: interior commercial t.i. of (e) space. non-structural demo of (e) t.i. and build-out of new including non-structural partitions, doors, & sidelites, suspended ceilings, casework, & finishes. mep & life safety systems are design-build under separate permit. | $450,562 |
| May 11, 2023 | Completed final sign-off Feb 2024 | 2 Embarcadero Center | Gci, Inc | ste 2200, 22nd fl - interior ccommercial ti of (e) tenant space includes non-structural demo of (e) ti and build out of new including non-structural partitions, doors and sidelites, suspended ceilings, casework and finishes. mep and life safety systems are design build under a separate permitDetails
ste 2200, 22nd fl - interior ccommercial ti of (e) tenant space includes non-structural demo of (e) ti and build out of new including non-structural partitions, doors and sidelites, suspended ceilings, casework and finishes. mep and life safety systems are design build under a separate permit | $948,383 |
| May 4, 2023 | Completed final sign-off Dec 2023 | 1 Embarcadero Center | Gci, Inc | interior commercial ti of (e) tenant space, includes non structural demo of (e) ti and build out of new including non structural partitions, doors and sidelites, suspened ceilings, casework, and finishes mep and life safety systems are design -build under separate permitDetails
interior commercial ti of (e) tenant space, includes non structural demo of (e) ti and build out of new including non structural partitions, doors and sidelites, suspened ceilings, casework, and finishes mep and life safety systems are design -build under separate permit | $575,693 |
| Mar 16, 2023 | Completed final sign-off Feb 2024 | 1 Embarcadero Center | M C S Construction Services | 25/f: restroom and elevator lobby remodel with new hallway non-structural partitions and new demising non-structural partitions. no change in occupancy, use, or areaDetails
25/f: restroom and elevator lobby remodel with new hallway non-structural partitions and new demising non-structural partitions. no change in occupancy, use, or area | $275,000 |
| Mar 10, 2023 | Completed final sign-off Aug 2023 | 535 Mission St | M C S Construction Services | 22nd fl, ste 2250 interior ti including non structural demo. non structural (n) partitions, doors, millwork and finishesDetails
22nd fl, ste 2250 interior ti including non structural demo. non structural (n) partitions, doors, millwork and finishes | $592,524 |
| Mar 7, 2023 | Completed final sign-off May 2023 | 4 Embarcadero Center | Hp Build | 37th fl-ste 3720: non-structural demo tenant improvement (partial suite), incl non-struct partition removal & removing one door. life safety & sprinklers deferred. no ceiling work.Details
37th fl-ste 3720: non-structural demo tenant improvement (partial suite), incl non-struct partition removal & removing one door. life safety & sprinklers deferred. no ceiling work. | $85,456 |
| Mar 3, 2023 | Completed final sign-off Jul 2023 | 3 Embarcadero Center | Peacock Construction | 16th fl: non structural demo upgrade toilet rooms to full t24 compliance (n) finishes in elev. lobby & common corridor no change in occupancy use or area mep, life safet and sprinkers defferedDetails
16th fl: non structural demo upgrade toilet rooms to full t24 compliance (n) finishes in elev. lobby & common corridor no change in occupancy use or area mep, life safet and sprinkers deffered | $175,000 |
| Apr 27, 2017 | Expired or cancelled cancelled Oct 2026 | 2950 Pacific Av | Impact Builders Llc, Thompson Suskind L P | provide temporary shoring to facilitate excavation and construction of bldg reference to application # 201602028565 remodel. n/a maher ord. 155-13Details
provide temporary shoring to facilitate excavation and construction of bldg reference to application # 201602028565 remodel. n/a maher ord. 155-13 | $80,000 |