207 permits since 2000 (architect on 198 permits, designer on 4 permits, engineer on 2 permits, lessee on 2 permits, authorized agent-others on 1 permit): 168 completed, 2 in progress, 28 never finaled, 9 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 207.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 23, 2025 | In progress issued Jan 2025 | 1155 Battery St | Sc Builders, Inc | 5th & 7th fl revision to pa # 2024-0927-1790 modification of (e) conference rooms & offices. new interior partitions. new doors & finishes. minor rework of (e) mech & electrical under separate permit for projectDetails
5th & 7th fl revision to pa # 2024-0927-1790 modification of (e) conference rooms & offices. new interior partitions. new doors & finishes. minor rework of (e) mech & electrical under separate permit for project | |
| Sep 27, 2024 | In progress issued Jan 2025 | 1155 Battery St | Sc Builders, Inc | 4,5, and 7th fl multi level area ti modifications of existing spaces to conference rooms and office. new interior partitions, new doors and new finishes rk f e mech and electrical. 4th fl 880 sf, 5th 1404 sf, 7th fl 1472 sfDetails
4,5, and 7th fl multi level area ti modifications of existing spaces to conference rooms and office. new interior partitions, new doors and new finishes rk f e mech and electrical. 4th fl 880 sf, 5th 1404 sf, 7th fl 1472 sf | $300,000 |
| Apr 10, 2024 | Completed final sign-off Nov 2024 | 1 Sansome St | Mc Carthy Building Companies Inc | suite 1900: interior office remodel. new non structural walls, new electrical, new millwork, rework existing mechanical, flooring, new ceiling, breakroom.Details
suite 1900: interior office remodel. new non structural walls, new electrical, new millwork, rework existing mechanical, flooring, new ceiling, breakroom. | $3,100,000 |
| Mar 11, 2024 | Completed final sign-off Nov 2024 | 1 Sansome St | Mc Carthy Building Companies Inc | suite 1900: interior office demo of non structural paritions, ceiling, flooring, some mech and elec work. existing egress not impacted by demo work. existing sprinklers to remain.Details
suite 1900: interior office demo of non structural paritions, ceiling, flooring, some mech and elec work. existing egress not impacted by demo work. existing sprinklers to remain. | $95,000 |
| Mar 13, 2023 | Never finaled issued Mar 2023, no final | 855 Geary St | Skyline Construction | removal of existing striping and re-striping of ground floor garage only. memorialization of change of planning use from public to private parking; ref cua# 2022-005541Details
removal of existing striping and re-striping of ground floor garage only. memorialization of change of planning use from public to private parking; ref cua# 2022-005541 | $6,000 |
| Feb 28, 2023 | Completed final sign-off Apr 2024 | 855 Geary St | Skyline Construction | replacement parking garage entry gates and doorsDetails
replacement parking garage entry gates and doors | $95,000 |
| Dec 29, 2022 | Completed final sign-off Sep 2023 | 1 California St | Field Construction Inc. | 29/f: interior renovation of tenant suite including addition of four (4) private offices with non-load bearing walls, new tiles, new light fixtures, finishes and furniture. mech and electrical upgrades.Details
29/f: interior renovation of tenant suite including addition of four (4) private offices with non-load bearing walls, new tiles, new light fixtures, finishes and furniture. mech and electrical upgrades. | $304,000 |
| Jul 25, 2022 | Completed final sign-off May 2023 | 855 Geary St | Skyline Capital Builders Llc | 1st fl- expansion of office to include new act ceiling, non load bearing walls and finishes. remodel and add one restroom and new platform for ada lift.Details
1st fl- expansion of office to include new act ceiling, non load bearing walls and finishes. remodel and add one restroom and new platform for ada lift. | $1,500,000 |
| Jun 29, 2022 | Never finaled issued Sep 2022, no final | 1275 Market St | San Francisco Commercial Builders Inc | administrative permit to memorialize cafe for dph. no work under this permit ref work permit 201406279881/r1. operational assembly permit deferred.Details
administrative permit to memorialize cafe for dph. no work under this permit ref work permit 201406279881/r1. operational assembly permit deferred. | |
| May 20, 2022 | Completed final sign-off Sep 2022 | 855 Geary St | Skyline Construction | two new vehicle lifts at basement level, and ada stair handrail upgrades. lifts are for maintenance only. no addition of new parking or alteration of striping approved under pa# 202204071820.Details
two new vehicle lifts at basement level, and ada stair handrail upgrades. lifts are for maintenance only. no addition of new parking or alteration of striping approved under pa# 202204071820. | $45,000 |
| May 10, 2022 | Completed final sign-off Feb 2023 | 1800 Owens St | Principal Builders Inc. | floor c5: demolition of existing non-load bearing partitions and ceilings in existing kitchen. removal of all kitchen equipment.Details
floor c5: demolition of existing non-load bearing partitions and ceilings in existing kitchen. removal of all kitchen equipment. | $449,158 |
| Apr 7, 2022 | Never finaled issued Apr 2022, no final | 855 Geary St | Skyline Capital Builders Llc | change of use per planning from private parking to public parking. car share & bicycle parking at ground floor only per planning com motion no.20531. no change of use at basement or 2nd fl which remain private parking. no change of occupancy. all work is striping/barrier removal for ada parking.Details
change of use per planning from private parking to public parking. car share & bicycle parking at ground floor only per planning com motion no.20531. no change of use at basement or 2nd fl which remain private parking. no change of occupancy. all work is striping/barrier removal for ada parking. | $50,000 |
| Feb 15, 2022 | Completed final sign-off Jun 2022 | 425 Market St | Skyline Construction | 13th floor:revision to pa #202012070382 to relocate extg exit signage and card reader location.Details
13th floor:revision to pa #202012070382 to relocate extg exit signage and card reader location. | |
| Feb 15, 2022 | Completed final sign-off Jun 2022 | 425 Market St | Skyline Construction | 12th floor:revision to pa #202012070367 to relocate extg exit signage and card reader location.Details
12th floor:revision to pa #202012070367 to relocate extg exit signage and card reader location. | |
| Dec 15, 2021 | Never finaled issued Dec 2021, no final | 1800 Owens St | Principal Builders Inc. | 12th fl bldg c - administrative conversion of existing library (b occupancy) to classroom (a occupancy) occ load: 84.Details
12th fl bldg c - administrative conversion of existing library (b occupancy) to classroom (a occupancy) occ load: 84. | |
| Dec 15, 2021 | Completed final sign-off Jul 2022 | 201 Mendell St | rev to pa202107305451: mod (e) space. repair ceilings affcted by demo. (e) security gates and bars to be removed.Details
rev to pa202107305451: mod (e) space. repair ceilings affcted by demo. (e) security gates and bars to be removed. | ||
| Dec 10, 2021 | Completed final sign-off Sep 2023 | 630 Cesar Chavez St | Truebeck Construction | demolition of existing warehouse, including foundationDetails
demolition of existing warehouse, including foundation | $15,000 |
| Nov 12, 2021 | Completed final sign-off May 2022 | 500 03rd St | Rossi Builders Inc. | suite 110: interior renovation: new ceiling tiles, new light fixtures, new flooring throughout. selectrive demo and construction as shower on plans. deferrered mep & fire/life safety. maher n/a.Details
suite 110: interior renovation: new ceiling tiles, new light fixtures, new flooring throughout. selectrive demo and construction as shower on plans. deferrered mep & fire/life safety. maher n/a. | $199,000 |
| Nov 10, 2021 | Expired or cancelled withdrawn Jun 2022 | 630 Cesar Chavez St | Truebeck Construction | erect new 1-story bldg, type 1-a, occup. use f-1/s-1, for new maintenance and vehicle charging facility for cruise.Details
erect new 1-story bldg, type 1-a, occup. use f-1/s-1, for new maintenance and vehicle charging facility for cruise. | $750,000 |
| Sep 8, 2021 | Completed final sign-off Jul 2022 | 1800 Owens St | Principal Builders Inc. | 4th fl ti in sectors c and d. work includes non structural partitoins, act, fixtures and finishesDetails
4th fl ti in sectors c and d. work includes non structural partitoins, act, fixtures and finishes | $1,500,000 |
| Aug 19, 2021 | Completed final sign-off Feb 2022 | 100 California St | Principal Builders Inc. | 14/f: interior renovation of tenant suite. renovation of 2 converence rooms, 2 huddle rooms into 2 private offices and 1 small conference room and seating area. new non load bearing walls,ceiling tiles, new lights, finishesDetails
14/f: interior renovation of tenant suite. renovation of 2 converence rooms, 2 huddle rooms into 2 private offices and 1 small conference room and seating area. new non load bearing walls,ceiling tiles, new lights, finishes | $170,000 |
| Jul 30, 2021 | Never finaled issued Dec 2021, no final | 201 Mendell St | Plant Construction Co, Lp | interior renovations of commercial tenant space to include new doors at demising wall, new ceiling tiles, new ada upgrades to (e) restrooms. portion of the building change of use from assembly to photo studio(a-3 to b). mep and fire life safety under separate permit.Details
interior renovations of commercial tenant space to include new doors at demising wall, new ceiling tiles, new ada upgrades to (e) restrooms. portion of the building change of use from assembly to photo studio(a-3 to b). mep and fire life safety under separate permit. | $750,000 |
| Jun 15, 2021 | Never finaled issued Jun 2021, no final | 425 Market St | Skyline Construction | 13/f: rev to pa20201207382 to show new and existing card readers and updated door schedule. maher n/aDetails
13/f: rev to pa20201207382 to show new and existing card readers and updated door schedule. maher n/a | |
| Jun 2, 2021 | Never finaled issued Jul 2021, no final | 425 Market St | Skyline Construction | revision to 202012070367 to show new and existing card readers. show updated door shedule and new mill workDetails
revision to 202012070367 to show new and existing card readers. show updated door shedule and new mill work | |
| May 14, 2021 | Expired or cancelled cancelled Jan 2026 | 425 Market St | revison to pa# 2020-1207-0367. installation of card readers - 12/f.Details
revison to pa# 2020-1207-0367. installation of card readers - 12/f. | ||
| Mar 22, 2021 | Never finaled issued May 2021, no final | 1800 Owens St | Principal Builders Inc. | 2nd fl: tenant improvement includes demo of non-load bearing partitions. construction to include new non-load bearing partitions, lighting, millwork, & finishes. mep & fire life safety under separate permit.Details
2nd fl: tenant improvement includes demo of non-load bearing partitions. construction to include new non-load bearing partitions, lighting, millwork, & finishes. mep & fire life safety under separate permit. | $300,000 |
| Jan 13, 2021 | Never finaled issued Jun 2021, no final | 1501 Tennessee St | administrative change of use to document land use designation from storage warehouse to motor vehicle tow service.no work under this permit; all life-safety and egress to be revied under future t.i. permit. no cfc to be issued for this use until future t.i is filed and issued.Details
administrative change of use to document land use designation from storage warehouse to motor vehicle tow service.no work under this permit; all life-safety and egress to be revied under future t.i. permit. no cfc to be issued for this use until future t.i is filed and issued. | ||
| Dec 7, 2020 | Completed final sign-off Jun 2022 | 425 Market St | Skyline Construction | 13th floor: interior modifications of existing office space, demo of non-loading partitions, ceilings. new non-load beaing partitions, new finishes, etc. mep, life safety, & sprinklers under separate permit. building fully sprinklered.Details
13th floor: interior modifications of existing office space, demo of non-loading partitions, ceilings. new non-load beaing partitions, new finishes, etc. mep, life safety, & sprinklers under separate permit. building fully sprinklered. | $750,000 |
| Dec 7, 2020 | Completed final sign-off May 2022 | 425 Market St | Skyline Construction | 12/f: interior modification of (e) office space. demo of non-load bearing partitions, (n) non-load bearing partitions, (n) finishes etc. mep, life safety and sprinklers under separate permit. building fully sprinkleredDetails
12/f: interior modification of (e) office space. demo of non-load bearing partitions, (n) non-load bearing partitions, (n) finishes etc. mep, life safety and sprinklers under separate permit. building fully sprinklered | $750,000 |
| Nov 30, 2020 | Completed final sign-off Nov 2021 | 163 Freelon St | Sc Builders, Inc | tenant improvement consists of selective demolition of non load bearing partitions. demo of existing lighting. construction of new non load bearing partitions. mep under separate permit.Details
tenant improvement consists of selective demolition of non load bearing partitions. demo of existing lighting. construction of new non load bearing partitions. mep under separate permit. | $75,000 |
| Nov 23, 2020 | Completed final sign-off Aug 2021 | 901 Mission St | Sc Builders, Inc | 3/f: t.i. of (e) office space including selective demo of non-load bearing partitions, new finishes, millwork & furniture. mep under sep permit if affects (e) system if needed. bldg is fully sprinkled.Details
3/f: t.i. of (e) office space including selective demo of non-load bearing partitions, new finishes, millwork & furniture. mep under sep permit if affects (e) system if needed. bldg is fully sprinkled. | $2,200,000 |
| Oct 31, 2020 | Completed final sign-off Aug 2021 | 160 Spear St | Sc Builders, Inc | 15th fl, #1500: (e) office partial t.i.. (n) non-structural partition. (n) millwork, (n) flooring, (n) m.e.p. submitted separately.Details
15th fl, #1500: (e) office partial t.i.. (n) non-structural partition. (n) millwork, (n) flooring, (n) m.e.p. submitted separately. | $310,000 |
| Oct 17, 2020 | Completed final sign-off Dec 2021 | 1800 Owens St | Principal Builders Inc. | bldg c: 11th floor ti: add 8 offices, 1 print station. modify (e) conference room to reception area (area of work 1140 sq ft). 12th floor ti: add 6 offices, 1 print station. modify (e) quiet room into a "mother's room" (area of work 1009 sq ft.Details
bldg c: 11th floor ti: add 8 offices, 1 print station. modify (e) conference room to reception area (area of work 1140 sq ft). 12th floor ti: add 6 offices, 1 print station. modify (e) quiet room into a "mother's room" (area of work 1009 sq ft. | $500,000 |
| Aug 24, 2020 | Completed final sign-off Dec 2020 | 1100 Van Ness Av | Rudolph And Sletten Inc | modification of existing hardware on levels 4, 5 and 6Details
modification of existing hardware on levels 4, 5 and 6 | $160,000 |
| Aug 22, 2020 | Completed final sign-off Dec 2020 | 1100 Van Ness Av | Rudolph And Sletten Inc | modification of (e) hardware on levels 2 & 3. addition of electrical outlets in conference room on level 3 and addition of curtain and tracks to level 6. n/a maherDetails
modification of (e) hardware on levels 2 & 3. addition of electrical outlets in conference room on level 3 and addition of curtain and tracks to level 6. n/a maher | $160,000 |
| Mar 3, 2020 | Completed final sign-off Aug 2020 | 1100 Van Ness Av | Rudolph And Sletten Inc | modify electrical outlets, electrical panels, curtains, casework, and equipment in 1415 sq ft on level 4 & 5 of the existing medical office building and add a transformer to the existing mechanical room on level 2.Details
modify electrical outlets, electrical panels, curtains, casework, and equipment in 1415 sq ft on level 4 & 5 of the existing medical office building and add a transformer to the existing mechanical room on level 2. | $620,000 |
| Jan 15, 2020 | Expired or cancelled cancelled Jan 2026 | 160 Spear St | 3rd fl: interior office demolition only to existing partitions, plumbing, and finishes. per ab-017Details
3rd fl: interior office demolition only to existing partitions, plumbing, and finishes. per ab-017 | $50,000 | |
| Dec 20, 2019 | Never finaled issued Jan 2020, no final | 101 California St | Principal Builders Inc. | 15th fl - ti including construction of new non-load bearing full height demising wall for new sublease suite. minor mechanical & plumbing to be altered a required by new partitionDetails
15th fl - ti including construction of new non-load bearing full height demising wall for new sublease suite. minor mechanical & plumbing to be altered a required by new partition | $100,000 |
| Sep 24, 2019 | Completed final sign-off Nov 2020 | 500 Terry A Francois Bl | Principal Builders Inc. | demo of structural slab, construction of new commercial kitchen, refresh of furniture/finishes in dining room. mep upgrades to serve new work including (2) slab penetrations for exhaust duct to roofDetails
demo of structural slab, construction of new commercial kitchen, refresh of furniture/finishes in dining room. mep upgrades to serve new work including (2) slab penetrations for exhaust duct to roof | $2,500,000 |
| Sep 20, 2019 | Completed final sign-off Feb 2025 | 2 Embarcadero Center | Dome Construction Corp | suite r2308/promenade level: new door opening within (e) buildingDetails
suite r2308/promenade level: new door opening within (e) building | $11,000 |
| Jul 26, 2019 | Completed final sign-off Oct 2020 | 247 32nd Av | construction of wood post fence 10' ht at rear of property. new fence to be same height as (e) metal fence behindDetails
construction of wood post fence 10' ht at rear of property. new fence to be same height as (e) metal fence behind | $2,000 | |
| Jul 23, 2019 | Never finaled issued Dec 2020, no final | 2353 North Point St | Construction Concierge Inc. | addition of a partial 4th flr & roof deck on an (e) 3-story, (2) unit house. 1st flr expansion by 8'-0" @ rear. as well as the replacement of (2) (e) decks @ rear. structural permit to followDetails
addition of a partial 4th flr & roof deck on an (e) 3-story, (2) unit house. 1st flr expansion by 8'-0" @ rear. as well as the replacement of (2) (e) decks @ rear. structural permit to follow | $300,000 |
| Jul 9, 2019 | Completed final sign-off Aug 2020 | 2 Embarcadero Center | Dome Construction Corp | ec 2, promenade level, suite r2308. interior build-out of (e) building incl demo, (n) finishes, (n) plumbing, minor electrical and partitions. (e) mech, electrical, plumb and sprinkler system modification is under separate permitDetails
ec 2, promenade level, suite r2308. interior build-out of (e) building incl demo, (n) finishes, (n) plumbing, minor electrical and partitions. (e) mech, electrical, plumb and sprinkler system modification is under separate permit | $500,000 |
| Feb 6, 2019 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | 2nd & 3rd floor - revision to pa 2017-1020-1778 add card readers and exit signs and metal stud detailsDetails
2nd & 3rd floor - revision to pa 2017-1020-1778 add card readers and exit signs and metal stud details | |
| Feb 6, 2019 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | 5th floor - revision to pa 2017-0927-9716 and 2018-0517-9347 add card readers and exit signs and metal stud detailsDetails
5th floor - revision to pa 2017-0927-9716 and 2018-0517-9347 add card readers and exit signs and metal stud details | |
| Nov 15, 2018 | Completed final sign-off May 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | 7th flr - revisiont o 201710131168 adding card readers. removing and adding exit signs. adding recalimed wood panels approx 250sfDetails
7th flr - revisiont o 201710131168 adding card readers. removing and adding exit signs. adding recalimed wood panels approx 250sf | |
| Oct 24, 2018 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | 4th fl: revision to #201708175144 add card readers, adding and removing exit signs, adding metal stud framing detailsDetails
4th fl: revision to #201708175144 add card readers, adding and removing exit signs, adding metal stud framing details | |
| Oct 24, 2018 | Completed final sign-off Dec 2021 | 625 02nd St | Sc Builders, Inc, Cannon Constructors North Inc | 4th fl ti: selective demo (e) non-load bearing walls, lighting, etc; construct (n) partitions, ceiling, etc; mep/srpinkler will be design build under sep submittal. building is fully sprinklered.Details
4th fl ti: selective demo (e) non-load bearing walls, lighting, etc; construct (n) partitions, ceiling, etc; mep/srpinkler will be design build under sep submittal. building is fully sprinklered. | $600,000 |
| Oct 24, 2018 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | 6th fl: revision to #201709279722 add card readers, revised exit signs and add metal stud detailsDetails
6th fl: revision to #201709279722 add card readers, revised exit signs and add metal stud details | |
| May 17, 2018 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | 5th fl - revision to pa 2017-0927-9716 and 2018-0416-6404 adding gamma rey machine to scope and additional correction to building & engineering pagesDetails
5th fl - revision to pa 2017-0927-9716 and 2018-0416-6404 adding gamma rey machine to scope and additional correction to building & engineering pages | |
| Nov 17, 2017 | Completed final sign-off Dec 2020 | 3555 Cesar Chavez St | Rudolph And Sletten Inc | 1st floor: install new emergency generator and related equipment on new concrete pads within extg outdoor uncovered service yard. install new green wall/plant screen fence and gate at entrance to the yard. for maherDetails
1st floor: install new emergency generator and related equipment on new concrete pads within extg outdoor uncovered service yard. install new green wall/plant screen fence and gate at entrance to the yard. for maher | $1,129,102 |
| Oct 20, 2017 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | (2nd & 3rd flrs) medical office building (clinic, outpatient) t.i. mechanical, electrical, plumbing & structural included. 1st time build out. (oshpd 3 permit)Details
(2nd & 3rd flrs) medical office building (clinic, outpatient) t.i. mechanical, electrical, plumbing & structural included. 1st time build out. (oshpd 3 permit) | $7,285,102 |
| Sep 27, 2017 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | (5th fl): medical office bldg (clinic outpatient) is a t.i. project. 1st time buildout, single fl t.i. (mep, life safety and sprinklers under separate permit)Details
(5th fl): medical office bldg (clinic outpatient) is a t.i. project. 1st time buildout, single fl t.i. (mep, life safety and sprinklers under separate permit) | $4,641,551 |
| Sep 27, 2017 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | (6th flr) medical office bldg (clinic, outpatient) is a t.i. project, 1st time build out, single floor t.i.; meps, life safety & sprinklers under separate permit. maher n/a.Details
(6th flr) medical office bldg (clinic, outpatient) is a t.i. project, 1st time build out, single floor t.i.; meps, life safety & sprinklers under separate permit. maher n/a. | $4,393,775 |
| Aug 17, 2017 | Completed final sign-off Apr 2019 | 1100 Van Ness Av | Rudolph And Sletten Inc | 4/f- t. i. to a medical office building for clinic outpatient, 1st time build out, single floor t.i., meps. life safety and sprinklers under seperate permit. n/a maher ordinance #155-13Details
4/f- t. i. to a medical office building for clinic outpatient, 1st time build out, single floor t.i., meps. life safety and sprinklers under seperate permit. n/a maher ordinance #155-13 | $4,854,717 |
| Jul 6, 2017 | Completed final sign-off Nov 2020 | 222 Sutter St | Novo Construction Inc | 5th fl ti: including demo of non-loading partitions, (n) non-load bearing partitions. meps, structural, fire sprinkler and fire alarm will be submitted under seperate permit if needed. (building is fully sprinklered) maher naDetails
5th fl ti: including demo of non-loading partitions, (n) non-load bearing partitions. meps, structural, fire sprinkler and fire alarm will be submitted under seperate permit if needed. (building is fully sprinklered) maher na | $922,383 |
| Dec 29, 2016 | Completed final sign-off Dec 2017 | 325 Newhall St | Dome Construction Corp | tenant improvement of (e) warehouse bldg includes selective demolition, construction of (n) partitions, mezzanine, (n) doors & windows, finishes, ceiling, 2(n) restrooms, elect, mech & plumbing work as required by layout. new ext door. replace 3 (e)doors.Details
tenant improvement of (e) warehouse bldg includes selective demolition, construction of (n) partitions, mezzanine, (n) doors & windows, finishes, ceiling, 2(n) restrooms, elect, mech & plumbing work as required by layout. new ext door. replace 3 (e)doors. | $1,149,688 |
| May 6, 2016 | Completed final sign-off Jun 2016 | 128 Spear St | Principal Builders Inc. | 3rd floor: revision to app#201602260625 sliding door in conference room. n/a for maher.Details
3rd floor: revision to app#201602260625 sliding door in conference room. n/a for maher. | |
| Sep 23, 2015 | Completed final sign-off Nov 2015 | 111 Sutter St | Field Construction Inc. | ti includes the demo of non-structural partitions.Details
ti includes the demo of non-structural partitions. | $130,000 |
| Aug 27, 2015 | Completed final sign-off Apr 2016 | 250 Sutter St | Skyline Construction | 6th floor: ti - includes demo of non structural partitions and bldg back new non structural partition. all new or revised meps & life saftey & sprinkler work will be submitted under under sep permit. bld is fully sprinklered. maher naDetails
6th floor: ti - includes demo of non structural partitions and bldg back new non structural partition. all new or revised meps & life saftey & sprinkler work will be submitted under under sep permit. bld is fully sprinklered. maher na | $137,070 |
| Jul 29, 2015 | Completed final sign-off Sep 2016 | 1600 Geary Bl | Dettaglio Construction Inc Dba Dci Const | 1st floor: renovation of existing ground level podiatrist medical officesDetails
1st floor: renovation of existing ground level podiatrist medical offices | $208,208 |
| Jul 24, 2015 | Completed final sign-off Sep 2015 | 711 Van Ness Av | Perfect Quality Construction | #505- converting conference room into office and extending existing office, replace carpet, remodeling breakroom.Details
#505- converting conference room into office and extending existing office, replace carpet, remodeling breakroom. | $143,303 |
| Jul 17, 2015 | Completed final sign-off Aug 2015 | 711 Van Ness Av | 5th fl suite 505 demo only per ab-017Details
5th fl suite 505 demo only per ab-017 | $25,000 | |
| Nov 3, 2014 | Completed final sign-off May 2015 | 1 Maritime Pz | Principal Builders Inc. | 16th floor - t.i. on partial tenant floor space to demo & construct new partitions, doors, millwork & finishes as well as mep. life safety & fire sprinklers will be submitted separately. n/a mahor ordinanceDetails
16th floor - t.i. on partial tenant floor space to demo & construct new partitions, doors, millwork & finishes as well as mep. life safety & fire sprinklers will be submitted separately. n/a mahor ordinance | $350,000 |
| Oct 16, 2014 | Completed final sign-off Jan 2015 | 143 08th St | Bbc Construction Inc. | tenant improvement ti include demolition of interior partitions and relocation of door/frame 1/2nd fl. n/a maher ordinance 155-13Details
tenant improvement ti include demolition of interior partitions and relocation of door/frame 1/2nd fl. n/a maher ordinance 155-13 | |
| Oct 10, 2014 | Completed final sign-off Feb 2015 | 360 03rd St | Sc Builders, Inc | 4th flr, ste 400, t.i. includes the demo of non-structural partitions & building new non-structural paritions. all new or revised hvac, elec, plumbing & life safety, work will be design built & submitted separately, bldg is fully sprinklered; maher n/aDetails
4th flr, ste 400, t.i. includes the demo of non-structural partitions & building new non-structural paritions. all new or revised hvac, elec, plumbing & life safety, work will be design built & submitted separately, bldg is fully sprinklered; maher n/a | $150,000 |
| May 21, 2014 | Completed final sign-off Jan 2015 | 50 Fremont St | Hathaway Dinwiddie Co. | 22nd/23rd fl: demo only. demo of non structural partitions only. ti will follow with separate permit ab017Details
22nd/23rd fl: demo only. demo of non structural partitions only. ti will follow with separate permit ab017 | $90,000 |
| May 1, 2014 | Completed final sign-off Jul 2014 | 185 Berry St | Skyline Construction | 6th fl ti includes building new non structural partitions. all new or revised hvac, electrical, plumbing. life safety under separate permit. bldg not fully sprinklered. demo under 201404294421Details
6th fl ti includes building new non structural partitions. all new or revised hvac, electrical, plumbing. life safety under separate permit. bldg not fully sprinklered. demo under 201404294421 | $948,145 |
| Apr 29, 2014 | Completed final sign-off Jun 2014 | 185 Berry St | Skyline Construction | 6th fl: demo permit only. demolish non structural partitions. ti to be submitted separately. building is not is not fully sprinkleredDetails
6th fl: demo permit only. demolish non structural partitions. ti to be submitted separately. building is not is not fully sprinklered | $13,000 |
| Apr 17, 2014 | Completed final sign-off Jun 2014 | 1550 Bryant St | D A Pope Inc | #400 & #490- t.i. includes build out of a few full height non-structural partitions, doors/frames & glazing, all new or revised hvac, electrical, plumbing and life safety, work will be submitted seperately. bldg is fully sprinklered. n/a to ordinance #155-13.Details
#400 & #490- t.i. includes build out of a few full height non-structural partitions, doors/frames & glazing, all new or revised hvac, electrical, plumbing and life safety, work will be submitted seperately. bldg is fully sprinklered. n/a to ordinance #155-13. | $250,000 |
| Mar 27, 2014 | Expired or cancelled withdrawn Oct 2015 | 1455 Market St | 1st fl ti includes demo of non structural partitions, new non structural partitons. new or revised hvac, elec, plumbing and life safety will be design build and submitted separately. bldg fully sprinkleredDetails
1st fl ti includes demo of non structural partitions, new non structural partitons. new or revised hvac, elec, plumbing and life safety will be design build and submitted separately. bldg fully sprinklered | $20,000 | |
| Feb 28, 2014 | Completed final sign-off Aug 2015 | 1550 Bryant St | D A Pope Inc | 8th floor t.i. includes building new non-structural partitions, new raised floor area & kitchen. (all new or revised hvac, electrical, plumbing & life safety work will be design build & submitted for permit separately). building fully sprinklered, demo included.Details
8th floor t.i. includes building new non-structural partitions, new raised floor area & kitchen. (all new or revised hvac, electrical, plumbing & life safety work will be design build & submitted for permit separately). building fully sprinklered, demo included. | $750,000 |
| Feb 21, 2014 | Completed final sign-off May 2016 | 3435 Mission St | Paniagua Construction Inc | change of use and 1st 7 mezz level t.i. t.i. includes demo of non str. partitions and bldg new non st. partitions mech and elect included. includes new kitchenDetails
change of use and 1st 7 mezz level t.i. t.i. includes demo of non str. partitions and bldg new non st. partitions mech and elect included. includes new kitchen | $88,000 |
| Feb 6, 2014 | Never finaled issued Mar 2014, no final | 1145 Market St | Swinerton Builders | 2/f t.i. include demo of non-structural partitions and building new non-structural partitions. all new or revised hvac, electrical, plumbing and life safety . building is fully sprinklered but submitted separately.shelving and anchorage to be under separate permit.Details
2/f t.i. include demo of non-structural partitions and building new non-structural partitions. all new or revised hvac, electrical, plumbing and life safety . building is fully sprinklered but submitted separately.shelving and anchorage to be under separate permit. | $83,265 |
| Feb 3, 2014 | Completed final sign-off Apr 2014 | 1550 Bryant St | D A Pope Inc | 8th floor: interior demo only. ab-017 will remain unoccupied until t. i. permit is approved. n/a for maher ordinance #155-13Details
8th floor: interior demo only. ab-017 will remain unoccupied until t. i. permit is approved. n/a for maher ordinance #155-13 | $11,000 |
| Jan 28, 2014 | Completed final sign-off Jun 2014 | 601 California St | Swinerton Builders | 10th floor t.i. includes demo of non-structural partitoins & build (n) non-structural prtitions, all new or revised hvac, electrical, plumbing & life safety work will be design build & submitted separately.Details
10th floor t.i. includes demo of non-structural partitoins & build (n) non-structural prtitions, all new or revised hvac, electrical, plumbing & life safety work will be design build & submitted separately. | $375,000 |
| Jan 24, 2014 | Completed final sign-off Oct 2014 | 600 Montgomery St | Field Construction Inc. | 12th & 13th floor t.i. includes the demo of non-structural pratitions & new non-structural partitions. improvements include re-work of (e) mech & electrical equipment & fixtures within the tenant space. bldg is fully sprinklered.Details
12th & 13th floor t.i. includes the demo of non-structural pratitions & new non-structural partitions. improvements include re-work of (e) mech & electrical equipment & fixtures within the tenant space. bldg is fully sprinklered. | $949,815 |
| Jan 13, 2014 | Completed final sign-off Feb 2016 | 55 02nd St | Hathaway Dinwiddie Co. | 12th & 14th flr t.i. includes (n) offices, open office areas, break area, meeting room etc. (n) elevator lobby upgrade, restrm upgrades, replace stair. all mech,elec,plbg,struct under separate permits. (demo under 2013.1211.3864). compliance with ordinance #155-13 not required. excavation <50 cu yd.Details
12th & 14th flr t.i. includes (n) offices, open office areas, break area, meeting room etc. (n) elevator lobby upgrade, restrm upgrades, replace stair. all mech,elec,plbg,struct under separate permits. (demo under 2013.1211.3864). compliance with ordinance #155-13 not required. excavation <50 cu yd. | $1,200,000 |
| Dec 23, 2013 | Completed final sign-off Jul 2014 | 303 02nd St | Bcci Construction Company | ste 680: ti includes semo of non structural partitoins (suiete a to include building new non structural partitions) suite b to remain unoccupied. ti separate permit. all new revised hvac, elec, plumbinf, l/s design build sep permit.Details
ste 680: ti includes semo of non structural partitoins (suiete a to include building new non structural partitions) suite b to remain unoccupied. ti separate permit. all new revised hvac, elec, plumbinf, l/s design build sep permit. | $202,850 |
| Dec 23, 2013 | Completed final sign-off Sep 2014 | 115 Sansome St | Field Construction Inc. | 12th fl ti including demo of non structural paritons and building new non structural partitions. all new or revised hvac, electriclal, plumbing, and life safety work will be design, build and submitted for permit separately. building is fully sprinkleredDetails
12th fl ti including demo of non structural paritons and building new non structural partitions. all new or revised hvac, electriclal, plumbing, and life safety work will be design, build and submitted for permit separately. building is fully sprinklered | $438,000 |
| Dec 16, 2013 | Never finaled issued Jan 2014, no final | 1145 Market St | Swinerton Builders | 1st and 3rd fl ti. demo of non structural partitons, new non structural partitons. new or revised hvac electrical, plumbing, life safety fully engineered and submitted separately . bldg is fully sprinkleredDetails
1st and 3rd fl ti. demo of non structural partitons, new non structural partitons. new or revised hvac electrical, plumbing, life safety fully engineered and submitted separately . bldg is fully sprinklered | $493,290 |
| Dec 13, 2013 | Completed final sign-off Feb 2014 | 221 Main St | Rossi Builders Inc. | 16th floor. revision to pa#2013-1007-8703. mechanic & electrical/lighting. replacing lights and replacing vav boxesDetails
16th floor. revision to pa#2013-1007-8703. mechanic & electrical/lighting. replacing lights and replacing vav boxes | |
| Dec 11, 2013 | Completed final sign-off Feb 2016 | 55 02nd St | Hathaway Dinwiddie Co. | (12 & 14th floor). demo only of applied finishes. non-structural partitions, hvac, electrical, plumbing and life safety equipment on two floors. t.i under separate permit. bldg is fully sprinklered. per ab-017Details
(12 & 14th floor). demo only of applied finishes. non-structural partitions, hvac, electrical, plumbing and life safety equipment on two floors. t.i under separate permit. bldg is fully sprinklered. per ab-017 | $190,000 |
| Nov 22, 2013 | Completed final sign-off Apr 2015 | 115 Sansome St | Field Construction Inc. | 3/f- t.i. includes the demo of non-structural partitions and building new non-structural partitions. all new or revised meps, life safety work will be design build and submitted seperately.Details
3/f- t.i. includes the demo of non-structural partitions and building new non-structural partitions. all new or revised meps, life safety work will be design build and submitted seperately. | $375,000 |
| Nov 13, 2013 | Never finaled issued Nov 2013, no final | 1245 04th St | D Kelly Construction Inc. | revision to 201309096307. patch membrane from drain addition. add new floor drainDetails
revision to 201309096307. patch membrane from drain addition. add new floor drain | |
| Nov 8, 2013 | Never finaled issued Nov 2013, no final | 550 Kearny St | Skyline Construction | 10th floor tenant improvement to include the additoin of a glass door & sidelite to an existing room. mep & life safety under separate permit.Details
10th floor tenant improvement to include the additoin of a glass door & sidelite to an existing room. mep & life safety under separate permit. | $7,000 |
| Nov 5, 2013 | Completed final sign-off Feb 2014 | 1550 Bryant St | D A Pope Inc | 7/f- removal of section of partition and interior glazing at existing elevator lobby, if applicable, all new or modified hvac, electrical and life safety work will be design build and submitted seperatelyDetails
7/f- removal of section of partition and interior glazing at existing elevator lobby, if applicable, all new or modified hvac, electrical and life safety work will be design build and submitted seperately | $5,000 |
| Oct 24, 2013 | Completed final sign-off Jan 2014 | 115 Sansome St | Field Construction Inc. | 9th fl. ti includes demo of non structural partitions and building new. non structural paritions. all new or revised hvac, elec, plumbing and life safety. work be design build and submitted separtelyDetails
9th fl. ti includes demo of non structural partitions and building new. non structural paritions. all new or revised hvac, elec, plumbing and life safety. work be design build and submitted separtely | $375,000 |
| Oct 18, 2013 | Completed final sign-off Jan 2014 | 2 Embarcadero Center | Hathaway Dinwiddie Co. | 6th fl ti includes demo of non structural partitions, new non structural partitoins. new or revised hvac, elec, plumbing, life safety design build sep permit. bldg fully sprinkleredDetails
6th fl ti includes demo of non structural partitions, new non structural partitoins. new or revised hvac, elec, plumbing, life safety design build sep permit. bldg fully sprinklered | $100,000 |
| Oct 7, 2013 | Completed final sign-off Jun 2015 | 250 Brannan St | Hathaway Dinwiddie Co. | (roof) roof work; 2 air handling units, 2 new exhaust fans, 2 new condensing units. 2 new tef. new refrigerent riser pipes from below. all mech. t-24 are being shared by the meps of pa# 2013/08/14/4246. please use structural calcs. mech t-24 for roof project portion only.Details
(roof) roof work; 2 air handling units, 2 new exhaust fans, 2 new condensing units. 2 new tef. new refrigerent riser pipes from below. all mech. t-24 are being shared by the meps of pa# 2013/08/14/4246. please use structural calcs. mech t-24 for roof project portion only. | $50,000 |
| Oct 7, 2013 | Completed final sign-off Feb 2014 | 221 Main St | Rossi Builders Inc. | 16th fl. ti includes demo of non structural partitons and building new non structural partitions. new or revised hvac and electrical will be included in this permit. life safety and sprinklers and sprinklers will be submittedDetails
16th fl. ti includes demo of non structural partitons and building new non structural partitions. new or revised hvac and electrical will be included in this permit. life safety and sprinklers and sprinklers will be submitted | $180,000 |
| Sep 26, 2013 | Completed final sign-off Dec 2013 | 201 Post St | Sc Builders, Inc | the demo of non-structural partitions under ab0.17. mep and life safety under seperate permit. 11th floorDetails
the demo of non-structural partitions under ab0.17. mep and life safety under seperate permit. 11th floor | $30,000 |
| Sep 19, 2013 | Completed final sign-off Apr 2014 | 185 Berry St | Skyline Construction | tenant improvement on 4th floor to build ne non load bearing partitions, doors, millwork and finishes mep on separate permitDetails
tenant improvement on 4th floor to build ne non load bearing partitions, doors, millwork and finishes mep on separate permit | $425,987 |
| Aug 14, 2013 | Completed final sign-off Nov 2013 | 115 Sansome St | Field Construction Inc. | 14/f, 15/f- t.i. includes the demo of non-structural partitions and building (n) non structural partitions. all new or revised hvac, electrical, plumbing and life safety work will be design-build and submitted seperately, building fully sprinklered.Details
14/f, 15/f- t.i. includes the demo of non-structural partitions and building (n) non structural partitions. all new or revised hvac, electrical, plumbing and life safety work will be design-build and submitted seperately, building fully sprinklered. | $423,000 |
| Aug 14, 2013 | Completed final sign-off Jun 2015 | 250 Brannan St | Hathaway Dinwiddie Co. | basement through 3rd floor. t.i. includes demo of non structural partitions and bldg n non structural partitons and showers. see mep engineering. plans for all new or revised hvac, electrical , plumbing, & life safety. bldg is fully sprinklered. structural plans for solar tube under mep submittal.Details
basement through 3rd floor. t.i. includes demo of non structural partitions and bldg n non structural partitons and showers. see mep engineering. plans for all new or revised hvac, electrical , plumbing, & life safety. bldg is fully sprinklered. structural plans for solar tube under mep submittal. | $1,345,393 |
| Aug 12, 2013 | Completed final sign-off Mar 2014 | 100 Spear St | Peacock Construction Inc | 2/f- t.i. include demolishing of non structural partitions and build (n) non structural partitions. all new or revised hvac, electrical, plumbing and life safety are design build submitted seperately, fully sprinkler.Details
2/f- t.i. include demolishing of non structural partitions and build (n) non structural partitions. all new or revised hvac, electrical, plumbing and life safety are design build submitted seperately, fully sprinkler. | $275,000 |
| Aug 12, 2013 | Never finaled issued Sep 2013, no final | 100 Spear St | Peacock Construction Inc | 3rd flr: ste 325, tenant improvement include the demolishing of non structural partitions and building new non structural partitions. all new or revised. hvac, electrical, plumbing and life safety work will be design- build and submitted separately./ bldg fully sprinkledDetails
3rd flr: ste 325, tenant improvement include the demolishing of non structural partitions and building new non structural partitions. all new or revised. hvac, electrical, plumbing and life safety work will be design- build and submitted separately./ bldg fully sprinkled | $215,000 |
| Aug 12, 2013 | Never finaled issued Sep 2013, no final | 100 Spear St | Peacock Construction Inc | ground floor suite 120 & 130 t.i. include the demolishing of non-structural partitions & building new non-structural partitions. all new or revised hvac, electrical, pldg & life safety will be design build & submitted separately. bldg fully sprinklered.Details
ground floor suite 120 & 130 t.i. include the demolishing of non-structural partitions & building new non-structural partitions. all new or revised hvac, electrical, pldg & life safety will be design build & submitted separately. bldg fully sprinklered. | $100,000 |
| Aug 12, 2013 | Never finaled issued Sep 2013, no final | 100 Spear St | Peacock Construction Inc | 14th flr: tenant improvement include the demolishing of non structural partitions and building new non structural partitions. all new or revised. hvac, electrical, plumbing and life safety work will be design- build and submitted separately./ bldg fully sprinkledDetails
14th flr: tenant improvement include the demolishing of non structural partitions and building new non structural partitions. all new or revised. hvac, electrical, plumbing and life safety work will be design- build and submitted separately./ bldg fully sprinkled | $90,000 |
| Aug 12, 2013 | Completed final sign-off Mar 2014 | 100 Spear St | Peacock Construction Inc | 4th floor elevator lobby & corridor improvements include finishes, all new or revised hvac, electrical, plbg & life safety work will be design build & sumbitted separately, bldg fully sprinklered.Details
4th floor elevator lobby & corridor improvements include finishes, all new or revised hvac, electrical, plbg & life safety work will be design build & sumbitted separately, bldg fully sprinklered. | $90,000 |