Skyline Capital Builders Llc
- Based in
- Walnut Creek
- On San Francisco permits
- Dec 2017 to Oct 2023
- Last 24 months
- 0 permits filed
57 permits since 2000: 53 completed, 2 never finaled, 2 expired or cancelled.
Of the 2 never-finaled permits, 2 are 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Oct 6, 2023 | Completed final sign-off Oct 2024 | 2750 19th St | add freight loading/service vehicle use in the pdr interior space with new curb-cut along bryant street. no change to the building as-built. ref 201712156655 s.Details
add freight loading/service vehicle use in the pdr interior space with new curb-cut along bryant street. no change to the building as-built. ref 201712156655 s. | |
| Aug 24, 2023 | Expired or cancelled withdrawn Jun 2024 | 2750 19th St | revision to pa# 201712156665-s. provide wheelchair lift as allowed per cbc 11b-410 to provide accessible route to mezzannie. provide new 2nd stari per 1006.2-1 & small metal deck / infill @ (e) opening @ mezzanine deck.Details
revision to pa# 201712156665-s. provide wheelchair lift as allowed per cbc 11b-410 to provide accessible route to mezzannie. provide new 2nd stari per 1006.2-1 & small metal deck / infill @ (e) opening @ mezzanine deck. | |
| Jun 28, 2023 | Completed final sign-off Sep 2023 | 170 Valencia St | level 1 + lower level: evacuation signsDetails
level 1 + lower level: evacuation signs | $2,000 |
| May 26, 2023 | Expired or cancelled withdrawn Aug 2023 | 2750 19th St | revision to issued permit 201712156665-s2 (arch/mep). provide new stair and small area of mezzanine deck infill, required for 2nd accessible egress due to travel distance being over 100 feet per cbc table 1006.2.1. stairways considered accessible means of egress/ 1009.3 exception 1.Details
revision to issued permit 201712156665-s2 (arch/mep). provide new stair and small area of mezzanine deck infill, required for 2nd accessible egress due to travel distance being over 100 feet per cbc table 1006.2.1. stairways considered accessible means of egress/ 1009.3 exception 1. | |
| Apr 6, 2023 | Completed final sign-off Oct 2023 | 170 Valencia St | modify plumbing as required for ti project. modify 1st fl restroom exhaust. all central hvac cooling/heating and outside air equipment in existing to remain. replaces misc grills at 1st fl with new of same dimensions. ref pa 2022-1026-5195Details
modify plumbing as required for ti project. modify 1st fl restroom exhaust. all central hvac cooling/heating and outside air equipment in existing to remain. replaces misc grills at 1st fl with new of same dimensions. ref pa 2022-1026-5195 | $18,000 |
| Feb 27, 2023 | Completed final sign-off Mar 2025 | 200 Rhode Island St | priority process - brb for main core & shell. reference pa # 201910023333.Details
priority process - brb for main core & shell. reference pa # 201910023333. | $111,522 |
| Feb 24, 2023 | Completed final sign-off Jan 2024 | 200 Rhode Island St | deferred stair 2, 3, 4, 5 for main core & shell. pa# 201910023333.Details
deferred stair 2, 3, 4, 5 for main core & shell. pa# 201910023333. | $280,000 |
| Feb 22, 2023 | Completed final sign-off Oct 2023 | 170 Valencia St | revision to 202210265195, 202301190393 for req adjustment to restroomsgiven e file conditions and conflicts. structural scope: modifications to restroom subfloor assembly framing and coorination of misc detail. no changes to restroom area plumbing fixture countsDetails
revision to 202210265195, 202301190393 for req adjustment to restroomsgiven e file conditions and conflicts. structural scope: modifications to restroom subfloor assembly framing and coorination of misc detail. no changes to restroom area plumbing fixture counts | |
| Feb 10, 2023 | Completed final sign-off Oct 2023 | 170 Valencia St | deferred mep for the chan national queer arts center. reference pa # 202210265195 & 202301190393.Details
deferred mep for the chan national queer arts center. reference pa # 202210265195 & 202301190393. | |
| Jan 24, 2023 | Completed final sign-off Jan 2024 | 200 Rhode Island St | deferred friction piles for the main core + shell permit #201910023333 per approved structural drawings, the drilled piers replace micropiles per contractor's optionDetails
deferred friction piles for the main core + shell permit #201910023333 per approved structural drawings, the drilled piers replace micropiles per contractor's option | |
| Jan 19, 2023 | Completed final sign-off Oct 2023 | 170 Valencia St | revision to 202210265195: install non structural acoustic panel in great hall, new double ddors in pre-function space. new acoustic and gyp ceiling in grand hall. add new millwork folding doors at pantryDetails
revision to 202210265195: install non structural acoustic panel in great hall, new double ddors in pre-function space. new acoustic and gyp ceiling in grand hall. add new millwork folding doors at pantry | $20,000 |
| Dec 1, 2022 | Completed final sign-off Mar 2025 | 200 Rhode Island St | revision to bpa#201910023333 fabricate a transom window to match adjacent, transom windows. steel tube crossmember to match the roll up door. new manual rolup door 11' x 14'-7" to match (e) frames @ other baysDetails
revision to bpa#201910023333 fabricate a transom window to match adjacent, transom windows. steel tube crossmember to match the roll up door. new manual rolup door 11' x 14'-7" to match (e) frames @ other bays | |
| Oct 25, 2022 | Completed final sign-off Oct 2023 | 170 Valencia St | demolition of interior non-structural walls, finishes, plubming fixtures, and stairs per ab-17.Details
demolition of interior non-structural walls, finishes, plubming fixtures, and stairs per ab-17. | $10,000 |
| Aug 8, 2022 | Completed final sign-off Jan 2023 | 1501 Tennessee St | installation of vehicle lift structures.Details
installation of vehicle lift structures. | $29,000 |
| Jul 25, 2022 | Completed final sign-off May 2023 | 855 Geary St | 1st fl- expansion of office to include new act ceiling, non load bearing walls and finishes. remodel and add one restroom and new platform for ada lift.Details
1st fl- expansion of office to include new act ceiling, non load bearing walls and finishes. remodel and add one restroom and new platform for ada lift. | $1,500,000 |
| Jun 27, 2022 | Completed final sign-off Sep 2022 | 101 Utah St | 1st-2nd fl: shop drawings, stair #2 structural drawings. ref pa# 201905312103 & 202104098253.Details
1st-2nd fl: shop drawings, stair #2 structural drawings. ref pa# 201905312103 & 202104098253. | |
| Jun 22, 2022 | Completed final sign-off Oct 2022 | 101 Utah St | 2nd fl show drawings frp (strengthing of roof) ref drawings 201905312103Details
2nd fl show drawings frp (strengthing of roof) ref drawings 201905312103 | |
| Jun 17, 2022 | Never finaled issued Jan 2023, no final | 200 Rhode Island St | new roof top patio built on top of the (e) 5-story bldg portion of the site. roof deck consist of pedestal pavers and planters with seating area. ref 201910023333 for c + s approvals and roof deck entitlements as a deffered submittal.Details
new roof top patio built on top of the (e) 5-story bldg portion of the site. roof deck consist of pedestal pavers and planters with seating area. ref 201910023333 for c + s approvals and roof deck entitlements as a deffered submittal. | $500,000 |
| Jun 1, 2022 | Completed final sign-off Sep 2022 | 101 Utah St | interior stair #3 deferred submittal for 2019-0531-2103Details
interior stair #3 deferred submittal for 2019-0531-2103 | |
| May 4, 2022 | Completed final sign-off Oct 2022 | 101 Utah St | 1st floor through 4th floor: revision to 201905312103, 202104098253. building type of tower revised to 3b. tower occupancy is b use (3rd & 4th floors. t-24 upgrade, door from roof to be proposed locked. add 48" wide elevator control room door.Details
1st floor through 4th floor: revision to 201905312103, 202104098253. building type of tower revised to 3b. tower occupancy is b use (3rd & 4th floors. t-24 upgrade, door from roof to be proposed locked. add 48" wide elevator control room door. | |
| Apr 7, 2022 | Never finaled issued Apr 2022, no final | 855 Geary St | change of use per planning from private parking to public parking. car share & bicycle parking at ground floor only per planning com motion no.20531. no change of use at basement or 2nd fl which remain private parking. no change of occupancy. all work is striping/barrier removal for ada parking.Details
change of use per planning from private parking to public parking. car share & bicycle parking at ground floor only per planning com motion no.20531. no change of use at basement or 2nd fl which remain private parking. no change of occupancy. all work is striping/barrier removal for ada parking. | $50,000 |
| Mar 28, 2022 | Completed final sign-off Sep 2022 | 101 Utah St | shop drawings (structural) for project related to pa #201905312103, 201906254344, & 202104098253.Details
shop drawings (structural) for project related to pa #201905312103, 201906254344, & 202104098253. | |
| Dec 20, 2021 | Completed final sign-off Jan 2023 | 465 California St | revision to bpa# 2020.0903.3366. adjustment of new curb cut location off california st,due to structrual constraits.Details
revision to bpa# 2020.0903.3366. adjustment of new curb cut location off california st,due to structrual constraits. | |
| Nov 29, 2021 | Completed final sign-off Mar 2022 | 170 Valencia St | replace one supply fan and 2 duct heaters with new duct work serving project area. includes associated electrical work. no structural work required.Details
replace one supply fan and 2 duct heaters with new duct work serving project area. includes associated electrical work. no structural work required. | $100,000 |
| Oct 8, 2021 | Completed final sign-off Sep 2024 | 2750 19th St | tower crane erection and dismantle to facilitation new construction. ref to 2017 1215 6665 s.Details
tower crane erection and dismantle to facilitation new construction. ref to 2017 1215 6665 s. | $70,000 |
| Sep 28, 2021 | Completed final sign-off Apr 2022 | 101 Utah St | submittal with holms structure response to rf#20 for micropile design lifespan and corrision protection. (shop drawings)Details
submittal with holms structure response to rf#20 for micropile design lifespan and corrision protection. (shop drawings) | |
| Apr 9, 2021 | Completed final sign-off Dec 2021 | 200 Rhode Island St | (2-story bldg) deferred brb for voluntary seismic work. ref pa# 201909181993.Details
(2-story bldg) deferred brb for voluntary seismic work. ref pa# 201909181993. | |
| Apr 9, 2021 | Completed final sign-off Jan 2023 | 101 Utah St | revision to arch/structural pa 201905312103 and mep pa 201906254344. elimanate large roof skylights; rr (new) removed from shell scope: electrical scope changed; adjust stair #2 layout; see page ao.01r for more specifics.Details
revision to arch/structural pa 201905312103 and mep pa 201906254344. elimanate large roof skylights; rr (new) removed from shell scope: electrical scope changed; adjust stair #2 layout; see page ao.01r for more specifics. | |
| Apr 9, 2021 | Completed final sign-off Dec 2021 | 200 Rhode Island St | (5-story bldg) deferred brb for voluntary seismic work. ref pa# 201909181992.Details
(5-story bldg) deferred brb for voluntary seismic work. ref pa# 201909181992. | |
| Jan 21, 2021 | Completed final sign-off Sep 2022 | 55 New Montgomery St | barrier removal at one ground level tenant suite (house of shields). addition of a power door operator at (e) historic entry doors & associated high-low push buttons.Details
barrier removal at one ground level tenant suite (house of shields). addition of a power door operator at (e) historic entry doors & associated high-low push buttons. | $2,500 |
| Jan 21, 2021 | Completed final sign-off May 2021 | 888 Post St | priority project: deferred submittal for revision to architectural addendum 2 & mep addendum 3 due to revisions to original site permit. original site permit and addendums all approved under pa# 2019-1223-0310. revision to original site permit approved under pa# 2020-1006-5970.Details
priority project: deferred submittal for revision to architectural addendum 2 & mep addendum 3 due to revisions to original site permit. original site permit and addendums all approved under pa# 2019-1223-0310. revision to original site permit approved under pa# 2020-1006-5970. | $25,000 |
| Jan 8, 2021 | Completed final sign-off Apr 2024 | 2750 19th St | demo of(e) wood frame structure with retention of brick facade. reference bpa# 201712156665 for new addition.Details
demo of(e) wood frame structure with retention of brick facade. reference bpa# 201712156665 for new addition. | $250,000 |
| Jan 8, 2021 | Completed final sign-off Jan 2024 | 2055 Bryant St | underpinning for new construction at 2750 - 19th st/ reference bpa# 201712156665-sDetails
underpinning for new construction at 2750 - 19th st/ reference bpa# 201712156665-s | $300,000 |
| Jan 8, 2021 | Completed final sign-off Sep 2023 | 2700 19th St | underpinning for new construction at 2750 - 19th st/ reference bpa# 201712156665-sDetails
underpinning for new construction at 2750 - 19th st/ reference bpa# 201712156665-s | $300,000 |
| Dec 28, 2020 | Completed final sign-off Oct 2023 | 200 Rhode Island St | fire sprinkler for core & shell alteration to integratio of three structures (on same lot) reference pa #2019-1002-3333.Details
fire sprinkler for core & shell alteration to integratio of three structures (on same lot) reference pa #2019-1002-3333. | $100,000 |
| Dec 23, 2020 | Completed final sign-off May 2021 | 1201 Bryant St | installation of pre-fabricated radar chamber on level 1.Details
installation of pre-fabricated radar chamber on level 1. | $5,000 |
| Dec 21, 2020 | Completed final sign-off Aug 2022 | 111 Pine St | demo existing water-cooled chiller plants & towers and replace with new air-cooled chiller plant on the roof. new structural support on roof with distribution pumps and hydronic specialties on penthouse level.Details
demo existing water-cooled chiller plants & towers and replace with new air-cooled chiller plant on the roof. new structural support on roof with distribution pumps and hydronic specialties on penthouse level. | $1,350,000 |
| Dec 21, 2020 | Completed final sign-off Aug 2022 | 111 Pine St | demo existing base-building centrifugal supply fans (x4) & replace with new fan wall technology with new vfd drive controller & power connections. new structural support for access platform for the fan wall.Details
demo existing base-building centrifugal supply fans (x4) & replace with new fan wall technology with new vfd drive controller & power connections. new structural support for access platform for the fan wall. | $715,000 |
| Dec 14, 2020 | Completed final sign-off Jun 2021 | 1201 Bryant St | provide and install condensing unit system mounted on roof (2 units) distributed (vrf) fan coils located in basement. including all associated mep work. reference to pa #202007210568Details
provide and install condensing unit system mounted on roof (2 units) distributed (vrf) fan coils located in basement. including all associated mep work. reference to pa #202007210568 | |
| Nov 3, 2020 | Completed final sign-off Oct 2023 | 200 Rhode Island St | install new underground 6" fire service from city main connection at curb to inside the bldg wall at basement level. service terminates in fire pump room. reference p.a. # 2019-1002-3333Details
install new underground 6" fire service from city main connection at curb to inside the bldg wall at basement level. service terminates in fire pump room. reference p.a. # 2019-1002-3333 | $5,000 |
| Oct 6, 2020 | Completed final sign-off Feb 2021 | 888 Post St | priority - revisions to site permit 201912230310: delete 1st floor tenant improvement, demolish existing stair penthouse on roof, install new roof access hatch, and document technical infeasibility for existing non-compliant conditions in the stairway discovered during the course of construction.Details
priority - revisions to site permit 201912230310: delete 1st floor tenant improvement, demolish existing stair penthouse on roof, install new roof access hatch, and document technical infeasibility for existing non-compliant conditions in the stairway discovered during the course of construction. | $25,000 |
| Sep 3, 2020 | Completed final sign-off Jan 2023 | 465 California St | work on 1st floor to update storefront at main entry and leidesdorff st. entry, sidewalk replacement, lighting along leidesdorff st. hallway ceiling and lighting, art niche in central lobby, glazing and elecrical.Details
work on 1st floor to update storefront at main entry and leidesdorff st. entry, sidewalk replacement, lighting along leidesdorff st. hallway ceiling and lighting, art niche in central lobby, glazing and elecrical. | $1,500,000 |
| Aug 25, 2020 | Completed final sign-off Dec 2025 | 55 New Montgomery St | new fire rated shaftwall construction for new electrical & mechanical systems on level 2 to 8. new fire protected stair enclosures. new electrical room in basement & 1 hour fire rated corridor on roof new mechanical units. steel equipment platforms & new tpo single - ply roofing system.Details
new fire rated shaftwall construction for new electrical & mechanical systems on level 2 to 8. new fire protected stair enclosures. new electrical room in basement & 1 hour fire rated corridor on roof new mechanical units. steel equipment platforms & new tpo single - ply roofing system. | $6,500,000 |
| Aug 22, 2020 | Completed final sign-off Mar 2022 | 200 Rhode Island St | revision to pa# 201909181992. micropiles have been revised, new foundation for elevator pit and trash lift pit. new elevator & trash lift will be submitted under separate architectural permit applications.Details
revision to pa# 201909181992. micropiles have been revised, new foundation for elevator pit and trash lift pit. new elevator & trash lift will be submitted under separate architectural permit applications. | $40,000 |
| Aug 22, 2020 | Completed final sign-off Oct 2020 | 201 11th St | installation of a vehicle repair lift on concrete slab.Details
installation of a vehicle repair lift on concrete slab. | $5,000 |
| Aug 19, 2020 | Completed final sign-off Feb 2022 | 200 Rhode Island St | deferred micropile submittal for seismic upgrade. ref pa201909181992.Details
deferred micropile submittal for seismic upgrade. ref pa201909181992. | $253,000 |
| Aug 19, 2020 | Completed final sign-off Feb 2022 | 200 Rhode Island St | deferred micropile submittal for seismic upgrade. ref pa201909181993.Details
deferred micropile submittal for seismic upgrade. ref pa201909181993. | $20,000 |
| Jul 21, 2020 | Completed final sign-off Jun 2021 | 1201 Bryant St | modify several rms located in basement, doors & relites. partial enclosures of central communcating stairs at basement level to create security barrier. stairs not egress. install prefab test chamber on 3rd flr. mep + f/a, sprinklers on separate permit.Details
modify several rms located in basement, doors & relites. partial enclosures of central communcating stairs at basement level to create security barrier. stairs not egress. install prefab test chamber on 3rd flr. mep + f/a, sprinklers on separate permit. | $525,000 |
| Jul 15, 2020 | Completed final sign-off Jan 2026 | 2750 19th St | change the construction type from iii-a to i-a for the issued pa# 201712156665-s. ** maher: n/a **Details
change the construction type from iii-a to i-a for the issued pa# 201712156665-s. ** maher: n/a ** | |
| Feb 13, 2020 | Completed final sign-off Sep 2022 | 55 New Montgomery St | demolition of sidewalk & basement area, new construction of new underground pg & e vault installationDetails
demolition of sidewalk & basement area, new construction of new underground pg & e vault installation | $325,000 |
| Dec 23, 2019 | Completed final sign-off May 2021 | 888 Post St | change of use from retail/office/storage to office storage homeless shelter & navigation center for homeless youth w/ training & other office use. seismic strenthening per asce 41-13 & tenant improvements associated, utility upgrade, 1st fl for donation & job training,Details
change of use from retail/office/storage to office storage homeless shelter & navigation center for homeless youth w/ training & other office use. seismic strenthening per asce 41-13 & tenant improvements associated, utility upgrade, 1st fl for donation & job training, | $9,499,595 |
| Dec 16, 2019 | Completed final sign-off Jun 2023 | 2750 19th St | shoring & brick facade retention for the fitzgerald project at 2750 19th st. ref pa #2017-1215-6665 (s).Details
shoring & brick facade retention for the fitzgerald project at 2750 19th st. ref pa #2017-1215-6665 (s). | $450,000 |
| Sep 19, 2019 | Completed final sign-off May 2020 | 55 New Montgomery St | floors 4-8: selective demo of non load bearing partitions, ceiling finishes, light fixtures, millwork, and plumbing fixtures. no ceiling demo. vacant under ab-017. n/a for maherDetails
floors 4-8: selective demo of non load bearing partitions, ceiling finishes, light fixtures, millwork, and plumbing fixtures. no ceiling demo. vacant under ab-017. n/a for maher | $161,600 |
| Sep 18, 2019 | Completed final sign-off Jan 2021 | 200 Rhode Island St | voluntary seismic retrofit of 2 story tilt up building.**maher n/a**Details
voluntary seismic retrofit of 2 story tilt up building.**maher n/a** | $750,000 |
| Sep 18, 2019 | Completed final sign-off Dec 2021 | 200 Rhode Island St | voluntary seismic retrofit of 5 story urm building. reference to tenant improvement pa #201910023333 **maher n/a**Details
voluntary seismic retrofit of 5 story urm building. reference to tenant improvement pa #201910023333 **maher n/a** | $3,000,000 |
| May 31, 2019 | Completed final sign-off Jan 2023 | 101 Utah St | ada upgrade entrance / rrs / parking / ramp. ti include structural seismic upgrade in conformances with attached pre application letter. alterations include modifying exterior wall openings, add skylights & floor openings. new non structural partitions. mep & fire life safety under separate permitDetails
ada upgrade entrance / rrs / parking / ramp. ti include structural seismic upgrade in conformances with attached pre application letter. alterations include modifying exterior wall openings, add skylights & floor openings. new non structural partitions. mep & fire life safety under separate permit | $6,000,000 |
| Dec 15, 2017 | Completed final sign-off Jan 2026 | 2750 19th St | entire removal of (e) wood frame structure with retention of brick facade, 6 story addition including new subterranean parking, new ground floor commercial & 63 new residential units. (r-2,m,a-2,a-3,s-2) ** maher: n/a **Details
entire removal of (e) wood frame structure with retention of brick facade, 6 story addition including new subterranean parking, new ground floor commercial & 63 new residential units. (r-2,m,a-2,a-3,s-2) ** maher: n/a ** | $20,000,000 |