Block 3776, lot 115
500 03rd St
- City’s use
- Industrial
- Built
- 1927
- Stories
- 6
- Units
- 2
- Rooms
- 18 bathrooms
- Building
- 140,375 sq ft
- Lot
- 31,920 sq ft
- Zoning
- SLI
- Construction type
- B
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
53 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 26, 2022 | Completed final sign-off May 2022 | 500 03rd St | Rossi Builders Inc. | ste 110 mep permit: electrical - power receptacles revision and lighting alterations. plumbing - replace sinks, add under sink mounted waterheaters. ref. permit 202111122242.Details
ste 110 mep permit: electrical - power receptacles revision and lighting alterations. plumbing - replace sinks, add under sink mounted waterheaters. ref. permit 202111122242. | $130,000 |
| Dec 3, 2021 | Completed final sign-off Mar 2022 | 500 03rd St | Sure Fire Protection | suite 110: due to addition of new walls & ceilings: relocate 13sp ssu, add 1 new sr ssu, add 1 new qr for new workshop extended ceiling. ref t.i. 202111122242.Details
suite 110: due to addition of new walls & ceilings: relocate 13sp ssu, add 1 new sr ssu, add 1 new qr for new workshop extended ceiling. ref t.i. 202111122242. | $5,800 |
| Nov 12, 2021 | Completed final sign-off May 2022 | 500 03rd St | Rossi Builders Inc. | suite 110: interior renovation: new ceiling tiles, new light fixtures, new flooring throughout. selectrive demo and construction as shower on plans. deferrered mep & fire/life safety. maher n/a.Details
suite 110: interior renovation: new ceiling tiles, new light fixtures, new flooring throughout. selectrive demo and construction as shower on plans. deferrered mep & fire/life safety. maher n/a. | $199,000 |
| Jun 3, 2019 | Completed final sign-off Jun 2019 | 520 03rd St | R L H Fire Protection Inc | 3rd flr, fire sprinkler t.i. 3 new pendent, 2 new upright, 2 relocated pendent, 1 relocated upright. 8 heads total. ref p.a 201903114932.Details
3rd flr, fire sprinkler t.i. 3 new pendent, 2 new upright, 2 relocated pendent, 1 relocated upright. 8 heads total. ref p.a 201903114932. | $8,188 |
| Mar 11, 2019 | Never finaled issued Apr 2019, no final | 520 03rd St | Clune Construction Company L P | suite 305. sub-dividing the (e) wired office space into two offices suites. the secondary space will be leased to a sub-tenant. the (e) accessbile restroms and break room will be shared by the two office suites. n/a maherDetails
suite 305. sub-dividing the (e) wired office space into two offices suites. the secondary space will be leased to a sub-tenant. the (e) accessbile restroms and break room will be shared by the two office suites. n/a maher | $150,000 |
| Jul 10, 2017 | Never finaled issued Jul 2017, no final | 500 03rd St | street spaceDetails
street space | ||
| Apr 27, 2016 | Never finaled issued Apr 2016, no final | 500 03rd St | Acco Engineered Systems Inc. Dba Acco En | furnish & install (1) new condensing split vrf system with (2) new wall mounted fan coil units for the t.i. room. n/a ordinance #155-13Details
furnish & install (1) new condensing split vrf system with (2) new wall mounted fan coil units for the t.i. room. n/a ordinance #155-13 | $45,000 |
| Mar 29, 2016 | Never finaled issued Apr 2016, no final | 500 03rd St | Electrical Services Co | electrical lighting title 24 and controlled outlets. ew 201602246452, ref pa 2016-0114-7140. maher naDetails
electrical lighting title 24 and controlled outlets. ew 201602246452, ref pa 2016-0114-7140. maher na | $52,880 |
| Mar 3, 2016 | Never finaled issued Mar 2016, no final | 500 03rd St | Rossi Builders Inc. | revision to pa 2016-0114-7140, remove existing unisex toilet rooms and renovate to storage room.Details
revision to pa 2016-0114-7140, remove existing unisex toilet rooms and renovate to storage room. | $2,000 |
| Jan 14, 2016 | Never finaled issued Feb 2016, no final | 500 03rd St | Rossi Builders Inc. | disabled access barrier removal project. gr fl new code compliant restrooms, new partitions, minor mech, elec, plumbing, fire sp, alarm. mep,fire, alarm design build interim/maherDetails
disabled access barrier removal project. gr fl new code compliant restrooms, new partitions, minor mech, elec, plumbing, fire sp, alarm. mep,fire, alarm design build interim/maher | $851,208 |
| Dec 10, 2015 | Never finaled issued Dec 2015, no final | 500 03rd St | street spaceDetails
street space | ||
| Nov 23, 2015 | Completed final sign-off Sep 2016 | 500 03rd St | Metropolitan Electrical Construction, Mastec Network Solutions Inc | instalal 2 (n) omnidirectional antennas, 1 (n) weather sensor/gps unit and 1 (n) equipment cabinet on roof top. power to be ran from (e) electrical room. maher naDetails
instalal 2 (n) omnidirectional antennas, 1 (n) weather sensor/gps unit and 1 (n) equipment cabinet on roof top. power to be ran from (e) electrical room. maher na | $5,000 |
| Jun 9, 2015 | Completed final sign-off Aug 2016 | 500 03rd St | Rossi Builders Inc. | this project consists of the removal of existing non-compliant pipe handrails within two of the building existing stairwells & installing new handrails & guardrails that meet the disabled access. n/a maher ordinanceDetails
this project consists of the removal of existing non-compliant pipe handrails within two of the building existing stairwells & installing new handrails & guardrails that meet the disabled access. n/a maher ordinance | $200,000 |
| Aug 13, 2014 | Completed final sign-off Jun 2015 | 520 03rd St | Principal Builders Inc. | installation of new kitchen breakroom area in existing tenant space. please see 201312194593 for ti work will be revised under this permit to show food service drawings & kitchen added to original scope. compliance with maher ordinance no. 155-13 not required.Details
installation of new kitchen breakroom area in existing tenant space. please see 201312194593 for ti work will be revised under this permit to show food service drawings & kitchen added to original scope. compliance with maher ordinance no. 155-13 not required. | $50,000 |
| Aug 4, 2014 | Completed final sign-off Sep 2014 | 500 03rd St | Western Builders | fire escape ladder repair. replace browken top bracket of ladder. replace machine bolt. realign ladder and straighten bent handrail. test ladder for proper operationDetails
fire escape ladder repair. replace browken top bracket of ladder. replace machine bolt. realign ladder and straighten bent handrail. test ladder for proper operation | $2,000 |
| Jun 27, 2014 | Completed final sign-off Sep 2014 | 500 03rd St | Pyro-Comm Systems, Inc. | voluntary one for one replacement of existing sprinkler monitoring elevator recall system. 1 facu, 1 annunciator, 1 pull station, 12 smoke detectors, 2 heat detectors, 17 modules; maher naDetails
voluntary one for one replacement of existing sprinkler monitoring elevator recall system. 1 facu, 1 annunciator, 1 pull station, 12 smoke detectors, 2 heat detectors, 17 modules; maher na | $11,700 |
| Jun 23, 2014 | Completed final sign-off Jan 2015 | 520 03rd St | R L H Fire Protection Inc | 3rd flr: 90 new pendant hds, 32 new modifed upright hds, tenant improvement reference 201312194593; maher n/aDetails
3rd flr: 90 new pendant hds, 32 new modifed upright hds, tenant improvement reference 201312194593; maher n/a | $41,506 |
| Dec 23, 2013 | Completed final sign-off Apr 2015 | 520 03rd St | Principal Builders Inc. | mechanical electrical title 24 for full floor ti on 3rd fl to demo and construct/relocate lighting and hvac equipment; compliance with ord. 155-13 not requiredDetails
mechanical electrical title 24 for full floor ti on 3rd fl to demo and construct/relocate lighting and hvac equipment; compliance with ord. 155-13 not required | $200,000 |
| Dec 23, 2013 | Completed final sign-off Sep 2014 | 520 03rd St | Principal Builders Inc. | structural plans to remove structural partitons and reinforce openings on 3/f t.i. please refer to pa#2013.1219.4593. compliance w/ordinance #155-13 not required. excavation <50 cu. yd.Details
structural plans to remove structural partitons and reinforce openings on 3/f t.i. please refer to pa#2013.1219.4593. compliance w/ordinance #155-13 not required. excavation <50 cu. yd. | $90,000 |
| Dec 19, 2013 | Completed final sign-off Jun 2015 | 520 03rd St | Principal Builders Inc. | t.i. on 3rd floor to demo and construct new non-structural partitions doors, millwork, & finishes, mep life safety and sprinklers on seperate permit.Details
t.i. on 3rd floor to demo and construct new non-structural partitions doors, millwork, & finishes, mep life safety and sprinklers on seperate permit. | $2,200,000 |
| Sep 17, 2012 | Never finaled issued Sep 2012, no final | 500 03rd St | O'connor Plumbing & Fire Protection | provide and install 12 new sprinkler heads off extg system below new t bar cieling on ground floor only in unit 110/ t.i #201208147314Details
provide and install 12 new sprinkler heads off extg system below new t bar cieling on ground floor only in unit 110/ t.i #201208147314 | $2,400 |
| Sep 10, 2012 | Completed final sign-off Feb 2013 | 500 03rd St | Clinton Heating & A/C Inc | relocate one (e) pnuematic thermostat. provide and install one 5 ton heat pump fan coil to service two conference rooms and two phone rooms. provide and install one 2 ton wall mounted ductless ac only unit for the server room. hang condersers in garbage storage area with discharge air thru louverDetails
relocate one (e) pnuematic thermostat. provide and install one 5 ton heat pump fan coil to service two conference rooms and two phone rooms. provide and install one 2 ton wall mounted ductless ac only unit for the server room. hang condersers in garbage storage area with discharge air thru louver | $30,000 |
| Aug 14, 2012 | Completed final sign-off Oct 2012 | 500 03rd St | Rossi Builders Inc. | suite 110 ti - demolition of partition walls & carpet. build new walls, install new doors/frames/hardware, install interior glazing, t-bar ceiling, mech, elec, hvac split sytem & fire sprinkler under separate permit.Details
suite 110 ti - demolition of partition walls & carpet. build new walls, install new doors/frames/hardware, install interior glazing, t-bar ceiling, mech, elec, hvac split sytem & fire sprinkler under separate permit. | $200,000 |
| Aug 2, 2012 | Completed final sign-off Aug 2012 | 500 03rd St | O'connor Plumbing & Fire Protection | 4th floor #455 - add 5 new sprinkler heads in office only at new phone booth area. t.i. #2012.0503.9767.Details
4th floor #455 - add 5 new sprinkler heads in office only at new phone booth area. t.i. #2012.0503.9767. | $1,500 |
| Jul 2, 2012 | Completed final sign-off Jul 2013 | 500 03rd St | Rossi Builders Inc. | 5th floor t.i. demolition of (e) non-structural partition & mezzanine area, construct of non-structural partition for area of work.Details
5th floor t.i. demolition of (e) non-structural partition & mezzanine area, construct of non-structural partition for area of work. | $50,000 |
| May 3, 2012 | Completed final sign-off Aug 2012 | 500 03rd St | Rossi Builders Inc. | t.i. suite 455 new interior partitions, new doors, new finishes, paint and carpetDetails
t.i. suite 455 new interior partitions, new doors, new finishes, paint and carpet | $75,000 |
| May 3, 2012 | Completed final sign-off Aug 2012 | 500 03rd St | Rossi Builders Inc. | suite 455, new interior partitoins, new doors, new finishes, paint and carpet joining suites, relocate e light fixturesDetails
suite 455, new interior partitoins, new doors, new finishes, paint and carpet joining suites, relocate e light fixtures | $250,000 |
| Jun 10, 2008 | Never finaled issued Jun 2008, no final | 500 03rd St | street space permit only.Details
street space permit only. | ||
| Apr 22, 2008 | Never finaled issued Apr 2008, no final | 500 03rd St | street spaceDetails
street space | ||
| Feb 23, 2005 | Completed final sign-off Mar 2005 | 500 03rd St | Aquamatic Fire Protection | tenant improvement for aidlin darling desing 3,250sf relocate six sprinklersDetails
tenant improvement for aidlin darling desing 3,250sf relocate six sprinklers | $1,560 |
| Oct 26, 2004 | Completed final sign-off Mar 2005 | 500 03rd St | Northern Sun Associates | oti-2, 4th floor, elDetails
oti-2, 4th floor, el | $60,000 |
| Sep 29, 2004 | Completed final sign-off Mar 2005 | 500 03rd St | Northern Sun Associates | oti-1 on 4th floor. el.Details
oti-1 on 4th floor. el. | $60,000 |
| Feb 12, 2003 | Completed final sign-off Jun 2003 | 510 03rd St | at mezzanine stair, add disabled barrier guardrailDetails
at mezzanine stair, add disabled barrier guardrail | $5,000 | |
| Dec 10, 2002 | Completed final sign-off Mar 2003 | 510 03rd St | Rossi Builders Inc. | oti-3 1st flr,meDetails
oti-3 1st flr,me | $2,000 |
| Nov 15, 2002 | Completed final sign-off Mar 2003 | 510 03rd St | Baxter Electric Inc | oti-2 1st floor elDetails
oti-2 1st floor el | $65,000 |
| Nov 6, 2002 | Completed final sign-off Mar 2003 | 510 03rd St | Allan Automatic Sprinkler | add 9 new sprinkler heads for t.i.Details
add 9 new sprinkler heads for t.i. | $2,753 |
| Sep 24, 2002 | Completed final sign-off Mar 2003 | 510 03rd St | Rossi Builders Inc. | oti-1 1st floor el, me, spDetails
oti-1 1st floor el, me, sp | $180,000 |
| Aug 28, 2002 | Completed final sign-off Mar 2003 | 510 03rd St | Rossi Builders Inc. | no structural work-remove one, plus portion of a second existing porch, in fill facade, repair existDetails
no structural work-remove one, plus portion of a second existing porch, in fill facade, repair exist | $25,000 |
| Jun 3, 2002 | Expired or cancelled expired Oct 2002 | 520 03rd St | T C B Builders Inc | to renew app#2000/11/07/5132 & 2000/11/22/6424 for final inspection only.Details
to renew app#2000/11/07/5132 & 2000/11/22/6424 for final inspection only. | |
| Dec 27, 2001 | Expired or cancelled expired Apr 2002 | 510 03rd St | R L H Fire Protection Inc | renew 2000/01/28/477 with remainder of work & for final insepctionDetails
renew 2000/01/28/477 with remainder of work & for final insepction | $500 |
| Jul 19, 2001 | Expired or cancelled expired Nov 2001 | 500 03rd St | address assignmentDetails
address assignment | ||
| Jun 7, 2001 | Expired or cancelled expired Aug 2003 | 510 03rd St | R L H Fire Protection Inc | oti-2 4th fl sp onlyDetails
oti-2 4th fl sp only | $2,800 |
| May 15, 2001 | Expired or cancelled expired Aug 2003 | 510 03rd St | T C B Builders Inc | revision to 200012288788Details
revision to 200012288788 | $5,000 |
| Mar 9, 2001 | Expired or cancelled cancelled Aug 2001 | 510 03rd St | existing window conversion to roll-up doorDetails
existing window conversion to roll-up door | $50,000 | |
| Jan 8, 2001 | Expired or cancelled expired Oct 2003 | 520 03rd St | renewal of permit app#200009079935Details
renewal of permit app#200009079935 | ||
| Jan 4, 2001 | Expired or cancelled expired Sep 2001 | 510 03rd St | oti-1 4th flr stuc work only new opening cncrte wall slab infill 200012288788 has archit scopeDetails
oti-1 4th flr stuc work only new opening cncrte wall slab infill 200012288788 has archit scope | $10,000 | |
| Dec 28, 2000 | Expired or cancelled expired Mar 2002 | 510 03rd St | oti-1 4th floor el, me, spDetails
oti-1 4th floor el, me, sp | $140,000 | |
| Nov 22, 2000 | Expired or cancelled expired Apr 2002 | 510 03rd St | T C B Builders Inc | addendum to app#9917708 str'l details for elevator shaftDetails
addendum to app#9917708 str'l details for elevator shaft | $10,000 |
| Nov 7, 2000 | Expired or cancelled expired Oct 2003 | 520 03rd St | renewal of application 9917708 for final inspection onlyDetails
renewal of application 9917708 for final inspection only | ||
| Nov 7, 2000 | Expired or cancelled expired Oct 2003 | 510 03rd St | T C B Builders Inc | renewal of application 20000128477Details
renewal of application 20000128477 | |
| Sep 7, 2000 | Expired or cancelled expired Oct 2003 | 520 03rd St | T C B Builders Inc | renew expired appl #9601834Details
renew expired appl #9601834 | |
| Feb 8, 2000 | Expired or cancelled expired Jun 2000 | 520 03rd St | assign street numberDetails
assign street number | ||
| Jan 28, 2000 | Expired or cancelled expired Oct 2003 | 510 03rd St | remodel (e) & (n) stairs & lobby areas, 19 sprinklers -work for sprinklers only-pipe scheduleDetails
remodel (e) & (n) stairs & lobby areas, 19 sprinklers -work for sprinklers only-pipe schedule |