Block 3749, lot 062
303 02nd St
- City’s use
- Commercial Office
- Built
- 1988
- Stories
- 10
- Rooms
- 20 bathrooms
- Building
- 809,986 sq ft
- Lot
- 136,442 sq ft
- Zoning
- SSO
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
The 200 most recent permits filed for this property.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 8, 2026 | In progress issued Oct 2026 | 303 02nd St | Bradshaw Group Inc | revision to 202608126437. update door dimensions. revise title 24 for light changes. receptacle loations updated. hardlid ceiling added at changing room. revise electrical panel schedule.Details
revision to 202608126437. update door dimensions. revise title 24 for light changes. receptacle loations updated. hardlid ceiling added at changing room. revise electrical panel schedule. | $5,000 |
| Aug 12, 2026 | In progress issued Sep 2026 | 303 02nd St | Bradshaw Group Inc | ste - n115: ti project, renovation of (e) b occupancy space. no change in occupancy ref bpa: 201603182443 stamp new recive pages ibmDetails
ste - n115: ti project, renovation of (e) b occupancy space. no change in occupancy ref bpa: 201603182443 stamp new recive pages ibm | $140,000 |
| Aug 3, 2026 | In progress issued Aug 2026 | 303 02nd St | Field Construction Inc. | 5th fl: mechanical and electrical for pa#202604038836.Details
5th fl: mechanical and electrical for pa#202604038836. | $35,000 |
| Jun 11, 2026 | In progress issued Jun 2026 | 303 02nd St | Neon Works Creations | suite 105: install 1 electric, wall, single faced sign "freshroll", 9'7" x 24", white led channel letter 3" dept.Details
suite 105: install 1 electric, wall, single faced sign "freshroll", 9'7" x 24", white led channel letter 3" dept. | $4,000 |
| May 28, 2026 | Completed final sign-off Sep 2026 | 303 02nd St | Gci, Inc | interior non structural demolition of walls and mill work ab-017Details
interior non structural demolition of walls and mill work ab-017 | $8,000 |
| Apr 21, 2026 | In progress issued Apr 2026 | 303 02nd St | Gci, Inc | 7/f: installation of (6) new modular phone booths in open office area.Details
7/f: installation of (6) new modular phone booths in open office area. | $15,000 |
| Apr 3, 2026 | In progress issued Jun 2026 | 303 02nd St | Field Construction Inc. | 5th floor: interior tenant improvement work including selective non-strucutral demolition and new interior construction. scope includes new partitions, ceilings, lighting, power/data layout, and finishers per plans.Details
5th floor: interior tenant improvement work including selective non-strucutral demolition and new interior construction. scope includes new partitions, ceilings, lighting, power/data layout, and finishers per plans. | $250,000 |
| Mar 24, 2026 | In progress issued Aug 2026 | 303 02nd St | Bradshaw Group Inc | deferred electrcial for 202507211257.Details
deferred electrcial for 202507211257. | $94,384 |
| Mar 17, 2026 | Completed final sign-off Aug 2026 | 303 02nd St | Gci, Inc | 6/fl-revision 202512121724 to change (e) finishes and remove (e) card readers, revise concrete column mounted tv to be ceiling mounted. update dedicated cooling unit. revise door material and hardwareDetails
6/fl-revision 202512121724 to change (e) finishes and remove (e) card readers, revise concrete column mounted tv to be ceiling mounted. update dedicated cooling unit. revise door material and hardware | |
| Jan 28, 2026 | Completed final sign-off Feb 2026 | 303 02nd St | Phase One Fire Life Safety Systems Inc | fire alarm as built permit to pa#: 202512101409. ste 105Details
fire alarm as built permit to pa#: 202512101409. ste 105 | |
| Dec 18, 2025 | Completed final sign-off Jun 2026 | 303 02nd St | Gci, Inc | strengthening of communicating stair between 8th and 7th floor to reduce vibration and stair tread cracking.Details
strengthening of communicating stair between 8th and 7th floor to reduce vibration and stair tread cracking. | $60,000 |
| Dec 12, 2025 | Completed final sign-off Aug 2026 | 303 02nd St | Gci, Inc | interior t.i to include new partition, new finishes, a new all gender restroom & meeting rooms. 6/fDetails
interior t.i to include new partition, new finishes, a new all gender restroom & meeting rooms. 6/f | $1,200,000 |
| Dec 10, 2025 | Completed final sign-off Feb 2026 | 303 02nd St | Phase One Fire Life Safety Systems Inc | permit: 202507211257. this is a fire alarm t.i. scope. installation of 6 speaker strobes will be added in suite 105 to (e) fire alarm system. ste 105Details
permit: 202507211257. this is a fire alarm t.i. scope. installation of 6 speaker strobes will be added in suite 105 to (e) fire alarm system. ste 105 | $24,961 |
| Dec 3, 2025 | Completed final sign-off Jan 2026 | 303 02nd St | 1st fl suite #105 ref pa # 202507211257: fire sprinkler permit. relocate 20, add 8 and delete 5 sprinklers.Details
1st fl suite #105 ref pa # 202507211257: fire sprinkler permit. relocate 20, add 8 and delete 5 sprinklers. | $17,500 | |
| Oct 2, 2025 | Completed final sign-off May 2026 | 303 02nd St | Gci, Inc | 8th fl- demolish (e) suite entry door and replace with new entry door with glass light.Details
8th fl- demolish (e) suite entry door and replace with new entry door with glass light. | $100,000 |
| Sep 2, 2025 | Completed final sign-off Jun 2026 | 303 02nd St | Gci, Inc | 3rd fl - installation of new phone booths in open office areaDetails
3rd fl - installation of new phone booths in open office area | $25,000 |
| Sep 2, 2025 | Completed final sign-off Jun 2026 | 303 02nd St | Gci, Inc | 7th fl - installation of 12 new phone booths in open office areaDetails
7th fl - installation of 12 new phone booths in open office area | $30,000 |
| Aug 13, 2025 | Completed final sign-off Oct 2025 | 303 02nd St | Enterprise Roofing Service Inc | re roofing: no hot work. sure-flex pvc white solar reflectance .87 thermal remit .89 sir 110Details
re roofing: no hot work. sure-flex pvc white solar reflectance .87 thermal remit .89 sir 110 | $950,000 |
| Jul 21, 2025 | In progress issued Nov 2025 | 303 02nd St | Bradshaw Group Inc | #105: interior tenant improvement including renovation of non bearing interiror partitoins and finishes,modification to the lighting, modiifcation to the electrical and data,modification to the plumbing and fixtures,new kitchen equipment, with no change to building envelope or shear bracing walls.Details
#105: interior tenant improvement including renovation of non bearing interiror partitoins and finishes,modification to the lighting, modiifcation to the electrical and data,modification to the plumbing and fixtures,new kitchen equipment, with no change to building envelope or shear bracing walls. | $916,112 |
| Apr 22, 2025 | Completed final sign-off Apr 2025 | 303 02nd St | Phase One Fire Life Safety Systems Inc | 1st - fire alarm ti project consist of 1 new control relay to turnstile release ref pa 202501228806Details
1st - fire alarm ti project consist of 1 new control relay to turnstile release ref pa 202501228806 | $600 |
| Apr 3, 2025 | Completed final sign-off Oct 2025 | 303 02nd St | Legacy Mechanical & Energy Services, Inc | penthouse boiler and pump replacementDetails
penthouse boiler and pump replacement | $1,200,000 |
| Mar 10, 2025 | Completed final sign-off Aug 2025 | 303 02nd St | Pavion Corp | suite 400 interior ti: upgrade door hardware. upgrade (e) analog video intercom to a new video digital system and door operator at/for the suite main entry, power supply, back up battery, all associated hardware, conduit & cabling & software installationDetails
suite 400 interior ti: upgrade door hardware. upgrade (e) analog video intercom to a new video digital system and door operator at/for the suite main entry, power supply, back up battery, all associated hardware, conduit & cabling & software installation | $32,104 |
| Jan 22, 2025 | Completed final sign-off Aug 2025 | 303 02nd St | Gci, Inc | 1/f: commercial t.ii. install new security turn stiles syste at the elevatorlobby at the south tower. acessibily upgrades to (e) shower room.Details
1/f: commercial t.ii. install new security turn stiles syste at the elevatorlobby at the south tower. acessibily upgrades to (e) shower room. | $10,000 |
| Dec 23, 2024 | In progress filed Dec 2024, not yet issued | 303 02nd St | ground floor exterior plaza: scope or work includes installing poles and caternary lighting fixtures at existing plaza to activate outdoor seating.Details
ground floor exterior plaza: scope or work includes installing poles and caternary lighting fixtures at existing plaza to activate outdoor seating. | $100,000 | |
| Aug 8, 2024 | Completed final sign-off Sep 2024 | 303 02nd St | Rapid Fire Safety&Security Llc Dba Pafa | 8th fl: fire alarm t.i.: adding 24 speakers-strobes and 1 power supply to existing notifier nfs2-3030 fire alarm system. ref to 202406265304Details
8th fl: fire alarm t.i.: adding 24 speakers-strobes and 1 power supply to existing notifier nfs2-3030 fire alarm system. ref to 202406265304 | $16,780 |
| Aug 5, 2024 | Completed final sign-off Aug 2024 | 303 02nd St | Rapid Fire Safety&Security Llc Dba Pafa | 1/f suite 135: ref archictectural permit 202310319879. fire alarm ti only - adding 7 speaker strobes, 1 control relay, and 1 monitor module to existing notifiter nfs2-3030 for suite 135 of south tower.Details
1/f suite 135: ref archictectural permit 202310319879. fire alarm ti only - adding 7 speaker strobes, 1 control relay, and 1 monitor module to existing notifiter nfs2-3030 for suite 135 of south tower. | $15,000 |
| Jul 16, 2024 | Completed final sign-off Aug 2024 | 303 02nd St | Pioneer Fire Inc. | relocate 18 pendent. add 1 pendent. gc til pa#202406265304Details
relocate 18 pendent. add 1 pendent. gc til pa#202406265304 | $3,300 |
| Jul 15, 2024 | Expired or cancelled withdrawn Aug 2024 | 303 02nd St | Hp Build | rev 202310319879- suite n135- mechanical and electrical changes to restaurantDetails
rev 202310319879- suite n135- mechanical and electrical changes to restaurant | |
| Jun 26, 2024 | Completed final sign-off Dec 2024 | 303 02nd St | Gci, Inc | 8/f: new phone booths. new power for phone booths.Details
8/f: new phone booths. new power for phone booths. | $100,000 |
| Jun 4, 2024 | Completed final sign-off Jul 2024 | 303 02nd St | fire sprinklers - relocate 17, add 4, and delete 4 sprinklers on the ground floor. ref permit# 202310319879Details
fire sprinklers - relocate 17, add 4, and delete 4 sprinklers on the ground floor. ref permit# 202310319879 | $6,800 | |
| May 13, 2024 | Completed final sign-off Aug 2024 | 303 02nd St | Edison Fire Extinguisher Company Inc | #s135: hood and duct fire system installation ref pa 202310319879Details
#s135: hood and duct fire system installation ref pa 202310319879 | $3,713 |
| May 1, 2024 | Completed final sign-off Mar 2025 | 303 02nd St | Enterprise Roofing Service Inc | re-roofing (7th floor decks)Details
re-roofing (7th floor decks) | $479,729 |
| Mar 6, 2024 | Completed final sign-off Mar 2024 | 303 02nd St | Gci, Inc | re-striping in parking garage (private). reference bpa# 202212158430Details
re-striping in parking garage (private). reference bpa# 202212158430 | $10,000 |
| Mar 5, 2024 | Completed final sign-off Aug 2024 | 303 02nd St | Signage Solutions Corporation | ste #135: install 1 illuminated wall sign "mendocino farms" facing courtyardDetails
ste #135: install 1 illuminated wall sign "mendocino farms" facing courtyard | $9,000 |
| Mar 5, 2024 | Completed final sign-off Aug 2024 | 303 02nd St | Signage Solutions Corporation | ste #135: install 1 illuminated wall sign logo facing courtyardDetails
ste #135: install 1 illuminated wall sign logo facing courtyard | $6,000 |
| Mar 5, 2024 | Completed final sign-off Aug 2024 | 303 02nd St | Signage Solutions Corporation | ste #135: install 1 vinyl sign on (e) structure facing courtyard " mendo"Details
ste #135: install 1 vinyl sign on (e) structure facing courtyard " mendo" | $1,000 |
| Jan 26, 2024 | In progress filed Jan 2024, not yet issued | 303 02nd St | Gci, Inc | new ev charging stations. remove/reloate e wheel stops and modify stripping to convert 4 standard parking stalls to become 1 van accessible charging space and 1 non accessible ev charging space access aisle and accessible route to existing building entryDetails
new ev charging stations. remove/reloate e wheel stops and modify stripping to convert 4 standard parking stalls to become 1 van accessible charging space and 1 non accessible ev charging space access aisle and accessible route to existing building entry | $350,000 |
| Dec 21, 2023 | In progress filed Dec 2023, not yet issued | 303 02nd St | north & south tower entries to comply w/ accessilbe business entry 51-61. abe 201911017697. install power door operator & tape down interior walk off door matt, all work inside property line/plazaDetails
north & south tower entries to comply w/ accessilbe business entry 51-61. abe 201911017697. install power door operator & tape down interior walk off door matt, all work inside property line/plaza | $70,000 | |
| Dec 18, 2023 | Expired or cancelled cancelled May 2024 | 303 02nd St | Golden Gate Sign Company Inc. | 1-interior non-illumnited single face wall sign "wells fargo" (sign a)Details
1-interior non-illumnited single face wall sign "wells fargo" (sign a) | $2,000 |
| Dec 4, 2023 | Completed final sign-off Jan 2024 | 303 02nd St | Hp Build | construction of 1 non-structural demising wall between states. patch and match where neededDetails
construction of 1 non-structural demising wall between states. patch and match where needed | $100,000 |
| Oct 31, 2023 | Completed final sign-off Aug 2024 | 303 02nd St | Hp Build | suite# 135 - t.i. of (e) space consisting of cafe kitchen and boh remodel w/ new kitchen, new partition walls. mep distribution modification.Details
suite# 135 - t.i. of (e) space consisting of cafe kitchen and boh remodel w/ new kitchen, new partition walls. mep distribution modification. | $250,000 |
| Oct 26, 2023 | Completed final sign-off Dec 2023 | 303 02nd St | Commercial Interior Builders Inc | 8th fl demolition of non structural partitions, ceiling, lighting & finishes. ref pa 2023-1025-9395Details
8th fl demolition of non structural partitions, ceiling, lighting & finishes. ref pa 2023-1025-9395 | $25,000 |
| Oct 26, 2023 | Completed final sign-off Dec 2023 | 303 02nd St | Commercial Interior Builders Inc | 7th fl demolition of non structural partitions, ceiling, lighting & finishes. ref pa 2023-1025-9395Details
7th fl demolition of non structural partitions, ceiling, lighting & finishes. ref pa 2023-1025-9395 | $35,000 |
| Oct 25, 2023 | Completed final sign-off Nov 2023 | 303 02nd St | Golden Gate Fire Protection Inc | fire sprinklers; delete 10 pendents on the 7/f and delete 6 concelaed pendents on the 8/f and the associated pipingDetails
fire sprinklers; delete 10 pendents on the 7/f and delete 6 concelaed pendents on the 8/f and the associated piping | $9,920 |
| Oct 19, 2023 | Completed final sign-off Nov 2023 | 303 02nd St | Rapid Fire Safety&Security Llc Dba Pafa | fire alarm ti resubmittal as builts adding 1 relay module for av system shutdown to existing notifier nfs2-3030 fire alarm system. refe 202309086153Details
fire alarm ti resubmittal as builts adding 1 relay module for av system shutdown to existing notifier nfs2-3030 fire alarm system. refe 202309086153 | |
| Oct 3, 2023 | Completed final sign-off Oct 2023 | 303 02nd St | Pribuss Engineering Inc | permit rev to pa#202309126355. add sprinklers per sffd inspector for coverage - total 16 heads added from previousDetails
permit rev to pa#202309126355. add sprinklers per sffd inspector for coverage - total 16 heads added from previous | $8,000 |
| Sep 12, 2023 | Never finaled issued Sep 2023, no final | 303 02nd St | Pribuss Engineering Inc | modify sprinkler head locations to accommodate new ceiling and partition layout for new office space on the 5th fl. total sprinklers in project 50Details
modify sprinkler head locations to accommodate new ceiling and partition layout for new office space on the 5th fl. total sprinklers in project 50 | $25,700 |
| Sep 8, 2023 | Completed final sign-off Oct 2023 | 303 02nd St | Rapid Fire Safety&Security Llc Dba Pafa | fire alarm ti: (5th floor) adding (1) power supply (22) speaker-strobes, and (2) duckt detectors to (e) notifier nfsl-3030 fire alarm system. ref bpa# 202306019072Details
fire alarm ti: (5th floor) adding (1) power supply (22) speaker-strobes, and (2) duckt detectors to (e) notifier nfsl-3030 fire alarm system. ref bpa# 202306019072 | $18,240 |
| Jul 26, 2023 | Completed final sign-off Jun 2024 | 303 02nd St | Principal Builders Inc. | 5/f: mep for pa# 202306019072.Details
5/f: mep for pa# 202306019072. | $500,000 |
| Jun 1, 2023 | Completed final sign-off Jun 2024 | 303 02nd St | Principal Builders Inc. | 5/f: interior t.i. (n) non-load bearing partitions, glazing, doors, millwork, & finishes. mepDetails
5/f: interior t.i. (n) non-load bearing partitions, glazing, doors, millwork, & finishes. mep | $2,000,000 |
| Mar 16, 2023 | Completed final sign-off Apr 2023 | 303 02nd St | Anderson, Rowe & Buckley, Inc. | 6/f: fire sprinkler only. remove 3 phone booth. remove 3 pendents and plug-off at branch line.Details
6/f: fire sprinkler only. remove 3 phone booth. remove 3 pendents and plug-off at branch line. | $1,500 |
| Jan 23, 2023 | Completed final sign-off May 2023 | 303 02nd St | Enterprise Roofing Service Inc | reroofingDetails
reroofing | $1,314,937 |
| Jan 10, 2023 | Completed final sign-off Apr 2023 | 303 02nd St | Field Construction Inc. | install 1 vav box, ductwork for new floor layout, lighting fistures and associated circuiting/controls, power and signal devices and wiring ref 202210043682Details
install 1 vav box, ductwork for new floor layout, lighting fistures and associated circuiting/controls, power and signal devices and wiring ref 202210043682 | $170,000 |
| Jan 9, 2023 | Completed final sign-off Mar 2023 | 303 02nd St | Golden Gate Fire Protection Inc | 4th floor: fire sprinklers; relocate 7 pendents, 9 concealed pendents, and 15 uprights in suite 450. ref t.i. pa#202210043682Details
4th floor: fire sprinklers; relocate 7 pendents, 9 concealed pendents, and 15 uprights in suite 450. ref t.i. pa#202210043682 | $16,926 |
| Dec 30, 2022 | Completed final sign-off Apr 2024 | 303 02nd St | Pacific Auxiliary Fire Alarm | 4/flr ste 450: fire alarm ti- adding 12 speaker-strobes to existing notifier nfs2-3030 fire alarm systemDetails
4/flr ste 450: fire alarm ti- adding 12 speaker-strobes to existing notifier nfs2-3030 fire alarm system | $14,136 |
| Dec 15, 2022 | Completed final sign-off Mar 2024 | 303 02nd St | Gci, Inc | to convert (4)(e) parking stalls into (1) van accessible ev charging stall & (1) standard ev charging stall. new type-3 ev chargers provided at each stall per sf ordinance 244-19Details
to convert (4)(e) parking stalls into (1) van accessible ev charging stall & (1) standard ev charging stall. new type-3 ev chargers provided at each stall per sf ordinance 244-19 | $350,000 |
| Dec 13, 2022 | Expired or cancelled cancelled Jan 2026 | 303 02nd St | 4th/flr: restroom upgrades: includes removal of all existing finishes, wallpaper & corner guards, particle walls & prep for new finish. remove plumbing fixtures, equipments, accessories, toilet partitions. provide new finishes, plumbing fixtures, equipments, accessories & toilet partitions.Details
4th/flr: restroom upgrades: includes removal of all existing finishes, wallpaper & corner guards, particle walls & prep for new finish. remove plumbing fixtures, equipments, accessories, toilet partitions. provide new finishes, plumbing fixtures, equipments, accessories & toilet partitions. | $400,000 | |
| Dec 12, 2022 | Completed final sign-off Dec 2022 | 303 02nd St | fire sprinkler permit. add 4 sprinklers in meeting booths on the 6th floor. t.i. 202101273427Details
fire sprinkler permit. add 4 sprinklers in meeting booths on the 6th floor. t.i. 202101273427 | $2,000 | |
| Oct 4, 2022 | Completed final sign-off Apr 2023 | 303 02nd St | Field Construction Inc. | demolition of non structural paritions, ceiling, lighting, millwork and finsihes. new construction of non structural partitoins, ceiling, lighting, elec, finishes.Details
demolition of non structural paritions, ceiling, lighting, millwork and finsihes. new construction of non structural partitoins, ceiling, lighting, elec, finishes. | $220,000 |
| Sep 14, 2022 | Never finaled issued Sep 2022, no final | 303 02nd St | G L C Construction Company Inc | removal of (1 of 2) (e) atm's @ wells fargo bank exterior storefront and replacing solid storefront panels with new tinted glazing to match existing. (inside property line)Details
removal of (1 of 2) (e) atm's @ wells fargo bank exterior storefront and replacing solid storefront panels with new tinted glazing to match existing. (inside property line) | $2,000 |
| Aug 19, 2022 | Completed final sign-off Sep 2022 | 303 02nd St | Skyline Construction | 5/f:revision to pa# 202201146043. scope of work includes to provide framing partitions behind toilet in women ada stall per dbi inspector comments.Details
5/f:revision to pa# 202201146043. scope of work includes to provide framing partitions behind toilet in women ada stall per dbi inspector comments. | $6,000 |
| Jun 27, 2022 | Completed final sign-off Aug 2022 | 303 02nd St | Pacific Auxiliary Fire Alarm | 5th fl: fire alarm t.i.: adding 6 speakers/strobes, 1 strobe, and 3 speakers to existing notifier nfs2-3030 fire alarm system.Details
5th fl: fire alarm t.i.: adding 6 speakers/strobes, 1 strobe, and 3 speakers to existing notifier nfs2-3030 fire alarm system. | $13,698 |
| Jun 27, 2022 | Completed final sign-off Aug 2022 | 303 02nd St | Pacific Auxiliary Fire Alarm | 4th fl: fire alarm t.i.: adding 6 speakers, 4 speaker/strobes, and 1 strobe to existing notifier nfs2-3030 fire alarm system.Details
4th fl: fire alarm t.i.: adding 6 speakers, 4 speaker/strobes, and 1 strobe to existing notifier nfs2-3030 fire alarm system. | $13,846 |
| Jun 23, 2022 | Completed final sign-off Aug 2022 | 303 02nd St | Pioneer Fire Inc. | ste n450: fire sprinklers: relocate 2 pendent heads & convert 4 pendents to uprights. ref t.i. pa#202206075734. maher n/a.Details
ste n450: fire sprinklers: relocate 2 pendent heads & convert 4 pendents to uprights. ref t.i. pa#202206075734. maher n/a. | $2,000 |
| Jun 23, 2022 | Completed final sign-off Aug 2022 | 303 02nd St | Pioneer Fire Inc. | ste n550: fire sprinklers: convert 78 pendents to uprights. ref t.i. pa202201146043. maher n/a.Details
ste n550: fire sprinklers: convert 78 pendents to uprights. ref t.i. pa202201146043. maher n/a. | $19,500 |
| Jun 15, 2022 | Completed final sign-off Oct 2022 | 303 02nd St | G L C Construction Company Inc | revision to pa 2021-1117-2614 1 supply & return grille added. no new fsd are being added. add lighting and power to first floor.Details
revision to pa 2021-1117-2614 1 supply & return grille added. no new fsd are being added. add lighting and power to first floor. | |
| Jun 10, 2022 | Completed final sign-off Jul 2022 | 303 02nd St | Pacific Auxiliary Fire Alarm | 1/f plaza north tower: fire alarm ti. adding 2 speaker/strobes and 1 speaker to existing notifier nfs-3030 fire alarm system. ref ti permit 202111172614.Details
1/f plaza north tower: fire alarm ti. adding 2 speaker/strobes and 1 speaker to existing notifier nfs-3030 fire alarm system. ref ti permit 202111172614. | $11,390 |
| Jun 7, 2022 | Completed final sign-off Sep 2022 | 303 02nd St | Skyline Construction | 5th fl - mechanical and electrical for ti at suite n550 ref pa 2022-0114-6043.Details
5th fl - mechanical and electrical for ti at suite n550 ref pa 2022-0114-6043. | $15,000 |
| Jun 7, 2022 | Completed final sign-off Sep 2022 | 303 02nd St | Skyline Construction | ste n401 & n450: mechanical & electrical work for tenant improvement. ref arch pa# 202203109672.Details
ste n401 & n450: mechanical & electrical work for tenant improvement. ref arch pa# 202203109672. | $20,000 |
| Jun 1, 2022 | Completed final sign-off Jul 2022 | 303 02nd St | G L C Construction Company Inc | revision to pa# 202111172614. existing restroom to remain unchanged.Details
revision to pa# 202111172614. existing restroom to remain unchanged. | |
| Mar 10, 2022 | Completed final sign-off Sep 2022 | 303 02nd St | Skyline Construction | 4/f suite n401 & n450: demolition of non-structural partitions, ceiling, lighting, millwork and finishes. new construction of non-structural partitions, ceiling, lighting, millwork and finishes.mep will be deferred submittal.Details
4/f suite n401 & n450: demolition of non-structural partitions, ceiling, lighting, millwork and finishes. new construction of non-structural partitions, ceiling, lighting, millwork and finishes.mep will be deferred submittal. | $1,000,000 |
| Feb 4, 2022 | Completed final sign-off Oct 2022 | 303 02nd St | G L C Construction Company Inc | intall 2 new atm units. structural work only.Details
intall 2 new atm units. structural work only. | $3,000 |
| Jan 14, 2022 | Completed final sign-off Sep 2022 | 303 02nd St | Skyline Construction | suite n550, tenant improvement demo of non structural partition, ceiling, lighting, millwork+finishes, new construction of non-structural partition, ceiling , lighting, millwork and finishes.Details
suite n550, tenant improvement demo of non structural partition, ceiling, lighting, millwork+finishes, new construction of non-structural partition, ceiling , lighting, millwork and finishes. | $250,000 |
| Nov 17, 2021 | Completed final sign-off Jul 2022 | 303 02nd St | G L C Construction Company Inc | ground fl remove furniture, mill work, equipment and flooring in (e) wells fargo bank; install new interior finishes and new wall partitions (non bearing) new furnitureDetails
ground fl remove furniture, mill work, equipment and flooring in (e) wells fargo bank; install new interior finishes and new wall partitions (non bearing) new furniture | $136,000 |
| Nov 16, 2021 | Completed final sign-off Nov 2021 | 303 02nd St | Anderson, Rowe & Buckley, Inc. | t.i. of (e) fire sprinkler system. , relocate 1 . ref pa 202110140463.Details
t.i. of (e) fire sprinkler system. , relocate 1 . ref pa 202110140463. | $1,000 |
| Nov 16, 2021 | Completed final sign-off Nov 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | 7th fl - fire alarm ti resubmittal: fa drawings reflect changes per notes by field inspector. no new/additional equipment ref pa 2021-0614-2337Details
7th fl - fire alarm ti resubmittal: fa drawings reflect changes per notes by field inspector. no new/additional equipment ref pa 2021-0614-2337 | |
| Nov 16, 2021 | Completed final sign-off Nov 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | 6th fl - fire alarm ti resubmittal: fa drawings reflect changes per notes by field inspector. no new/additional equipment ref pa 2021-0614-2339Details
6th fl - fire alarm ti resubmittal: fa drawings reflect changes per notes by field inspector. no new/additional equipment ref pa 2021-0614-2339 | |
| Oct 14, 2021 | Completed final sign-off Jan 2022 | 303 02nd St | Novo Construction Inc | mechanical and electrical work for ti on 6th fl ref 201907186225Details
mechanical and electrical work for ti on 6th fl ref 201907186225 | $45,000 |
| Sep 28, 2021 | Completed final sign-off Jan 2022 | 303 02nd St | Pacific Auxiliary Fire Alarm | 3rd floor:fire alarm ti: adding 1 smoke detector, 1 relay module, 1 dual monitor module, 1 speaker, 1 strobe and 2 speaker strobes to extg notifier nfs2-3030 fire alarm systemDetails
3rd floor:fire alarm ti: adding 1 smoke detector, 1 relay module, 1 dual monitor module, 1 speaker, 1 strobe and 2 speaker strobes to extg notifier nfs2-3030 fire alarm system | $12,607 |
| Sep 20, 2021 | Never finaled issued Sep 2021, no final | 303 02nd St | Skyline Construction | 3/f: new lighting & controls in open office area, hallways, private offices, & receiption. power & data (e) to remain throughout space.Details
3/f: new lighting & controls in open office area, hallways, private offices, & receiption. power & data (e) to remain throughout space. | $7,000 |
| Aug 23, 2021 | Completed final sign-off Sep 2021 | 303 02nd St | Golden Gate Fire Protection Inc | 6th & 7th floors - fire sprinkler, as built to permit#2021-0806-5928. show 2 heads in each bathroom on 6th & 7th flrs, install of 3 per restroom. t.i. ref#2021-0127-3427 6th flr & 2021-0127-3430 7th .Details
6th & 7th floors - fire sprinkler, as built to permit#2021-0806-5928. show 2 heads in each bathroom on 6th & 7th flrs, install of 3 per restroom. t.i. ref#2021-0127-3427 6th flr & 2021-0127-3430 7th . | $1,000 |
| Aug 6, 2021 | Completed final sign-off Sep 2021 | 303 02nd St | Golden Gate Fire Protection Inc | fire sprinkler as-built to 2021 0520 0706. relocate 5 sprinkler heads in bathroom on 6 & 7/fs (10 new heads to job); show (3) upright heads in room 601 on 6/f instead of concealed. t.i. ref 202101273427 (6/f) & 2021 0127 3430 (7/f).Details
fire sprinkler as-built to 2021 0520 0706. relocate 5 sprinkler heads in bathroom on 6 & 7/fs (10 new heads to job); show (3) upright heads in room 601 on 6/f instead of concealed. t.i. ref 202101273427 (6/f) & 2021 0127 3430 (7/f). | $1,000 |
| Jul 12, 2021 | Completed final sign-off Feb 2023 | 303 02nd St | Pacific Auxiliary Fire Alarm | 9th floor: fire alarm t.i. removing 1 dual monitor module from notifier nfs2-3030 fire alarm system.Details
9th floor: fire alarm t.i. removing 1 dual monitor module from notifier nfs2-3030 fire alarm system. | $2,836 |
| Jul 7, 2021 | Completed final sign-off Oct 2022 | 303 02nd St | Skyline Construction | 3rd fl: renovation of (e) elevator lobby & multi-stall restrooms proposed tenant improvement entils construction of new paint, tile, and wall, covering finishes. including mep.Details
3rd fl: renovation of (e) elevator lobby & multi-stall restrooms proposed tenant improvement entils construction of new paint, tile, and wall, covering finishes. including mep. | $350,000 |
| Jun 14, 2021 | Completed final sign-off Nov 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm and two-communication system for tenant improvement on the 6th floor. add 29 4~encrypt&strobes.Details
fire alarm and two-communication system for tenant improvement on the 6th floor. add 29 4~encrypt&strobes. | $15,000 |
| Jun 14, 2021 | Completed final sign-off Nov 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm and two-communication system for tenant improvement on the 7th floor.Details
fire alarm and two-communication system for tenant improvement on the 7th floor. | $20,000 |
| May 24, 2021 | Never finaled issued Jun 2021, no final | 303 02nd St | Skyline Construction | 6th fl - mechanical, electrical and plumbing for tenant improvement. ref pa 2021-0127-3427.Details
6th fl - mechanical, electrical and plumbing for tenant improvement. ref pa 2021-0127-3427. | |
| May 20, 2021 | Never finaled issued Aug 2021, no final | 303 02nd St | Skyline Construction | 7/f: mechanical, electrical and plumbing for t.i. ref arch 202101273430Details
7/f: mechanical, electrical and plumbing for t.i. ref arch 202101273430 | |
| May 20, 2021 | Completed final sign-off Sep 2021 | 303 02nd St | Golden Gate Fire Protection Inc | fire sprinklers: relocate 26 pendent sprinklers and relocate 15 uprights ,add 1 upright on the 6th floor. relocate 30 pendent sprinklers and relocate 17 uprights on the 7th floor. t.i. ref #2021-0127-3427 (6th fl), 2021-0127-3430 (7th fl)Details
fire sprinklers: relocate 26 pendent sprinklers and relocate 15 uprights ,add 1 upright on the 6th floor. relocate 30 pendent sprinklers and relocate 17 uprights on the 7th floor. t.i. ref #2021-0127-3427 (6th fl), 2021-0127-3430 (7th fl) | $47,250 |
| Mar 24, 2021 | Completed final sign-off Oct 2021 | 303 02nd St | Skyline Construction | revision to pa# 202007019450. to revise the step and ramp at exterior pation on the 9th floor.Details
revision to pa# 202007019450. to revise the step and ramp at exterior pation on the 9th floor. | $20,000 |
| Jan 27, 2021 | Never finaled issued Apr 2021, no final | 303 02nd St | Skyline Construction | 7th fl tenant improvement to include new non-structural partitions, multi purpose room expansion, all gender restrooms, upgrades to mens & womens restrooms, interior finishes.Details
7th fl tenant improvement to include new non-structural partitions, multi purpose room expansion, all gender restrooms, upgrades to mens & womens restrooms, interior finishes. | $1,250,000 |
| Jan 27, 2021 | Never finaled issued Apr 2021, no final | 303 02nd St | Skyline Construction | 6th floor: t.i. to include new non rated partitions, breakroom, all gender restrooms, parents room. upgrade extg mens and women's restrooms new finishes. mep, life safty and fire sprinkler under seperate perimit.Details
6th floor: t.i. to include new non rated partitions, breakroom, all gender restrooms, parents room. upgrade extg mens and women's restrooms new finishes. mep, life safty and fire sprinkler under seperate perimit. | $1,500,000 |
| Jan 21, 2021 | Never finaled issued Mar 2021, no final | 303 02nd St | Skyline Construction | 7/f: partial demolition of existing construction for future tenant improvement in compliance to ab-017. maher n/a. eniter 7th floor is vacantDetails
7/f: partial demolition of existing construction for future tenant improvement in compliance to ab-017. maher n/a. eniter 7th floor is vacant | $85,000 |
| Jan 19, 2021 | Completed final sign-off Mar 2023 | 303 02nd St | Skyline Construction | 6th fl partial demolition of existing construction for future tenant improvement. ab-017. entire 6th floor is vacant.Details
6th fl partial demolition of existing construction for future tenant improvement. ab-017. entire 6th floor is vacant. | $65,000 |
| Jan 12, 2021 | Completed final sign-off Feb 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | 3rd fl fire alarm ti: adding (1) power supply, (5) smoke detectors, (15) duct detectors, (1) relay module, (10) monitor modules, (1) speaker and (46) speaker-strobe to existing notifier nfs2-3030 fire alarm system. arch & mech 2020-0624-9087Details
3rd fl fire alarm ti: adding (1) power supply, (5) smoke detectors, (15) duct detectors, (1) relay module, (10) monitor modules, (1) speaker and (46) speaker-strobe to existing notifier nfs2-3030 fire alarm system. arch & mech 2020-0624-9087 | $31,012 |
| Dec 15, 2020 | Completed final sign-off Mar 2023 | 303 02nd St | fire sprinkler permit. relocate 108 and add 188 sprinklers on the 3rd floor. demo permit #2020-0117-2190. ti # 2020-0629-9087.Details
fire sprinkler permit. relocate 108 and add 188 sprinklers on the 3rd floor. demo permit #2020-0117-2190. ti # 2020-0629-9087. | $118,000 | |
| Dec 10, 2020 | Completed final sign-off Feb 2021 | 303 02nd St | Pioneer Fire Inc. | fire sprinkler relocate 12 uprights, 44 relocated concealed pendents, 30 added concealed pendents. gc permits: 2020-0624-9087 (3rd), 2020-0701-9450 (9th). 2020-0624-9094 (10th).Details
fire sprinkler relocate 12 uprights, 44 relocated concealed pendents, 30 added concealed pendents. gc permits: 2020-0624-9087 (3rd), 2020-0701-9450 (9th). 2020-0624-9094 (10th). | $43,000 |
| Dec 9, 2020 | Completed final sign-off Feb 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | 10th fl fire alarm ti: adding (2) smoke detectors, (20) duct detectors, (4) monitor modules, and (68) speaker-strobes to existing notifier nfs2-3030 fire alarm system. adding (1) call station to existing cornell 2-way comm system. ref ti 2020-0624-9094.Details
10th fl fire alarm ti: adding (2) smoke detectors, (20) duct detectors, (4) monitor modules, and (68) speaker-strobes to existing notifier nfs2-3030 fire alarm system. adding (1) call station to existing cornell 2-way comm system. ref ti 2020-0624-9094. | $31,918 |
| Dec 2, 2020 | Completed final sign-off Dec 2020 | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm ti: adding (2) power supplies, (95) speaker-strobes, (1) strobe, (5) duct detectors, (3) smoke detectors and (3) relay modules to existing notifier nfs2-3030 fire alarm system.Details
fire alarm ti: adding (2) power supplies, (95) speaker-strobes, (1) strobe, (5) duct detectors, (3) smoke detectors and (3) relay modules to existing notifier nfs2-3030 fire alarm system. | $17,966 |
| Dec 1, 2020 | Never finaled issued Mar 2021, no final | 303 02nd St | Skyline Construction | rev to pa# 202007019450; to add additional work at patio 965 to add guard railsDetails
rev to pa# 202007019450; to add additional work at patio 965 to add guard rails | $15,000 |
| Nov 6, 2020 | Completed final sign-off Feb 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm ti: adding (1) loop control module, (9) smoke detectors, (16) duct detectors, (3) relay modules, (7) monitor modules and (6) speaker-strobes to existing notifier nfs2-3030 fa system. arch ref 2020-0701-9450. two-way commDetails
fire alarm ti: adding (1) loop control module, (9) smoke detectors, (16) duct detectors, (3) relay modules, (7) monitor modules and (6) speaker-strobes to existing notifier nfs2-3030 fa system. arch ref 2020-0701-9450. two-way comm | $31,444 |
| Oct 27, 2020 | Completed final sign-off Sep 2021 | 303 02nd St | Skyline Construction | demo and replace (1) closed circuit cooling tower, (2) condenser water pumps, (1) expansion tank & (1) control panel.Details
demo and replace (1) closed circuit cooling tower, (2) condenser water pumps, (1) expansion tank & (1) control panel. | $250,000 |
| Oct 15, 2020 | Completed final sign-off Feb 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm only - tenant improvement to existing notifier nfs2-3030. adding 2 smoke detectors. building permit 2019-0612-3176.Details
fire alarm only - tenant improvement to existing notifier nfs2-3030. adding 2 smoke detectors. building permit 2019-0612-3176. | $5,500 |
| Sep 26, 2020 | Completed final sign-off Feb 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | 3/f, south: fire alarm only, t.i. 2-way emergency communication system. adding (1) call stationDetails
3/f, south: fire alarm only, t.i. 2-way emergency communication system. adding (1) call station | $7,000 |
| Sep 19, 2020 | Completed final sign-off Mar 2021 | 303 02nd St | Skyline Construction | 3rd fl: mechanical, electrical & plumbing for ti. ref pa# 202002265504.Details
3rd fl: mechanical, electrical & plumbing for ti. ref pa# 202002265504. | $220,000 |
| Sep 12, 2020 | Completed final sign-off Jan 2021 | 303 02nd St | Bevilacqua & Sons | restroom upgrades on 3/f scope of work includes new stall partitions, reinstalling (e) plumbing fixtures & restroom accessories, or providing new as required. scope of work to be barrier removal only.Details
restroom upgrades on 3/f scope of work includes new stall partitions, reinstalling (e) plumbing fixtures & restroom accessories, or providing new as required. scope of work to be barrier removal only. | $75,000 |
| Jul 1, 2020 | Completed final sign-off Oct 2021 | 303 02nd St | Skyline Construction | ti of existing office space on the entire 9th fl. work includes non-structural partitions, new lighting , ceilings, doors, carpets and paint. mep included.Details
ti of existing office space on the entire 9th fl. work includes non-structural partitions, new lighting , ceilings, doors, carpets and paint. mep included. | $8,782,000 |
| Jun 24, 2020 | Completed final sign-off Sep 2021 | 303 02nd St | Skyline Construction | suite #350: ti work entails construction of new non-bearing partitions, millwork, ceiling system w/new lighting, doors & frames, power & communication, fixtures & furniture systems, carpet & paint finishes. maher naDetails
suite #350: ti work entails construction of new non-bearing partitions, millwork, ceiling system w/new lighting, doors & frames, power & communication, fixtures & furniture systems, carpet & paint finishes. maher na | $5,892,369 |
| Jun 24, 2020 | Completed final sign-off Oct 2021 | 303 02nd St | Skyline Construction | ti of existing office space on the entire 10th fl. work includes non-structural partitions, mep, finishes, and re-cladding of an (e) communicating stair.Details
ti of existing office space on the entire 10th fl. work includes non-structural partitions, mep, finishes, and re-cladding of an (e) communicating stair. | $8,249,316 |
| Feb 26, 2020 | Completed final sign-off Mar 2021 | 303 02nd St | Skyline Construction | full floor tenant improvement on the 3rd fl to include new non rated partitions, breakrooms all gender restrooms, mothers room and upgrade multi occupant restrooms. new finishes. mep sep permitDetails
full floor tenant improvement on the 3rd fl to include new non rated partitions, breakrooms all gender restrooms, mothers room and upgrade multi occupant restrooms. new finishes. mep sep permit | $3,830,000 |
| Feb 24, 2020 | Expired or cancelled cancelled Feb 2022 | 303 02nd St | Pioneer Fire Inc. | 4/f: suite 401: fire sprinklers: relocate 7 pendents, add 2 pendents and relocate 1 upright. ref t.i. pa201911127095. maher n/a.Details
4/f: suite 401: fire sprinklers: relocate 7 pendents, add 2 pendents and relocate 1 upright. ref t.i. pa201911127095. maher n/a. | $5,000 |
| Feb 20, 2020 | Expired or cancelled cancelled Jan 2026 | 303 02nd St | refe. pa#????????????; 4/f installation of new vav boxes and accompanying doct work and diffusers air balance of new and existing diffusers.Details
refe. pa#????????????; 4/f installation of new vav boxes and accompanying doct work and diffusers air balance of new and existing diffusers. | $15,000 | |
| Feb 19, 2020 | Completed final sign-off Aug 2020 | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alar ti add 1 duct detector , 1 relay module, relocate 1 sprinkler strobe to e notifier nfs2 3030 fire alarm system ref 201912189855Details
fire alar ti add 1 duct detector , 1 relay module, relocate 1 sprinkler strobe to e notifier nfs2 3030 fire alarm system ref 201912189855 | $6,746 |
| Jan 27, 2020 | Completed final sign-off Apr 2020 | 303 02nd St | Golden Gate Fire Protection Inc | ref ti; 201912189855: fire sprinkler: relocate 6 upright fire sprinklers in studio room on the 6th floor.Details
ref ti; 201912189855: fire sprinkler: relocate 6 upright fire sprinklers in studio room on the 6th floor. | $3,000 |
| Jan 22, 2020 | Completed final sign-off Oct 2021 | 303 02nd St | Skyline Construction | interior demolition on 3rd, 9th, and 10th fls. per ab-017.Details
interior demolition on 3rd, 9th, and 10th fls. per ab-017. | $275,000 |
| Jan 17, 2020 | Never finaled issued Jan 2020, no final | 303 02nd St | 3/f: interior demo of fire sprinklers. ref demo pa202001172193. maher n/a.Details
3/f: interior demo of fire sprinklers. ref demo pa202001172193. maher n/a. | $15,000 | |
| Jan 17, 2020 | Completed final sign-off Jul 2020 | 303 02nd St | Skyline Construction | 3/f: interior non-structural demo of partitions, ceilings and floor finishes - to comply with ab-017. maher n/a.Details
3/f: interior non-structural demo of partitions, ceilings and floor finishes - to comply with ab-017. maher n/a. | $40,000 |
| Dec 23, 2019 | Never finaled issued Feb 2020, no final | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm ti: adding 2-way communicaiton system (master) to north tower fcc. adding expansion equipment to south tower level 2 & 7. adding call master to south tower level 8. adding pull station, 2 relay modules, 5 monitoring modules to existing notifier nfs2-3030 fa system. ref pa #201910285682.Details
fire alarm ti: adding 2-way communicaiton system (master) to north tower fcc. adding expansion equipment to south tower level 2 & 7. adding call master to south tower level 8. adding pull station, 2 relay modules, 5 monitoring modules to existing notifier nfs2-3030 fa system. ref pa #201910285682. | $33,098 |
| Dec 18, 2019 | Completed final sign-off Feb 2020 | 303 02nd St | Pacific Auxiliary Fire Alarm | 9th floor: fire alarm t.i. as built drawings showing change from speaker to speaker strobes per sffd field inspector request 12/4/19. ref app#201806192267.Details
9th floor: fire alarm t.i. as built drawings showing change from speaker to speaker strobes per sffd field inspector request 12/4/19. ref app#201806192267. | |
| Dec 18, 2019 | Completed final sign-off Aug 2020 | 303 02nd St | Novo Construction Inc | renovation of partial tenant space to include new millwork and finishes. elec work under sep permitDetails
renovation of partial tenant space to include new millwork and finishes. elec work under sep permit | $40,000 |
| Dec 10, 2019 | Never finaled issued Dec 2019, no final | 303 02nd St | Pacific Auxiliary Fire Alarm | 6/f & 8/f: north tower: fire alarm system (tie into existing) - adding 2 relay modules to existing notifier nfs2-3030 alarm system.Details
6/f & 8/f: north tower: fire alarm system (tie into existing) - adding 2 relay modules to existing notifier nfs2-3030 alarm system. | $5,662 |
| Dec 5, 2019 | Completed final sign-off Feb 2020 | 303 02nd St | Pacific Auxiliary Fire Alarm | 6th floor north:fire alarm t.i.: adding 2 relay module and 2 dual point monitor modules to extg notifier nfs-3030 fire alarm system.Details
6th floor north:fire alarm t.i.: adding 2 relay module and 2 dual point monitor modules to extg notifier nfs-3030 fire alarm system. | $7,762 |
| Nov 25, 2019 | Completed final sign-off Feb 2020 | 303 02nd St | True North Signs & Graphic Services | 5th fl, south tower - 4 evacuation signsDetails
5th fl, south tower - 4 evacuation signs | $1,400 |
| Nov 21, 2019 | Completed final sign-off Feb 2020 | 303 02nd St | Pacific Auxiliary Fire Alarm | ref 201910023297; fire alarm t.i. 1 speaker strobe to be relocated, 1 speaker strobe to be removed from (e) notifier nfs2-3030 fa systemDetails
ref 201910023297; fire alarm t.i. 1 speaker strobe to be relocated, 1 speaker strobe to be removed from (e) notifier nfs2-3030 fa system | $4,026 |
| Nov 14, 2019 | Never finaled issued Nov 2019, no final | 303 02nd St | Gci, Inc | occupant load calculation only room 504a circulation, 504b commons, 505 coffee #570 roof deck #506 x-large training. ref pa 2019-1101-6211. maher n/a.Details
occupant load calculation only room 504a circulation, 504b commons, 505 coffee #570 roof deck #506 x-large training. ref pa 2019-1101-6211. maher n/a. | |
| Nov 12, 2019 | Never finaled issued Feb 2020, no final | 303 02nd St | Novo Construction Inc | suite #401 4th floor: new construction of non-structural wall. new millwork, addition of power and data and replaceing light fixtures in suite #401. no structural work inlcuded in scope. no increase in area. no change in occupancy or use. fire/life safety, mech, elec, plumbing separate permitDetails
suite #401 4th floor: new construction of non-structural wall. new millwork, addition of power and data and replaceing light fixtures in suite #401. no structural work inlcuded in scope. no increase in area. no change in occupancy or use. fire/life safety, mech, elec, plumbing separate permit | $600,000 |
| Nov 12, 2019 | Never finaled issued Feb 2020, no final | 303 02nd St | Novo Construction Inc | #401 4th floor: demo of existing non-structural demising wall in suite 401. no increase in area. no change in occupancy or use. mech, electrical, and fire/life safety scopes are not part of project work. remodel per pf #201911127095Details
#401 4th floor: demo of existing non-structural demising wall in suite 401. no increase in area. no change in occupancy or use. mech, electrical, and fire/life safety scopes are not part of project work. remodel per pf #201911127095 | $30,000 |
| Nov 12, 2019 | Completed final sign-off Feb 2020 | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm ti add 1 power supply, 39 speaker strobes, 6 duct det, 1 smoke det, 1 relay module to exist notifier nfs2 3030 fa systemDetails
fire alarm ti add 1 power supply, 39 speaker strobes, 6 duct det, 1 smoke det, 1 relay module to exist notifier nfs2 3030 fa system | $8,752 |
| Nov 8, 2019 | Completed final sign-off Nov 2019 | 303 02nd St | fire sprinkler permit 7th fl: revision to #201908017557. install 12 new pendent sprinkler for new stair opening. add 3 & relocate 1 additional upright sprinkler. ti #201905090220.Details
fire sprinkler permit 7th fl: revision to #201908017557. install 12 new pendent sprinkler for new stair opening. add 3 & relocate 1 additional upright sprinkler. ti #201905090220. | $8,000 | |
| Nov 8, 2019 | Completed final sign-off May 2022 | 303 02nd St | Gci, Inc | replace (e) window with door (not visible from st) for 5th fl. (e) roof terrace, suite 500s. (n) interior landing & steps.Details
replace (e) window with door (not visible from st) for 5th fl. (e) roof terrace, suite 500s. (n) interior landing & steps. | $180,000 |
| Nov 5, 2019 | Completed final sign-off Mar 2020 | 303 02nd St | Golden Gate Fire Protection Inc | 5th floor: revision to app#201910033459. new phone booths in varies areas.add 25 pendents within item.Details
5th floor: revision to app#201910033459. new phone booths in varies areas.add 25 pendents within item. | $1,000 |
| Nov 5, 2019 | Completed final sign-off Jan 2021 | 303 02nd St | Pacific Auxiliary Fire Alarm | 5th flr fire alarm ti 5th fl: adding 1 power supply, 63 speaker strobem 1 speaker and 1 control module to existing notifier nfs2-3030 fa system. ref arch pa #201909232430 (rev #201911016211). maher naDetails
5th flr fire alarm ti 5th fl: adding 1 power supply, 63 speaker strobem 1 speaker and 1 control module to existing notifier nfs2-3030 fa system. ref arch pa #201909232430 (rev #201911016211). maher na | $13,802 |
| Nov 1, 2019 | Completed final sign-off Jun 2022 | 303 02nd St | Gci, Inc | mechanical and electrical work ti on 5th fl ref 201909232430. maher n/a.Details
mechanical and electrical work ti on 5th fl ref 201909232430. maher n/a. | $416,000 |
| Nov 1, 2019 | Completed final sign-off Nov 2019 | 303 02nd St | Golden Gate Fire Protection Inc | 9/f:relocate (4) pendants, add (1), and relocate (4) uprights for suite #900.Details
9/f:relocate (4) pendants, add (1), and relocate (4) uprights for suite #900. | $4,500 |
| Nov 1, 2019 | Completed final sign-off May 2022 | 303 02nd St | Gci, Inc | revision to 2019092323430 to provide revised exiting plan and power and signal plan ref 201909232430Details
revision to 2019092323430 to provide revised exiting plan and power and signal plan ref 201909232430 | |
| Nov 1, 2019 | Completed final sign-off Nov 2019 | 303 02nd St | Golden Gate Fire Protection Inc | relocate 2 pendents & 6 uprights for app dynamics game roomDetails
relocate 2 pendents & 6 uprights for app dynamics game room | $4,000 |
| Nov 1, 2019 | Never finaled issued Nov 2019, no final | 303 02nd St | Novo Construction Inc | mechanical and elec work for ti 6th fl ref 201910023297Details
mechanical and elec work for ti 6th fl ref 201910023297 | $5,000 |
| Oct 28, 2019 | Never finaled issued Oct 2019, no final | 303 02nd St | revision to pa 201906123172 to provide 2-way communication video intercom, door at 8th flr elevator lobby to comply with cbc 1010.1.912Details
revision to pa 201906123172 to provide 2-way communication video intercom, door at 8th flr elevator lobby to comply with cbc 1010.1.912 | ||
| Oct 24, 2019 | Completed final sign-off Jan 2020 | 303 02nd St | Novo Construction Inc | 6/f: rev to pa201811196226 to add automatic controle damper at shaft/breakroom #604. maher n/a.Details
6/f: rev to pa201811196226 to add automatic controle damper at shaft/breakroom #604. maher n/a. | |
| Oct 23, 2019 | Never finaled issued Oct 2019, no final | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm ti adding 2 power supplies 44 speaker strobes, 1 speaker, 4 duct detectors, 1 smoke detector and 1 relay to e notifier nfs2-3030 fire alarm system maher not reqDetails
fire alarm ti adding 2 power supplies 44 speaker strobes, 1 speaker, 4 duct detectors, 1 smoke detector and 1 relay to e notifier nfs2-3030 fire alarm system maher not req | $13,424 |
| Oct 23, 2019 | Completed final sign-off Jan 2020 | 303 02nd St | Novo Construction Inc | 9th fl - mep for ti. ref pa 2018-0202-0269Details
9th fl - mep for ti. ref pa 2018-0202-0269 | $8,000 |
| Oct 22, 2019 | Never finaled issued Oct 2019, no final | 303 02nd St | Pacific Auxiliary Fire Alarm | 2nd fl - fire alarm ti adding 40, speaker-strobes & 5 duct detectors to existing notifier nfs2-3030 fa system. ref pa 2019-0807-8121 (mech pa) & 2019-0509-0218 (arch pa)Details
2nd fl - fire alarm ti adding 40, speaker-strobes & 5 duct detectors to existing notifier nfs2-3030 fa system. ref pa 2019-0807-8121 (mech pa) & 2019-0509-0218 (arch pa) | $13,424 |
| Oct 22, 2019 | Never finaled issued Oct 2019, no final | 303 02nd St | Pacific Auxiliary Fire Alarm | 8th fl - fire alarm ti - add 2 poiwer supplies, 87 speaker-strobes, 5 duct dtectors, 2 smoke detectors, 2 relays to e9) notifier nfs2-3030 fa system. ref pa 2019-0807-8127 (mep pa) and 2019-0612-3172 (arch pa)Details
8th fl - fire alarm ti - add 2 poiwer supplies, 87 speaker-strobes, 5 duct dtectors, 2 smoke detectors, 2 relays to e9) notifier nfs2-3030 fa system. ref pa 2019-0807-8127 (mep pa) and 2019-0612-3172 (arch pa) | $13,424 |
| Oct 17, 2019 | Completed final sign-off Mar 2021 | 303 02nd St | Gci, Inc | 4th floor: partial floor office tenant retrofit to include lighting, power and signal wiring lighting, and controls. ref app#201907317423. n/a for maherDetails
4th floor: partial floor office tenant retrofit to include lighting, power and signal wiring lighting, and controls. ref app#201907317423. n/a for maher | $8,000 |
| Oct 3, 2019 | Completed final sign-off Dec 2019 | 303 02nd St | Golden Gate Fire Protection Inc | fire sprinkler only - relocate 25 pendent & 28 uprights for knotel 5th fl. (south tower).Details
fire sprinkler only - relocate 25 pendent & 28 uprights for knotel 5th fl. (south tower). | $18,000 |
| Oct 2, 2019 | Completed final sign-off Jan 2020 | 303 02nd St | Novo Construction Inc | 6th floor: renovate of partial tenant space includes non-structural wall demo, finishes and lighting. electrical under separate permit.Details
6th floor: renovate of partial tenant space includes non-structural wall demo, finishes and lighting. electrical under separate permit. | $70,036 |
| Sep 27, 2019 | Completed final sign-off Jun 2022 | 303 02nd St | Gci, Inc | demolition of non structural walls, door, light fixtures and suspended ceilings. 5th fl demo remain vacancy under ab17. sprinkler demo ref pa #201910033459.Details
demolition of non structural walls, door, light fixtures and suspended ceilings. 5th fl demo remain vacancy under ab17. sprinkler demo ref pa #201910033459. | $50,000 |
| Sep 23, 2019 | Completed final sign-off May 2022 | 303 02nd St | Gci, Inc | 5th flr. demolition of non-structural walls.new construction including modifiying existing ceiling.replcing light fixtures.addition of new power/data. no structural work included in scope.no increse in area.l/s& mep under separatDetails
5th flr. demolition of non-structural walls.new construction including modifiying existing ceiling.replcing light fixtures.addition of new power/data. no structural work included in scope.no increse in area.l/s& mep under separat | $1,098,688 |
| Sep 16, 2019 | Completed final sign-off Mar 2021 | 303 02nd St | Gci, Inc | 4/f: demolish ductwork to accommadte reloction of (e) vav boxes. install (1) new water source heat pump. ref t.i. pa201907317423.Details
4/f: demolish ductwork to accommadte reloction of (e) vav boxes. install (1) new water source heat pump. ref t.i. pa201907317423. | $12,000 |
| Sep 10, 2019 | Completed final sign-off Jan 2020 | 303 02nd St | M C S Construction Services | deferred electrical 201906193897 scope includes improvement to suite on 4th fl suite 450 n consturction of non structural partitions, ceilings, light fixtures, millwork, finishesDetails
deferred electrical 201906193897 scope includes improvement to suite on 4th fl suite 450 n consturction of non structural partitions, ceilings, light fixtures, millwork, finishes | $150,000 |
| Sep 10, 2019 | Completed final sign-off Jan 2020 | 303 02nd St | M C S Construction Services | deferred elec 201905193897 cope includes improvements to suite on the 4th fl suiten 450n consturction of non struct partitoins,ceilings, light fixtures, millwork finishesDetails
deferred elec 201905193897 cope includes improvements to suite on the 4th fl suiten 450n consturction of non struct partitoins,ceilings, light fixtures, millwork finishes | $8,000 |
| Aug 26, 2019 | Completed final sign-off Apr 2021 | 303 02nd St | fire sprinklers relocate 12 and add 7 sprinklers on the 4th flr ref 201907317423Details
fire sprinklers relocate 12 and add 7 sprinklers on the 4th flr ref 201907317423 | $5,000 | |
| Aug 14, 2019 | Completed final sign-off Oct 2019 | 303 02nd St | Novo Construction Inc | mech and ele for ti ref 201907186225Details
mech and ele for ti ref 201907186225 | $6,000 |
| Aug 8, 2019 | Completed final sign-off Feb 2020 | 303 02nd St | Pacific Auxiliary Fire Alarm | north/suite 410: fire alarm ti adding 3 speaker strobes to e notifier nfs2-3030 fa systemDetails
north/suite 410: fire alarm ti adding 3 speaker strobes to e notifier nfs2-3030 fa system | $6,818 |
| Aug 7, 2019 | Never finaled issued Aug 2019, no final | 303 02nd St | Skyline Construction | 8th flr. electrical, mech and plumb for tenant improvement. ref arch 201906123172Details
8th flr. electrical, mech and plumb for tenant improvement. ref arch 201906123172 | $150,000 |
| Aug 7, 2019 | Never finaled issued Aug 2019, no final | 303 02nd St | Skyline Construction | 2nd fl - mep for ti ref pa 2019-0509-0220Details
2nd fl - mep for ti ref pa 2019-0509-0220 | $150,000 |
| Aug 7, 2019 | Never finaled issued Aug 2019, no final | 303 02nd St | Skyline Construction | 7th flr. electrical, mech and plumb for tenant improvement.Details
7th flr. electrical, mech and plumb for tenant improvement. | $150,000 |
| Aug 1, 2019 | Never finaled issued Aug 2019, no final | 303 02nd St | 7th flr - fire sprinklers relocate 69, add 21 delete 25 ref 201905090220Details
7th flr - fire sprinklers relocate 69, add 21 delete 25 ref 201905090220 | $25,000 | |
| Aug 1, 2019 | Completed final sign-off Jun 2021 | 303 02nd St | 8th - fire sprinkler relocate 10 add 36 and delete 35 sprinkler ref 201906123172Details
8th - fire sprinkler relocate 10 add 36 and delete 35 sprinkler ref 201906123172 | $39,000 | |
| Aug 1, 2019 | Never finaled issued Aug 2019, no final | 303 02nd St | 2nd flr - fire sprinkler relocate 45 add 15 and delete 10 sprinkler ref 201905090218Details
2nd flr - fire sprinkler relocate 45 add 15 and delete 10 sprinkler ref 201905090218 | $36,000 | |
| Jul 31, 2019 | Completed final sign-off Apr 2021 | 303 02nd St | Gci, Inc | 4th floor: new construction consists of non structural wall, new millwork and replacing light fixture. no structural work including in scope, no increase in area. no change in occupancy or use. mep and life safty to be differed. n/a for maherDetails
4th floor: new construction consists of non structural wall, new millwork and replacing light fixture. no structural work including in scope, no increase in area. no change in occupancy or use. mep and life safty to be differed. n/a for maher | $917,000 |
| Jul 18, 2019 | Never finaled issued Sep 2019, no final | 303 02nd St | Skyline Construction | 8/f: steel beam to be removed/demolished beams were part of a 1990 floor stregthening for high density file storage the space is no longer used for file storageDetails
8/f: steel beam to be removed/demolished beams were part of a 1990 floor stregthening for high density file storage the space is no longer used for file storage | $5,000 |
| Jul 18, 2019 | Completed final sign-off Oct 2019 | 303 02nd St | Novo Construction Inc | ti on 6th fl to include new millwork, finishes. mep & fire life safety under separate permit. maher naDetails
ti on 6th fl to include new millwork, finishes. mep & fire life safety under separate permit. maher na | $174,836 |
| Jul 2, 2019 | Completed final sign-off Jan 2021 | 303 02nd St | Fire Safety Supply Inc | upgrading existing commercial kitchen hood fire suppression system.Details
upgrading existing commercial kitchen hood fire suppression system. | $6,000 |
| Jul 2, 2019 | Never finaled issued Jul 2019, no final | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm ti - removing 2 monitor pts from existing notifier nfs2-3030 fa system (existing halon system is being removed)Details
fire alarm ti - removing 2 monitor pts from existing notifier nfs2-3030 fa system (existing halon system is being removed) | $2,864 |
| Jun 27, 2019 | Completed final sign-off Jul 2019 | 303 02nd St | M C S Construction Services | 10th flr restroom upgrades. new stall partitions, re-installing the plumbing fixtures and accessories to be code compliantDetails
10th flr restroom upgrades. new stall partitions, re-installing the plumbing fixtures and accessories to be code compliant | $15,000 |
| Jun 26, 2019 | Completed final sign-off Aug 2019 | 303 02nd St | Pacific Auxiliary Fire Alarm | north tower: fire alarm t.i. adding 2 relay modules, 1 smoke detector, 1 speaker-strobe to spaces on 7th and 8th floors. extg notifier nfs-330 fa system. approved mech #201905150663Details
north tower: fire alarm t.i. adding 2 relay modules, 1 smoke detector, 1 speaker-strobe to spaces on 7th and 8th floors. extg notifier nfs-330 fa system. approved mech #201905150663 | $6,718 |
| Jun 20, 2019 | Completed final sign-off Oct 2019 | 303 02nd St | Commercial Interior Builders Inc | 4th floor: includes removal of non-compliant modular ramps and door hardware, and installation of new compliant modular ramps and door hardware. n/a for maherDetails
4th floor: includes removal of non-compliant modular ramps and door hardware, and installation of new compliant modular ramps and door hardware. n/a for maher | $30,000 |
| Jun 19, 2019 | Completed final sign-off Jan 2020 | 303 02nd St | M C S Construction Services | scope of work includes improvement to the suite on 4th fl suite 450n. construction of non structural partitoins, ceilings, light fixtures, millwork and finishesDetails
scope of work includes improvement to the suite on 4th fl suite 450n. construction of non structural partitoins, ceilings, light fixtures, millwork and finishes | $18,000 |
| Jun 18, 2019 | Completed final sign-off Jan 2020 | 303 02nd St | M C S Construction Services | 4th floor ti suite #401n: construction of non-structural paertitions, demising wall, ceiling light fixtures, finishes and accessiblity upgrade. all interior work only.Details
4th floor ti suite #401n: construction of non-structural paertitions, demising wall, ceiling light fixtures, finishes and accessiblity upgrade. all interior work only. | $150,000 |
| Jun 12, 2019 | Never finaled issued Aug 2019, no final | 303 02nd St | Skyline Construction | 7th and 8th flr, t.i. (n) conviece stair connecting floors 7 and 8.Details
7th and 8th flr, t.i. (n) conviece stair connecting floors 7 and 8. | $50,000 |
| Jun 12, 2019 | Never finaled issued Aug 2019, no final | 303 02nd St | Skyline Construction | 8th flr, t.i. (n) non load-bearing partitions, floor finishes, ceilings, millwork.//operation permit for assembly space required from sffd// vif card readers in elevator lobby, two way communication requiredDetails
8th flr, t.i. (n) non load-bearing partitions, floor finishes, ceilings, millwork.//operation permit for assembly space required from sffd// vif card readers in elevator lobby, two way communication required | $1,300,000 |
| Jun 4, 2019 | Completed final sign-off Oct 2019 | 303 02nd St | Pioneer Fire Inc. | suite 401n, fire sprinklers. relocate 8 pendents and 4 uprights. maher n/a.Details
suite 401n, fire sprinklers. relocate 8 pendents and 4 uprights. maher n/a. | $6,000 |
| May 22, 2019 | Completed final sign-off Nov 2019 | 303 02nd St | M C S Construction Services | north tower. new door and jamb signage, new vertical actuation bar and extg fixture and accessories to be code compliant. n/a for maherDetails
north tower. new door and jamb signage, new vertical actuation bar and extg fixture and accessories to be code compliant. n/a for maher | $8,000 |
| May 15, 2019 | Completed final sign-off Oct 2019 | 303 02nd St | Novo Construction Inc | install 2 new floor mounted heatpumps and install condenser water pipingDetails
install 2 new floor mounted heatpumps and install condenser water piping | $10,000 |
| May 9, 2019 | Never finaled issued Jun 2019, no final | 303 02nd St | Skyline Construction | ti to 7th fl to include new non0load bearing partitions, floor finishes, ceilings, millworks. mech, elec, life safety and sprinkler under separate permit.Details
ti to 7th fl to include new non0load bearing partitions, floor finishes, ceilings, millworks. mech, elec, life safety and sprinkler under separate permit. | $1,300,000 |
| May 9, 2019 | Never finaled issued May 2019, no final | 303 02nd St | Skyline Construction | ti to 2nd fl to include new non0load bearing partitions, floor finishes, ceilings, millworks. mech, elec, life safety and sprinkler under separate permit.Details
ti to 2nd fl to include new non0load bearing partitions, floor finishes, ceilings, millworks. mech, elec, life safety and sprinkler under separate permit. | $800,000 |
| May 3, 2019 | Completed final sign-off Nov 2019 | 303 02nd St | M C S Construction Services | all gender rr accessibility improvements on the ground fl: scope of work includes new door and jamb signage, new lavatory and existing plumbing fixtures and accessories to be compliant.Details
all gender rr accessibility improvements on the ground fl: scope of work includes new door and jamb signage, new lavatory and existing plumbing fixtures and accessories to be compliant. | $10,000 |
| May 1, 2019 | Never finaled issued May 2019, no final | 303 02nd St | Gci, Inc | revision to pa 201812178495. update to (e) plan at roof terrace to reflect path to both doors & furniture at terrace & break room per sfdbi request.Details
revision to pa 201812178495. update to (e) plan at roof terrace to reflect path to both doors & furniture at terrace & break room per sfdbi request. | |
| Apr 8, 2019 | Never finaled issued Apr 2019, no final | 303 02nd St | 7th flr, fire sprinklers. add 15, relocate 1 and delete 25 sprinklers.Details
7th flr, fire sprinklers. add 15, relocate 1 and delete 25 sprinklers. | $8,000 | |
| Apr 8, 2019 | Never finaled issued Apr 2019, no final | 303 02nd St | 2nd flr, fire sprinklers. delete 25 pendents, relocate 1 and add 14 uprights.Details
2nd flr, fire sprinklers. delete 25 pendents, relocate 1 and add 14 uprights. | $7,500 | |
| Apr 8, 2019 | Never finaled issued Apr 2019, no final | 303 02nd St | 8th flr, fire sprinklers. add 68, relocate 2 and delete 66 sprinklers.Details
8th flr, fire sprinklers. add 68, relocate 2 and delete 66 sprinklers. | $29,500 | |
| Apr 8, 2019 | Never finaled issued Apr 2019, no final | 303 02nd St | Skyline Construction | 2nd, 7th & 8th flrs. interior demo. ref : sprinkler pa 201904087335, 201904087334 & 201904087333Details
2nd, 7th & 8th flrs. interior demo. ref : sprinkler pa 201904087335, 201904087334 & 201904087333 | $5,000 |
| Apr 5, 2019 | Never finaled issued Apr 2019, no final | 303 02nd St | Gci, Inc | 9th floor: mechanical demo ductwork. install 3 new fan coil units. install 1 new rooftop condenser unit. intall dx piping per plans. n/a for maherDetails
9th floor: mechanical demo ductwork. install 3 new fan coil units. install 1 new rooftop condenser unit. intall dx piping per plans. n/a for maher | $198,000 |
| Apr 1, 2019 | Never finaled issued Apr 2019, no final | 303 02nd St | A S F Electric Inc | electrical t-24 4th flr bmp ref 201810123050 maher naDetails
electrical t-24 4th flr bmp ref 201810123050 maher na | $1,500 |
| Apr 1, 2019 | Never finaled issued Apr 2019, no final | 303 02nd St | A S F Electric Inc | electrical t-24all gender restroom 4th floor ref 201901039518 maher naDetails
electrical t-24all gender restroom 4th floor ref 201901039518 maher na | $1,500 |
| Mar 4, 2019 | Completed final sign-off Apr 2019 | 303 02nd St | Pacific Auxiliary Fire Alarm | ref pa# 201812178495; scope fire alarm 5th fl 1 speaker strobeDetails
ref pa# 201812178495; scope fire alarm 5th fl 1 speaker strobe | $6,000 |
| Mar 4, 2019 | Completed final sign-off May 2019 | 303 02nd St | Pacific Auxiliary Fire Alarm | 4th flr. fire alarm 4th fl add 1 speaker strobeDetails
4th flr. fire alarm 4th fl add 1 speaker strobe | $6,000 |
| Feb 21, 2019 | Completed final sign-off Apr 2019 | 303 02nd St | Golden Gate Fire Protection Inc | 4th flr. fire sprinklers only. northside restrooms. relocate 2 pendents, add 2 pendents.Details
4th flr. fire sprinklers only. northside restrooms. relocate 2 pendents, add 2 pendents. | $2,250 |
| Feb 8, 2019 | Expired or cancelled withdrawn May 2019 | 303 02nd St | 4th fl: removal of existing non-compliant module ramps & door hardware, and installation of new compliant ramps and door hardware.Details
4th fl: removal of existing non-compliant module ramps & door hardware, and installation of new compliant ramps and door hardware. | $30,000 | |
| Jan 23, 2019 | Completed final sign-off Jan 2019 | 303 02nd St | Pacific Auxiliary Fire Alarm | fire alarm add 2 smoke detectors, 1 addressable relay, 201509106566Details
fire alarm add 2 smoke detectors, 1 addressable relay, 201509106566 | |
| Jan 18, 2019 | Completed final sign-off Mar 2019 | 303 02nd St | Pacific Auxiliary Fire Alarm | 4th fl. (3) speaker strobesDetails
4th fl. (3) speaker strobes | $5,000 |
| Jan 3, 2019 | Completed final sign-off May 2019 | 303 02nd St | Gci, Inc | 4th floor: revision to app#201711022937 and 201809281699. scope of work includes demolition of extg plumbing fixtures and finishes. construction includes new non structural partitions, finishes, plmg fixtures, lighting, and ceiling. n/a for maherDetails
4th floor: revision to app#201711022937 and 201809281699. scope of work includes demolition of extg plumbing fixtures and finishes. construction includes new non structural partitions, finishes, plmg fixtures, lighting, and ceiling. n/a for maher | $150,000 |
| Dec 18, 2018 | Completed final sign-off Dec 2018 | 303 02nd St | Pacific Auxiliary Fire Alarm | suite 400: fire alarm t.i. 4th floor to (e) notifier nfs2-3030 adding 6 speaker strobes- ti number 201810123050. maher n/a.Details
suite 400: fire alarm t.i. 4th floor to (e) notifier nfs2-3030 adding 6 speaker strobes- ti number 201810123050. maher n/a. | $7,100 |
| Dec 17, 2018 | Completed final sign-off May 2019 | 303 02nd St | Gci, Inc | 5th floor: replace (e) window with door (not visible from street)for roof terrace, in suite 500n. remodel (e) interior ramp at (e) door. n/a for maherDetails
5th floor: replace (e) window with door (not visible from street)for roof terrace, in suite 500n. remodel (e) interior ramp at (e) door. n/a for maher | $209,000 |
| Nov 20, 2018 | Completed final sign-off Nov 2018 | 303 02nd St | Pacific Auxiliary Fire Alarm | ref pa# 201806071277; fire alarm whole fl. t.i. to (e) nfs2-3030 adding (1) strobe power supplly ; 120 s[ealer strobes, 4 speakers, 9 smoke detectors, 11 duct detectors, 5 control relays and 1 monitor moduleDetails
ref pa# 201806071277; fire alarm whole fl. t.i. to (e) nfs2-3030 adding (1) strobe power supplly ; 120 s[ealer strobes, 4 speakers, 9 smoke detectors, 11 duct detectors, 5 control relays and 1 monitor module | $34,000 |
| Nov 19, 2018 | Completed final sign-off Feb 2019 | 303 02nd St | Novo Construction Inc | 6th fl - revision to pa 2018-0323-4421, 2018-0607-1277 and 2018-0410-5918 to revise layout including mechanical and electricalDetails
6th fl - revision to pa 2018-0323-4421, 2018-0607-1277 and 2018-0410-5918 to revise layout including mechanical and electrical | |
| Nov 8, 2018 | Completed final sign-off Jan 2019 | 303 02nd St | M C S Construction Services | demo of non structural partitions, ceiling lights & associated lights, mech, plm, ele in unoccupied space. ref fire sprinkers 201811014707Details
demo of non structural partitions, ceiling lights & associated lights, mech, plm, ele in unoccupied space. ref fire sprinkers 201811014707 | $50,000 |
| Nov 6, 2018 | Completed final sign-off Nov 2018 | 303 02nd St | Golden Gate Fire Protection Inc | fire sprinkler only - relocate 8 pendents, relocate 1 uprights\ & add 2 for bm0 4th fl - north tower. ref pa #201810123050.Details
fire sprinkler only - relocate 8 pendents, relocate 1 uprights\ & add 2 for bm0 4th fl - north tower. ref pa #201810123050. | $5,500 |
| Nov 5, 2018 | Completed final sign-off Jun 2019 | 303 02nd St | Gci, Inc | suite 400n: mechanical work for management office. maher n/a.Details
suite 400n: mechanical work for management office. maher n/a. |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Pacific Auxiliary Fire Alarm (36), Skyline Construction (32), Gci, Inc (27), Golden Gate Fire Protection Inc (12), Novo Construction Inc (12), M C S Construction Services (8), Pioneer Fire Inc. (6), G L C Construction Company Inc (5), Bradshaw Group Inc (4), Field Construction Inc. (4), Rapid Fire Safety&Security Llc Dba Pafa (4), Commercial Interior Builders Inc (3), Enterprise Roofing Service Inc (3), Hp Build (3), Phase One Fire Life Safety Systems Inc (3), Signage Solutions Corporation (3), A S F Electric Inc (2), Anderson, Rowe & Buckley, Inc. (2), Pribuss Engineering Inc (2), Principal Builders Inc. (2), Bevilacqua & Sons, Edison Fire Extinguisher Company Inc, Fire Safety Supply Inc, Golden Gate Sign Company Inc., Legacy Mechanical & Energy Services, Inc, Neon Works Creations, Pavion Corp, True North Signs & Graphic Services
- Architects
- Teresa Emery (18), Eric Ibsen (13), Bert Deviterbo (4), David B. Powyszynski (4), Gervais Tompkins (3), Ian Lawlor (3), Marc Penninger (3), Madeline Tartakovsky (2), Rodolpho Bustos (2), Sergio Rivas Jr (2), Stanley H Lew (2), Daniel Spiegel, Greg Sheppard, Guion Cabell Childress, Jayson Haines, Neil Kaye, Niccolo Valerio, Roland Lau, William Ogle
- Engineers
- Rudolfo P Bustos Iii (7), Julian White (6), Amit Wadhwa (5), Levi Abarte (5), Alexander Joseph Pacheco (3), Jayson Haines (3), Xuong Quach (3), Christian Dalimarta (2), Dennis Cheung (2), Ian Lawlor (2), Daniel Spiegel, Daniel Wong, Dean Macy, Eric Ibsen, Greg A. Sheppard, Jeffrey Taner, Levi F. Malabuyo, Mozart Faizi, Ramil Batiancila, Shakeel Ahmed, Todd Gottshall, Tu Diep, William Hadinger, Wilson Lee
- Authorized agents
- Jon Toby (2)
- Designers
- Pacific Auxiliary Fire Alarm (3), William James Musgrave (2), Anderson, Rowe & Buckley, Inc., Habtom Nugusse Tewelde
- Pmt consultant/expediters
- Donald D. Dammen
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.