Permit 201907317423
303 02nd St
4th floor: new construction consists of non structural wall, new millwork and replacing light fixture. no structural work including in scope, no increase in area. no change in occupancy or use. mep and life safty to be differed. n/a for maher
- Outcome
- Completed (city status: complete, Apr 8, 2021)
- Filed
- Jul 31, 2019
- Permit issued
- Aug 16, 2019
- Final sign-off
- Apr 8, 2021
- Declared cost
- $917,000
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Gci, Inc (license 689958)
- Property
- All permits at this address (block 3749, lot 062)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Gci, Inc (license 689958)
- Architect
- Ian Lawlor, Stantec (license C24453)