138 permits since 2000 (engineer on 136 permits, architect on 2 permits): 91 completed, 19 in progress, 18 never finaled, 10 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 138.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 23, 2026 | In progress filed Sep 2026, not yet issued | 731 Columbus Av | 1/f t.i. w/ added drink service and ext mods. int:(n) mercantile and espresso bar layout, new pvt loung space; ada upgrades. add ada restroom; new moment frames. ext: new finishes & tile, add canopy at entry, new exterior signage (sep); shift entry doors/config.Details
1/f t.i. w/ added drink service and ext mods. int:(n) mercantile and espresso bar layout, new pvt loung space; ada upgrades. add ada restroom; new moment frames. ext: new finishes & tile, add canopy at entry, new exterior signage (sep); shift entry doors/config. | $1,942,026 | |
| May 14, 2026 | In progress issued Aug 2026 | 1569 Sloat Bl | Oak Park Construction | proposed warm dark shell renovations to demise existing retail space of approximately 8,731 sf into two (2) new retail spaces suite a300 (1694 sf) and suite a302 (7,037 sf) and provide landlord improvements in suite a300. future tenant in suite a300 to be a pilates studio (under separete permit).Details
proposed warm dark shell renovations to demise existing retail space of approximately 8,731 sf into two (2) new retail spaces suite a300 (1694 sf) and suite a302 (7,037 sf) and provide landlord improvements in suite a300. future tenant in suite a300 to be a pilates studio (under separete permit). | $100,000 |
| Apr 14, 2026 | In progress issued May 2026 | 211 Jefferson St | Embree Construction Group Inc | revision to 202412176961, outline s the design revisions to door and storefront modificiations, existing door was removed and replaced, delta a changesDetails
revision to 202412176961, outline s the design revisions to door and storefront modificiations, existing door was removed and replaced, delta a changes | $7,000 |
| Apr 6, 2026 | In progress issued Jul 2026 | 5260 Diamond Heights Bl | T J Nisbet Construction Incorporated | add new elevator and machine room to replace exiting elements along the side of an existing 2 story shopping center. gross sf is 19,322. overall footprint remains generally unchanged as the elevator will replace an existing kiosk. upgrades to mep as req. addition of mech unit on the roof.Details
add new elevator and machine room to replace exiting elements along the side of an existing 2 story shopping center. gross sf is 19,322. overall footprint remains generally unchanged as the elevator will replace an existing kiosk. upgrades to mep as req. addition of mech unit on the roof. | $500,000 |
| Mar 16, 2026 | In progress issued Mar 2026 | 1251 Connecticut St | install heating and air conditioning in (e) warehouse. hvac less than 400 lbs.Details
install heating and air conditioning in (e) warehouse. hvac less than 400 lbs. | $48,000 | |
| Mar 13, 2026 | Completed final sign-off Mar 2026 | 350 11th St | Ewsf Inc. | floor 2, 3, 4 offices: deferred mechanical modification to permit 202411134880.Details
floor 2, 3, 4 offices: deferred mechanical modification to permit 202411134880. | $3,000 |
| Mar 10, 2026 | In progress issued Apr 2026 | 255 Winston Dr | Foresite Construction Inc | revision to bpa 2025.0428.5369 - revision includes demolition, dining interior, exterior facade, kitchen, and site changesDetails
revision to bpa 2025.0428.5369 - revision includes demolition, dining interior, exterior facade, kitchen, and site changes | $10,000 |
| Mar 4, 2026 | In progress issued Apr 2026 | 1314 Fitzgerald Av | Mcdevitt Construction Partners Inc | graffeo coffee roasting: t.i. within an existing 3,176 sq ft commercial tenant space (unit 2). scope of work to include installation of coffe roasting equipments and construction of new break room. no change to building footprint and no exteriorDetails
graffeo coffee roasting: t.i. within an existing 3,176 sq ft commercial tenant space (unit 2). scope of work to include installation of coffe roasting equipments and construction of new break room. no change to building footprint and no exterior | $83,000 |
| Jan 12, 2026 | In progress filed Jan 2026, not yet issued | 3900 Geary Bl | remodel of (e) restaurant & offices to incorporate mixed-use conversion. (e) restaurant formula retail (burger king) shall remain while (e) office space will be converted into 9 residential units. 1.5 story vertical addition with a total of 4 stories will be constructed to accomodate new residentialDetails
remodel of (e) restaurant & offices to incorporate mixed-use conversion. (e) restaurant formula retail (burger king) shall remain while (e) office space will be converted into 9 residential units. 1.5 story vertical addition with a total of 4 stories will be constructed to accomodate new residential | $5,619,200 | |
| Jan 5, 2026 | In progress issued Mar 2026 | 211 Jefferson St | Embree Construction Group Inc | reference to pa#202412176961, owner reflected exterior and interior changes.Details
reference to pa#202412176961, owner reflected exterior and interior changes. | $50,000 |
| Dec 11, 2025 | Completed final sign-off Aug 2026 | 2727 Mariposa St | 2/fl- ti continuation for previous use . upgrade restrooms to meet accessibility code for (n) partitions, lighting, mepDetails
2/fl- ti continuation for previous use . upgrade restrooms to meet accessibility code for (n) partitions, lighting, mep | $300,000 | |
| Nov 10, 2025 | Completed final sign-off Dec 2025 | 28 02nd St | Infinium Air Inc | ground floor: furnish and install mechanical equipments which consist of 2 outdoor heat pumps, 3 indoor fan coils, and 2 exhaust fans. all associated ductwork per plans. ref t.i permit 202505287421Details
ground floor: furnish and install mechanical equipments which consist of 2 outdoor heat pumps, 3 indoor fan coils, and 2 exhaust fans. all associated ductwork per plans. ref t.i permit 202505287421 | $30,000 |
| Oct 21, 2025 | In progress issued Jan 2026 | 211 Jefferson St | Embree Construction Group Inc | 1/f -to include the construction of non bearing partitions that was graphically shown on permitted drawings but not detailed theirin. to perform mech and elec work in this adjacent tenant space (art gallery) necessitated by the previously permitted work.Details
1/f -to include the construction of non bearing partitions that was graphically shown on permitted drawings but not detailed theirin. to perform mech and elec work in this adjacent tenant space (art gallery) necessitated by the previously permitted work. | $100,000 |
| Oct 14, 2025 | Completed final sign-off May 2026 | 1010 16th St | Acg Construction Inc | interior build out of an (e) ground fl space at 1010 16th st for cracked & battered. subject unit 13 "retail 1". work includes: (n) restrooms, (n) kitchen equipment, (n) coffee bar & equipment, (n) interior finishes, (n) associated plumbing & electrical.Details
interior build out of an (e) ground fl space at 1010 16th st for cracked & battered. subject unit 13 "retail 1". work includes: (n) restrooms, (n) kitchen equipment, (n) coffee bar & equipment, (n) interior finishes, (n) associated plumbing & electrical. | $900,000 |
| Jul 16, 2025 | In progress issued Dec 2025 | 255 Winston Dr | Foresite Construction Inc | removal of existing non operable freight elevator & associate equipment. also installation of a new lula elevator within the existing shaft & all associated equipment. this work to be performed concurrently with tenant improvement work for pa 202504285369Details
removal of existing non operable freight elevator & associate equipment. also installation of a new lula elevator within the existing shaft & all associated equipment. this work to be performed concurrently with tenant improvement work for pa 202504285369 | $150,000 |
| May 12, 2025 | In progress issued Nov 2025 | 211 Jefferson St | Embree Construction Group Inc | change of use a3 to a2 occupancy-partial demo, renovation and conversion of 1st floor of (e) 3 story building from gallery to restaurant. (n) work includes remodel of 1st floor, mep work, minor structural scope, minor exterior storefront and utility improvementsDetails
change of use a3 to a2 occupancy-partial demo, renovation and conversion of 1st floor of (e) 3 story building from gallery to restaurant. (n) work includes remodel of 1st floor, mep work, minor structural scope, minor exterior storefront and utility improvements | $6,000,000 |
| Apr 28, 2025 | In progress issued Dec 2025 | 255 Winston Dr | Foresite Construction Inc | the proposed project is tenant improvement & facade work for 4019 square ft restaurant this includes work in existing basement (additional) 2599 sq ft & exterior facade work. certificate of final completeion not to be issued prior to issuance and final of pa# 2025-0716-0988.Details
the proposed project is tenant improvement & facade work for 4019 square ft restaurant this includes work in existing basement (additional) 2599 sq ft & exterior facade work. certificate of final completeion not to be issued prior to issuance and final of pa# 2025-0716-0988. | $800,000 |
| Feb 26, 2025 | Completed final sign-off Dec 2025 | 90 Charter Oak Av | John A Lehman Dba Lehman Construction | k14/k15 1/f: interior ti of a portion of the first floor of (e) facility. combining (2) kitchens for single operator w/ fse install, plumbing, and electrical. no structural.Details
k14/k15 1/f: interior ti of a portion of the first floor of (e) facility. combining (2) kitchens for single operator w/ fse install, plumbing, and electrical. no structural. | $55,000 |
| Jan 30, 2025 | In progress issued Feb 2025 | 201 Bay Shore Bl | Colbear Contracting Group Llc | revision to pa 202310138659 (n) mechanical room w/equipment. no structural workDetails
revision to pa 202310138659 (n) mechanical room w/equipment. no structural work | $50,000 |
| Jan 16, 2025 | Completed final sign-off Oct 2025 | 720 Terry A Francois Bl | Skyline Construction | space #28: new interior t.i. inclusive of partitions, ceiling, lighting, finishes, and millwork. new bar area with equipment and millwork. new bar area with equipment and storage area with 3-compartment sink for dishwashing/hot water heater. new ventilation to support kitchen storage/dish area.Details
space #28: new interior t.i. inclusive of partitions, ceiling, lighting, finishes, and millwork. new bar area with equipment and millwork. new bar area with equipment and storage area with 3-compartment sink for dishwashing/hot water heater. new ventilation to support kitchen storage/dish area. | $313,225 |
| Aug 15, 2024 | Completed final sign-off Feb 2026 | 2343 Fillmore St | Vertex Builders Dba Signal Hill Builders | non structural interior improvement of (e) animal hospital. non-structural reconfiguration of lvl 1 & 2. ada compliance maintained throughout bldg. upgrade of (e) storefront windows to improve thermal performance & enhance storefront transparency in visibility zone. fire life safety deferred.Details
non structural interior improvement of (e) animal hospital. non-structural reconfiguration of lvl 1 & 2. ada compliance maintained throughout bldg. upgrade of (e) storefront windows to improve thermal performance & enhance storefront transparency in visibility zone. fire life safety deferred. | $2,650,000 |
| Aug 5, 2024 | In progress issued Aug 2024 | 177 Stillman St | Hp Build | ref pa # 2024-0226-6507 utilities installed the fpw line not to our instruction. this permit is to get the information in the recordDetails
ref pa # 2024-0226-6507 utilities installed the fpw line not to our instruction. this permit is to get the information in the record | |
| Jun 24, 2024 | Completed final sign-off Oct 2025 | 1 Warriors Wy | Hathaway Dinwiddie Co. | space 22: new ti inclusive of partitions, ceilings, lighting, finishes, and millwork. new commercial kitchen w/ new equipment and plumbing for prep area, scullery, dry storage, walk-in fridge and freezer. new mech equipment to support kitchen, including type 1 and 2 exhaust. single occupant bathroomDetails
space 22: new ti inclusive of partitions, ceilings, lighting, finishes, and millwork. new commercial kitchen w/ new equipment and plumbing for prep area, scullery, dry storage, walk-in fridge and freezer. new mech equipment to support kitchen, including type 1 and 2 exhaust. single occupant bathroom | $705,820 |
| Feb 27, 2024 | Completed final sign-off Dec 2024 | 163 West Portal Av | Mone Construction Co Inc | deferred mep work associated w/ approved ti pa# 202311140752.Details
deferred mep work associated w/ approved ti pa# 202311140752. | $122,000 |
| Feb 26, 2024 | Completed final sign-off Sep 2024 | 177 Stillman St | Cosco Fire Protection Inc. | ref pa# 202302172168 connect (n) 6 "fpw line to existing water meter. (n) 6" riser fire riser stubbed up from floor below.Details
ref pa# 202302172168 connect (n) 6 "fpw line to existing water meter. (n) 6" riser fire riser stubbed up from floor below. | |
| Feb 6, 2024 | Completed final sign-off Feb 2025 | 2343 Fillmore St | Blueline Associates Inc | renovation of existing interior garage for use in medical imaging.Details
renovation of existing interior garage for use in medical imaging. | $200,399 |
| Oct 20, 2023 | In progress issued Oct 2023 | 701 03rd St | Cookline Construction Inc | revision to bpa# 202304256420 (t.i. of g/f bar/restaurant), revised mechanical equipment/duct layout.Details
revision to bpa# 202304256420 (t.i. of g/f bar/restaurant), revised mechanical equipment/duct layout. | |
| Oct 13, 2023 | In progress issued Jan 2025 | 201 Bay Shore Bl | Colbear Contracting Group Llc | ti new rooftop mechanical equipment, new insulation, new security gates, new equipment padDetails
ti new rooftop mechanical equipment, new insulation, new security gates, new equipment pad | $280,000 |
| Aug 4, 2023 | Completed final sign-off May 2024 | 2575 Ocean Av | Method Construction Inc. | change of use from health studio/meditation into office use. interior partition. update mechanical, electrical, and plumbing.Details
change of use from health studio/meditation into office use. interior partition. update mechanical, electrical, and plumbing. | $100,000 |
| Jul 24, 2023 | In progress issued Dec 2023 | 915 North Point St | Js Sullivan Construction Inc | storm water control plan submittal for pa#201912200210-s.Details
storm water control plan submittal for pa#201912200210-s. | |
| Jun 29, 2023 | Completed final sign-off Feb 2025 | 275 South Van Ness Av | C C I Commercial Construction & Improv | revision to 202304206090 & 202304106091 at dist plumbing inspector req to memorialize plumbing changes per planDetails
revision to 202304206090 & 202304106091 at dist plumbing inspector req to memorialize plumbing changes per plan | |
| Jun 29, 2023 | Completed final sign-off Feb 2025 | 275 South Van Ness Av | C C I Commercial Construction & Improv | revision to 202304206090 & 202304106091 at dist plumbing inspector req to memorialize plumbing changes per planDetails
revision to 202304206090 & 202304106091 at dist plumbing inspector req to memorialize plumbing changes per plan | |
| Jun 9, 2023 | Completed final sign-off Jan 2026 | 335 27th St | comply w/nov#202182998.-rear structure-provide a space heating system for the proposed provide kitchen throught the additon of an oven, hood& vent.replace the studio alternating tread device w/ a compliant staircase. replace driveway(e)driveway of the main residence.ordinance #95-17(add 1 state adu)Details
comply w/nov#202182998.-rear structure-provide a space heating system for the proposed provide kitchen throught the additon of an oven, hood& vent.replace the studio alternating tread device w/ a compliant staircase. replace driveway(e)driveway of the main residence.ordinance #95-17(add 1 state adu) | $25,000 | |
| May 31, 2023 | Completed final sign-off Feb 2025 | 275 South Van Ness Av | C C I Commercial Construction & Improv | change of occupancy: ti to existing building to establish distillery with accessory tasting room and cafe. associated bp#s:2022-1222-9044, 2022-1222-9047, 2023-0414-5798 and 2023-0414-5800. certificate of occupancy for this permit only after associated permits receive certificate of occupancy.Details
change of occupancy: ti to existing building to establish distillery with accessory tasting room and cafe. associated bp#s:2022-1222-9044, 2022-1222-9047, 2023-0414-5798 and 2023-0414-5800. certificate of occupancy for this permit only after associated permits receive certificate of occupancy. | $324,000 |
| May 23, 2023 | Completed final sign-off Feb 2025 | 275 South Van Ness Av | C C I Commercial Construction & Improv | change of occupancy: ti to existing building to establish distillery with accessory tasting room and cafe. associated bp#s:2022-1222-9044, 2022-1222-9047, 2023-0414-5798 and 2023-0414-5800. certificate of occupancy for this permit only after certificate of occupancy for associated permits.Details
change of occupancy: ti to existing building to establish distillery with accessory tasting room and cafe. associated bp#s:2022-1222-9044, 2022-1222-9047, 2023-0414-5798 and 2023-0414-5800. certificate of occupancy for this permit only after certificate of occupancy for associated permits. | $324,000 |
| Apr 25, 2023 | Completed final sign-off Mar 2024 | 701 03rd St | Cookline Construction Inc | revision to pa#201910235416. t.i. of a grd flr bar & restaurant. (n) non structural partitions & finishes, lightings. millwork & kitchen equipment. includes (n) mep work associated w/ project. fire sprinklers is design/built under a separate permit.Details
revision to pa#201910235416. t.i. of a grd flr bar & restaurant. (n) non structural partitions & finishes, lightings. millwork & kitchen equipment. includes (n) mep work associated w/ project. fire sprinklers is design/built under a separate permit. | $244,228 |
| Apr 20, 2023 | Completed final sign-off Feb 2025 | 275 South Van Ness Av | C C I Commercial Construction & Improv | deferred mep associated w/ approved t.i pa# 202212229047, 202212229044 & revision pa# 202304145800 & 202304145798.Details
deferred mep associated w/ approved t.i pa# 202212229047, 202212229044 & revision pa# 202304145800 & 202304145798. | |
| Apr 20, 2023 | Completed final sign-off Feb 2025 | 275 South Van Ness Av | C C I Commercial Construction & Improv | deferred mep associated w/ approved t.i pa# 202212229047, 202212229044 & revision pa# 202304145800 & 202304145798.Details
deferred mep associated w/ approved t.i pa# 202212229047, 202212229044 & revision pa# 202304145800 & 202304145798. | |
| Feb 21, 2023 | Completed final sign-off Feb 2025 | 988 Harrison St | Js Sullivan Construction Inc | storm water control plan submittal for bpa# 2019-1212-9351Details
storm water control plan submittal for bpa# 2019-1212-9351 | |
| Jan 19, 2023 | Expired or cancelled expired Mar 2024 | 1200 Market St | K Bali Construction | revision to 202109158511 and 202206307517. relocation of electrical gear and corresponding layout change to kitchen b104.Details
revision to 202109158511 and 202206307517. relocation of electrical gear and corresponding layout change to kitchen b104. | |
| Dec 28, 2022 | Completed final sign-off Apr 2026 | 340 Fell St | Gci, Inc | renovate two story portion into an electrical automobile service center and one story portion will be an automobile showroom. building does not have an elevator per cbc 11b-206.2.3 exception 1.1 the project includes core and shell modifications the ti willl be submitted under separate permit.Details
renovate two story portion into an electrical automobile service center and one story portion will be an automobile showroom. building does not have an elevator per cbc 11b-206.2.3 exception 1.1 the project includes core and shell modifications the ti willl be submitted under separate permit. | $5,000,000 |
| Dec 23, 2022 | Never finaled issued Jul 2023, no final | 3352 Steiner St | R 3 Builders Inc. | interior remodel of existing restaurant. upgrade (e) accessible restroom. no exterior alterations. no structural work.Details
interior remodel of existing restaurant. upgrade (e) accessible restroom. no exterior alterations. no structural work. | $180,000 |
| Dec 19, 2022 | In progress issued Feb 2025 | 228 Jersey St | 415 Remodeling Inc, Aaron Gordon Construction Inc | renovation of an (e) 2-story single family home, including: (1) demo (e) rear yard porch, (2) new single story addition at rear, (3) new interior wall layout, (4) replacing existing foundation w/ associated excavation work, (5) repair/replace exterior finishes, (6) replacing exterior windows & doorsDetails
renovation of an (e) 2-story single family home, including: (1) demo (e) rear yard porch, (2) new single story addition at rear, (3) new interior wall layout, (4) replacing existing foundation w/ associated excavation work, (5) repair/replace exterior finishes, (6) replacing exterior windows & doors | $400,000 |
| Dec 6, 2022 | Completed final sign-off Jan 2024 | 120 Folsom St | Barrett Karber Built Llc | we are building a coffee shop inside a newly constructed commercial condo at 120 folsom st. includes coffee bar & service counter w/seating for the sale + consumption of coffee and pastry. first time t.i.Details
we are building a coffee shop inside a newly constructed commercial condo at 120 folsom st. includes coffee bar & service counter w/seating for the sale + consumption of coffee and pastry. first time t.i. | $250,000 |
| Nov 30, 2022 | Never finaled issued Feb 2023, no final | 701 08th St | E.A.Davidovits &Co.,Inc. | mercantile tenant improvement for ground floor space in a newly constructed existing shell building includes open showeroom space, smaller display spaces, employee offices, office support areas, and restrooms.Details
mercantile tenant improvement for ground floor space in a newly constructed existing shell building includes open showeroom space, smaller display spaces, employee offices, office support areas, and restrooms. | $1,200,000 |
| Nov 1, 2022 | Expired or cancelled cancelled Jan 2026 | 2840 16th St | 1/f: t.i. for proposed gallery in vacant retail space, (e) bldg w/ground floor entrance. (3) accessible restrooms (e) & permitted under bpa#201707051030-s. f/s & f/a to be design build separate permitsDetails
1/f: t.i. for proposed gallery in vacant retail space, (e) bldg w/ground floor entrance. (3) accessible restrooms (e) & permitted under bpa#201707051030-s. f/s & f/a to be design build separate permits | $970,200 | |
| Oct 19, 2022 | Completed final sign-off Oct 2023 | 555 Larkin St | Zone 4 Power Inc | 1/f: t.i. ground floor storefront. metal stud framing w/painted gyp bd, ceiling treatments, offices, break/copy room, & flex room. change of use to b-office. deferred submittal: signageDetails
1/f: t.i. ground floor storefront. metal stud framing w/painted gyp bd, ceiling treatments, offices, break/copy room, & flex room. change of use to b-office. deferred submittal: signage | $925,000 |
| Sep 22, 2022 | Expired or cancelled cancelled Jan 2026 | 88 Kearny St | Richlen Construction | 7/f: demo/construction of toilet partitions, new plumbing & finishesDetails
7/f: demo/construction of toilet partitions, new plumbing & finishes | $10,000 |
| Apr 26, 2022 | Completed final sign-off Apr 2023 | 201 Powell St | Wells Construction Inc | t.i. for a take out only coffee shop in (e) shell. new non-structural partitions, storefront, equipment, fixtures, finishes, and mep upgrades.Details
t.i. for a take out only coffee shop in (e) shell. new non-structural partitions, storefront, equipment, fixtures, finishes, and mep upgrades. | $192,800 |
| Apr 8, 2022 | Completed final sign-off Nov 2024 | 299 02nd St | Precision Hotel Interiors Inc | expansion of (e) fitness center, including (n) fitness equipment, flor, wall & ceiling finishes. infill (e) indoor pool & spa & convert space into a meeting room. expansion of (e) outdoor patio on 2nd fl. (n) bi-folding door & storefront at deck.Details
expansion of (e) fitness center, including (n) fitness equipment, flor, wall & ceiling finishes. infill (e) indoor pool & spa & convert space into a meeting room. expansion of (e) outdoor patio on 2nd fl. (n) bi-folding door & storefront at deck. | $900,000 |
| Feb 3, 2022 | Expired or cancelled expired Mar 2024 | 1200 Market St | Apg Plumbing | plumbing review only for work associated with food hall and kitchens under pa 202109158511, 202109158499 & 202109148433Details
plumbing review only for work associated with food hall and kitchens under pa 202109158511, 202109158499 & 202109148433 | |
| Feb 3, 2022 | Completed final sign-off Mar 2024 | 1200 Market St | K Bali Construction | t.i. mechanical & electrical work associated with food hall and kitchens.Details
t.i. mechanical & electrical work associated with food hall and kitchens. | $175,000 |
| Jan 18, 2022 | Completed final sign-off Sep 2022 | 2100 Chestnut St | Paradigm General Contractors | tenant improvement interior ti in (e) shell space, including including interior walk-up atms, for (n) wells fargo bank; the proposal is to establish a formula retail use to dba wells fargo @ 2100 chestnut st (currently occupied by pottery barn). the proposed project will allow (e) wells fargoDetails
tenant improvement interior ti in (e) shell space, including including interior walk-up atms, for (n) wells fargo bank; the proposal is to establish a formula retail use to dba wells fargo @ 2100 chestnut st (currently occupied by pottery barn). the proposed project will allow (e) wells fargo | $561,470 |
| Dec 22, 2021 | Completed final sign-off Nov 2022 | 3820 24th St | Sphinx Inc Dba Pharaoh Construction | tenant improvement for veterinary clinic. new partition, new ceilings, new lighting, new m&p, new accessible restroom, and new finishes. the possible future expansion of the clinic by constructing a shaft for a future elevator b/t the street and basement levels.Details
tenant improvement for veterinary clinic. new partition, new ceilings, new lighting, new m&p, new accessible restroom, and new finishes. the possible future expansion of the clinic by constructing a shaft for a future elevator b/t the street and basement levels. | $400,000 |
| Nov 29, 2021 | Completed final sign-off Feb 2022 | 1110 04th St | Bay Area Builders Inc. | revision to permit 202009265080. work includes layout revision to pet washing and isolation suite. added handwash sink station in the corridor. multiple doors to be switced from hinged to sliding doorsDetails
revision to permit 202009265080. work includes layout revision to pet washing and isolation suite. added handwash sink station in the corridor. multiple doors to be switced from hinged to sliding doors | |
| Nov 5, 2021 | Completed final sign-off Jan 2022 | 701 03rd St | Yum's Mechanical Co Inc | install type ii (2) condensate hood, exhaust fan and make-up air fan, ref pa20190013240.Details
install type ii (2) condensate hood, exhaust fan and make-up air fan, ref pa20190013240. | $14,600 |
| Jul 13, 2021 | Completed final sign-off Jul 2023 | 1580 Pacific Av | Js Sullivan Construction Inc | plumbing only review of sand interceptor for sfpuc storm water control. ref new bldg pa# 2019.12.12.9356 sDetails
plumbing only review of sand interceptor for sfpuc storm water control. ref new bldg pa# 2019.12.12.9356 s | $1,000 |
| Jul 12, 2021 | Completed final sign-off Sep 2023 | 4033 Judah St | Concore Development Group | unit a: 15ft rear yard addition, single story, and commercial ti. no work to 2nd flr residential, no work to front facade,project includes plumbing, new lighting,new doors and roof w/ skylight.Details
unit a: 15ft rear yard addition, single story, and commercial ti. no work to 2nd flr residential, no work to front facade,project includes plumbing, new lighting,new doors and roof w/ skylight. | $85,000 |
| Jun 25, 2021 | Completed final sign-off Aug 2021 | 8 Boardman Pl | Martin Building Co | mep/ t24 for addition of non structural interior office spaces and restroom. ref pa 202106021457Details
mep/ t24 for addition of non structural interior office spaces and restroom. ref pa 202106021457 | $10,000 |
| Jun 16, 2021 | Completed final sign-off Oct 2021 | 7 Drumm St | Wells Construction Inc | revision to app#202012221572 store front and interior changes. (minimum)Details
revision to app#202012221572 store front and interior changes. (minimum) | $2,000 |
| May 28, 2021 | Never finaled issued Jun 2021, no final | 2797 16th St | Ecotechnikos | revision to pa 202102235191. change to mechanical specifications and layout. ansul fire suppression permit already issued.Details
revision to pa 202102235191. change to mechanical specifications and layout. ansul fire suppression permit already issued. | |
| May 4, 2021 | Completed final sign-off Jul 2022 | 1100 Van Ness Av | T C B Builders Inc | g/f: interior t.i. for coffee shop in (e) shell.new non-structural partitions, new electrical plans and remote transformer at back of house. new equipment, lighting fixtures, furniture and finishes. maher n/a.Details
g/f: interior t.i. for coffee shop in (e) shell.new non-structural partitions, new electrical plans and remote transformer at back of house. new equipment, lighting fixtures, furniture and finishes. maher n/a. | $182,700 |
| May 4, 2021 | Completed final sign-off Jun 2022 | 3595 California St | Wells Construction Inc | g/f: interior t.i. into (e) starbucks. new non-structural partitions, update restrooms, new equipment, new cabinets and new finishes, upate (e) lighting and electrical. no exterior work. no increase in square footage. maher n/a.Details
g/f: interior t.i. into (e) starbucks. new non-structural partitions, update restrooms, new equipment, new cabinets and new finishes, upate (e) lighting and electrical. no exterior work. no increase in square footage. maher n/a. | $117,500 |
| Apr 26, 2021 | Never finaled issued May 2021, no final | 160 Spear St | Sc Builders, Inc | 15th fl: revision to pa# 202010317929. mep for the project.Details
15th fl: revision to pa# 202010317929. mep for the project. | $50,000 |
| Apr 6, 2021 | Completed final sign-off Nov 2021 | 495 Beach St | Excel Hotel Services | revision to pa 201909181934. new finishes per dph request, remodeled area into beverage station, new walk in cooler at existing location, identified accessible seating in dining area. accessible counter at fitness room. 1st flr guest room work.Details
revision to pa 201909181934. new finishes per dph request, remodeled area into beverage station, new walk in cooler at existing location, identified accessible seating in dining area. accessible counter at fitness room. 1st flr guest room work. | $465,000 |
| Mar 17, 2021 | Never finaled issued Apr 2022, no final | 430 Folsom St | R 3 Builders Inc. | tenant improvement for proposed restaurant & bar located at current vacant retail space 2 & 5. including full commercial kitchen, 2 ada restrooms, and sushi bar at retail 2, and full bar & seating at retail 5. upgrade existing path of travel from folsom st with new 1:20 ramp.Details
tenant improvement for proposed restaurant & bar located at current vacant retail space 2 & 5. including full commercial kitchen, 2 ada restrooms, and sushi bar at retail 2, and full bar & seating at retail 5. upgrade existing path of travel from folsom st with new 1:20 ramp. | $467,000 |
| Jan 13, 2021 | Completed final sign-off Sep 2022 | 198 Valencia St | Js Sullivan Construction Inc | plumbing only review of sand interceptor for sfpuc storm water control. ref new bldg pa# 202007109964 s & pa# 201408053094 s.Details
plumbing only review of sand interceptor for sfpuc storm water control. ref new bldg pa# 202007109964 s & pa# 201408053094 s. | |
| Dec 22, 2020 | Completed final sign-off Mar 2022 | 7 Drumm St | Wells Construction Inc | tenant improvement for a take out only coffee shop in (e) shell. new non-structural partitions, storefront, equipment, fixtures, finishes, and mep upgrades.Details
tenant improvement for a take out only coffee shop in (e) shell. new non-structural partitions, storefront, equipment, fixtures, finishes, and mep upgrades. | $96,500 |
| Nov 24, 2020 | Completed final sign-off Mar 2021 | 555 Golden Gate Av | Js Sullivan Construction Inc | revision to pa #201712156653s2 (arch & mep), revised plans to show fsd matrix, include smoke control panel, design.Details
revision to pa #201712156653s2 (arch & mep), revised plans to show fsd matrix, include smoke control panel, design. | |
| Sep 23, 2020 | Completed final sign-off Oct 2021 | 495 Beach St | Acco Engineered Systems Inc. Dba Acco En | new toilet exhaust fans & ductwork in rooms. ref t.i. pa201909303101. maher n/a.Details
new toilet exhaust fans & ductwork in rooms. ref t.i. pa201909303101. maher n/a. | $12,000 |
| Jun 23, 2020 | Completed final sign-off Feb 2024 | 42 Walter St | Arbor Homes Inc, Modern Craft Construction | 4 vertical and horizontal addition at rear, full renovation of interior.Details
4 vertical and horizontal addition at rear, full renovation of interior. | $450,000 |
| Feb 20, 2020 | Completed final sign-off Dec 2021 | 230 07th St | Js Sullivan Construction Inc | strom water control plan review only. for pa# 2019/03/29/6630-s1 & pa# 2018/06/26/3029-s1. ** maher: n/a **Details
strom water control plan review only. for pa# 2019/03/29/6630-s1 & pa# 2018/06/26/3029-s1. ** maher: n/a ** | |
| Dec 27, 2019 | Never finaled issued Jul 2023, no final | 723 Larkin St | Aligned Technologies Llc Dba Aligned Dev | bringing warm shell space to occupy a restaruant n/a maherDetails
bringing warm shell space to occupy a restaruant n/a maher | $100,000 |
| Dec 18, 2019 | Completed final sign-off Nov 2020 | 2190 Market St | Allsite Corp Goods/Services Construction | rev to pa201902253723: change to mechanical ducts configuration, minor electrical changes.Details
rev to pa201902253723: change to mechanical ducts configuration, minor electrical changes. | |
| Dec 9, 2019 | Never finaled issued Jan 2020, no final | 1115 Polk St | 2 Y Construction Inc. | rev to pa# 201901281428; mech revisionDetails
rev to pa# 201901281428; mech revision | $12,000 |
| Oct 30, 2019 | Completed final sign-off May 2020 | 75 Boardman Pl | Skyline Construction | replace lighting in e space, add outlets and elec connections. add elec fixtures, camaras reconfigure e restrooms, add 3 small meeting roomsDetails
replace lighting in e space, add outlets and elec connections. add elec fixtures, camaras reconfigure e restrooms, add 3 small meeting rooms | $75,000 |
| Oct 7, 2019 | Expired or cancelled cancelled Jan 2026 | 49 Stevenson St | tenant improvement of (e) basement restrooms, corridor, stairway & ground floor dining & take-out areas. no work to (e) egress components. new interior non-structural partitions & associated finishes, lighting, mechanical, electrical, & plumbing.Details
tenant improvement of (e) basement restrooms, corridor, stairway & ground floor dining & take-out areas. no work to (e) egress components. new interior non-structural partitions & associated finishes, lighting, mechanical, electrical, & plumbing. | $285,000 | |
| Oct 7, 2019 | Completed final sign-off Dec 2021 | 49 Stevenson St | Terra Nova Industries | tenant improvement of (e) basement kitchen space. no work to ground floor dining or ground floor kitchen areas. no work to (e) egress components. new interior non-structural partitions & associated finishes, and lighting, mep associated w/all kitchen equipment. addition of employee use restroom.Details
tenant improvement of (e) basement kitchen space. no work to ground floor dining or ground floor kitchen areas. no work to (e) egress components. new interior non-structural partitions & associated finishes, and lighting, mep associated w/all kitchen equipment. addition of employee use restroom. | $230,000 |
| Sep 18, 2019 | Completed final sign-off Sep 2021 | 495 Beach St | Excel Hotel Services | partial interior remodel of (e) ground floor public area and kitchen spaces. memp and kitchen includedDetails
partial interior remodel of (e) ground floor public area and kitchen spaces. memp and kitchen included | $1,500,000 |
| Aug 7, 2019 | Never finaled issued Nov 2019, no final | 2797 16th St | Ecotechnikos, Lindquist Custom Construction Inc | tenant improvement of existing restaurant, new tenant (bakery) storefront, new kitchen, restrooms, mep included.Details
tenant improvement of existing restaurant, new tenant (bakery) storefront, new kitchen, restrooms, mep included. | $7,000 |
| Feb 25, 2019 | Completed final sign-off Jul 2021 | 8 Boardman Pl | Martin Building Co | deferred mep associated with pa #201810092631.Details
deferred mep associated with pa #201810092631. | $35,000 |
| Feb 19, 2019 | Completed final sign-off Sep 2019 | 101 01st St | Eric F Anderson Incorporated | 5/f: revision to smoke control for adding a 3rd acd. revision to app#201901251278. n/a for maherDetails
5/f: revision to smoke control for adding a 3rd acd. revision to app#201901251278. n/a for maher | $10,000 |
| Jan 25, 2019 | Completed final sign-off Sep 2019 | 101 01st St | Eric F Anderson Incorporated | mep revision to 2010805148996Details
mep revision to 2010805148996 | $10,000 |
| Jan 17, 2019 | Expired or cancelled cancelled Sep 2020 | 101 01st St | Dome Construction Corp | project is new cafe and bar gr fl in existing vacant retail restaurant space. includes takeaway retail food service, comm kitchen and bakery, restrooms, mezzanine for storage and mech. scope e building lobby is a bar and lounge.Details
project is new cafe and bar gr fl in existing vacant retail restaurant space. includes takeaway retail food service, comm kitchen and bakery, restrooms, mezzanine for storage and mech. scope e building lobby is a bar and lounge. | $600,000 |
| Dec 11, 2018 | Completed final sign-off Aug 2026 | 1224 Funston Av | Woods Const Co, Kohlmyer | erect (n) 4-story single family residence, this is a front building.Details
erect (n) 4-story single family residence, this is a front building. | $831,000 |
| Oct 5, 2018 | Completed final sign-off Sep 2020 | 241 10th St | Js Sullivan Construction Inc | g/f: #101: tenant improvement to formerly unoccupied space for professional services office. space is fully compliant per cbc chapter 11b ada. ada compliant bath is existing.Details
g/f: #101: tenant improvement to formerly unoccupied space for professional services office. space is fully compliant per cbc chapter 11b ada. ada compliant bath is existing. | $80,000 |
| Sep 21, 2018 | Never finaled issued Oct 2018, no final | 2444 Lombard St | Js Sullivan Construction Inc | plumbing review for stormwater plantersDetails
plumbing review for stormwater planters | |
| Jun 15, 2018 | Completed final sign-off Jan 2019 | 1945 Irving St | G Swanson Constr. Inc. | t.i. of extg bank of america. interior scope includes new partitions, restroom and breakroom. regrade exterior sidewalk to provide level landing at main entry door and extg atm and night depository.Details
t.i. of extg bank of america. interior scope includes new partitions, restroom and breakroom. regrade exterior sidewalk to provide level landing at main entry door and extg atm and night depository. | $750,000 |
| May 10, 2018 | Completed final sign-off Oct 2019 | 1750 Taylor St | Black Mountain Development | #2301: interior remodel of one unit in a multi-family apt building. scope of work all interior-remodel, proposed work in non-structural & does not affect envelope. replacement of glazing & windows in kind only.Details
#2301: interior remodel of one unit in a multi-family apt building. scope of work all interior-remodel, proposed work in non-structural & does not affect envelope. replacement of glazing & windows in kind only. | $366,000 |
| Apr 23, 2018 | Completed final sign-off Jul 2018 | 2200 Market St | Western Construction Inc | to comply nov 201499071 - revise location of grease exhaust fan unit on roof from originally issued permit 201404294447 to new location with duct work installation.Details
to comply nov 201499071 - revise location of grease exhaust fan unit on roof from originally issued permit 201404294447 to new location with duct work installation. | $3,000 |
| Feb 15, 2018 | Completed final sign-off Apr 2020 | 2224 Clement St | L P Construction | revision to pa #201611213210. gas meter relocation - minor changes to first floor adding insulation on roof.Details
revision to pa #201611213210. gas meter relocation - minor changes to first floor adding insulation on roof. | |
| Dec 20, 2017 | Never finaled issued Feb 2018, no final | 1439 Egbert Av | D B Group Construction Inc | unit c, addition of food service & addition & relocation of production equipment. less than 1452 sf maher n/a.Details
unit c, addition of food service & addition & relocation of production equipment. less than 1452 sf maher n/a. | $30,000 |
| Dec 19, 2017 | Expired or cancelled withdrawn Nov 2023 | 3300 Mission St | to comply w/nov 201623526.remodel(e)a-2 occupancies on 1/fl&bsmt&r-2 occupancies on 2nd,3rd&roof.proj incl struc seismic,new exit stairs& elevator,new mep&fixtures&finishes.roof penthouse&mech,&1/fl commercial storefrt under sep #201712156602. priority permit processing.Details
to comply w/nov 201623526.remodel(e)a-2 occupancies on 1/fl&bsmt&r-2 occupancies on 2nd,3rd&roof.proj incl struc seismic,new exit stairs& elevator,new mep&fixtures&finishes.roof penthouse&mech,&1/fl commercial storefrt under sep #201712156602. priority permit processing. | $1,300,000 | |
| Dec 19, 2017 | Completed final sign-off Sep 2019 | 2301 Mission St | L C Builders Inc. | interior remodel of (e) commercial space; including, reconfiguration of prfessional services, reconfiguration of retail space & construction of new accessible bathrooms. retail space to be divided into 5 different tenant spaces.Details
interior remodel of (e) commercial space; including, reconfiguration of prfessional services, reconfiguration of retail space & construction of new accessible bathrooms. retail space to be divided into 5 different tenant spaces. | $200,000 |
| Dec 19, 2017 | Completed final sign-off Sep 2019 | 2301 Mission St | L C Builders Inc. | interior remodel of (e) commercial space; including construction of new limited resturaunt vendors (2), with common dining space. reference #201712196847 for commercial space remodel.Details
interior remodel of (e) commercial space; including construction of new limited resturaunt vendors (2), with common dining space. reference #201712196847 for commercial space remodel. | $125,000 |
| Dec 15, 2017 | Expired or cancelled withdrawn Nov 2023 | 3300 Mission St | remodel to (e) a-2 occupancies on 1st fl & basement, and r-2 occupancies on 2nd, 3rd and roof. project includes structural seismic, new exit stairs and elevator, new mep and fixtures and finishes. roof penthouse and mechanical, and 1st fl commercial storefront. to comply with nov 201623526Details
remodel to (e) a-2 occupancies on 1st fl & basement, and r-2 occupancies on 2nd, 3rd and roof. project includes structural seismic, new exit stairs and elevator, new mep and fixtures and finishes. roof penthouse and mechanical, and 1st fl commercial storefront. to comply with nov 201623526 | $300,000 | |
| Dec 14, 2017 | Completed final sign-off Feb 2025 | 377 06th St | Js Sullivan Construction Inc | to erect 8 stories, no basement, type i-a, 90 units residential with commercial mixed use building and parking. (r-2, a-2, s)Details
to erect 8 stories, no basement, type i-a, 90 units residential with commercial mixed use building and parking. (r-2, a-2, s) | $26,068,060 |
| Nov 9, 2017 | Completed final sign-off Jan 2018 | 4343 03rd St | Infinium Air Inc | installation of two inline fans with duct work. n/a ordinance #155-13Details
installation of two inline fans with duct work. n/a ordinance #155-13 | $6,000 |
| Nov 7, 2017 | Never finaled issued Nov 2017, no final | 650 California St | Bcci Construction Company | 30th floor - interior tenant improvement of an existing space. new partitions, new millwork, countertops, fixtures, m.e.p., card reader in elevator lobby. n/a maher ordinanceDetails
30th floor - interior tenant improvement of an existing space. new partitions, new millwork, countertops, fixtures, m.e.p., card reader in elevator lobby. n/a maher ordinance | $1,500,000 |
| Nov 1, 2017 | Completed final sign-off May 2019 | 455 Market St | T C B Builders Inc | suite #100 - renovation of existing unit "starbucks coffee" - remove existing & install new walls, doors, casework, furniture, finishes, ceilings & lighting. new restrooms fixtures & accessories for compliance. permit 201605036413 is to be cancelled. maher naDetails
suite #100 - renovation of existing unit "starbucks coffee" - remove existing & install new walls, doors, casework, furniture, finishes, ceilings & lighting. new restrooms fixtures & accessories for compliance. permit 201605036413 is to be cancelled. maher na | $129,245 |