Black Mountain Development
- Based in
- Pleasanton
- On San Francisco permits
- Aug 2007 to Aug 2026
- Last 24 months
- 23 permits filed
195 permits since 2000: 148 completed, 16 in progress, 22 never finaled, 9 expired or cancelled.
Of the 22 never-finaled permits, 5 are 3 to 5 years old, 12 are 5 to 10 years old, 5 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
Showing the 100 most recent of 195.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 19, 2026 | In progress issued Sep 2026 | 3 Presidio Tr | revision to 202606042559, int remodel @ all floors. add bathroom @ 2nd fl, remodel primary closet. add laundry room @ 2nd flr. new lighting & electrical throughout. remove 2 interior stairs. new hvac @ 3rd floor. also, revise scope of work for pa 202606042559 to: remodel of 6 bathrooms 1 kitcenDetails
revision to 202606042559, int remodel @ all floors. add bathroom @ 2nd fl, remodel primary closet. add laundry room @ 2nd flr. new lighting & electrical throughout. remove 2 interior stairs. new hvac @ 3rd floor. also, revise scope of work for pa 202606042559 to: remodel of 6 bathrooms 1 kitcen | $95,000 |
| Aug 13, 2026 | In progress issued Sep 2026 | 2850 Broadway | revision to bpa: 202606253925 - removal of structural steel post at main and upper floors. (grid 3b and 4b) reframing of walls at upper level (grid 1c and 2c)Details
revision to bpa: 202606253925 - removal of structural steel post at main and upper floors. (grid 3b and 4b) reframing of walls at upper level (grid 1c and 2c) | |
| Jun 25, 2026 | In progress issued Jul 2026 | 2850 Broadway | remodel kitchen & bathrooms, remodel courtyard & new landscaping. related electrical & plumbing will be performed. no change of use, no floor area added, no facade change.Details
remodel kitchen & bathrooms, remodel courtyard & new landscaping. related electrical & plumbing will be performed. no change of use, no floor area added, no facade change. | $185,000 |
| Jun 4, 2026 | In progress issued Jun 2026 | 3 Presidio Tr | remodel 5 baths, 1 powder room, 1 kitchen, everything in-kind, new finishes throughout. no structural work, no wall stud demolition or construction.Details
remodel 5 baths, 1 powder room, 1 kitchen, everything in-kind, new finishes throughout. no structural work, no wall stud demolition or construction. | $130,000 |
| Mar 20, 2026 | In progress issued Apr 2026 | 2912 Pacific Av | revision to pa#202511240277: replace all windows at all levels, replace (e) garage door with (n). replace floor finish at 3rd floor deck and rear yard ptio. new operable gates at driveway, remove rear fountain and stone paving replacement at rear yard.Details
revision to pa#202511240277: replace all windows at all levels, replace (e) garage door with (n). replace floor finish at 3rd floor deck and rear yard ptio. new operable gates at driveway, remove rear fountain and stone paving replacement at rear yard. | $15,000 |
| Feb 25, 2026 | In progress issued Feb 2026 | 765 Market St | unit 32d: repair water damage to master bedroom and master bath. all finishes in kind.Details
unit 32d: repair water damage to master bedroom and master bath. all finishes in kind. | $50,000 |
| Jan 26, 2026 | In progress issued Jan 2026 | 2850 Broadway | exploratory demo: investigative sheetrock removal & replacement to investigate hvac runs, foundation and shear walls, structual design, domestic waterlines. approx 15 areas 2x2 and 2 x 10.Details
exploratory demo: investigative sheetrock removal & replacement to investigate hvac runs, foundation and shear walls, structual design, domestic waterlines. approx 15 areas 2x2 and 2 x 10. | $10,000 |
| Jan 13, 2026 | In progress issued Jan 2026 | 2850 Broadway | remodel in kind: 1 kitchen, 7 bathrooms, 2 half bathrooms.Details
remodel in kind: 1 kitchen, 7 bathrooms, 2 half bathrooms. | $100,000 |
| Jan 13, 2026 | In progress issued Jan 2026 | 706 Mission St | remodel 1 bath in kind, install new decorative light fixtures throughout. install new built in cabinet at entry.Details
remodel 1 bath in kind, install new decorative light fixtures throughout. install new built in cabinet at entry. | $25,000 |
| Nov 24, 2025 | In progress issued Dec 2025 | 2912 Pacific Av | replace and addition of guardrails, fencing, and gates at front and rear yards. replace guardrail at primary bedroom. remove decorative cornices and living room window surround at front facade. replace in kind doors and windows at 1st and 3rd floor. refinish patio surface at 3/f deck. new gate at..Details
replace and addition of guardrails, fencing, and gates at front and rear yards. replace guardrail at primary bedroom. remove decorative cornices and living room window surround at front facade. replace in kind doors and windows at 1st and 3rd floor. refinish patio surface at 3/f deck. new gate at.. | $50,000 |
| Aug 15, 2025 | In progress issued Aug 2025 | 2912 Pacific Av | remove and replace plywood subfloor at deck for proper slope. add new waterproofing membrane. 745 sq ft. re tile deck 745 sq ft. replaced damaged doors and windows in kind.Details
remove and replace plywood subfloor at deck for proper slope. add new waterproofing membrane. 745 sq ft. re tile deck 745 sq ft. replaced damaged doors and windows in kind. | $55,000 |
| Jul 17, 2025 | Completed final sign-off Oct 2025 | 2502 Broadway | to obtain final inspection for work approved under pa# 202110080167 and 202105049759. all work is complete.Details
to obtain final inspection for work approved under pa# 202110080167 and 202105049759. all work is complete. | |
| Jun 6, 2025 | Completed final sign-off Apr 2026 | 2121 Webster St | gph3: replace exterior window and door system-west wall on one floor. provide new concrete curb for new window/door sill. patch and repair finishes around window replacement.Details
gph3: replace exterior window and door system-west wall on one floor. provide new concrete curb for new window/door sill. patch and repair finishes around window replacement. | $15,000 |
| Jun 5, 2025 | In progress issued Jul 2025 | 2912 Pacific Av | remodel to (e) primary bathroom, closets, office, kitchen and butlers pantry. fixture and cabinetry improvements at baths, laundry and wet bar. redesign at living room & family room fireplace surround & topDetails
remodel to (e) primary bathroom, closets, office, kitchen and butlers pantry. fixture and cabinetry improvements at baths, laundry and wet bar. redesign at living room & family room fireplace surround & top | $120,000 |
| May 27, 2025 | In progress issued Jun 2025 | 280 Spear St | remove closet in the media room and add 2x soffitsDetails
remove closet in the media room and add 2x soffits | $1,000 |
| Mar 20, 2025 | Completed final sign-off Aug 2025 | 280 Spear St | new interior lighting with new dropped ceiling in areas to accomodate new led cans.Details
new interior lighting with new dropped ceiling in areas to accomodate new led cans. | $10,000 |
| Mar 12, 2025 | In progress issued Mar 2025 | 2912 Pacific Av | remodel kitchen, 4 baths, 1 powder room in kind. replace stair banister on inside.Details
remodel kitchen, 4 baths, 1 powder room in kind. replace stair banister on inside. | $120,000 |
| Mar 10, 2025 | Completed final sign-off Dec 2025 | 188 Minna St | 22nd fl, 22d - interior non-structurl remodel: remove a portion of all for (n) 3'0" fire rated door to connect units 22d & 22e; all interior finishes, fixture to remainDetails
22nd fl, 22d - interior non-structurl remodel: remove a portion of all for (n) 3'0" fire rated door to connect units 22d & 22e; all interior finishes, fixture to remain | $15,000 |
| Mar 10, 2025 | Completed final sign-off Dec 2025 | 188 Minna St | 22nd fl, 22e - interior non-structurl remodel: remove a portion of all for (n) 3'0" fire rated door to connect units 22d & 22e; all interior finishes, fixture to remain; (n) grab bars @ bath 2Details
22nd fl, 22e - interior non-structurl remodel: remove a portion of all for (n) 3'0" fire rated door to connect units 22d & 22e; all interior finishes, fixture to remain; (n) grab bars @ bath 2 | $19,000 |
| Feb 13, 2025 | In progress issued Feb 2025 | 301 Mission St | gpha: removal of existing ceiling in kitchen and living room. removal of existing kitchen island, new construction of architctural partitions, finishes & fixtures for the addition of a primary bedroom suite, laundry, guest room & bath, new kitchen island, other cabinetry.Details
gpha: removal of existing ceiling in kitchen and living room. removal of existing kitchen island, new construction of architctural partitions, finishes & fixtures for the addition of a primary bedroom suite, laundry, guest room & bath, new kitchen island, other cabinetry. | $718,000 |
| Feb 12, 2025 | In progress issued Feb 2025 | 1750 Taylor St | unit #305: remodel primary bathroom and closet, remodel bath 2 and powder room, new cabinetry in bedroom 2 and entry, reconfigure kitchen including new appliances and finishes. new lighting throughout, new tile and waterproofing at balconies. replace in kind window wall on west bedroom and northDetails
unit #305: remodel primary bathroom and closet, remodel bath 2 and powder room, new cabinetry in bedroom 2 and entry, reconfigure kitchen including new appliances and finishes. new lighting throughout, new tile and waterproofing at balconies. replace in kind window wall on west bedroom and north | $100,000 |
| Jan 30, 2025 | Completed final sign-off Aug 2025 | 280 Spear St | unit#: 39d; remove and replace 12 interior wood doors install new cabinet at entry living room, laundry room, bedroom #2.Details
unit#: 39d; remove and replace 12 interior wood doors install new cabinet at entry living room, laundry room, bedroom #2. | $6,000 |
| Oct 17, 2024 | Expired or cancelled cancelled Mar 2025 | 1750 Taylor St | unit 305: remodel (e) 1 kitchen & bathroom in-kind.Details
unit 305: remodel (e) 1 kitchen & bathroom in-kind. | $60,000 |
| Aug 28, 2024 | Completed final sign-off May 2025 | 1101 Green St | layout change for interior remodel of bathrooms, kitchen & closets. replace floorings, re-paint entire space, replace doors, replace kitchen appliances w/energy efficient modles, replace window shade. replace all lighting outlets & controls. revision to pa 202405142083Details
layout change for interior remodel of bathrooms, kitchen & closets. replace floorings, re-paint entire space, replace doors, replace kitchen appliances w/energy efficient modles, replace window shade. replace all lighting outlets & controls. revision to pa 202405142083 | $50,000 |
| Jun 18, 2024 | Completed final sign-off Feb 2025 | 188 Minna St | unit 27b: in kitchen: replace tile backsplash, replace garbage disposal, replace faucet, new cabinet pull hardward. new trim throughout unit. patch & paint drywall throughout. new flooring htroughout. no work in bathrooms.Details
unit 27b: in kitchen: replace tile backsplash, replace garbage disposal, replace faucet, new cabinet pull hardward. new trim throughout unit. patch & paint drywall throughout. new flooring htroughout. no work in bathrooms. | $60,000 |
| Jun 3, 2024 | Expired or cancelled cancelled Jun 2024 | 1750 Taylor St | #2302: remodel 1 kitchen i kind, remodel 2 bathroom in kind. new finishes thoughout.Details
#2302: remodel 1 kitchen i kind, remodel 2 bathroom in kind. new finishes thoughout. | $60,000 |
| May 16, 2024 | Completed final sign-off Sep 2024 | 2121 Webster St | remodel laundry room. remove (e) lower cabinetry and plumbing fixtures. install (n) cabinetry & plumbing fixturesDetails
remodel laundry room. remove (e) lower cabinetry and plumbing fixtures. install (n) cabinetry & plumbing fixtures | $10,000 |
| May 14, 2024 | Completed final sign-off Sep 2025 | 1101 Green St | unit #1101: remodel in kind 1 kitchen, 2 baths. new finishes throughout. trim floors.Details
unit #1101: remodel in kind 1 kitchen, 2 baths. new finishes throughout. trim floors. | $50,000 |
| Feb 21, 2024 | Completed final sign-off Feb 2025 | 188 Minna St | revision to 202303153740, wall changes for full apt renovation. this is an adaptable dwelling unit. all accessible/adaptable features must be maintained in compliance with 2002 cbc chapter 11a. no change to dwelling size or location. this is an adaptable dwelling unit.Details
revision to 202303153740, wall changes for full apt renovation. this is an adaptable dwelling unit. all accessible/adaptable features must be maintained in compliance with 2002 cbc chapter 11a. no change to dwelling size or location. this is an adaptable dwelling unit. | $40,000 |
| Nov 21, 2023 | Completed final sign-off Mar 2024 | 2121 Webster St | add new closet at entryway. dining room- remove (e) recessed downlight and replace with (n) chandelier. replace bathroom vanities in kind.Details
add new closet at entryway. dining room- remove (e) recessed downlight and replace with (n) chandelier. replace bathroom vanities in kind. | $10,000 |
| Nov 21, 2023 | Completed final sign-off Mar 2024 | 2121 Webster St | bedroom 3- remove (e) cabinetry. bulkhead diffuser and recessed downlights then patch ceiling. install furniture by others and relocate (e) downlights. siting room- remove cabinetry, non structural walls, (e) diffuser bulkhead, recessed downlights, patch ceiling. relocate diffuser and downlights...Details
bedroom 3- remove (e) cabinetry. bulkhead diffuser and recessed downlights then patch ceiling. install furniture by others and relocate (e) downlights. siting room- remove cabinetry, non structural walls, (e) diffuser bulkhead, recessed downlights, patch ceiling. relocate diffuser and downlights... | $10,000 |
| Aug 16, 2023 | Completed final sign-off Dec 2025 | 1080 Chestnut St | replace non confirming railing w/new code compliant guards, replace drain at 1 balcany. add topping and waterproofing to (e) balcony surface to improve slope drainage at north and east balconies. add new pedestal pavers at all balcaniesDetails
replace non confirming railing w/new code compliant guards, replace drain at 1 balcany. add topping and waterproofing to (e) balcony surface to improve slope drainage at north and east balconies. add new pedestal pavers at all balcanies | $20,000 |
| Jun 27, 2023 | Never finaled issued Jun 2023, no final | 1750 Taylor St | to obtain final inspection for work approved under pa# 202106172682, 202110070028 and 202203230706. all work is complete.Details
to obtain final inspection for work approved under pa# 202106172682, 202110070028 and 202203230706. all work is complete. | |
| Apr 21, 2023 | Completed final sign-off Nov 2023 | 301 Mission St | (1) kitchen & (2) & half bathrooms remodel in-kind. (n) wood flooring throughout. (n) led lighting throughout.Details
(1) kitchen & (2) & half bathrooms remodel in-kind. (n) wood flooring throughout. (n) led lighting throughout. | $45,000 |
| Mar 15, 2023 | Completed final sign-off Feb 2025 | 188 Minna St | reface kitchen cabinets, (n) countertops, (n) dishwasher, new led lights in kitchen, 2 bathrooms, and one 1/2 bath. replace fan in 1/2 bathroom. new trim in 2 bathrooms and in sitting room. new window treatments.Details
reface kitchen cabinets, (n) countertops, (n) dishwasher, new led lights in kitchen, 2 bathrooms, and one 1/2 bath. replace fan in 1/2 bathroom. new trim in 2 bathrooms and in sitting room. new window treatments. | $40,000 |
| Mar 14, 2023 | Completed final sign-off Sep 2024 | 301 Mission St | modification from planning code sec 305.1 to provide temporary door / connection bet unit 48d & 48e w/o hearing under sec 317. temporary connecting door to be 45 min rated. non-structural remodel of kitchen, reconfigure 2 bedrooms, remove 1 bathroom & remodel 1 for cbc 11a accessDetails
modification from planning code sec 305.1 to provide temporary door / connection bet unit 48d & 48e w/o hearing under sec 317. temporary connecting door to be 45 min rated. non-structural remodel of kitchen, reconfigure 2 bedrooms, remove 1 bathroom & remodel 1 for cbc 11a access | $87,400 |
| Mar 14, 2023 | Completed final sign-off Sep 2024 | 301 Mission St | modification from planning code sec 305.1 to provide temporary door / connection between unit 48e & 48d without hearing under sec 317. temporary door / connecting to be 45 minute rated. reconfigure (e) den / bedroom to become dining room. (non-structural interior remodel).Details
modification from planning code sec 305.1 to provide temporary door / connection between unit 48e & 48d without hearing under sec 317. temporary door / connecting to be 45 minute rated. reconfigure (e) den / bedroom to become dining room. (non-structural interior remodel). | $42,800 |
| Mar 14, 2023 | Completed final sign-off Sep 2023 | 1750 Taylor St | remodel elevator lobby on 22nd fl. paint walls and doors as noted. demo & replace ceiling. new light fixtures.Details
remodel elevator lobby on 22nd fl. paint walls and doors as noted. demo & replace ceiling. new light fixtures. | $10,000 |
| Feb 28, 2023 | Expired or cancelled withdrawn Mar 2023 | 188 Minna St | remodel kitchen & 3 1/2 bath in kind. new finishes throughoutDetails
remodel kitchen & 3 1/2 bath in kind. new finishes throughout | $75,000 |
| Jan 26, 2023 | Completed final sign-off Apr 2023 | 3630 Jackson St | to renew for final inspection pa# 201502118088, 200008107489. all work is complete.Details
to renew for final inspection pa# 201502118088, 200008107489. all work is complete. | |
| Jan 26, 2023 | Completed final sign-off Apr 2023 | 3630 Jackson St | to renew for final inspection: pa#'s 201708104496, 201510159863, and 201611082199. all work is complete.Details
to renew for final inspection: pa#'s 201708104496, 201510159863, and 201611082199. all work is complete. | |
| Jan 26, 2023 | Completed final sign-off Mar 2023 | 3630 Jackson St | to renew for final inspection pa#: 20000118256, 200205136400, 9909424s. all work is complete.Details
to renew for final inspection pa#: 20000118256, 200205136400, 9909424s. all work is complete. | |
| Nov 9, 2022 | Completed final sign-off Nov 2024 | 1080 Chestnut St | 18 fl: demo (e) int walls and finishes. construct new walls, ceilings, install new plumbing, cabinetry, and appliances. paint and new floor finishes.Details
18 fl: demo (e) int walls and finishes. construct new walls, ceilings, install new plumbing, cabinetry, and appliances. paint and new floor finishes. | $400,000 |
| Nov 2, 2022 | Completed final sign-off Sep 2023 | 1750 Taylor St | provide and install 3/4 ton and one 1 ton split system hear pump cassette units to a one 5 ton unit condenser - provide and install one in line exhaust fan and duct it to all restrooms - all supply and return diffusers are to be 4ft x 1" linear type. ref bpa 202209233087Details
provide and install 3/4 ton and one 1 ton split system hear pump cassette units to a one 5 ton unit condenser - provide and install one in line exhaust fan and duct it to all restrooms - all supply and return diffusers are to be 4ft x 1" linear type. ref bpa 202209233087 | $10,000 |
| Sep 30, 2022 | Never finaled issued Oct 2022, no final | 1 Steuart Ln | unit #2001: demo of non-structural partitions, new interior lighting, new interior partitions, installation of new finishes, plumbing fixtures, and new cabinetry. no structural work.Details
unit #2001: demo of non-structural partitions, new interior lighting, new interior partitions, installation of new finishes, plumbing fixtures, and new cabinetry. no structural work. | $80,000 |
| Sep 23, 2022 | Completed final sign-off Sep 2023 | 1750 Taylor St | unit 605-interior remodel: new walls, doors, cabinetry, flooring. new appliances & fixtures. replace glazing & exterior sliding doors as noted. no structural work. revision to 2022 0627 7187.Details
unit 605-interior remodel: new walls, doors, cabinetry, flooring. new appliances & fixtures. replace glazing & exterior sliding doors as noted. no structural work. revision to 2022 0627 7187. | $85,000 |
| Jun 27, 2022 | Completed final sign-off Sep 2023 | 1750 Taylor St | apt 605: remodel 3 bathrooms, in-kind, replace appliances in kitchen. new finishes throughout including floors & paint.Details
apt 605: remodel 3 bathrooms, in-kind, replace appliances in kitchen. new finishes throughout including floors & paint. | $60,000 |
| May 3, 2022 | Expired or cancelled withdrawn Jun 2022 | 706 Mission St | throughout to include new lighting & controls, new finishes throughout adjust hvac dust location to accomodate revised layout remodel kitchen.Details
throughout to include new lighting & controls, new finishes throughout adjust hvac dust location to accomodate revised layout remodel kitchen. | $400,000 |
| Apr 19, 2022 | Completed final sign-off Jun 2023 | 2121 Webster St | unit# 603. installation of non-bearing walls, including plumbing walls, rerouting of piping & conduit as required. new lighting, plumbing & electrical fixtures. new interior finishes & doors.Details
unit# 603. installation of non-bearing walls, including plumbing walls, rerouting of piping & conduit as required. new lighting, plumbing & electrical fixtures. new interior finishes & doors. | $100,000 |
| Mar 23, 2022 | Never finaled issued Mar 2022, no final | 1750 Taylor St | structural submittal for bpa 202110070028. expansion of (e) guard stations.Details
structural submittal for bpa 202110070028. expansion of (e) guard stations. | |
| Mar 22, 2022 | Completed final sign-off Oct 2022 | 2121 Webster St | unit 603: remodel 2 bathrooms. 1 kitchen. in kind. new finishes throughout.Details
unit 603: remodel 2 bathrooms. 1 kitchen. in kind. new finishes throughout. | $40,000 |
| Feb 7, 2022 | Completed final sign-off May 2022 | 188 Minna St | to obtain final inspection for work approved under permit applications: 201311252754 and 201303061592. all work is complete.Details
to obtain final inspection for work approved under permit applications: 201311252754 and 201303061592. all work is complete. | |
| Feb 4, 2022 | Completed final sign-off Nov 2024 | 1080 Chestnut St | remodel 5 bath 1 powder room 1 kitchen in kind new finishes throughout. penthouse #eDetails
remodel 5 bath 1 powder room 1 kitchen in kind new finishes throughout. penthouse #e | $100,000 |
| Jan 26, 2022 | Completed final sign-off May 2022 | 2503 Broadway | replace 2000sf approx drtwall due water damage and new cabinetsDetails
replace 2000sf approx drtwall due water damage and new cabinets | $40,000 |
| Nov 29, 2021 | Never finaled issued Dec 2021, no final | 3007 Jackson St | 3rd floor: add cabinet in 2 extg bedroom. patch and paint drywall approx. 100 sq ft. no framing modification- no structural work.Details
3rd floor: add cabinet in 2 extg bedroom. patch and paint drywall approx. 100 sq ft. no framing modification- no structural work. | $2,000 |
| Nov 3, 2021 | Completed final sign-off Oct 2023 | 1750 Taylor St | 2201: interior remodel of unit 2201. new walls, doors, cabinetry, counters, flooring, finishes throughout. new appliances and fixtures. replace glaszing and exterior sliding doors.Details
2201: interior remodel of unit 2201. new walls, doors, cabinetry, counters, flooring, finishes throughout. new appliances and fixtures. replace glaszing and exterior sliding doors. | $100,000 |
| Oct 8, 2021 | Expired or cancelled expired Oct 2025 | 2502 Broadway | remove existing mezzanine combined with addition of a niche. remove fire place at dining. as-built for no-plan permit 202105049759.Details
remove existing mezzanine combined with addition of a niche. remove fire place at dining. as-built for no-plan permit 202105049759. | $20,000 |
| Oct 7, 2021 | Never finaled issued Mar 2022, no final | 1750 Taylor St | expansion to (e) security guard station at entry of building.Details
expansion to (e) security guard station at entry of building. | $15,000 |
| Jun 17, 2021 | Never finaled issued Jun 2021, no final | 1750 Taylor St | mep defered submittal per app#202105180514Details
mep defered submittal per app#202105180514 | $80,000 |
| May 18, 2021 | Completed final sign-off Aug 2023 | 1750 Taylor St | remodel gymnasium spage, fitness studios & toilet rooms to include (n) framing, fixtures, finishes & services. (n) management office, (n) exterior glazed openings. modify (e) interior openings & add glazing. reconfigure & remodel (e) management offices into communal library & lounge for residents.Details
remodel gymnasium spage, fitness studios & toilet rooms to include (n) framing, fixtures, finishes & services. (n) management office, (n) exterior glazed openings. modify (e) interior openings & add glazing. reconfigure & remodel (e) management offices into communal library & lounge for residents. | $150,000 |
| May 4, 2021 | Expired or cancelled expired Oct 2025 | 2502 Broadway | remodel kitchen 6 bathrooms, exterior railing in rear all in kind.Details
remodel kitchen 6 bathrooms, exterior railing in rear all in kind. | $75,000 |
| Feb 8, 2021 | Completed final sign-off Jan 2022 | 201 Folsom St | unit #42a: 1 kitchen & 3 1/2 bath remodel in kind, no wall modification, no structural workDetails
unit #42a: 1 kitchen & 3 1/2 bath remodel in kind, no wall modification, no structural work | $40,000 |
| Jan 25, 2021 | Completed final sign-off Oct 2021 | 1750 Taylor St | unit 1701: new kitchen millwork/appliances. new master bathroom & fixturs and new living room celing - luminares. amend to (e) pa202007280867.Details
unit 1701: new kitchen millwork/appliances. new master bathroom & fixturs and new living room celing - luminares. amend to (e) pa202007280867. | $27,000 |
| Dec 15, 2020 | Completed final sign-off Mar 2021 | 2121 Webster St | unit#408: new case work in laundry, around 2 wine refridg., around tv parch floors. new cabinetry throughout.Details
unit#408: new case work in laundry, around 2 wine refridg., around tv parch floors. new cabinetry throughout. | $20,000 |
| Nov 30, 2020 | Expired or cancelled cancelled Jul 2021 | 2411 Broadway | replacement of existing rear yard fence on east & west.Details
replacement of existing rear yard fence on east & west. | $4,500 |
| Oct 2, 2020 | Completed final sign-off May 2021 | 1080 Chestnut St | kitchen and 1 bathroom remodel in-kind. new finish throughout. no change in layor/walls/opening.Details
kitchen and 1 bathroom remodel in-kind. new finish throughout. no change in layor/walls/opening. | $50,000 |
| Sep 15, 2020 | Completed final sign-off Dec 2020 | 1000 03rd St | revision to pa 201905100343. relocation of fire rated entry door to unit 1603. reuse existing fire rated door, jamb and hardware. the change is already approved by building's hoa.Details
revision to pa 201905100343. relocation of fire rated entry door to unit 1603. reuse existing fire rated door, jamb and hardware. the change is already approved by building's hoa. | |
| Sep 2, 2020 | Completed final sign-off Sep 2021 | 706 Mission St | unit 17a: replace (3) toilets, reconfigure master closet, lower ceiling in living room, dining room, family room, & master bedroom to add recessed lighting, create soffits for downlights in bedrooms, install window shades. mech & fire protection are deferred under separate permitDetails
unit 17a: replace (3) toilets, reconfigure master closet, lower ceiling in living room, dining room, family room, & master bedroom to add recessed lighting, create soffits for downlights in bedrooms, install window shades. mech & fire protection are deferred under separate permit | $100,000 |
| Sep 2, 2020 | Never finaled issued Nov 2020, no final | 188 Minna St | revision to pa #2020-0714-0119: interior remodel. moved partitions to accomodate slight layout change.Details
revision to pa #2020-0714-0119: interior remodel. moved partitions to accomodate slight layout change. | $10,000 |
| Jul 28, 2020 | Completed final sign-off Oct 2021 | 1750 Taylor St | upgrade faces of 3 fire places, new floor finishes,new trim throughout. remodel powder room & existing home office in kindDetails
upgrade faces of 3 fire places, new floor finishes,new trim throughout. remodel powder room & existing home office in kind | $49,000 |
| Jul 14, 2020 | Completed final sign-off Sep 2021 | 188 Minna St | interior remodel, kitchen,baths & misc. living spaces of existing single story condo unit in multi-unit bldg, including associated electrical, plumbing & mechanical work. no structural work & no work to the exterior.Details
interior remodel, kitchen,baths & misc. living spaces of existing single story condo unit in multi-unit bldg, including associated electrical, plumbing & mechanical work. no structural work & no work to the exterior. | $47,000 |
| Jun 26, 2020 | Never finaled issued Jul 2020, no final | 765 Market St | (unit# 25d) remodel kitchen & bathroom in-kindDetails
(unit# 25d) remodel kitchen & bathroom in-kind | $20,000 |
| Jun 12, 2020 | Never finaled issued Jan 2021, no final | 765 Market St | interior tenant improvement to remove & replace non-structural walls, finishes,plumbing fixtures & lighting fixtures. no structural work to be performed.Details
interior tenant improvement to remove & replace non-structural walls, finishes,plumbing fixtures & lighting fixtures. no structural work to be performed. | $100,000 |
| Mar 3, 2020 | Completed final sign-off Apr 2021 | 2121 Webster St | unit 801 gph1 - revision to pa 2018-0827-8429 providing not accessible/adaptable bathroom on 2nd floor of the unit as not required by codeDetails
unit 801 gph1 - revision to pa 2018-0827-8429 providing not accessible/adaptable bathroom on 2nd floor of the unit as not required by code | |
| Oct 18, 2019 | Completed final sign-off Jan 2021 | 1250 Jones St | unit #1301: kitchen remodel new cabinets, appliances and fixtures. remodel master bath: remove tub, vanities and fixtures. new shower vanity and fixtures. remodel bath, remove tub, vanity and fixtures. new shower, vanity & fixtures. new carpet and paint through out, tile floors in bath. (1xk+2xb).Details
unit #1301: kitchen remodel new cabinets, appliances and fixtures. remodel master bath: remove tub, vanities and fixtures. new shower vanity and fixtures. remodel bath, remove tub, vanity and fixtures. new shower, vanity & fixtures. new carpet and paint through out, tile floors in bath. (1xk+2xb). | $300,000 |
| Sep 30, 2019 | Completed final sign-off Oct 2019 | 765 Market St | relocate 3 fire alarm speaker device within 5' of original location ref 201901100021Details
relocate 3 fire alarm speaker device within 5' of original location ref 201901100021 | $1,500 |
| Aug 26, 2019 | Never finaled issued Aug 2019, no final | 2121 Webster St | street spaceDetails
street space | |
| Aug 21, 2019 | Never finaled issued Sep 2019, no final | 2121 Webster St | revision to pa 2019-0425-8942 exterior remodel to include - replacement of various door and window sections using same system; addition of metal trellis. for (e) egress see approved pa 2013-1122-2660. all interior modifications approved for unit gph4 under pa 2019-0425-8942Details
revision to pa 2019-0425-8942 exterior remodel to include - replacement of various door and window sections using same system; addition of metal trellis. for (e) egress see approved pa 2013-1122-2660. all interior modifications approved for unit gph4 under pa 2019-0425-8942 | $100,000 |
| Aug 20, 2019 | Never finaled issued Aug 2019, no final | 2121 Webster St | street spaceDetails
street space | |
| Aug 12, 2019 | Completed final sign-off May 2021 | 1750 Taylor St | rev to pa# 201904087407 (unit# 405) demo of interior walls, doors, cabinetry, counters, flooring, and finishes as noted removal of appliances and fixtures as noted, removal and replacement of glazing and exterior siding doors as noted removal and replacement of exterior decking to complh with royalDetails
rev to pa# 201904087407 (unit# 405) demo of interior walls, doors, cabinetry, counters, flooring, and finishes as noted removal of appliances and fixtures as noted, removal and replacement of glazing and exterior siding doors as noted removal and replacement of exterior decking to complh with royal | $378,814 |
| May 10, 2019 | Completed final sign-off Feb 2022 | 1000 03rd St | #1603 - interior remodel of (e) condo units and addition of fire rated door btwn 2 units.Details
#1603 - interior remodel of (e) condo units and addition of fire rated door btwn 2 units. | $650,000 |
| May 10, 2019 | Completed final sign-off Feb 2022 | 1000 03rd St | #1602 - interior remodel of (e) condo units and addition of fire rated door btwn 2 units (#1603).Details
#1602 - interior remodel of (e) condo units and addition of fire rated door btwn 2 units (#1603). | $650,000 |
| Apr 25, 2019 | Never finaled issued Apr 2019, no final | 2121 Webster St | 5/f - unit #501 - remove non-structural walls as noted and reconfigure. remove portion of master bath, cap utility, use area as additional closet space. construct new walls, install new plumbing, new cabinetry and appliances, paint, install cardio/video systemDetails
5/f - unit #501 - remove non-structural walls as noted and reconfigure. remove portion of master bath, cap utility, use area as additional closet space. construct new walls, install new plumbing, new cabinetry and appliances, paint, install cardio/video system | $500,000 |
| Apr 25, 2019 | Completed final sign-off Jan 2022 | 2121 Webster St | unit 804 (gph4): interior fitout of (e) shell, ref approved bpa#201311222660, relocating (e) stair, new interior partitions, all new finishes, sprinkler/mechanical systems under seperate permit.Details
unit 804 (gph4): interior fitout of (e) shell, ref approved bpa#201311222660, relocating (e) stair, new interior partitions, all new finishes, sprinkler/mechanical systems under seperate permit. | $2,000,000 |
| Apr 8, 2019 | Completed final sign-off May 2021 | 1750 Taylor St | #405: kitchen & bathroom (3.5) remodel; all fixtures and finishes to be replaced in kind and in place; all appliances to be replaced in kind and in place; all cabinetry and interior doors to be replaced in kind and in place. no structural work- no wall modification.Details
#405: kitchen & bathroom (3.5) remodel; all fixtures and finishes to be replaced in kind and in place; all appliances to be replaced in kind and in place; all cabinetry and interior doors to be replaced in kind and in place. no structural work- no wall modification. | $100,607 |
| Apr 5, 2019 | Completed final sign-off Mar 2020 | 765 Market St | remodel kitchen, bathrooms & floors. all new doors & casing. new lighting throughout unit.Details
remodel kitchen, bathrooms & floors. all new doors & casing. new lighting throughout unit. | $100,000 |
| Mar 21, 2019 | Completed final sign-off May 2021 | 188 Minna St | #38a demo bath 2 & reconfigure walls for (n) master closet various changes to plumbing, electrical, lighting. (n) millwork & finishes, fixtures.Details
#38a demo bath 2 & reconfigure walls for (n) master closet various changes to plumbing, electrical, lighting. (n) millwork & finishes, fixtures. | $750,000 |
| Feb 8, 2019 | Never finaled issued Feb 2019, no final | 2121 Webster St | street spaceDetails
street space | |
| Feb 8, 2019 | Never finaled issued Feb 2019, no final | 2121 Webster St | street spaceDetails
street space | |
| Jan 10, 2019 | Never finaled issued Jan 2019, no final | 765 Market St | #36f -new plm fix, tile, counter, tibs appl. new cabintry, pocket doors. trim & moulding. new recessed light fix, modernized shades. new hardwood floors and carpet and tile. new paint/wallpaper throughout. remove mstr bedrm opening, remove kit pony wall, remove ceiling projector/screen & wood panelDetails
#36f -new plm fix, tile, counter, tibs appl. new cabintry, pocket doors. trim & moulding. new recessed light fix, modernized shades. new hardwood floors and carpet and tile. new paint/wallpaper throughout. remove mstr bedrm opening, remove kit pony wall, remove ceiling projector/screen & wood panel | $650,000 |
| Oct 18, 2018 | Completed final sign-off May 2022 | 301 Main St | renovation of apt 37b - demo of non-bearing walls & drop ceiling; construct new walls & ceiling, install new finishes and plumbing fixtures to replace existing. mep and fire sprinkler to be under separate permitDetails
renovation of apt 37b - demo of non-bearing walls & drop ceiling; construct new walls & ceiling, install new finishes and plumbing fixtures to replace existing. mep and fire sprinkler to be under separate permit | $1,000,000 |
| Sep 12, 2018 | Completed final sign-off Nov 2021 | 2121 Webster St | construct new walls, ceiling, install new plumbing, new cabinetry & appliances. paint and new floor finishes. (build out of unfinished condo unit #ph7.)Details
construct new walls, ceiling, install new plumbing, new cabinetry & appliances. paint and new floor finishes. (build out of unfinished condo unit #ph7.) | $840,000 |
| Sep 12, 2018 | Completed final sign-off Nov 2021 | 2121 Webster St | construct new walls, ceiling, install new plumbing, new cabinetry & appliances. paint and new floor finishes. (build out of unfinished condo unit #ph1.)Details
construct new walls, ceiling, install new plumbing, new cabinetry & appliances. paint and new floor finishes. (build out of unfinished condo unit #ph1.) | $840,000 |
| Sep 12, 2018 | Completed final sign-off Nov 2021 | 2121 Webster St | build out of (2) unfinished condo units ph1 & ph7 including: demo existing wall. new (1) hour separation wall w/ communicating door.Details
build out of (2) unfinished condo units ph1 & ph7 including: demo existing wall. new (1) hour separation wall w/ communicating door. | $20,000 |
| Aug 27, 2018 | Completed final sign-off Apr 2021 | 2121 Webster St | gph 1: new interior buildout of an extg shell. relocating extg stair, structural changes, new residential elevator, new kitchen and bathrooms. sprinkler and mep system under seperate permit. n/a for maherDetails
gph 1: new interior buildout of an extg shell. relocating extg stair, structural changes, new residential elevator, new kitchen and bathrooms. sprinkler and mep system under seperate permit. n/a for maher | $1,800,000 |
| Jun 29, 2018 | Completed final sign-off May 2019 | 2121 Webster St | unit #608 remove non structural walls as noted and referenced/ replace 3 decorative light fixtures. finish carpentry, repaint entire unit. remove hall bathtub, cap plumbing, use area as a storage closet. tile and hardwood repairs. install audio/video system maher naDetails
unit #608 remove non structural walls as noted and referenced/ replace 3 decorative light fixtures. finish carpentry, repaint entire unit. remove hall bathtub, cap plumbing, use area as a storage closet. tile and hardwood repairs. install audio/video system maher na | $55,000 |
| May 10, 2018 | Completed final sign-off Oct 2019 | 1750 Taylor St | #2301: interior remodel of one unit in a multi-family apt building. scope of work all interior-remodel, proposed work in non-structural & does not affect envelope. replacement of glazing & windows in kind only.Details
#2301: interior remodel of one unit in a multi-family apt building. scope of work all interior-remodel, proposed work in non-structural & does not affect envelope. replacement of glazing & windows in kind only. | $366,000 |
| Apr 11, 2018 | Completed final sign-off Jun 2021 | 2411 Broadway | revision to permit #201802121047. reinforce (e) 4th fl roof structure. maher naDetails
revision to permit #201802121047. reinforce (e) 4th fl roof structure. maher na | $30,000 |
| Mar 26, 2018 | Completed final sign-off Jun 2019 | 999 Green St | replace master bth, kitchen, guest bath. new electrical lighting, hardwood flooring. new paint throughout. replace extg a/c fan coil and condensor.Details
replace master bth, kitchen, guest bath. new electrical lighting, hardwood flooring. new paint throughout. replace extg a/c fan coil and condensor. | $760,000 |
| Feb 23, 2018 | Completed final sign-off May 2018 | 2121 Webster St | closing off (e) door to bedroom #3, removal of (e) closet, install of new full height cabinet under soffit, removal/capping of (2) fire sprinkler heads (sep permit), provide 8'-0" opening (non structural wall) to seperat living room and bedroom #4, replace (3) sconce light fixtures at mstr bath, repDetails
closing off (e) door to bedroom #3, removal of (e) closet, install of new full height cabinet under soffit, removal/capping of (2) fire sprinkler heads (sep permit), provide 8'-0" opening (non structural wall) to seperat living room and bedroom #4, replace (3) sconce light fixtures at mstr bath, rep | $10,000 |