- Jun 2000 to Dec 2019
158 permits since 2000 (architect on 141 permits, authorized agent-others on 11 permits, engineer on 6 permits): 117 completed, 18 never finaled, 23 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 158.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 18, 2019 | Completed final sign-off Feb 2021 | 211 Main St | Dome Construction Corp | 6th fl: commercial ti to include new conference storefronts, offices, breakroom, finishes, and ada upgrades in restrooms. new lighting throughout.Details
6th fl: commercial ti to include new conference storefronts, offices, breakroom, finishes, and ada upgrades in restrooms. new lighting throughout. | $1,200,000 |
| May 23, 2018 | Never finaled issued Jun 2018, no final | 211 Main St | Hathaway Dinwiddie Co. | tenant improvement to include demising wall, carpet, paint, new lights; fire alarm and sprinklers separateDetails
tenant improvement to include demising wall, carpet, paint, new lights; fire alarm and sprinklers separate | $50,000 |
| May 23, 2018 | Completed final sign-off Oct 2018 | 50 Beale St | Field Construction Inc. | 10th floor: demolition of non-structural partitions, ceiling, lighting, finishes, and any associated plumbing, mechanical and electrical. additions include new paint finish, elect. fixtures, & accessibility upgrades in restrooms. n/a for maher.Details
10th floor: demolition of non-structural partitions, ceiling, lighting, finishes, and any associated plumbing, mechanical and electrical. additions include new paint finish, elect. fixtures, & accessibility upgrades in restrooms. n/a for maher. | $400,000 |
| Feb 21, 2018 | Completed final sign-off Apr 2018 | 100 01st St | Commercial Interior Builders Inc | restroom accessibility improvements on the 14th fl. scope of work includes install new stall partitions & new drinking fountain and re-install existing accessories to be code compliant.Details
restroom accessibility improvements on the 14th fl. scope of work includes install new stall partitions & new drinking fountain and re-install existing accessories to be code compliant. | $55,278 |
| Feb 15, 2018 | Completed final sign-off Oct 2018 | 501 Tunnel Av | Westates Mechanical Corporation Inc | relocation of 6"underground on private hydrant system..ef pa 2016-0526-8444Details
relocation of 6"underground on private hydrant system..ef pa 2016-0526-8444 | $8,000 |
| Feb 14, 2018 | Completed final sign-off Nov 2018 | 303 02nd St | Peacock Construction | 9th floor: restroom upgrades scope includes removal of all extg finishes, plmg fixtures, equipments, accessories, toilet partitions, full height partition & lighting. provide new toilet partitions, plmg fixtures, accessories, full height partition, lighting & finishes. n/a for maherDetails
9th floor: restroom upgrades scope includes removal of all extg finishes, plmg fixtures, equipments, accessories, toilet partitions, full height partition & lighting. provide new toilet partitions, plmg fixtures, accessories, full height partition, lighting & finishes. n/a for maher | $50,000 |
| Feb 14, 2018 | Completed final sign-off Nov 2018 | 303 02nd St | Peacock Construction | 6th floor: restroom upgrades scope includes removal of all extg finishes, plmg fixtures, equipments, accessories, toilet partitions, full height partition & lighting. provide new toilet partitions, plmg fixtures, accessories, full height partition, lighting & finishes. n/a for maherDetails
6th floor: restroom upgrades scope includes removal of all extg finishes, plmg fixtures, equipments, accessories, toilet partitions, full height partition & lighting. provide new toilet partitions, plmg fixtures, accessories, full height partition, lighting & finishes. n/a for maher | $50,000 |
| Jan 31, 2018 | Completed final sign-off Jul 2018 | 211 Main St | Hathaway Dinwiddie Co. | 13th flr - commercial ti to include private offices and ipgrades to (e) office & conference rrooms. new led lighting throughout. new ada upgrades in restrooms. maher naDetails
13th flr - commercial ti to include private offices and ipgrades to (e) office & conference rrooms. new led lighting throughout. new ada upgrades in restrooms. maher na | $480,000 |
| Jan 31, 2018 | Completed final sign-off Jul 2018 | 211 Main St | Hathaway Dinwiddie Co. | 7th flr - commercial ti to include private offices and ipgrades to (e) office & conference rrooms. new led lighting throughout. new ada upgrades in restrooms. maher naDetails
7th flr - commercial ti to include private offices and ipgrades to (e) office & conference rrooms. new led lighting throughout. new ada upgrades in restrooms. maher na | $480,000 |
| Dec 20, 2017 | Completed final sign-off Dec 2018 | 1 Market St | Dpr Construction | 12th fl amep ti full floor. no structural, soft demo under separate pa #201712085901, new office, meeting rooms, new restrooms. no changes to bldg core. 2-hr horizontal exit . n/a maher ordinance.Details
12th fl amep ti full floor. no structural, soft demo under separate pa #201712085901, new office, meeting rooms, new restrooms. no changes to bldg core. 2-hr horizontal exit . n/a maher ordinance. | $3,200,000 |
| Nov 14, 2017 | Completed final sign-off Jun 2018 | 601 Montgomery St | Rossi Builders Inc. | suite 120 - revision to pa #201706169579: add grease trap. n/a maher ordinanceDetails
suite 120 - revision to pa #201706169579: add grease trap. n/a maher ordinance | |
| Nov 10, 2017 | Expired or cancelled cancelled Aug 2023 | 600 Montgomery St | emergency evacuation signage submittal. n/a for maherDetails
emergency evacuation signage submittal. n/a for maher | $1,000 | |
| Sep 15, 2017 | Never finaled issued Jun 2019, no final | 600 Montgomery St | Hathaway Dinwiddie Co. | change of occupancy and use from b-office to a-2 assembly on 48th fl for after hours events. scope includes upgrading (1) restroom to fully accessible single user restroom, new signage, water fountain/bottle filler, and increasing headroom at exit access stairDetails
change of occupancy and use from b-office to a-2 assembly on 48th fl for after hours events. scope includes upgrading (1) restroom to fully accessible single user restroom, new signage, water fountain/bottle filler, and increasing headroom at exit access stair | $50,000 |
| Sep 8, 2017 | Completed final sign-off Jul 2018 | 601 Montgomery St | Rossi Builders Inc. | 7/f partial floor spec suite #770- commercial t.i. to include demo non-structural partitions, lighting and finishes. construction of non-structural partitions includes mep. n/a ordinance #155-13. ref pa 201704285167 for rated corridor to meet exit separation reqts, fire under separate permit(s)Details
7/f partial floor spec suite #770- commercial t.i. to include demo non-structural partitions, lighting and finishes. construction of non-structural partitions includes mep. n/a ordinance #155-13. ref pa 201704285167 for rated corridor to meet exit separation reqts, fire under separate permit(s) | $40,000 |
| Aug 22, 2017 | Completed final sign-off Dec 2017 | 369 Pine St | San Francisco Commercial Builders Inc | 3rd floor restroom upgrades. work scope includes removal of all existing finishes, plumbing fixtures, accessories, ceiling & lighting. provide new accessible toilet stalls, plumbing fixtures & accessories as well as new finsihes, ceiling & lighting.Details
3rd floor restroom upgrades. work scope includes removal of all existing finishes, plumbing fixtures, accessories, ceiling & lighting. provide new accessible toilet stalls, plumbing fixtures & accessories as well as new finsihes, ceiling & lighting. | $100,000 |
| Aug 8, 2017 | Completed final sign-off Nov 2018 | 501 Tunnel Av | Nibbi Bros Assoc Inc. | work under permit #201605268444-s3 extends over property line. retaining wall to extend over property line. all property owned by same ownerDetails
work under permit #201605268444-s3 extends over property line. retaining wall to extend over property line. all property owned by same owner | |
| Jun 16, 2017 | Never finaled issued Oct 2017, no final | 601 Montgomery St | Rossi Builders Inc. | 1st & 3rd floors, commercial ti which includes electrical work for commercial appliances. includes accessibility upgrades. limited food service, non cooking facilityDetails
1st & 3rd floors, commercial ti which includes electrical work for commercial appliances. includes accessibility upgrades. limited food service, non cooking facility | $179,000 |
| Apr 28, 2017 | Never finaled issued Jun 2017, no final | 601 Montgomery St | High Level Construction Co | 7th floor unit 750 srs: commercial t.i. which includes demolition of non-structural partitions, lighting, and finishes. construction of non structural partitions includes accessibility upgrades, mechanical, electrical and plumbing.Details
7th floor unit 750 srs: commercial t.i. which includes demolition of non-structural partitions, lighting, and finishes. construction of non structural partitions includes accessibility upgrades, mechanical, electrical and plumbing. | $300,000 |
| Apr 28, 2017 | Never finaled issued Jun 2017, no final | 601 Montgomery St | High Level Construction Co | 7th floor, common areas : commercial t.i. which includes demolition of non-structural partitions, lighting, and finishes. construction of non structural partitions includes accessibility upgrades, mechanical, electrical and plumbing.Details
7th floor, common areas : commercial t.i. which includes demolition of non-structural partitions, lighting, and finishes. construction of non structural partitions includes accessibility upgrades, mechanical, electrical and plumbing. | $150,000 |
| Apr 17, 2017 | Never finaled issued Apr 2017, no final | 211 Main St | Hathaway Dinwiddie Co. | 14th floor commercial tenant improvement to include new private offices & upgrades to exisitng offices, conference rooms & break area. new led lighting throughout. new ada upgrades in restrooms. n/a maher ordinanceDetails
14th floor commercial tenant improvement to include new private offices & upgrades to exisitng offices, conference rooms & break area. new led lighting throughout. new ada upgrades in restrooms. n/a maher ordinance | $50,000 |
| Apr 17, 2017 | Never finaled issued Apr 2017, no final | 211 Main St | Hathaway Dinwiddie Co. | 15th floor commercial tenant improvement to include new private offices & upgrades to exisitng offices, conference rooms & break area. new led lighting throughout. new ada upgrades in restrooms. n/a maher ordinanceDetails
15th floor commercial tenant improvement to include new private offices & upgrades to exisitng offices, conference rooms & break area. new led lighting throughout. new ada upgrades in restrooms. n/a maher ordinance | $50,000 |
| Feb 8, 2017 | Completed final sign-off Jul 2017 | 275 Battery St | Field Construction Inc. | renovation of the 12th floor for the offices of pensco trust company. construction includes new layout of walls & offices, casework, ceiling & soffits & mep work - mep to be deferred submittalsDetails
renovation of the 12th floor for the offices of pensco trust company. construction includes new layout of walls & offices, casework, ceiling & soffits & mep work - mep to be deferred submittals | $704,877 |
| Dec 21, 2016 | Completed final sign-off Oct 2017 | 211 Main St | Dome Construction Corp | 11/f: commercial tenant improvements to include new conference rooms, offices, and huddle rooms. new led lighting throughout. new ada upgrdes in the bathrooms. maher n/aDetails
11/f: commercial tenant improvements to include new conference rooms, offices, and huddle rooms. new led lighting throughout. new ada upgrdes in the bathrooms. maher n/a | $853,491 |
| Dec 20, 2016 | Completed final sign-off Oct 2017 | 211 Main St | Dome Construction Corp | 10/f: commercial tenant improvements to include new conference rooms, offices, and huddle rooms. new led lighting throughout. new ada upgrdes in the bathrooms. maher n/aDetails
10/f: commercial tenant improvements to include new conference rooms, offices, and huddle rooms. new led lighting throughout. new ada upgrdes in the bathrooms. maher n/a | $853,491 |
| Dec 16, 2016 | Completed final sign-off Mar 2017 | 4 Embarcadero Center | Sc Builders, Inc | suite #2640: commercial t.i. to unoccupied suite on 26th floor. demolition of finishes, millwork, and limited ceiling demo. new non-structural partitions, glazing and millwork, includes restroom accessibility upgrades. n/a for maher.Details
suite #2640: commercial t.i. to unoccupied suite on 26th floor. demolition of finishes, millwork, and limited ceiling demo. new non-structural partitions, glazing and millwork, includes restroom accessibility upgrades. n/a for maher. | $148,407 |
| Nov 23, 2016 | Completed final sign-off Mar 2017 | 50 Beale St | Field Construction Inc. | 8th & 9th floors: demo of non structural partitions, ceiling, lighting, millwork, finih\shes, elect fixtures, plumb fixtures and mechanical maher na, tenant improvement under separate permit per ab-017Details
8th & 9th floors: demo of non structural partitions, ceiling, lighting, millwork, finih\shes, elect fixtures, plumb fixtures and mechanical maher na, tenant improvement under separate permit per ab-017 | $350,000 |
| Nov 8, 2016 | Completed final sign-off May 2017 | 303 02nd St | 7/f #750- commercial t.i. to unoccupied suite, demo finishes & millwork, new non structural partitions, glazing, millwork & finishes includes accessibility upgrades to restrooms. n/a ordinance #155-13Details
7/f #750- commercial t.i. to unoccupied suite, demo finishes & millwork, new non structural partitions, glazing, millwork & finishes includes accessibility upgrades to restrooms. n/a ordinance #155-13 | $38,400 | |
| Nov 7, 2016 | Completed final sign-off Aug 2017 | 3 Embarcadero Center | Bcci Construction Company | 6th flr: t.i.- construction of new noload bearing partitions, doors, interior glazing, ceilings, power & communications infrastructure and finishes. no new fsd's, i.t. room per dbi definition. maher naDetails
6th flr: t.i.- construction of new noload bearing partitions, doors, interior glazing, ceilings, power & communications infrastructure and finishes. no new fsd's, i.t. room per dbi definition. maher na | $1,874,290 |
| Nov 7, 2016 | Completed final sign-off Mar 2017 | 50 Beale St | Field Construction Inc. | 7th floor: demo non structural partitions, ceilings, lighting, millwork, finishes, electrical fixtures, plmg fixtures, mechanical construction. non-structural partitions, ceilings, lighting, electrical fixtures and mechanical. n/a for maher. core & shell work unfinish floor only.Details
7th floor: demo non structural partitions, ceilings, lighting, millwork, finishes, electrical fixtures, plmg fixtures, mechanical construction. non-structural partitions, ceilings, lighting, electrical fixtures and mechanical. n/a for maher. core & shell work unfinish floor only. | $580,000 |
| Nov 7, 2016 | Expired or cancelled cancelled Jan 2026 | 50 Beale St | 8th and 9th floors: demo non structural partitions, ceilings, lighting, millwork, finishes, electrical fixtures, plmg fixtures and mechanical construction. construction consisting of finishes and title 24 lighting. n/a for maher.Details
8th and 9th floors: demo non structural partitions, ceilings, lighting, millwork, finishes, electrical fixtures, plmg fixtures and mechanical construction. construction consisting of finishes and title 24 lighting. n/a for maher. | $769,000 | |
| Oct 14, 2016 | Never finaled issued Nov 2016, no final | 601 Montgomery St | High Level Construction Co | commercial tenant improvement which includes demo of non-structural partitions, lighting, and finshes. construction of non-structural partitions. includes mep.Details
commercial tenant improvement which includes demo of non-structural partitions, lighting, and finshes. construction of non-structural partitions. includes mep. | $375,600 |
| Sep 13, 2016 | Completed final sign-off May 2017 | 303 02nd St | Skyline Construction | #950n- demolition of existing non-structural partitions, ceiling, lighting, floor finishes and any associated mechanical, electrical & plumbing in an unoccupied tenant suite per ab-017. n/a ordinance #155-13Details
#950n- demolition of existing non-structural partitions, ceiling, lighting, floor finishes and any associated mechanical, electrical & plumbing in an unoccupied tenant suite per ab-017. n/a ordinance #155-13 | $100,000 |
| Sep 13, 2016 | Completed final sign-off May 2017 | 303 02nd St | Skyline Construction | #400n- demolition of existing non-structural partitions, ceiling, lighting, floor finishes and any associated mechanical, electrical & plumbing in an unoccupied tenant suite per ab-017. n/a ordinance #155-13Details
#400n- demolition of existing non-structural partitions, ceiling, lighting, floor finishes and any associated mechanical, electrical & plumbing in an unoccupied tenant suite per ab-017. n/a ordinance #155-13 | $100,000 |
| Jul 25, 2016 | Completed final sign-off Oct 2016 | 601 Montgomery St | Rossi Builders Inc. | barrier removal including upgrades to be accessibleDetails
barrier removal including upgrades to be accessible | $15,000 |
| Jul 15, 2016 | Completed final sign-off Oct 2016 | 601 Montgomery St | Rossi Builders Inc. | #1450 - commercial tenant improvement which includes demolition of non-structural partitions, lighting, & finishes. construction of non-structural partitions includes mechanical, electrical & plumbing.Details
#1450 - commercial tenant improvement which includes demolition of non-structural partitions, lighting, & finishes. construction of non-structural partitions includes mechanical, electrical & plumbing. | $259,690 |
| May 13, 2016 | Completed final sign-off Nov 2016 | 475 Brannan St | Field Construction Inc. | #210: commercial t.i. which includes demolition on non-structural partitions, light fixtures, electrical devices, millwork, and finishes. construction of millwork, finishes, plumbing fixtures, light fixtures, and electrical. n/a for maher.Details
#210: commercial t.i. which includes demolition on non-structural partitions, light fixtures, electrical devices, millwork, and finishes. construction of millwork, finishes, plumbing fixtures, light fixtures, and electrical. n/a for maher. | $75,000 |
| Mar 7, 2016 | Completed final sign-off Jun 2016 | 600 Montgomery St | Hathaway Dinwiddie Co. | 22nd floor:demolition of non-structural partitions. removed of floor finish and one extg door. salvage and reuse extg doors and side light. n/a for maherDetails
22nd floor:demolition of non-structural partitions. removed of floor finish and one extg door. salvage and reuse extg doors and side light. n/a for maher | $115,000 |
| Mar 4, 2016 | Completed final sign-off May 2017 | 1 Market St | Peacock Construction | 7th flr: steuart tower, ti consisting of demolition of (e) millwork,finishes,lighting & associated elec. construction of new non-structural partitions,elec fixtures,millwork,doors/frames/hardware & associated mechanical,relocation of (e) plumbing; maher n/aDetails
7th flr: steuart tower, ti consisting of demolition of (e) millwork,finishes,lighting & associated elec. construction of new non-structural partitions,elec fixtures,millwork,doors/frames/hardware & associated mechanical,relocation of (e) plumbing; maher n/a | $131,760 |
| Feb 5, 2016 | Completed final sign-off May 2016 | 101 Spear St | suite 400: demolition of (e) non-structural partitions, millwork and ceiling. removal of (e) mep distribution. re-suport lights throughout. maher naDetails
suite 400: demolition of (e) non-structural partitions, millwork and ceiling. removal of (e) mep distribution. re-suport lights throughout. maher na | $96,000 | |
| Jan 27, 2016 | Completed final sign-off Oct 2016 | 50 Beale St | Peacock Construction | commercial t.i. consisting of demolition of (e) finishes and electrical, power/data, construction of new non-structural partitions, electrical fixtures, plumbing, millwork, doors/frames/hardware and associated mechanical. mep. deferred. n/a ordinance #155-13.Details
commercial t.i. consisting of demolition of (e) finishes and electrical, power/data, construction of new non-structural partitions, electrical fixtures, plumbing, millwork, doors/frames/hardware and associated mechanical. mep. deferred. n/a ordinance #155-13. | $210,000 |
| Jan 22, 2016 | Completed final sign-off Jun 2016 | 600 Montgomery St | Hathaway Dinwiddie Co. | tenant improvements new offices and support facilities. new stair to connect to the 20th fl. mep under separate permitDetails
tenant improvements new offices and support facilities. new stair to connect to the 20th fl. mep under separate permit | $685,000 |
| Jan 22, 2016 | Completed final sign-off Apr 2016 | 601 Montgomery St | Clune Construction Company L P | #1400 -commercial t.i. includes demolition, new non-structural partitions, lighting, electrical, millwork and finishes. f/a sprinkler under separate permit. n/a ordinance #155-13Details
#1400 -commercial t.i. includes demolition, new non-structural partitions, lighting, electrical, millwork and finishes. f/a sprinkler under separate permit. n/a ordinance #155-13 | $762,841 |
| Jan 21, 2016 | Completed final sign-off Jun 2016 | 601 Montgomery St | Clune Construction Company L P | 14th floor - scope of work includes new 1-hr rated corridor linking future proposed suites & ada restroom upgrade. work includes 1-hr rated full height partition, elevator lobby ceiling & finishes.Details
14th floor - scope of work includes new 1-hr rated corridor linking future proposed suites & ada restroom upgrade. work includes 1-hr rated full height partition, elevator lobby ceiling & finishes. | $231,516 |
| Dec 18, 2015 | Completed final sign-off Sep 2016 | 222 Sutter St | Field Construction Inc. | 4th floor: restrooms, restroom vestibules, and elevator lobby. demo of non structural partitions, ceiling, lighting, fixtures and finishes as required, ceiling, lighting, fixtures and finishes. n/a for maher. electrical- sprinklers and fire alarm sep.Details
4th floor: restrooms, restroom vestibules, and elevator lobby. demo of non structural partitions, ceiling, lighting, fixtures and finishes as required, ceiling, lighting, fixtures and finishes. n/a for maher. electrical- sprinklers and fire alarm sep. | $103,800 |
| Dec 18, 2015 | Completed final sign-off Sep 2016 | 222 Sutter St | Field Construction Inc. | 5th floor:scope includes restrooms, restroom vestibules. demo of non structural partitions, ceiling, lighting, fixtures and finishes as required to accomodate new partitions, ceiling, lighting, fixtures and finishes. n/a for maher.Details
5th floor:scope includes restrooms, restroom vestibules. demo of non structural partitions, ceiling, lighting, fixtures and finishes as required to accomodate new partitions, ceiling, lighting, fixtures and finishes. n/a for maher. | $42,000 |
| Dec 2, 2015 | Completed final sign-off Feb 2017 | 600 Montgomery St | Field Construction Inc. | 15th fl - suite 1550 - elevator lobby, corridor & restrooms- work to include minor demo & upgrade, add non-structural act ceiling, grid and 2x2 light fixtures, non structural partitions and millwork. mechanical & plumbing fixtures included. n/a ordinance #155-13Details
15th fl - suite 1550 - elevator lobby, corridor & restrooms- work to include minor demo & upgrade, add non-structural act ceiling, grid and 2x2 light fixtures, non structural partitions and millwork. mechanical & plumbing fixtures included. n/a ordinance #155-13 | $625,000 |
| Nov 23, 2015 | Completed final sign-off May 2016 | 215 Fremont St | Dome Construction Corp | ground floor lobby renovation limited to new finishes at the elevator wall elevation, new building directory signage and new carpet within the elevator cabs. n/a ordinance #155-13Details
ground floor lobby renovation limited to new finishes at the elevator wall elevation, new building directory signage and new carpet within the elevator cabs. n/a ordinance #155-13 | $55,000 |
| Nov 19, 2015 | Completed final sign-off Apr 2016 | 601 Montgomery St | High Level Construction Co | suite # 1830: commercial t.i. which includes new non-structural partitions, lighting, plumbin, mechnical, electrical, millwork and finishes. n/a for maher.Details
suite # 1830: commercial t.i. which includes new non-structural partitions, lighting, plumbin, mechnical, electrical, millwork and finishes. n/a for maher. | $214,420 |
| Sep 24, 2015 | Completed final sign-off Dec 2016 | 100 01st St | Commercial Interior Builders Inc | 3rd floor improvements to an unoccupied office suite. improvement include non-structural partitions, casement, ceilings, lighting & finishes. deferred submittals for t-24 mechanical & electrical, life safety & sprinklers.Details
3rd floor improvements to an unoccupied office suite. improvement include non-structural partitions, casement, ceilings, lighting & finishes. deferred submittals for t-24 mechanical & electrical, life safety & sprinklers. | $319,540 |
| Jun 11, 2015 | Completed final sign-off Jul 2016 | 345 Stockton St | Ledcor Construction Inc | patch and repair interior finishes from construction, iunstallation of new and e doors, replace and install wall coverings, finishes, non structural partitions damaged of removed for construction under 201312164258Details
patch and repair interior finishes from construction, iunstallation of new and e doors, replace and install wall coverings, finishes, non structural partitions damaged of removed for construction under 201312164258 | $100,000 |
| Jun 9, 2015 | Expired or cancelled cancelled Aug 2022 | 191 Sutter St | barrier removal to provide accessible path to adjacent roof deck and opening in property line wall with ab-010. n/a ordinance #155-13Details
barrier removal to provide accessible path to adjacent roof deck and opening in property line wall with ab-010. n/a ordinance #155-13 | $50,000 | |
| May 28, 2015 | Completed final sign-off Jun 2016 | 345 Stockton St | Skyline Construction, Ledcor Construction Inc | ti for redwood room in 3rd basement of hotel. work includes new doors, wall coverings operable partitions, finishes, acoustical tile and grid, reinstallation of e light fixturesDetails
ti for redwood room in 3rd basement of hotel. work includes new doors, wall coverings operable partitions, finishes, acoustical tile and grid, reinstallation of e light fixtures | $100,000 |
| Mar 12, 2015 | Completed final sign-off Nov 2016 | 459 Geary St | Charles Pankow Builders Ltd | revision to pa #2014.0627.9895 - install bison pedestal system with 850 s.f. of ipe wood deck palletes on previously submitted roof deck.Details
revision to pa #2014.0627.9895 - install bison pedestal system with 850 s.f. of ipe wood deck palletes on previously submitted roof deck. | $50,000 |
| Feb 25, 2015 | Completed final sign-off Nov 2016 | 459 Geary St | Charles Pankow Builders Ltd | revision to appl #2014.0627.9895: remvoe installation of casework & plumbing fixtures from scope of permit. provide rough in only, electrical outlet locations & miscellanous lighting revisions.Details
revision to appl #2014.0627.9895: remvoe installation of casework & plumbing fixtures from scope of permit. provide rough in only, electrical outlet locations & miscellanous lighting revisions. | |
| Feb 24, 2015 | Completed final sign-off Dec 2015 | 535 Powell St | Arrow Sign Company | remove (e) sign, replace with new. lower to meet code complianceDetails
remove (e) sign, replace with new. lower to meet code compliance | $2,500 |
| Feb 24, 2015 | Completed final sign-off Jul 2015 | 535 Powell St | Arrow Sign Company | sign - remove (e) and attach new address numbers and letters directly to buildingDetails
sign - remove (e) and attach new address numbers and letters directly to building | $500 |
| Feb 4, 2015 | Completed final sign-off Jul 2015 | 459 Geary St | Charles Pankow Builders Ltd | 2nd flr: revision to permit 201403180983 office t.i., to remove gyp ceilings from scope of work over office & circulation areas; install surface mounted light fixtures; paint underside of exposed structure & all exposed pipes & conduit.Details
2nd flr: revision to permit 201403180983 office t.i., to remove gyp ceilings from scope of work over office & circulation areas; install surface mounted light fixtures; paint underside of exposed structure & all exposed pipes & conduit. | |
| Dec 31, 2014 | Completed final sign-off Jun 2015 | 222 Sutter St | Bluewater Environmentl Svc Inc | ste #700: commercial ti- includes installation of break room flooring finishes, paint, millwork & plumbing fixtures.; maher n/aDetails
ste #700: commercial ti- includes installation of break room flooring finishes, paint, millwork & plumbing fixtures.; maher n/a | $30,636 |
| Nov 4, 2014 | Completed final sign-off Dec 2014 | 1600 15th St | Huey Const Mngmt Co Inc - Dba M H Const. | construction of walls to demise (3) retail units, construction of (3) fully compliant accessible restrooms, mep under deferred submittal. n/a ordinance #155-13Details
construction of walls to demise (3) retail units, construction of (3) fully compliant accessible restrooms, mep under deferred submittal. n/a ordinance #155-13 | $150,000 |
| Aug 20, 2014 | Completed final sign-off Jul 2015 | 459 Geary St | Charles Pankow Builders Ltd | revision to (e) t.i. pa#201312204743 to increase size of basement level office.Details
revision to (e) t.i. pa#201312204743 to increase size of basement level office. | $1,500 |
| Jun 27, 2014 | Completed final sign-off Nov 2016 | 459 Geary St | Charles Pankow Builders Ltd | interior & exterior owner improvement on 2 levels to create 1 dwelling unit. new kitchen, 3 bedrooms, 4 baths, wet bar, therapy pool, and landscaping. ref pa# 2012/06/08/2224.Details
interior & exterior owner improvement on 2 levels to create 1 dwelling unit. new kitchen, 3 bedrooms, 4 baths, wet bar, therapy pool, and landscaping. ref pa# 2012/06/08/2224. | $500,000 |
| Jun 25, 2014 | Completed final sign-off Nov 2014 | 601 Montgomery St | Commercial Interior Builders Inc | 11th flr, ste #1100- partial interior only demolition to existing suite, proposed interior only partition construction. new lights, and ceiling throughout. construction of new copy area and networking closet; maher n/aDetails
11th flr, ste #1100- partial interior only demolition to existing suite, proposed interior only partition construction. new lights, and ceiling throughout. construction of new copy area and networking closet; maher n/a | $250,000 |
| May 28, 2014 | Completed final sign-off Jul 2015 | 601 Montgomery St | Rossi Builders Inc. | 10th floor: to comply with current code. upgrade finishes in lobby, corridors, restrooms to current bldg standard. installation of new suspended ceiling tile system, lighting, and relocation hvac as required. new extg signs. provide 2nd exit at suite 1000. demo to interior partitions.Details
10th floor: to comply with current code. upgrade finishes in lobby, corridors, restrooms to current bldg standard. installation of new suspended ceiling tile system, lighting, and relocation hvac as required. new extg signs. provide 2nd exit at suite 1000. demo to interior partitions. | $170,000 |
| Apr 4, 2014 | Completed final sign-off Sep 2015 | 2001 37th Av | Pacific Door & Hardware Inc | replacement of existing exterior doorsDetails
replacement of existing exterior doors | $400,000 |
| Mar 18, 2014 | Completed final sign-off Jul 2015 | 459 Geary St | Charles Pankow Builders Ltd | tenant improvement, office space, photograph studio, 2 restrooms, 1 shower and 1 kitchenette. previous approved pa#201206082224 is adding the residential unit. on 2nd floor.Details
tenant improvement, office space, photograph studio, 2 restrooms, 1 shower and 1 kitchenette. previous approved pa#201206082224 is adding the residential unit. on 2nd floor. | $250,000 |
| Dec 27, 2013 | Never finaled issued Jun 2014, no final | 2016 Market St | L M Quality Builders Inc | tenant improvement in existing space. installation of cabinetry equipment, fixtures & finishes. sprinkler work is to be design build under sep permit. tenant is formula retail and approval is per planning commission. compliance w/ord no. 155-13 not req, excav <50 cu.yd.Details
tenant improvement in existing space. installation of cabinetry equipment, fixtures & finishes. sprinkler work is to be design build under sep permit. tenant is formula retail and approval is per planning commission. compliance w/ord no. 155-13 not req, excav <50 cu.yd. | $100,000 |
| Dec 20, 2013 | Completed final sign-off Jul 2015 | 459 Geary St | Charles Pankow Builders Ltd | tenant improvement for art gallerty and office and retail on the gr floor and basement level of existing 7 story building. core and shell upgrades already underway 201206082224. no exterior work.Details
tenant improvement for art gallerty and office and retail on the gr floor and basement level of existing 7 story building. core and shell upgrades already underway 201206082224. no exterior work. | $200,000 |
| Sep 3, 2013 | Completed final sign-off Apr 2014 | 1 Market St | Bcci Construction Company | t.i. on the 25th floor including demolition of nonstructural partitions, ceiling and finishes. construction of nonstructural partitions, new ceiling, finishes and millwork. fire alarm, sprinklers, electrical, mechcanical, to be submitted on sep permits. jjcDetails
t.i. on the 25th floor including demolition of nonstructural partitions, ceiling and finishes. construction of nonstructural partitions, new ceiling, finishes and millwork. fire alarm, sprinklers, electrical, mechcanical, to be submitted on sep permits. jjc | $653,429 |
| Aug 21, 2013 | Expired or cancelled cancelled Feb 2017 | 3331 24th St | comply with nov# 201315121-convert (e) parking area to a patio connected to an (e) restaurant, work includes construction of a 6ft high fence with doors. construct bench seating & a raised deck with a rampDetails
comply with nov# 201315121-convert (e) parking area to a patio connected to an (e) restaurant, work includes construction of a 6ft high fence with doors. construct bench seating & a raised deck with a ramp | $25,000 | |
| Aug 13, 2013 | Completed final sign-off Dec 2013 | 170 Ofarrell St | Trainor Commercial Construction Inc. | 7th floor-tenant improvement of non structural low walls in furniture floor, paint & associated electrical outletsDetails
7th floor-tenant improvement of non structural low walls in furniture floor, paint & associated electrical outlets | $35,000 |
| Aug 1, 2013 | Completed final sign-off Feb 2014 | 44 Montgomery St | Rudolph Commercial Interiors Inc, Rci | modification of 41st floor common corridors, elevator lobby and public restrooms. includes demo and construction of new ceilings, new light fixtures and new finishes. elec/mech under separate permit. life safety work will be done under separate permit. sprinlker work under separate permitDetails
modification of 41st floor common corridors, elevator lobby and public restrooms. includes demo and construction of new ceilings, new light fixtures and new finishes. elec/mech under separate permit. life safety work will be done under separate permit. sprinlker work under separate permit | $200,000 |
| Jul 24, 2013 | Expired or cancelled withdrawn Jun 2015 | 191 Sutter St | barrier removal including addition of accessible platform lift, stair, landing, door & exterior wall opening @ property for existing opening to adjacent property. must provide updated ab-010 (communicating opening at prop line).Details
barrier removal including addition of accessible platform lift, stair, landing, door & exterior wall opening @ property for existing opening to adjacent property. must provide updated ab-010 (communicating opening at prop line). | $20,000 | |
| Jul 22, 2013 | Completed final sign-off Dec 2013 | 98 Mission St | Terra Nova Industries | tenant improvement of (e) restaurant-new equipment, finishes with associated electrical & plumbingDetails
tenant improvement of (e) restaurant-new equipment, finishes with associated electrical & plumbing | $45,500 |
| Jul 12, 2013 | Completed final sign-off Jun 2015 | 459 Geary St | Charles Pankow Builders Ltd | revision to pa #2012.06.08.2224 (basement level) - revised restroom layout & revised utility rooms on basement floor.Details
revision to pa #2012.06.08.2224 (basement level) - revised restroom layout & revised utility rooms on basement floor. | $5,000 |
| May 30, 2013 | Completed final sign-off Jul 2013 | 3251 20th Av | West Coast Commercial Interiors | remove (e) non structural walls & display shelving. provide new shape walls & relocate light fixtures (macy's)Details
remove (e) non structural walls & display shelving. provide new shape walls & relocate light fixtures (macy's) | $35,000 |
| May 7, 2013 | Completed final sign-off Jul 2014 | 2223 Market St | Astorga Const Company | remove existing dining room door & provide window. remove (e) wood shingles and provide stucco finish to match existing. remove (e) awning and provide sign. signage under seperate permit.Details
remove existing dining room door & provide window. remove (e) wood shingles and provide stucco finish to match existing. remove (e) awning and provide sign. signage under seperate permit. | $8,500 |
| Apr 26, 2013 | Never finaled issued Apr 2013, no final | 340 Bryant St | Charles Pankow Builders Ltd | 1st/2nd/3rd/4th floors-limited interior demolition of portion of slab on grade & floor penitrations per ab-017Details
1st/2nd/3rd/4th floors-limited interior demolition of portion of slab on grade & floor penitrations per ab-017 | $25,000 |
| Apr 26, 2013 | Completed final sign-off Jan 2016 | 340 Bryant St | Charles Pankow Builders Ltd, Construction Studios, Inc | interior/core rehab of (e) & accessibility element, including: new elevator, two exit stairs, improved lobby & stair, new accessible restrooms. mep, sprinklers under separate permits.Details
interior/core rehab of (e) & accessibility element, including: new elevator, two exit stairs, improved lobby & stair, new accessible restrooms. mep, sprinklers under separate permits. | $500,000 |
| Apr 26, 2013 | Expired or cancelled cancelled Apr 2014 | 262 Sutter St | remove (e) fabric awning & provide new awning w/2 decorative water cut panels.Details
remove (e) fabric awning & provide new awning w/2 decorative water cut panels. | $12,000 | |
| Apr 16, 2013 | Completed final sign-off May 2013 | 2516 Mission St | occupant load verification and approval for public assembly permit for roof deck, approved for 152 occupants. previously approved under pa# 2011-1214-0681 fire alarm sep permitDetails
occupant load verification and approval for public assembly permit for roof deck, approved for 152 occupants. previously approved under pa# 2011-1214-0681 fire alarm sep permit | ||
| Apr 8, 2013 | Completed final sign-off May 2013 | 2516 Mission St | Astorga Const Company | #2518 mission st-revision to pa# 2011-1214-0681-revise outdoor re-heat kitchen to be enclosed within building at rooftop. show (e) bar (service only) on rooftopDetails
#2518 mission st-revision to pa# 2011-1214-0681-revise outdoor re-heat kitchen to be enclosed within building at rooftop. show (e) bar (service only) on rooftop | $42,000 |
| Feb 28, 2013 | Completed final sign-off May 2013 | 345 California St | Peacock Construction Inc | demo of existing non structural partition, construct new demising non-structural partiton.Details
demo of existing non structural partition, construct new demising non-structural partiton. | $8,000 |
| Jul 3, 2012 | Never finaled issued Jul 2012, no final | 259 Post St | Peacock Construction Inc | demising partitions between 1st to 2nd and between 1st mezzanine to 2nd floors. 2 hour separation required at 2nd floor. spaces to remain vacant per ab-017Details
demising partitions between 1st to 2nd and between 1st mezzanine to 2nd floors. 2 hour separation required at 2nd floor. spaces to remain vacant per ab-017 | $22,000 |
| Jul 3, 2012 | Never finaled issued Dec 2012, no final | 259 Post St | Peacock Construction Inc | exterior demolition of sign band, awnings, related structure.entry door and frame. replacing doors, frame and sign band and column cladding.Details
exterior demolition of sign band, awnings, related structure.entry door and frame. replacing doors, frame and sign band and column cladding. | $15,000 |
| Jun 8, 2012 | Completed final sign-off Jun 2015 | 459 Geary St | Charles Pankow Builders Ltd | project consists of seismic upgrades to building's structural system, renovations to building's core & shell & interior improvement throughout (interior improvements to be documented & permitted under separate scope of work). note: occupant load verification required under separate permit.Details
project consists of seismic upgrades to building's structural system, renovations to building's core & shell & interior improvement throughout (interior improvements to be documented & permitted under separate scope of work). note: occupant load verification required under separate permit. | $3,289,287 |
| Apr 4, 2012 | Completed final sign-off Sep 2012 | 1275 Sacramento St | Birmingham Builders, Inc | a reconfiguration of (e) partial corridor space converted to a learning center & the reconfiguration of (e) classroom & office. scope of work occurs only at 4th flr.only non structural demo is being proposed. the new classroom is for students inthe upper classes limited to ,3rd through 8th gradeDetails
a reconfiguration of (e) partial corridor space converted to a learning center & the reconfiguration of (e) classroom & office. scope of work occurs only at 4th flr.only non structural demo is being proposed. the new classroom is for students inthe upper classes limited to ,3rd through 8th grade | $120,000 |
| Mar 8, 2012 | Completed final sign-off Mar 2012 | 1 Market St | Bcci Construction Company | ti on the 25th floor including demolitoin of 5' section of wall and addition of new doors and frameDetails
ti on the 25th floor including demolitoin of 5' section of wall and addition of new doors and frame | $3,500 |
| Jan 21, 2011 | Completed final sign-off Sep 2011 | 1 Front St | Bcci Construction Company | partially convert roof top of 1 front annex building to an occupied and accessible roof. includes new vestibule and exterior exit door, paving and related work (on roof of 2 story annex building)Details
partially convert roof top of 1 front annex building to an occupied and accessible roof. includes new vestibule and exterior exit door, paving and related work (on roof of 2 story annex building) | $85,000 |
| Dec 3, 2009 | Completed final sign-off Feb 2010 | 601 Montgomery St | High Level Construction Co | office tenant improvement; demise existing suite, add new door to corridor, remove one existing room(store rm.).Details
office tenant improvement; demise existing suite, add new door to corridor, remove one existing room(store rm.). | $46,126 |
| Jun 19, 2009 | Completed final sign-off Feb 2010 | 795 Folsom St | Rossi Builders Inc. | demolition of (e) offices, new doors, upgrade restrooms. remove (e) finishes in corridors & restrooms. install new finishes in restrooms & tenant suite. title-24 lighting compliance under separate permit.Details
demolition of (e) offices, new doors, upgrade restrooms. remove (e) finishes in corridors & restrooms. install new finishes in restrooms & tenant suite. title-24 lighting compliance under separate permit. | $214,000 |
| May 5, 2009 | Completed final sign-off Apr 2010 | 1275 Sacramento St | renovation of sacramento st entrance area to expand lobby/admin areas & library.Details
renovation of sacramento st entrance area to expand lobby/admin areas & library. | $1,200,000 | |
| Oct 21, 2008 | Completed final sign-off Nov 2009 | 640 Sutter St | Turner Construction Co | this permit is in reference to approved permit app #200608179733. supply and install new pre fabricated central stairs from 3rd floor to roof level. shop drawings by steel fabricator,glacier iron works, include structural steel framing and calcs. see letter attached rom both the architect of recordDetails
this permit is in reference to approved permit app #200608179733. supply and install new pre fabricated central stairs from 3rd floor to roof level. shop drawings by steel fabricator,glacier iron works, include structural steel framing and calcs. see letter attached rom both the architect of record | $225,000 |
| Apr 11, 2008 | Completed final sign-off Sep 2008 | 180 Montgomery St | Hathaway Dinwiddie Co. | repaving of (e) sidewalk and (e) pavers of exterior building arcade from (e) brick pavers to city standards conc. sidewalk & stone/tiles at exterior building arcade.Details
repaving of (e) sidewalk and (e) pavers of exterior building arcade from (e) brick pavers to city standards conc. sidewalk & stone/tiles at exterior building arcade. | $65,000 |
| Mar 27, 2008 | Expired or cancelled expired Jan 2010 | 640 Sutter St | Turner Construction Co | revision to appl #200608179733 - to change the means & methods of palcing identified walls in the basement as well as first floor from cast in place to shotcrete. revision to pa 200608179733Details
revision to appl #200608179733 - to change the means & methods of palcing identified walls in the basement as well as first floor from cast in place to shotcrete. revision to pa 200608179733 | |
| Feb 19, 2008 | Completed final sign-off Mar 2008 | 2 Embarcadero Center | revision to application 200710195941 adding a demizing wall at column line 8 to separate tenant space into 2 tenant spaces.Details
revision to application 200710195941 adding a demizing wall at column line 8 to separate tenant space into 2 tenant spaces. | $500 | |
| Jan 31, 2008 | Completed final sign-off Dec 2008 | 180 Montgomery St | Hathaway Dinwiddie Co. | g/f lobby- revision to pa # 200712170615: addition of exterior canopy, arcade ceiling painting, new lighting & signage. replacement of column wraps, new flooring in arcade and demolition of (e) tenants signage. all new work as indicated in clouding of 3.Details
g/f lobby- revision to pa # 200712170615: addition of exterior canopy, arcade ceiling painting, new lighting & signage. replacement of column wraps, new flooring in arcade and demolition of (e) tenants signage. all new work as indicated in clouding of 3. | $700,000 |
| Nov 26, 2007 | Completed final sign-off Jun 2008 | 650 California St | Gci, Inc | 23rd floor: non-structural demo of walls, partitions & doors to create vacant space for future t.i.Details
23rd floor: non-structural demo of walls, partitions & doors to create vacant space for future t.i. | $40,000 |
| Oct 24, 2007 | Completed final sign-off Nov 2009 | 640 Sutter St | Turner Construction Co | work in basement and common area. rev. to appl.#2006.08.17.9733. 1. repair (e) steel columns in alleyway-east side. 2. anchor bolt installation for slab reinstatement at (e) stair opening. 3. repairs to (e) level 1 conc. slab due to deteriroation. corrosion of reinforcing steel & concrete spacing.Details
work in basement and common area. rev. to appl.#2006.08.17.9733. 1. repair (e) steel columns in alleyway-east side. 2. anchor bolt installation for slab reinstatement at (e) stair opening. 3. repairs to (e) level 1 conc. slab due to deteriroation. corrosion of reinforcing steel & concrete spacing. | $3,000 |
| Aug 17, 2007 | Never finaled issued Mar 2008, no final | 493 Pine St | exterior work only under this permit - facade changes which incl steel channels, ceramic tile wainscot for walls, logo channel letters mounted on steel channel, sign under separate permit.Details
exterior work only under this permit - facade changes which incl steel channels, ceramic tile wainscot for walls, logo channel letters mounted on steel channel, sign under separate permit. | $20,000 | |
| Aug 7, 2007 | Completed final sign-off May 2008 | 505 Sansome St | non structural, mechanical & electrical improvement. bringing men's and women's restrooms to title 24 compliant condition. life safety differed.Details
non structural, mechanical & electrical improvement. bringing men's and women's restrooms to title 24 compliant condition. life safety differed. | $114,100 |