Block 0241, lot 025
650 California St
- City’s use
- Commercial Office
- Built
- 1963
- Stories
- 33
- Building
- 461,138 sq ft
- Lot
- 26,262 sq ft
- Zoning
- C3O
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
The 200 most recent permits filed for this property.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 14, 2026 | In progress issued Jul 2026 | 650 California St | Johnson Controls Fire | 22/fl-ref fire -26-989- modify (e) 2 way comm system. provide and install call box , 3 x emergency communiation signsDetails
22/fl-ref fire -26-989- modify (e) 2 way comm system. provide and install call box , 3 x emergency communiation signs | $750 |
| Jun 23, 2026 | In progress issued Jul 2026 | 650 California St | Richlen Construction | 27th floor: selective renovation and minor demolition. new construction includes floor, wall and ceiling finishes, power and lighting. fire sprinkler and alarm are deffered submittals.Details
27th floor: selective renovation and minor demolition. new construction includes floor, wall and ceiling finishes, power and lighting. fire sprinkler and alarm are deffered submittals. | $1,184,490 |
| Jun 22, 2026 | In progress issued Jun 2026 | 650 California St | Prima Acquire Inc Dba Lahue And Associat | 22nd floor: install (3) evacuation signsDetails
22nd floor: install (3) evacuation signs | |
| Jun 5, 2026 | Completed final sign-off Aug 2026 | 650 California St | Richlen Construction | 20th floor: mechanical and electrical work install 2 new cooling vav vox and ductwork air distribution. provide new lighting. ref 202602246378Details
20th floor: mechanical and electrical work install 2 new cooling vav vox and ductwork air distribution. provide new lighting. ref 202602246378 | $100,000 |
| Jun 4, 2026 | Completed final sign-off Nov 2026 | 650 California St | Skyline Construction | mechanical and electrical work for tenant improvement on 12th floor. ref. 202605111057Details
mechanical and electrical work for tenant improvement on 12th floor. ref. 202605111057 | $175,000 |
| May 21, 2026 | Completed final sign-off Sep 2026 | 650 California St | Skyline Construction | revision to pa#202512111537 ti revision of nono-stuct ceiling & lighting design. new const. to include non-structural ceiling & lighting, finishes and new ventless fireplace. all work interior only on 22/f: deferred mep and new ventless fireplace.Details
revision to pa#202512111537 ti revision of nono-stuct ceiling & lighting design. new const. to include non-structural ceiling & lighting, finishes and new ventless fireplace. all work interior only on 22/f: deferred mep and new ventless fireplace. | |
| May 11, 2026 | Completed final sign-off Nov 2026 | 650 California St | Skyline Construction | 12 flr: office t.i. including interior partitions, doors, finishes, ceiling, lights, millwork. seismic requirement for (9) new phone booths. mep deferred.Details
12 flr: office t.i. including interior partitions, doors, finishes, ceiling, lights, millwork. seismic requirement for (9) new phone booths. mep deferred. | $1,630,160 |
| Apr 6, 2026 | Completed final sign-off Nov 2026 | 650 California St | Skyline Construction | 22nd floor. mechanical and electrical for tenant improvement on the 22nd flr. ref#: 202512111537Details
22nd floor. mechanical and electrical for tenant improvement on the 22nd flr. ref#: 202512111537 | $290,000 |
| Mar 4, 2026 | Completed final sign-off Jul 2026 | 650 California St | Skyline Construction | 11th fl - demo non-structural wing walls. install of new power life safety & seismic bracing for 10 new phone booths. restroom & drinking fountain upgrades 20% of construction costDetails
11th fl - demo non-structural wing walls. install of new power life safety & seismic bracing for 10 new phone booths. restroom & drinking fountain upgrades 20% of construction cost | $35,000 |
| Feb 24, 2026 | Completed final sign-off Aug 2026 | 650 California St | Richlen Construction | ste# 2000/ 20th/f: selective demo & new const of interior partitions, doors, finishes, ceilings, lighting, electrical. scope of work included restroom accessibility upgrades. no exterior, site, landscaping or parking changes. fire life safety are deferredDetails
ste# 2000/ 20th/f: selective demo & new const of interior partitions, doors, finishes, ceilings, lighting, electrical. scope of work included restroom accessibility upgrades. no exterior, site, landscaping or parking changes. fire life safety are deferred | $707,557 |
| Dec 11, 2025 | Completed final sign-off Sep 2026 | 650 California St | Skyline Construction | 22nd fl:commercial ti,demolition of non-structural partitions,doors,ceiling &lighting,millwork & finishes throughout.new construction to include new non-structural partitions,door&glazing,ceiling & lighting, millwork & finishes.new mep to be design-build.all workto be interior only,no workDetails
22nd fl:commercial ti,demolition of non-structural partitions,doors,ceiling &lighting,millwork & finishes throughout.new construction to include new non-structural partitions,door&glazing,ceiling & lighting, millwork & finishes.new mep to be design-build.all workto be interior only,no work | $4,300,000 |
| Dec 10, 2025 | In progress issued Dec 2025 | 650 California St | Johnson Controls Fire | this is an as built permit for 202508213624. no new devices added. inspection comments to update evac matrix to reflect 30 and 31st is a combined floor.Details
this is an as built permit for 202508213624. no new devices added. inspection comments to update evac matrix to reflect 30 and 31st is a combined floor. | |
| Dec 5, 2025 | Completed final sign-off Dec 2025 | 650 California St | Johnson Controls Fire | 24th fl - as built for pa 202510318673 at inspector's request, plans add note for access controlDetails
24th fl - as built for pa 202510318673 at inspector's request, plans add note for access control | |
| Nov 18, 2025 | Completed final sign-off Dec 2025 | 650 California St | Golden Gate Fire Protection Inc | ground floor: relocate 3 uprights and add 2 uprights on the ground floor for new generator room. t.i. ref#202405021241Details
ground floor: relocate 3 uprights and add 2 uprights on the ground floor for new generator room. t.i. ref#202405021241 | $1,250 |
| Oct 31, 2025 | Completed final sign-off Dec 2025 | 650 California St | Johnson Controls Fire | 24th fl- provide and install (1) smoke detector, (8) speaker strobes (1) strobe. relocate and demo existing devices as planned. ref202307132056Details
24th fl- provide and install (1) smoke detector, (8) speaker strobes (1) strobe. relocate and demo existing devices as planned. ref202307132056 | $18,000 |
| Oct 8, 2025 | In progress issued Oct 2025 | 650 California St | Johnson Controls Fire | fire alarm modification: provide and install 2 duct detectors and 5 iams monitoring emergency generator machine devices as shown on drawings.Details
fire alarm modification: provide and install 2 duct detectors and 5 iams monitoring emergency generator machine devices as shown on drawings. | $3,500 |
| Oct 8, 2025 | In progress issued Oct 2025 | 650 California St | Johnson Controls Fire | 31st/fl: fire life safety: addition on the 31st floor lobby, add (2) smoke detection, add 1 sprinkler/strobes.Details
31st/fl: fire life safety: addition on the 31st floor lobby, add (2) smoke detection, add 1 sprinkler/strobes. | $2,000 |
| Oct 3, 2025 | In progress issued Oct 2025 | 650 California St | Ayoob & Peery Plumbing Co Inc | 30th and 31st flr. record as-built for bpa# 2025-0424-5182 fire sprinkers add (4) fire sprinkler per t.i. update drawings for adjusted piping plan job# 25-612. ref pa# 2024-1216-6915Details
30th and 31st flr. record as-built for bpa# 2025-0424-5182 fire sprinkers add (4) fire sprinkler per t.i. update drawings for adjusted piping plan job# 25-612. ref pa# 2024-1216-6915 | $2,484 |
| Sep 17, 2025 | Completed final sign-off May 2026 | 650 California St | Bcci Construction Company | 30th & 31st fl - revision to pa 202412166915 ref 202102164700 and 202305318876 updates the 320 sf elevator lobbies on level 30 & 31. new finishes and new lighting to replace existingDetails
30th & 31st fl - revision to pa 202412166915 ref 202102164700 and 202305318876 updates the 320 sf elevator lobbies on level 30 & 31. new finishes and new lighting to replace existing | $400,000 |
| Sep 15, 2025 | In progress issued Sep 2025 | 650 California St | Johnson Controls Fire | 33rd/fl: demo fire alarm deuices on the floor shown in the fire alarm plans per approved p/a 2025-0725-1650Details
33rd/fl: demo fire alarm deuices on the floor shown in the fire alarm plans per approved p/a 2025-0725-1650 | $1,500 |
| Aug 27, 2025 | Completed final sign-off Oct 2025 | 650 California St | Ayoob & Peery Plumbing Co Inc | 24th fl: add 30 relocate 30 fire sprinkler per t.i. 25th fl: add 8 relocate 8 fire sprinkelr per t.i. job #25-638 and ref #202505297483Details
24th fl: add 30 relocate 30 fire sprinkler per t.i. 25th fl: add 8 relocate 8 fire sprinkelr per t.i. job #25-638 and ref #202505297483 | $44,719 |
| Aug 21, 2025 | In progress issued Aug 2025 | 650 California St | Johnson Controls Fire | 30th & 31st/f: as-built ref 202505065871: no new devices added, only changes are device addresses update & combining access control relays into 1 replay due to install only 1 security panel. all changes are doubledDetails
30th & 31st/f: as-built ref 202505065871: no new devices added, only changes are device addresses update & combining access control relays into 1 replay due to install only 1 security panel. all changes are doubled | |
| Aug 14, 2025 | Completed final sign-off May 2026 | 650 California St | Bcci Construction Company | 30th & 31st/f: structural deferred permit for guardrail for interior staircase. ref 202412166915Details
30th & 31st/f: structural deferred permit for guardrail for interior staircase. ref 202412166915 | |
| Aug 6, 2025 | Completed final sign-off Sep 2025 | 650 California St | Anderson, Rowe & Buckley, Inc. | 33rd flr: fire protection t.i. change existing heads to uprights for demo permit. relocate/change out =103. ref#: pa#: 202507251650.Details
33rd flr: fire protection t.i. change existing heads to uprights for demo permit. relocate/change out =103. ref#: pa#: 202507251650. | $52,942 |
| Jul 25, 2025 | Completed final sign-off Sep 2025 | 650 California St | Novo Construction Inc | 33/f: interior demo of non-structural partit8iions , celing assenblies, light fixtures, milwork, finishes and associated mep infrastructure. ab-017.Details
33/f: interior demo of non-structural partit8iions , celing assenblies, light fixtures, milwork, finishes and associated mep infrastructure. ab-017. | $45,000 |
| Jun 16, 2025 | Completed final sign-off Mar 2026 | 650 California St | Bcci Construction Company | 24/f and 25/f: partial floor mechanical and electrical build to support approved architectural permit 202505297483.Details
24/f and 25/f: partial floor mechanical and electrical build to support approved architectural permit 202505297483. | $175,000 |
| May 29, 2025 | Completed final sign-off Mar 2026 | 650 California St | Bcci Construction Company | 24th & 25th/f: office t.i. renovation total 7912 sf. mep defferred. new patitions & officesDetails
24th & 25th/f: office t.i. renovation total 7912 sf. mep defferred. new patitions & offices | $715,000 |
| May 21, 2025 | In progress filed May 2025, not yet issued | 650 California St | Ayoob & Peery Plumbing Co Inc | installation of new rise pipe. installation of the dcw supply water piping fron the control valve at new dcw riser to the existing prv stations on the floors. job# 25-005Details
installation of new rise pipe. installation of the dcw supply water piping fron the control valve at new dcw riser to the existing prv stations on the floors. job# 25-005 | |
| May 6, 2025 | In progress issued May 2025 | 650 California St | Johnson Controls Fire | 30th & 31st fl:ref pa #2024-1216-6915 add 6 smoke detectors, 3 relays, 29 speaker/strobes, 3 strobe; 2 speakersDetails
30th & 31st fl:ref pa #2024-1216-6915 add 6 smoke detectors, 3 relays, 29 speaker/strobes, 3 strobe; 2 speakers | $27,700 |
| Apr 24, 2025 | Completed final sign-off Dec 2025 | 650 California St | Ayoob & Peery Plumbing Co Inc | 30/f - add 64, relocate 98 fire sprinkler per t.i. 31/f - add 1, relocate 6 fire sprinkler per t.i. ref permit 202412166915Details
30/f - add 64, relocate 98 fire sprinkler per t.i. 31/f - add 1, relocate 6 fire sprinkler per t.i. ref permit 202412166915 | $103,103 |
| Dec 16, 2024 | Completed final sign-off May 2026 | 650 California St | Bcci Construction Company | 30th & 31st fl ti: non structural partitions, ceilings, finishes & asccioated mep. work includes (n) convenience stairDetails
30th & 31st fl ti: non structural partitions, ceilings, finishes & asccioated mep. work includes (n) convenience stair | $2,200,000 |
| Oct 11, 2024 | Completed final sign-off Feb 2025 | 650 California St | Johnson Controls Fire | 28/f: rev 202408098300 to correct (e) condition of the smoke detection of the floors (e) return air fsd per inspector's comments. new new fsd has been added or modified.changes include to add 8 smoke detectors and 1 relay.Details
28/f: rev 202408098300 to correct (e) condition of the smoke detection of the floors (e) return air fsd per inspector's comments. new new fsd has been added or modified.changes include to add 8 smoke detectors and 1 relay. | $6,000 |
| Aug 21, 2024 | Completed final sign-off Aug 2024 | 650 California St | Ayoob & Peery Plumbing Co Inc | record as-built to pa#: 202408148671 adjust head count to match piping plan and fire sprinkler placements, removal of (1) pendant from plan set. ref#: 202311201081Details
record as-built to pa#: 202408148671 adjust head count to match piping plan and fire sprinkler placements, removal of (1) pendant from plan set. ref#: 202311201081 | |
| Aug 14, 2024 | Completed final sign-off Aug 2024 | 650 California St | Ayoob & Peery Plumbing Co Inc | 24/f: add 2 fire sprinkler . relocate 4 f/s per t.i. pa 202311201081.Details
24/f: add 2 fire sprinkler . relocate 4 f/s per t.i. pa 202311201081. | $3,106 |
| Aug 13, 2024 | In progress issued Aug 2024 | 650 California St | Durkin Signs & Graphics Inc | suite 2400 interior, electric, single faced wall sign "clearly gottlieb";Details
suite 2400 interior, electric, single faced wall sign "clearly gottlieb"; | $5,000 |
| Aug 9, 2024 | Completed final sign-off Feb 2025 | 650 California St | Johnson Controls Fire | ti ref 202404220445-mech pa 202405132023 28th/flr - to include addition of (2) detectors, 8 sprinklers/strobes, 4 speakers/strobes (wall) and 1 strobeDetails
ti ref 202404220445-mech pa 202405132023 28th/flr - to include addition of (2) detectors, 8 sprinklers/strobes, 4 speakers/strobes (wall) and 1 strobe | $12,000 |
| Aug 6, 2024 | Completed final sign-off Oct 2024 | 650 California St | Johnson Controls Fire | as-built to approved f/a 202406144531. add 1 duct detector & 1 smoke detector that was missed by jci in the design. ref pa 202312072109 & 202312132452Details
as-built to approved f/a 202406144531. add 1 duct detector & 1 smoke detector that was missed by jci in the design. ref pa 202312072109 & 202312132452 | $3,000 |
| Aug 6, 2024 | Completed final sign-off Oct 2024 | 650 California St | Edison Fire Extinguisher Company Inc | ul300 fire system installation ref pa 202312132452Details
ul300 fire system installation ref pa 202312132452 | $2,950 |
| Jul 26, 2024 | Completed final sign-off Aug 2024 | 650 California St | Ayoob & Peery Plumbing Co Inc | 24th fl: as built for pa # 2024-0312-7650 capture final locations at fire sprinkler heads. add (2) remove (9) from scope. job #24-613. ref pa 202311201081Details
24th fl: as built for pa # 2024-0312-7650 capture final locations at fire sprinkler heads. add (2) remove (9) from scope. job #24-613. ref pa 202311201081 | |
| Jul 10, 2024 | In progress issued Jul 2024 | 650 California St | Bcci Construction Company | rev 202312132452- 24th flr-to show two way communications devices in elevator lobby per sffd requestDetails
rev 202312132452- 24th flr-to show two way communications devices in elevator lobby per sffd request | |
| Jun 14, 2024 | Completed final sign-off Aug 2024 | 650 California St | Johnson Controls Fire | fire only:bpa# 2023-1207-2109: 2023-1213-2452: modify fa, add 2-way call boxes to f24 + f25: 24th: provide new devices: (2) speaker strobe, (1) strobe, (7) smoke detectors (1) heat detector, (1) nac panel, (3) duct detectors, (5) relays: 25th- 25 speakers strobes, 2 strobes, 7 smoke detectors, 1 nacDetails
fire only:bpa# 2023-1207-2109: 2023-1213-2452: modify fa, add 2-way call boxes to f24 + f25: 24th: provide new devices: (2) speaker strobe, (1) strobe, (7) smoke detectors (1) heat detector, (1) nac panel, (3) duct detectors, (5) relays: 25th- 25 speakers strobes, 2 strobes, 7 smoke detectors, 1 nac | $52,000 |
| Jun 11, 2024 | In progress issued Mar 2025 | 650 California St | Richlen Construction | retire (e) 450kw generator/fuel tank on roof. in garage, install (n) 500kw tier 2 generator w/ diesel particulate filter, free-standing fuel tank, automatic transfer switch, manual transfer switch, & distribution boards. construct new room to house generator. install new fuel pumping system toDetails
retire (e) 450kw generator/fuel tank on roof. in garage, install (n) 500kw tier 2 generator w/ diesel particulate filter, free-standing fuel tank, automatic transfer switch, manual transfer switch, & distribution boards. construct new room to house generator. install new fuel pumping system to | $1,786,903 |
| Jun 4, 2024 | Completed final sign-off Jul 2024 | 650 California St | Johnson Controls Fire | 8th floor: add 1 control relay for an existing heat pump. fls addition on 8th floor.Details
8th floor: add 1 control relay for an existing heat pump. fls addition on 8th floor. | $700 |
| May 22, 2024 | Completed final sign-off Nov 2024 | 650 California St | Bcci Construction Company | revision to pa# 202312132452: 24th fl - convert storage rooms to catering kitchen and dry storage. modifications to breakroom.Details
revision to pa# 202312132452: 24th fl - convert storage rooms to catering kitchen and dry storage. modifications to breakroom. | $70,000 |
| May 21, 2024 | Completed final sign-off Nov 2024 | 650 California St | Bcci Construction Company | revision to pa# 202312072109: 25/f - to include modifications to pantry and removal of drinking foundation.Details
revision to pa# 202312072109: 25/f - to include modifications to pantry and removal of drinking foundation. | $55,000 |
| May 13, 2024 | Completed final sign-off Feb 2025 | 650 California St | Bcci Construction Company | 28/f: mep to support approved arch permit. new heat pumps, vav boxes, ducts, lighting and plumbing. ref pa# 202404220445Details
28/f: mep to support approved arch permit. new heat pumps, vav boxes, ducts, lighting and plumbing. ref pa# 202404220445 | $815,000 |
| Apr 25, 2024 | Completed final sign-off Sep 2024 | 650 California St | Ayoob & Peery Plumbing Co Inc | 28th fl add 13, relocate 49 fire sprinkler per ti job 24-626 ref 202404220445Details
28th fl add 13, relocate 49 fire sprinkler per ti job 24-626 ref 202404220445 | $38,508 |
| Apr 22, 2024 | Completed final sign-off Feb 2025 | 650 California St | Bcci Construction Company | 28th fl scope includes construction of new interior partitcions, doors, frames, power data, act and lighting,millwork,finishes. currenty vacant shell. mep def, path trvl 202305318876, 28th fl restrms 202310118403Details
28th fl scope includes construction of new interior partitcions, doors, frames, power data, act and lighting,millwork,finishes. currenty vacant shell. mep def, path trvl 202305318876, 28th fl restrms 202310118403 | $2,355,840 |
| Mar 12, 2024 | Completed final sign-off May 2024 | 650 California St | Ayoob & Peery Plumbing Co Inc | ref pa# 202311201081 25th fl add (48) relocate (68) fire sprinkler job#24-613Details
ref pa# 202311201081 25th fl add (48) relocate (68) fire sprinkler job#24-613 | $72,048 |
| Mar 12, 2024 | Completed final sign-off Aug 2024 | 650 California St | Ayoob & Peery Plumbing Co Inc | ref pa# 202311201081 24th fl add (22) relocate (54) fire sprinklersDetails
ref pa# 202311201081 24th fl add (22) relocate (54) fire sprinklers | $47,204 |
| Feb 27, 2024 | In progress issued Feb 2024 | 650 California St | Johnson Controls Fire | ref 202401264707- as built permit for approved fire alarm. no additional devices were added only change is to correct device addresses of two smoke detectors per inspectors commentsDetails
ref 202401264707- as built permit for approved fire alarm. no additional devices were added only change is to correct device addresses of two smoke detectors per inspectors comments | |
| Feb 23, 2024 | Completed final sign-off May 2024 | 650 California St | Matrix Hg Inc | 27th fl ti using base building hvac system. modifications to air distribution system in tenant space to suite arch renovations, includidng installation of water source heat pump and associated ductwork. no new fire smoke dampers required. ref 202401123873 and 202310259410Details
27th fl ti using base building hvac system. modifications to air distribution system in tenant space to suite arch renovations, includidng installation of water source heat pump and associated ductwork. no new fire smoke dampers required. ref 202401123873 and 202310259410 | $45,000 |
| Feb 7, 2024 | Completed final sign-off Nov 2024 | 650 California St | Bcci Construction Company | 24+25/f: revision to pa2023-1120-1081 to document restroom re-design to be per subsequent issued permits under pa2023-1213-2452(24th) and 2023-1207-2109 (25th floor).Details
24+25/f: revision to pa2023-1120-1081 to document restroom re-design to be per subsequent issued permits under pa2023-1213-2452(24th) and 2023-1207-2109 (25th floor). | |
| Jan 26, 2024 | Completed final sign-off Mar 2024 | 650 California St | Johnson Controls Fire | ref pa 202310118403 28th fl. fa modification: add (3) new speaker and strobes. remove (2) strobes and (2) speakers. relocate (2) speaker and strobes, (2) smoke detectors and (1) pull stationDetails
ref pa 202310118403 28th fl. fa modification: add (3) new speaker and strobes. remove (2) strobes and (2) speakers. relocate (2) speaker and strobes, (2) smoke detectors and (1) pull station | $1,900 |
| Jan 18, 2024 | Completed final sign-off Feb 2024 | 650 California St | Johnson Controls Fire | 27/f: fa modification, add 3 speaker/strobes, relocate 3 speaker/strobes. ref pa# 202310259410.Details
27/f: fa modification, add 3 speaker/strobes, relocate 3 speaker/strobes. ref pa# 202310259410. | $650 |
| Jan 12, 2024 | Completed final sign-off May 2024 | 650 California St | Matrix Hg Inc | 27/f: ti using the (e) base building hvac system. modifications to the air distribution system in the tenant space to suit architectural renovations, including installation of new vav boxes and installation of new ductwork, no new fire smoke dampers required. building permit# 202310259410.Details
27/f: ti using the (e) base building hvac system. modifications to the air distribution system in the tenant space to suit architectural renovations, including installation of new vav boxes and installation of new ductwork, no new fire smoke dampers required. building permit# 202310259410. | $69,848 |
| Jan 9, 2024 | Completed final sign-off Jun 2024 | 650 California St | Gci, Inc | 10th & 11th /f: t.i. to (e) office: 7 new phone booths on fl 10. electricalf outlets alteration on 10 & 11 fl. light fixture replacement. no change in occupancyDetails
10th & 11th /f: t.i. to (e) office: 7 new phone booths on fl 10. electricalf outlets alteration on 10 & 11 fl. light fixture replacement. no change in occupancy | $42,000 |
| Jan 5, 2024 | In progress issued Jan 2024 | 650 California St | Capitol Electric Const | ste 2750: office tenant retrofit: light fixtures and associated circuiting, controls, power and signal devices and associated wiring.Details
ste 2750: office tenant retrofit: light fixtures and associated circuiting, controls, power and signal devices and associated wiring. | $32,638 |
| Jan 3, 2024 | Completed final sign-off Jul 2024 | 650 California St | Gci, Inc | 28th fl - mechanical install (1) vav box, ductowrk for new floor layout; electrical - power & lighting. ref pa 2023-1011-8403Details
28th fl - mechanical install (1) vav box, ductowrk for new floor layout; electrical - power & lighting. ref pa 2023-1011-8403 | $100,000 |
| Dec 19, 2023 | Completed final sign-off Jan 2024 | 650 California St | 28/f: fire sprinkler system, relocated ssp: 09, deleted sprinkler: 02, new ssp: 02, relocated ssu: 10, new ssu: 05, ref pa# 202310118403.Details
28/f: fire sprinkler system, relocated ssp: 09, deleted sprinkler: 02, new ssp: 02, relocated ssu: 10, new ssu: 05, ref pa# 202310118403. | $8,000 | |
| Dec 13, 2023 | Completed final sign-off Oct 2024 | 650 California St | Bcci Construction Company | 24th fl - selective demo and construction of non load bearing partitions, new door, frame & glazing, new suspended ceilings, ne light fixtures, new millwork and new finishesDetails
24th fl - selective demo and construction of non load bearing partitions, new door, frame & glazing, new suspended ceilings, ne light fixtures, new millwork and new finishes | $2,000,000 |
| Dec 7, 2023 | Completed final sign-off Oct 2024 | 650 California St | Bcci Construction Company | 25/f. demo and construction of non load bearing partition, new door, frames and glazing, new suspended ceiling, new light fixtures new millwork and new finishes, mep included.Details
25/f. demo and construction of non load bearing partition, new door, frames and glazing, new suspended ceiling, new light fixtures new millwork and new finishes, mep included. | $1,500,000 |
| Nov 27, 2023 | Completed final sign-off Jan 2024 | 650 California St | Ayoob & Peery Plumbing Co Inc | 24/f & 25/f: on 24/f add 8 relocate 6 fire sprinkler per ti. on 25th fl: add 1 relocate 4 fire sprnkler per ti job 23-694. 24/f: changeout 14, 25/f: changeout 26Details
24/f & 25/f: on 24/f add 8 relocate 6 fire sprinkler per ti. on 25th fl: add 1 relocate 4 fire sprnkler per ti job 23-694. 24/f: changeout 14, 25/f: changeout 26 | $21,648 |
| Nov 20, 2023 | Completed final sign-off Nov 2024 | 650 California St | Bcci Construction Company | soft demo at suite 2400 which includes portion of 24th fl and all of 25th fl. remodel 24th and 25th flr restrooms. 24th floor: extended corridor with carpet, paint, extended ceiling grid. mep and life safety deferred.Details
soft demo at suite 2400 which includes portion of 24th fl and all of 25th fl. remodel 24th and 25th flr restrooms. 24th floor: extended corridor with carpet, paint, extended ceiling grid. mep and life safety deferred. | $109,144 |
| Nov 14, 2023 | Completed final sign-off Dec 2023 | 650 California St | 27th fl - fire sprinkler permit, relocate 9, add 3 and delete 1 sprinkler. ref pa 202310259410Details
27th fl - fire sprinkler permit, relocate 9, add 3 and delete 1 sprinkler. ref pa 202310259410 | $3,000 | |
| Nov 3, 2023 | Never finaled issued Nov 2023, no final | 650 California St | Johnson Controls Fire | 8/f: fire alarm modification: add 1 control relay. relocate 2 speaker/strobe. remove 2 speaker/strobe. adjust 1 storbe to 110cd.Details
8/f: fire alarm modification: add 1 control relay. relocate 2 speaker/strobe. remove 2 speaker/strobe. adjust 1 storbe to 110cd. | $800 |
| Oct 25, 2023 | Completed final sign-off Apr 2024 | 650 California St | Richlen Construction | 27th fl:interior demolition of select partitions, finishes, and ceilings. relocation of some (e) light fixtures to accomodate new layout. new construction includes new private offices and dropped ceiling with lighting. patching of (e) finishes. mep and fls are deffered submittals.Details
27th fl:interior demolition of select partitions, finishes, and ceilings. relocation of some (e) light fixtures to accomodate new layout. new construction includes new private offices and dropped ceiling with lighting. patching of (e) finishes. mep and fls are deffered submittals. | $284,292 |
| Oct 11, 2023 | Completed final sign-off Jul 2024 | 650 California St | Gci, Inc | 28/f: interior demolition and new construction of non-structural elements including interior partitions, doors, finishes, ceilings, lighting, mechanical and electrical outlets and switches as well as restroom accessiblity upgrades. mechanical and electrical under separate permit.Details
28/f: interior demolition and new construction of non-structural elements including interior partitions, doors, finishes, ceilings, lighting, mechanical and electrical outlets and switches as well as restroom accessiblity upgrades. mechanical and electrical under separate permit. | $470,275 |
| Oct 4, 2023 | Completed final sign-off Oct 2023 | 650 California St | Ayoob & Peery Plumbing Co Inc | 8/f: relocate 4 fire sprikler per ti, ref pa# 202308164542.Details
8/f: relocate 4 fire sprikler per ti, ref pa# 202308164542. | $2,484 |
| Sep 18, 2023 | Completed final sign-off Dec 2023 | 650 California St | Novo Construction Inc | 8/f: mechanical and electrical work for tenant improvment, re pa# 202308164542Details
8/f: mechanical and electrical work for tenant improvment, re pa# 202308164542 | $22,000 |
| Aug 16, 2023 | Completed final sign-off Dec 2023 | 650 California St | Novo Construction Inc | 8/f: t.i., full floor occupancy, selective interior nonstructural demo/construction of partitions, millwork, door, ceiling, lighting & finishes. no change in occupancy/areaDetails
8/f: t.i., full floor occupancy, selective interior nonstructural demo/construction of partitions, millwork, door, ceiling, lighting & finishes. no change in occupancy/area | $185,000 |
| Jul 13, 2023 | Never finaled filed Jul 2023, never issued | 650 California St | 24-25/f:interior demo of non-structural elements including interior partitions, doors,finishes,ceilings, lighting, mechanical, electrical and switches. existing communicating stair to remain. fire sprinkler modification permit 202307101792.Details
24-25/f:interior demo of non-structural elements including interior partitions, doors,finishes,ceilings, lighting, mechanical, electrical and switches. existing communicating stair to remain. fire sprinkler modification permit 202307101792. | $620,000 | |
| Jul 10, 2023 | Expired or cancelled cancelled Feb 2024 | 650 California St | Golden Gate Fire Protection Inc | fire sprinkler ti: relocate 95 upright sprinklers on each floor: 24th and 25th floor. total 190 heads per nfpa 13.Details
fire sprinkler ti: relocate 95 upright sprinklers on each floor: 24th and 25th floor. total 190 heads per nfpa 13. | $123,500 |
| May 31, 2023 | Completed final sign-off Apr 2024 | 650 California St | Richlen Construction | upgrades only to the building path of travel to meet current code compliances. ab-056. mep, fire/lifesafety and fire sprinkler system is under sep permit. includes primary bldg entry, parking, ev charging and elevators (restrooms at all levels not included)Details
upgrades only to the building path of travel to meet current code compliances. ab-056. mep, fire/lifesafety and fire sprinkler system is under sep permit. includes primary bldg entry, parking, ev charging and elevators (restrooms at all levels not included) | $30,000 |
| Mar 16, 2023 | Expired or cancelled cancelled Jan 2026 | 650 California St | install 13 prefabricated phone booths: floors 4, 5, 6, 7Details
install 13 prefabricated phone booths: floors 4, 5, 6, 7 | $22,500 | |
| Feb 1, 2023 | Never finaled issued Feb 2023, no final | 650 California St | Johnson Controls Fire | 16/f: provide (1) new call emergency communication call station, (1) duct detector, (2) in duct smoke detectors, (1) smoke detector, (11) speaker strobes, (1) strobes, (2) speakers, (1) call box, (1) instructional signage. ref permit 202202158012Details
16/f: provide (1) new call emergency communication call station, (1) duct detector, (2) in duct smoke detectors, (1) smoke detector, (11) speaker strobes, (1) strobes, (2) speakers, (1) call box, (1) instructional signage. ref permit 202202158012 | $4,000 |
| Jun 21, 2022 | Never finaled issued Jun 2022, no final | 650 California St | Acco Engineered Systems Inc. Dba Acco En | 22nd fl: install new water-source heat pump in i.t. room.Details
22nd fl: install new water-source heat pump in i.t. room. | $50,000 |
| May 6, 2022 | Completed final sign-off Aug 2022 | 650 California St | Marchetti Group | ste #2000- ref to t.i. 202202188311. install 1 new cooling only vav. rework lowside deckwork and rebalance vav's as req. install 1 new wshp to serve it room.Details
ste #2000- ref to t.i. 202202188311. install 1 new cooling only vav. rework lowside deckwork and rebalance vav's as req. install 1 new wshp to serve it room. | $34,100 |
| Apr 6, 2022 | Completed final sign-off Jun 2022 | 650 California St | Pioneer Fire Inc. | 20/f: relocate/convert existing pendents, convert some to uprights. ref gcti permit 202202188311.Details
20/f: relocate/convert existing pendents, convert some to uprights. ref gcti permit 202202188311. | $2,000 |
| Feb 18, 2022 | Completed final sign-off Jul 2022 | 650 California St | Marchetti Group | commercial tenant imrovment of e office space. adding new rooms to include new doors, walls, ceiling reconfiguration, relocation of e light fixtures, addition of new light fixtures, minor reconfiguration of hvac, addition of vanity sink to mothers roomDetails
commercial tenant imrovment of e office space. adding new rooms to include new doors, walls, ceiling reconfiguration, relocation of e light fixtures, addition of new light fixtures, minor reconfiguration of hvac, addition of vanity sink to mothers room | $398,926 |
| Feb 15, 2022 | Completed final sign-off Mar 2023 | 650 California St | Johnson Controls Fire | modify (e) f/a system, install two-way com-elevator landing 16/f, (1) duck, (2) in-duct smoke detectors, (1) smoke detector, (11) speaker strobes, (1) strobe, (2) speakers. ref t.i. bpa # 202110190743Details
modify (e) f/a system, install two-way com-elevator landing 16/f, (1) duck, (2) in-duct smoke detectors, (1) smoke detector, (11) speaker strobes, (1) strobe, (2) speakers. ref t.i. bpa # 202110190743 | $10,600 |
| Feb 11, 2022 | Completed final sign-off Apr 2023 | 650 California St | Richlen Construction | mep associated with pa# 2021-1019-0743Details
mep associated with pa# 2021-1019-0743 | $500,000 |
| Jan 12, 2022 | Never finaled issued Jan 2022, no final | 650 California St | submittal to memorialize the correct occupant load of breakroom for sffd assembly permit. ref permit 201911056459.Details
submittal to memorialize the correct occupant load of breakroom for sffd assembly permit. ref permit 201911056459. | ||
| Jan 4, 2022 | Completed final sign-off Jan 2022 | 650 California St | Golden Gate Fire Protection Inc | 16th fl - fire sprinkler relocate 98 pendant sprinklers. ref pa 2021-1019-0743Details
16th fl - fire sprinkler relocate 98 pendant sprinklers. ref pa 2021-1019-0743 | $51,450 |
| Dec 10, 2021 | Never finaled filed Dec 2021, never issued | 650 California St | Golden Gate Fire Protection Inc | fire sprinkler add 4 pendent sprinklers in new phone booths on the 27th fl. ref pa 2021-0608-1949Details
fire sprinkler add 4 pendent sprinklers in new phone booths on the 27th fl. ref pa 2021-0608-1949 | $1,000 |
| Nov 10, 2021 | Completed final sign-off Nov 2021 | 650 California St | Johnson Controls Fire | 26/f: rev pa202109178685. add 1 2-way comm call station in elvator lobby per plans. (e) 2-way comm apporved under pa20180419679.Details
26/f: rev pa202109178685. add 1 2-way comm call station in elvator lobby per plans. (e) 2-way comm apporved under pa20180419679. | $2,600 |
| Oct 19, 2021 | Completed final sign-off Apr 2023 | 650 California St | Richlen Construction | 16/f: interior demolition & new construction of non-structural elements inlcuding inteiror partitions, door, finishes, celiing,slighting, mechanica & electrical outlets & switches. also inlcudes restroom accessibility upgrades. mep & fire life safety deferred.Details
16/f: interior demolition & new construction of non-structural elements inlcuding inteiror partitions, door, finishes, celiing,slighting, mechanica & electrical outlets & switches. also inlcudes restroom accessibility upgrades. mep & fire life safety deferred. | $500,000 |
| Sep 17, 2021 | Never finaled issued Oct 2021, no final | 650 California St | Johnson Controls Fire | 26/f: mod (e) fire alarm system. install 2 strobes, 3 speaker strobes and relocate 1 speaker strobe. ref ti pa202106081949. maher n/a.Details
26/f: mod (e) fire alarm system. install 2 strobes, 3 speaker strobes and relocate 1 speaker strobe. ref ti pa202106081949. maher n/a. | $1,500 |
| Sep 7, 2021 | Completed final sign-off Dec 2021 | 650 California St | Gci, Inc | deferred mech and electrical for t.i. t.i permit 202106081949. 26/fDetails
deferred mech and electrical for t.i. t.i permit 202106081949. 26/f | |
| Sep 2, 2021 | Completed final sign-off Nov 2021 | 650 California St | Johnson Controls Fire | fire alarm system modification to (e) system. remove,relocate,replace devices like for like. 11 smoke detectors, 3 manual pull stations, 2 dual replay, 33 speakers strobes and 5 strobes. 9 smokes. ref t.i. 202103116420.Details
fire alarm system modification to (e) system. remove,relocate,replace devices like for like. 11 smoke detectors, 3 manual pull stations, 2 dual replay, 33 speakers strobes and 5 strobes. 9 smokes. ref t.i. 202103116420. | $10,900 |
| Aug 2, 2021 | Completed final sign-off Nov 2021 | 650 California St | Golden Gate Fire Protection Inc | fire sprinklers, relocate 8 pendent sprinklers on 26th fl 202106081949Details
fire sprinklers, relocate 8 pendent sprinklers on 26th fl 202106081949 | $4,200 |
| Jul 12, 2021 | Completed final sign-off Sep 2021 | 650 California St | Richlen Construction | 28th floor: demo of non-structural partitions, millwork, finishes extg suspended ceiling grid and light fixtures. extg sprinklers heads will be turned up as part of this scope. ab-017 sprinkler subs app# 202107083943Details
28th floor: demo of non-structural partitions, millwork, finishes extg suspended ceiling grid and light fixtures. extg sprinklers heads will be turned up as part of this scope. ab-017 sprinkler subs app# 202107083943 | $45,000 |
| Jul 8, 2021 | Completed final sign-off Sep 2021 | 650 California St | Golden Gate Fire Protection Inc | 28th floor: fire sprinklers, relocate 91 upright sprinklers for demo permit.Details
28th floor: fire sprinklers, relocate 91 upright sprinklers for demo permit. | $47,775 |
| Jun 21, 2021 | Completed final sign-off Sep 2022 | 650 California St | Johnson Controls Fire | modify existing fire alarm system per tenant improvement. 20th & 21st floors. (2) new speaker strobes and revise notification zone per tenant stair infill. ref tii: 2021-0311-6420Details
modify existing fire alarm system per tenant improvement. 20th & 21st floors. (2) new speaker strobes and revise notification zone per tenant stair infill. ref tii: 2021-0311-6420 | $10,900 |
| Jun 8, 2021 | Completed final sign-off Nov 2021 | 650 California St | Gci, Inc | 26th floor t.i. consisting of non structural interior partitions, new finishes, lighting and plumbing.Details
26th floor t.i. consisting of non structural interior partitions, new finishes, lighting and plumbing. | $372,212 |
| May 11, 2021 | Completed final sign-off Aug 2021 | 650 California St | Ayoob & Peery Plumbing Co Inc | 20th fl: add (1) and relocate (1) sprinkler per t.i. ref #: 2021-0311-6420 job #: 21-627Details
20th fl: add (1) and relocate (1) sprinkler per t.i. ref #: 2021-0311-6420 job #: 21-627 | $750 |
| Apr 27, 2021 | Completed final sign-off Nov 2021 | 650 California St | Johnson Controls Fire | modify existing fire alarm system 31st floor. provide, replace like for like: (3) manual pull station, (2) dual relay iam, (33) speaker/strobes and (5) strobes. ref to ti: 2021-0216-4700Details
modify existing fire alarm system 31st floor. provide, replace like for like: (3) manual pull station, (2) dual relay iam, (33) speaker/strobes and (5) strobes. ref to ti: 2021-0216-4700 | $24,500 |
| Apr 21, 2021 | Completed final sign-off Apr 2022 | 650 California St | Bcci Construction Company | 31st fl: structural onlly installation of the support framing for an operable partition. ref pa 202102164700.Details
31st fl: structural onlly installation of the support framing for an operable partition. ref pa 202102164700. | $15,000 |
| Apr 13, 2021 | Completed final sign-off Jun 2021 | 650 California St | Golden Gate Fire Protection Inc | fire sprinkler; relocate 103 pendent sprinklers on the 31st floor t.i. ref # 2021-0216-4700Details
fire sprinkler; relocate 103 pendent sprinklers on the 31st floor t.i. ref # 2021-0216-4700 | $51,500 |
| Mar 11, 2021 | Completed final sign-off Oct 2022 | 650 California St | Dome Construction Corp | demo of existing interconnecting stairway.infill of slab at previous stair opening. light finishDetails
demo of existing interconnecting stairway.infill of slab at previous stair opening. light finish | $200,000 |
| Feb 16, 2021 | Completed final sign-off Apr 2022 | 650 California St | Bcci Construction Company | 31st floor: new non-structural partitions, ceilings and finishes. mep included. life safety deferred.Details
31st floor: new non-structural partitions, ceilings and finishes. mep included. life safety deferred. | $1,100,000 |
| Sep 10, 2020 | Completed final sign-off May 2021 | 650 California St | Bcci Construction Company | revision to pa #2019-1126-8224. combined rooms 3330, 3334-3340 into open office 3329, other misc. mep changes.Details
revision to pa #2019-1126-8224. combined rooms 3330, 3334-3340 into open office 3329, other misc. mep changes. | |
| Jun 12, 2020 | Never finaled issued Jul 2020, no final | 650 California St | Anderson, Rowe & Buckley, Inc. | 31/f:relocate (2) fire sprinkler heads. stair being infilled under 201911137147. ar&b to remove for demo, leave upright spirnkler under (e) deck for protection during in-fill proecess and then provide code compliant coverage after ceiling curing process/installed. maher n/a.Details
31/f:relocate (2) fire sprinkler heads. stair being infilled under 201911137147. ar&b to remove for demo, leave upright spirnkler under (e) deck for protection during in-fill proecess and then provide code compliant coverage after ceiling curing process/installed. maher n/a. | $1,000 |
| Jun 12, 2020 | Never finaled issued Nov 2020, no final | 650 California St | Johnson Controls Fire | 22/f: like-for-like replacement of notification appliances, (2) manual pull boxes, and (1) smoke sensor due to remodel of the 22nd floor. existing devices & equipment in the core areas (nic) to remain.Details
22/f: like-for-like replacement of notification appliances, (2) manual pull boxes, and (1) smoke sensor due to remodel of the 22nd floor. existing devices & equipment in the core areas (nic) to remain. | $2,300 |
| Mar 4, 2020 | Expired or cancelled cancelled Mar 2021 | 650 California St | Principal Builders Inc. | 26th fl: partial floor ti to demo and construct new partitions, finishes, doors, ceilings, millwork. mep, ls, sprinklers under sep permitDetails
26th fl: partial floor ti to demo and construct new partitions, finishes, doors, ceilings, millwork. mep, ls, sprinklers under sep permit | $697,000 |
| Mar 4, 2020 | Never finaled issued Mar 2020, no final | 650 California St | Richlen Construction | revision to #202001212386. provide new lighting & branch circuiting to existing panel. maintained some existing power & signal outlets and provided new power branch circuiting/raceway system as required to new power signal outlets. provide title 24. 29th flDetails
revision to #202001212386. provide new lighting & branch circuiting to existing panel. maintained some existing power & signal outlets and provided new power branch circuiting/raceway system as required to new power signal outlets. provide title 24. 29th fl | $40,000 |
| Mar 4, 2020 | Completed final sign-off Jul 2020 | 650 California St | Richlen Construction | revision to pa #202001131736, ti includes providing non-structural partitions. 29th flDetails
revision to pa #202001131736, ti includes providing non-structural partitions. 29th fl | $10,000 |
| Feb 28, 2020 | Completed final sign-off Mar 2021 | 650 California St | Johnson Controls Fire | fire alarm ti on 33rd fl ref 201911268224. in stall 5 smoke, 8 conv smoke detectors, 3 pull stations, 13 duct smokes, 1 induct, 3 module zam, 1 relay module, 9 strobes, 29 speaker strobesDetails
fire alarm ti on 33rd fl ref 201911268224. in stall 5 smoke, 8 conv smoke detectors, 3 pull stations, 13 duct smokes, 1 induct, 3 module zam, 1 relay module, 9 strobes, 29 speaker strobes | $46,800 |
| Feb 13, 2020 | Completed final sign-off Mar 2021 | 650 California St | Johnson Controls Fire | fire alarm ti on 32nd fl; ref pa #201911137142. install 13 smoke sensors, 3 pull stations, 22 duct detectors, 5 monitor modules, 1 relay, 35 notification appliances. in stall 1 new 2-way call box for existing 2-way ecs system.Details
fire alarm ti on 32nd fl; ref pa #201911137142. install 13 smoke sensors, 3 pull stations, 22 duct detectors, 5 monitor modules, 1 relay, 35 notification appliances. in stall 1 new 2-way call box for existing 2-way ecs system. | $46,000 |
| Feb 6, 2020 | Completed final sign-off Sep 2020 | 650 California St | Pacific Coast Trane Service Co. | replace existing 300 ton cooling tower, serving heat pump loop, with new 300 ton cooling tower, associated piping & electrical.Details
replace existing 300 ton cooling tower, serving heat pump loop, with new 300 ton cooling tower, associated piping & electrical. | $369,000 |
| Feb 5, 2020 | Never finaled issued Feb 2020, no final | 650 California St | Intelligent Technologies & Services Inc | 32nd fl-install pre-action detection and notification equipments for a mdf room.Details
32nd fl-install pre-action detection and notification equipments for a mdf room. | $19,933 |
| Jan 28, 2020 | Completed final sign-off Jul 2020 | 650 California St | Richlen Construction | 29th fl - provide and install new vav, duct, grills and equipment per hvac plans and balance as needed. ref pa #202001131736Details
29th fl - provide and install new vav, duct, grills and equipment per hvac plans and balance as needed. ref pa #202001131736 | $40,000 |
| Jan 27, 2020 | Completed final sign-off Apr 2020 | 650 California St | Golden Gate Fire Protection Inc | ref ti 2020-0113-1736: fire sprinkler: relocate 4 fire sprinkler pendents in suite # 2950.Details
ref ti 2020-0113-1736: fire sprinkler: relocate 4 fire sprinkler pendents in suite # 2950. | $2,000 |
| Jan 21, 2020 | Completed final sign-off Jul 2020 | 650 California St | Richlen Construction | provide new ligting and branch circut to (e) panel, maintained some of the (e) power and signal outlets and provide additional new power and raceway systems as required to new power and signal outlets, provide ca t-24 compliance formsDetails
provide new ligting and branch circut to (e) panel, maintained some of the (e) power and signal outlets and provide additional new power and raceway systems as required to new power and signal outlets, provide ca t-24 compliance forms | $15,000 |
| Jan 13, 2020 | Completed final sign-off Jul 2020 | 650 California St | Richlen Construction | 29th fl, ste 2950 - ti building of (n) non-structural partitions. electrical included. bldg is fully sprinklered (mech, plumbing, life safety & sprinklers under separate permit if needed)Details
29th fl, ste 2950 - ti building of (n) non-structural partitions. electrical included. bldg is fully sprinklered (mech, plumbing, life safety & sprinklers under separate permit if needed) | $70,000 |
| Jan 10, 2020 | Completed final sign-off Feb 2020 | 650 California St | Acco Engineered Systems Inc. Dba Acco En | 2nd floor - replace existing fire dampers with new like for like. existing fire dampers previously removed by others.Details
2nd floor - replace existing fire dampers with new like for like. existing fire dampers previously removed by others. | $50,000 |
| Jan 7, 2020 | Completed final sign-off Jul 2020 | 650 California St | Anderson, Rowe & Buckley, Inc. | 32nd fl - 7 added & 129 relocated sprinklers, 11 removed sprinklers; 33rd fl - 2 added & 131 relocated sprinklers, 6 removed sprinklersDetails
32nd fl - 7 added & 129 relocated sprinklers, 11 removed sprinklers; 33rd fl - 2 added & 131 relocated sprinklers, 6 removed sprinklers | $13,000 |
| Nov 26, 2019 | Completed final sign-off May 2021 | 650 California St | Bcci Construction Company | 33rd fl - ti work includes demo of existing tenant walls, ceiling. new drywall and demountable galss partitions, furn and finishes for offices. break room for employee use onlyDetails
33rd fl - ti work includes demo of existing tenant walls, ceiling. new drywall and demountable galss partitions, furn and finishes for offices. break room for employee use only | $4,678,605 |
| Nov 13, 2019 | Completed final sign-off May 2021 | 650 California St | Bcci Construction Company | demo of (e) communicating stair between floors 32-33 and floor slab infill on 33rd fl. fire and life safety system to remain in tact n/a maherDetails
demo of (e) communicating stair between floors 32-33 and floor slab infill on 33rd fl. fire and life safety system to remain in tact n/a maher | $10,000 |
| Nov 13, 2019 | Completed final sign-off Jul 2021 | 650 California St | Bcci Construction Company | addition of (4) supplental mechanical rooftop units (e) fire and life safety system to remain intact n/a maher (ref: 201911268224 for ti)Details
addition of (4) supplental mechanical rooftop units (e) fire and life safety system to remain intact n/a maher (ref: 201911268224 for ti) | $10,000 |
| Nov 13, 2019 | Completed final sign-off Jul 2021 | 650 California St | Bcci Construction Company | rev to pa# 201911056459; 32nd fl. revised door schedule and finished plans revised wall type from 2-hour to 1-hour at mdf room. include mep n/a maherDetails
rev to pa# 201911056459; 32nd fl. revised door schedule and finished plans revised wall type from 2-hour to 1-hour at mdf room. include mep n/a maher | |
| Nov 13, 2019 | Completed final sign-off Jul 2021 | 650 California St | Bcci Construction Company | demo of (e) stair between floors 31-32 and adjacent finishes and floor, elevations to match (e) floor elevations, fire and life safety system to remain intact n/a maherDetails
demo of (e) stair between floors 31-32 and adjacent finishes and floor, elevations to match (e) floor elevations, fire and life safety system to remain intact n/a maher | $10,000 |
| Nov 5, 2019 | Completed final sign-off May 2021 | 650 California St | Bcci Construction Company | 32nd floor: demo extg walls and ceilings. new drywall and demountable glass partitions, furn, and finishes for officers.Details
32nd floor: demo extg walls and ceilings. new drywall and demountable glass partitions, furn, and finishes for officers. | $4,000,000 |
| Nov 4, 2019 | Completed final sign-off Nov 2019 | 650 California St | Anderson, Rowe & Buckley, Inc. | 28th fl - ref pa 2019-0930-3110 (e) fire sprinkler system ti added 3 srpinklersDetails
28th fl - ref pa 2019-0930-3110 (e) fire sprinkler system ti added 3 srpinklers | $1,500 |
| Oct 29, 2019 | Expired or cancelled cancelled Jan 2026 | 650 California St | Bcci Construction Company | 32nd fl; remove non-structural partitons, plumbing, outlets, fixtures and finishes n/a maherDetails
32nd fl; remove non-structural partitons, plumbing, outlets, fixtures and finishes n/a maher | $75,000 |
| Sep 30, 2019 | Completed final sign-off Dec 2019 | 650 California St | Bcci Construction Company | 28th fl - work inlcudes selective removal of furniture, light fixture, relocateion and power relocation. new drywall, furniture and finishesDetails
28th fl - work inlcudes selective removal of furniture, light fixture, relocateion and power relocation. new drywall, furniture and finishes | $135,000 |
| Sep 10, 2019 | Never finaled issued Sep 2019, no final | 650 California St | Johnson Controls Fire | fire alarm: install 1 relay module to release access control system. 2 way communication: install one call box on the 3rd flr anbd connect on the ecsDetails
fire alarm: install 1 relay module to release access control system. 2 way communication: install one call box on the 3rd flr anbd connect on the ecs | $5,809 |
| Sep 5, 2019 | Expired or cancelled cancelled Aug 2023 | 650 California St | Johnson Controls Fire | fire alarm provide and add 1 2 way emergency communicatio call box to the ecs and add 1 relay iam module to the fire alarm system for access control system door releasingDetails
fire alarm provide and add 1 2 way emergency communicatio call box to the ecs and add 1 relay iam module to the fire alarm system for access control system door releasing | $5,809 |
| Sep 4, 2019 | Never finaled issued Sep 2019, no final | 650 California St | Skyline Construction | 1st fl - change of use for annex from b business to a2 assembly. ti ref pa 2018-0130-9904Details
1st fl - change of use for annex from b business to a2 assembly. ti ref pa 2018-0130-9904 | |
| Aug 2, 2019 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | rev to pa 201902041949; add heat pumpDetails
rev to pa 201902041949; add heat pump | |
| Jun 14, 2019 | Never finaled issued Jun 2019, no final | 650 California St | Johnson Controls Fire | 21st fl: add one call box to the existing 2-way emergency communication system call box located on the 21st fl in the elevator lobby.Details
21st fl: add one call box to the existing 2-way emergency communication system call box located on the 21st fl in the elevator lobby. | $5,281 |
| May 31, 2019 | Completed final sign-off Aug 2019 | 650 California St | Johnson Controls Fire | add 1 duct detector on the new heat pump unit on 8th flr which detects smoke alarm and shutdown the unit ref 201811206389Details
add 1 duct detector on the new heat pump unit on 8th flr which detects smoke alarm and shutdown the unit ref 201811206389 | $1,584 |
| May 20, 2019 | Never finaled issued Sep 2019, no final | 650 California St | Skyline Construction | 12th flr, revision to add emergency door release.Details
12th flr, revision to add emergency door release. | $1,000 |
| Apr 16, 2019 | Expired or cancelled cancelled May 2019 | 650 California St | Johnson Controls Fire | admin permit to correct job valuation to total $60,000. ref 201808107077 (original job valuation was $17,000)Details
admin permit to correct job valuation to total $60,000. ref 201808107077 (original job valuation was $17,000) | $43,000 |
| Apr 3, 2019 | Completed final sign-off Jun 2019 | 650 California St | Gci, Inc | suite 2950: mechanical: install new ducts, grilles, vav boxes & air balance. electrical: connect power to new or relocated light fixtures, power outlets & tenant equipment. title 24 compliance. maher n/a.Details
suite 2950: mechanical: install new ducts, grilles, vav boxes & air balance. electrical: connect power to new or relocated light fixtures, power outlets & tenant equipment. title 24 compliance. maher n/a. | $268,000 |
| Apr 3, 2019 | Completed final sign-off Apr 2019 | 650 California St | Skyline Construction | electrical work for ti on level 1 ref 201801309904 mahre na. applicant states no new fsd's.Details
electrical work for ti on level 1 ref 201801309904 mahre na. applicant states no new fsd's. | $20,000 |
| Mar 29, 2019 | Completed final sign-off Apr 2019 | 650 California St | Anderson, Rowe & Buckley, Inc. | 8th fl - existing fire sprinkler system ti as build 7 added sprinklers, 101 relocated sprinklers (-17), 16 remove sprinklers ref pa 2018-1120-6389Details
8th fl - existing fire sprinkler system ti as build 7 added sprinklers, 101 relocated sprinklers (-17), 16 remove sprinklers ref pa 2018-1120-6389 | |
| Mar 29, 2019 | Never finaled issued Mar 2019, no final | 650 California St | Anderson, Rowe & Buckley, Inc. | 29th fl - existing fire sprinkler system ti as build, 3 added sprinklers (-1), 56 relocated sprinklers (+14) original 2019-0214-2905 and 2019-0128-1344Details
29th fl - existing fire sprinkler system ti as build, 3 added sprinklers (-1), 56 relocated sprinklers (+14) original 2019-0214-2905 and 2019-0128-1344 | $8,000 |
| Mar 15, 2019 | Never finaled issued Mar 2019, no final | 650 California St | Johnson Controls Fire | 8th fl - adding 1 2-way communication call box and 3 pull station, 1 smoke detector, 8 pendent smoke sensor, 4 duct detectors, 2 replay iam, 3 monitor zam, 26 speaker/strobes, 9 strobes, 91 speaker in fire alarm system. ref pa 2018-1120-6389Details
8th fl - adding 1 2-way communication call box and 3 pull station, 1 smoke detector, 8 pendent smoke sensor, 4 duct detectors, 2 replay iam, 3 monitor zam, 26 speaker/strobes, 9 strobes, 91 speaker in fire alarm system. ref pa 2018-1120-6389 | $43,301 |
| Mar 15, 2019 | Never finaled issued Mar 2019, no final | 650 California St | Johnson Controls Fire | 29th fl - adding 10 speaker/strobe and 1 strobe. ref pa 2019-0128-1344Details
29th fl - adding 10 speaker/strobe and 1 strobe. ref pa 2019-0128-1344 | $6,865 |
| Feb 28, 2019 | Completed final sign-off Mar 2019 | 650 California St | Johnson Controls Fire | 23rd fl - modification to (e) pa 2018-1015-3146, fire alarm ti. addition of 1 two way emergency communication call box in elevator lobby. ref pa 2018-0726-5600Details
23rd fl - modification to (e) pa 2018-1015-3146, fire alarm ti. addition of 1 two way emergency communication call box in elevator lobby. ref pa 2018-0726-5600 | $2,000 |
| Feb 14, 2019 | Completed final sign-off Mar 2019 | 650 California St | Anderson, Rowe & Buckley, Inc. | 29/f: fire sprinkler mod: add 4 heads, relocate 41 sprinklers, ar&b job#19-018. ref t.i. 201901281344. maher n/a.Details
29/f: fire sprinkler mod: add 4 heads, relocate 41 sprinklers, ar&b job#19-018. ref t.i. 201901281344. maher n/a. | $23,000 |
| Feb 12, 2019 | Completed final sign-off Mar 2019 | 650 California St | Anderson, Rowe & Buckley, Inc. | 8th fl - existing fire sprinkler system ti 7 added sprinklers, 118 relocatd sprinklers, 16 sprinklers removed. ref pa 2018-1120-6389Details
8th fl - existing fire sprinkler system ti 7 added sprinklers, 118 relocatd sprinklers, 16 sprinklers removed. ref pa 2018-1120-6389 | $56,000 |
| Feb 4, 2019 | Never finaled issued Feb 2019, no final | 650 California St | Skyline Construction | 8th flr. mep for tenant improvement. (n) vav boxes,new transfer fan connecting power to (n) or relocated light fixtures, power outlets and tenant equipment. ref pa 201811206389Details
8th flr. mep for tenant improvement. (n) vav boxes,new transfer fan connecting power to (n) or relocated light fixtures, power outlets and tenant equipment. ref pa 201811206389 | $10,000 |
| Jan 28, 2019 | Completed final sign-off Jun 2019 | 650 California St | Gci, Inc | 29th fl, 2950 - ti demo of non structural partitions and building (n) non structural partitions. mep, life safety & sprinklers under separate permit. maher n/a.Details
29th fl, 2950 - ti demo of non structural partitions and building (n) non structural partitions. mep, life safety & sprinklers under separate permit. maher n/a. | $477,000 |
| Nov 20, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | 8/f: ti to include the construction of new separated restroom facilities non structural partitions, ceiling tiles and grids.Details
8/f: ti to include the construction of new separated restroom facilities non structural partitions, ceiling tiles and grids. | $500,000 |
| Oct 22, 2018 | Completed final sign-off Jun 2019 | 650 California St | Gci, Inc | 23rd flr. demo (e) ductwork and equipment per sheet 23m2.0. install new ductork w/ equip per 23m2.1. power and lighting. reference p.a. #2018 0726 5600Details
23rd flr. demo (e) ductwork and equipment per sheet 23m2.0. install new ductork w/ equip per 23m2.1. power and lighting. reference p.a. #2018 0726 5600 | $250,000 |
| Oct 15, 2018 | Never finaled issued Oct 2018, no final | 650 California St | Johnson Controls Fire | f/a 23rd fl: add to fire alarm 14 speaker/strobes, 1 speaker, 1 strobe. ref ti #201807265600. maher naDetails
f/a 23rd fl: add to fire alarm 14 speaker/strobes, 1 speaker, 1 strobe. ref ti #201807265600. maher na | $15,000 |
| Sep 26, 2018 | Completed final sign-off Feb 2019 | 650 California St | 23rd flr - fire sprinklers relocate 19, add 3 & delete 4 pendents. ref 201807265600 maher naDetails
23rd flr - fire sprinklers relocate 19, add 3 & delete 4 pendents. ref 201807265600 maher na | $4,500 | |
| Aug 27, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | 15th fl - revision to pa 2018-06273099, correct date of smoke control report date. n/a for maher.Details
15th fl - revision to pa 2018-06273099, correct date of smoke control report date. n/a for maher. | |
| Aug 21, 2018 | Completed final sign-off Sep 2018 | 650 California St | Gci, Inc | 8th flr - demo of (e) non structural partitions, repair shaft wall. plmb/sprinklers #201808076698. repair of existing 2 hour shaft wallDetails
8th flr - demo of (e) non structural partitions, repair shaft wall. plmb/sprinklers #201808076698. repair of existing 2 hour shaft wall | $160,000 |
| Aug 21, 2018 | Completed final sign-off Oct 2018 | 650 California St | Johnson Controls Fire | 15/f: install fire alarm for t.i. add 6 new speaker/strobes, move 2 speaker/strobevs, add1 new smoke detector.Details
15/f: install fire alarm for t.i. add 6 new speaker/strobes, move 2 speaker/strobevs, add1 new smoke detector. | $8,400 |
| Aug 10, 2018 | Never finaled issued Sep 2018, no final | 650 California St | Johnson Controls Fire | fire alarm audio enhancement. no (n) devices or appliances. all work limited to fire alarm cabinets - analog audio to digital audioDetails
fire alarm audio enhancement. no (n) devices or appliances. all work limited to fire alarm cabinets - analog audio to digital audio | $17,000 |
| Aug 7, 2018 | Never finaled issued Aug 2018, no final | 650 California St | fire sprinkler demolition permit change (92) pendent heads to uprightDetails
fire sprinkler demolition permit change (92) pendent heads to upright | $16,456 | |
| Aug 6, 2018 | Completed final sign-off Aug 2019 | 650 California St | Gci, Inc | 1st fl. revision to 201801229118; changing the single door for a double door.Details
1st fl. revision to 201801229118; changing the single door for a double door. | |
| Jul 26, 2018 | Completed final sign-off Jun 2019 | 650 California St | Gci, Inc | ti on 23rd fl - minor demo of finishes & non-structural partitions. new non-structural partitions, ceiling, lighting, finishes, accessibility upgrades and new shower room.Details
ti on 23rd fl - minor demo of finishes & non-structural partitions. new non-structural partitions, ceiling, lighting, finishes, accessibility upgrades and new shower room. | $705,360 |
| Jul 25, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | 15th flr. mep for tenant improvement. new vav boxes connecting power to new or relocated light fixtures, power, outlets, tenant equipment. ref pa # 201806263099. n/a for maher.Details
15th flr. mep for tenant improvement. new vav boxes connecting power to new or relocated light fixtures, power, outlets, tenant equipment. ref pa # 201806263099. n/a for maher. | $100,000 |
| Jul 6, 2018 | Completed final sign-off Oct 2018 | 650 California St | Pioneer Fire Inc. | relocate 10 pendents.Details
relocate 10 pendents. | $6,885 |
| Jun 27, 2018 | Completed final sign-off Sep 2021 | 650 California St | Skyline Construction | 15th flr - ti - new non structural partitions, ceiling tiles and grid, doors & hardware. mep/fire/life safety under sep permitDetails
15th flr - ti - new non structural partitions, ceiling tiles and grid, doors & hardware. mep/fire/life safety under sep permit | $450,000 |
| Jun 12, 2018 | Completed final sign-off Sep 2018 | 650 California St | Gci, Inc | 18th flr - ti demo of non structural partitions patching carpet mep & life safety under seperate permit maher naDetails
18th flr - ti demo of non structural partitions patching carpet mep & life safety under seperate permit maher na | $15,000 |
| Jun 12, 2018 | Completed final sign-off Mar 2019 | 650 California St | Gci, Inc | 15th - revision to 201801229116 to 3 layers of fire type staggered gypsum to the (e) restroom side of (e) shaft walls. there is an ab005 maher naDetails
15th - revision to 201801229116 to 3 layers of fire type staggered gypsum to the (e) restroom side of (e) shaft walls. there is an ab005 maher na | |
| May 25, 2018 | Completed final sign-off Apr 2019 | 650 California St | Skyline Construction | mechanical work tenant improvement ref 201801309904 at annexDetails
mechanical work tenant improvement ref 201801309904 at annex | $70,000 |
| May 18, 2018 | Completed final sign-off Jun 2018 | 650 California St | Johnson Controls Fire | f/a: annex building (1) nac extender panel (1) smoke detector (1) signal zam, (5) strobes and (6) speaker/strobes on annex. ref 201801309904. maher naDetails
f/a: annex building (1) nac extender panel (1) smoke detector (1) signal zam, (5) strobes and (6) speaker/strobes on annex. ref 201801309904. maher na | $12,000 |
| May 7, 2018 | Completed final sign-off Apr 2019 | 650 California St | Skyline Construction | annex & basement: installtion of new full height partitions, lighting and doors to create bike storage at level 1b.Details
annex & basement: installtion of new full height partitions, lighting and doors to create bike storage at level 1b. | $10,000 |
| Apr 19, 2018 | Completed final sign-off Feb 2019 | 650 California St | Johnson Controls Fire | new 2-way ecs for locked elevator lobbiesDetails
new 2-way ecs for locked elevator lobbies | $35,400 |
| Mar 23, 2018 | Completed final sign-off Apr 2018 | 650 California St | Pioneer Fire Inc. | return to shell condition, remove 50 pendents, and install info upright coverageDetails
return to shell condition, remove 50 pendents, and install info upright coverage | $8,944 |
| Mar 22, 2018 | Completed final sign-off Jun 2018 | 650 California St | Skyline Construction | 10th and 11th floor: new communicating stair between 10th and 11th floor. ref app#201711083445 and 201711083449Details
10th and 11th floor: new communicating stair between 10th and 11th floor. ref app#201711083445 and 201711083449 | $80,000 |
| Mar 16, 2018 | Completed final sign-off Apr 2018 | 650 California St | Johnson Controls Fire | 11th fl - ti consist of providiing new 12 smoke detectors, 3 duct detectors, 13 strobes, 27 speakers/strobes, 7 speakers, 1 call switch, 3 monitor modules. remove existing 3 pull stations with new. ref pa 2017-1108-3449Details
11th fl - ti consist of providiing new 12 smoke detectors, 3 duct detectors, 13 strobes, 27 speakers/strobes, 7 speakers, 1 call switch, 3 monitor modules. remove existing 3 pull stations with new. ref pa 2017-1108-3449 | $45,000 |
| Mar 16, 2018 | Completed final sign-off Apr 2018 | 650 California St | Johnson Controls Fire | 12th fl - ti consist of providing new 10 smoke detectors, 3 duct detectors, 8 strobes, 26 speaker/strobes, 6 speakers, 1 call switch & 1 replace 3 monitor modules.ref pa 2017-1108-3447Details
12th fl - ti consist of providing new 10 smoke detectors, 3 duct detectors, 8 strobes, 26 speaker/strobes, 6 speakers, 1 call switch & 1 replace 3 monitor modules.ref pa 2017-1108-3447 | $45,000 |
| Mar 14, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | 10th flr - ele work for ti . connecting power to new or relocated light fixtures. making connections to base ref 201711083445 bld panels maher naDetails
10th flr - ele work for ti . connecting power to new or relocated light fixtures. making connections to base ref 201711083445 bld panels maher na | $100,000 |
| Mar 14, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | electrical work for tenant improvement connecting powers to new or relocated light fixtures. making connections to base bldg panels. ref pa# 201711083447. maher naDetails
electrical work for tenant improvement connecting powers to new or relocated light fixtures. making connections to base bldg panels. ref pa# 201711083447. maher na | $100,000 |
| Mar 14, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | electrical work for tenant improvement connecting powers to new or relocated light fixtures. making connections to base bldg panels. ref pa# 201711083442Details
electrical work for tenant improvement connecting powers to new or relocated light fixtures. making connections to base bldg panels. ref pa# 201711083442 | $100,000 |
| Mar 14, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | electrical work for tenant improvement connecting powers to new or relocated light fixtures. making connections to base bldg panels. ref pa# 201711083449. maher naDetails
electrical work for tenant improvement connecting powers to new or relocated light fixtures. making connections to base bldg panels. ref pa# 201711083449. maher na | $100,000 |
| Mar 12, 2018 | Completed final sign-off Mar 2019 | 650 California St | Gci, Inc | mechanical 1 new exhaust fan & ductwork. ref pa 2018-0122-9116. electrical - new lighting and gfci receptacles inside men's & women's restrooms on the 15th floorDetails
mechanical 1 new exhaust fan & ductwork. ref pa 2018-0122-9116. electrical - new lighting and gfci receptacles inside men's & women's restrooms on the 15th floor | $55,000 |
| Mar 9, 2018 | Completed final sign-off Aug 2018 | 650 California St | Johnson Controls Fire | 15th floor - consist of replacing existing 2 speaker with 2 new speaker/strobes in the men's & women's toilet. demo 2 existing strobes. ref ti 2018-0122-9116. n/a for maher.Details
15th floor - consist of replacing existing 2 speaker with 2 new speaker/strobes in the men's & women's toilet. demo 2 existing strobes. ref ti 2018-0122-9116. n/a for maher. | $1,500 |
| Mar 9, 2018 | Completed final sign-off Feb 2019 | 650 California St | Johnson Controls Fire | 9th fl ti - adding (1) nac panel, (8) smoke detectors, 3 duct detectors, 1 relay module, 3 monitor modules, 10 strobes, 25 speaker/strobes & 1 call switch for 2 way communication. ref pa 2017-1108-3442. n/a for maher.Details
9th fl ti - adding (1) nac panel, (8) smoke detectors, 3 duct detectors, 1 relay module, 3 monitor modules, 10 strobes, 25 speaker/strobes & 1 call switch for 2 way communication. ref pa 2017-1108-3442. n/a for maher. | $37,000 |
| Mar 9, 2018 | Expired or cancelled cancelled Aug 2023 | 650 California St | Johnson Controls Fire | 10th fl ti - 13 smoke detectors, 3 duct detectors, 2 relay module, 3 monitor modules, 27 speaker/strobes, 12 strobes, 7 speakers & 1 call switch for 2 way communication. remove & replace (e) 3 pull ti 2017-1108-3445Details
10th fl ti - 13 smoke detectors, 3 duct detectors, 2 relay module, 3 monitor modules, 27 speaker/strobes, 12 strobes, 7 speakers & 1 call switch for 2 way communication. remove & replace (e) 3 pull ti 2017-1108-3445 | $45,000 |
| Mar 9, 2018 | Completed final sign-off Sep 2019 | 650 California St | Johnson Controls Fire | 10th fl ti - 13 smoke detectors, 3 duct detectors, 2 relay module, 3 monitor modules, 27 speaker/strobes, 12 strobes, 7 speakers & 1 call switch for 2 way communication. remove & replace (e) 3 pull stations w/ new. ti 2017-1108-3445. n/a for maher.Details
10th fl ti - 13 smoke detectors, 3 duct detectors, 2 relay module, 3 monitor modules, 27 speaker/strobes, 12 strobes, 7 speakers & 1 call switch for 2 way communication. remove & replace (e) 3 pull stations w/ new. ti 2017-1108-3445. n/a for maher. | $45,000 |
| Mar 2, 2018 | Never finaled issued Mar 2018, no final | 650 California St | Anderson, Rowe & Buckley, Inc. | relocate 4 fire sprinklers hds ref 201801229116 maher na. 15/fDetails
relocate 4 fire sprinklers hds ref 201801229116 maher na. 15/f | $2,100 |
| Feb 28, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | mechanical work for tenant improvement on 5th fl. ref pa 2018-1108-3442 & 201801259490Details
mechanical work for tenant improvement on 5th fl. ref pa 2018-1108-3442 & 201801259490 | $50,000 |
| Feb 28, 2018 | Completed final sign-off Nov 2019 | 650 California St | Skyline Construction | mechanical work for tenant improvement on 10th fl. ref pa 2017-1108-3445 & 201801259496Details
mechanical work for tenant improvement on 10th fl. ref pa 2017-1108-3445 & 201801259496 | $50,000 |
| Feb 28, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | mechanical work for tenant improvement on 12th fl. ref pa 2017-1108-3447Details
mechanical work for tenant improvement on 12th fl. ref pa 2017-1108-3447 | $50,000 |
| Feb 28, 2018 | Completed final sign-off Nov 2019 | 650 California St | Skyline Construction | mechanical work for tenant improvement on 11th fl. ref pa 2017-1108-3449 & 2018-0125-9497Details
mechanical work for tenant improvement on 11th fl. ref pa 2017-1108-3449 & 2018-0125-9497 | $50,000 |
| Jan 31, 2018 | Completed final sign-off Feb 2018 | 650 California St | Johnson Controls Fire | 20th floor: as built drawings consist of adding 2 duct detectors for fire smoke dampers. ref app#201711214500. n/a for maher.Details
20th floor: as built drawings consist of adding 2 duct detectors for fire smoke dampers. ref app#201711214500. n/a for maher. | |
| Jan 30, 2018 | Expired or cancelled cancelled Jan 2026 | 650 California St | Skyline Construction | ti o n 15th fl to add new breakrooom and pantry, occ load of space 278 people.Details
ti o n 15th fl to add new breakrooom and pantry, occ load of space 278 people. | $15,000 |
| Jan 30, 2018 | Completed final sign-off Apr 2019 | 650 California St | Skyline Construction | 1st fl - ti on annex level 1 of e office to consist of demo to handrail, skylight framing. constrution of new non-load bearing partitions. new open office space, new restrooms. mep & fire life safety under separate permitDetails
1st fl - ti on annex level 1 of e office to consist of demo to handrail, skylight framing. constrution of new non-load bearing partitions. new open office space, new restrooms. mep & fire life safety under separate permit | $629,264 |
| Jan 25, 2018 | Completed final sign-off Nov 2019 | 650 California St | Skyline Construction | 10th floor: revision to app#201711083445 to revise the originally approved restroom upgrade. ref app#201711083445. n/a for maherDetails
10th floor: revision to app#201711083445 to revise the originally approved restroom upgrade. ref app#201711083445. n/a for maher | |
| Jan 25, 2018 | Completed final sign-off Nov 2019 | 650 California St | Skyline Construction | 11th floor: revision to app#201711083449 to revise the originally approved restroom plans. ref app#201711083449. n/a for maherDetails
11th floor: revision to app#201711083449 to revise the originally approved restroom plans. ref app#201711083449. n/a for maher | |
| Jan 25, 2018 | Completed final sign-off Nov 2019 | 650 California St | Skyline Construction | 9th floor: revision to app#201711083442 to revise the originally approved restroom plans. ref app#201711083442. n/a for maherDetails
9th floor: revision to app#201711083442 to revise the originally approved restroom plans. ref app#201711083442. n/a for maher | |
| Jan 22, 2018 | Completed final sign-off Aug 2019 | 650 California St | Gci, Inc | 1st floor lobby - landlord ti: demo of non-structural exterior glazing partition and constructing (n) non-structural glazing partition with door. all new or revised mep/life safety/sprinklers work if needed. under separate permit. n/a maherDetails
1st floor lobby - landlord ti: demo of non-structural exterior glazing partition and constructing (n) non-structural glazing partition with door. all new or revised mep/life safety/sprinklers work if needed. under separate permit. n/a maher | $25,000 |
| Jan 22, 2018 | Completed final sign-off Mar 2019 | 650 California St | Gci, Inc | 15th flr - upgrade to men's and womens restrooms if mep/life safety work is needed it will be design build and submitted sep. bld is fully sprinklered maher naDetails
15th flr - upgrade to men's and womens restrooms if mep/life safety work is needed it will be design build and submitted sep. bld is fully sprinklered maher na | $160,000 |
| Jan 12, 2018 | Completed final sign-off Jan 2018 | 650 California St | Johnson Controls Fire | 30th floor: fire alarm t.i consists of adding 10 speaker/strobes as shown. t. i. ref app#201711073284. n/a for maherDetails
30th floor: fire alarm t.i consists of adding 10 speaker/strobes as shown. t. i. ref app#201711073284. n/a for maher | $6,000 |
| Jan 10, 2018 | Never finaled issued Jan 2018, no final | 650 California St | 30th floor: revision to app#201711073284. modify mech, elect, lighting layout, delete wd paneling, finish notes. n/a for maherDetails
30th floor: revision to app#201711073284. modify mech, elect, lighting layout, delete wd paneling, finish notes. n/a for maher | $72,000 | |
| Jan 9, 2018 | Completed final sign-off Oct 2019 | 650 California St | Skyline Construction | 15/f: interior non-structural demolition on the 15th floor ab-017, including the lowered ceiling.Details
15/f: interior non-structural demolition on the 15th floor ab-017, including the lowered ceiling. | $15,000 |
| Dec 22, 2017 | Completed final sign-off Jun 2019 | 650 California St | Pioneer Fire Inc. | 7th floor returning to warm shell condition remove all pendents & provide upright fire sprinkler protectionDetails
7th floor returning to warm shell condition remove all pendents & provide upright fire sprinkler protection | $97,911 |
| Dec 21, 2017 | Completed final sign-off Jun 2019 | 650 California St | Pioneer Fire Inc. | 15th floor: remodel of all outlined areas consisting of returning to shell condition. maher n/aDetails
15th floor: remodel of all outlined areas consisting of returning to shell condition. maher n/a | $2,500 |
| Dec 13, 2017 | Completed final sign-off Dec 2017 | 650 California St | Golden Gate Fire Protection Inc | 30th floor: fire sprinkler only: relocate 11 upright heads for "cross install". ref app#20171107328. n/a for maherDetails
30th floor: fire sprinkler only: relocate 11 upright heads for "cross install". ref app#20171107328. n/a for maher | $1,500 |
| Dec 5, 2017 | Completed final sign-off Dec 2017 | 650 California St | Johnson Controls Fire | 32nd fl ti consist of adding new 2 speaker/strobes and relocate (e) 1 speaker/strobe. ref pa 2017-1027-2513Details
32nd fl ti consist of adding new 2 speaker/strobes and relocate (e) 1 speaker/strobe. ref pa 2017-1027-2513 | $1,500 |
| Nov 21, 2017 | Completed final sign-off Dec 2017 | 650 California St | 20th fl - fire sprinkler permit, relocate 27 pendent and 26 uprights on the 20th floor. ref pa 2017-0929-9904Details
20th fl - fire sprinkler permit, relocate 27 pendent and 26 uprights on the 20th floor. ref pa 2017-0929-9904 | $12,000 | |
| Nov 21, 2017 | Completed final sign-off Apr 2018 | 650 California St | Gci, Inc | 20th fl, ste 2015 & 2050. revision to pa 2017-0929-9904 changing the wall rating and door rating. it should be a non-rated wall and door (non-reated corridor). maher naDetails
20th fl, ste 2015 & 2050. revision to pa 2017-0929-9904 changing the wall rating and door rating. it should be a non-rated wall and door (non-reated corridor). maher na |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Johnson Controls Fire (50), Skyline Construction (32), Bcci Construction Company (25), Gci, Inc (17), Richlen Construction (14), Ayoob & Peery Plumbing Co Inc (13), Anderson, Rowe & Buckley, Inc. (9), Golden Gate Fire Protection Inc (9), Pioneer Fire Inc. (5), Novo Construction Inc (3), Acco Engineered Systems Inc. Dba Acco En (2), Marchetti Group (2), Matrix Hg Inc (2), Capitol Electric Const, Dome Construction Corp, Durkin Signs & Graphics Inc, Edison Fire Extinguisher Company Inc, Intelligent Technologies & Services Inc, Pacific Coast Trane Service Co., Prima Acquire Inc Dba Lahue And Associat, Principal Builders Inc.
- Architects
- David De Valeria (8), Joseph Remling (8), Sashikala Murthy (7), Joyce Polhamus (3), Eric Ibsen (2), Joelle Rosander (2), Scott E Clement (2), Bert Deviterbo, Candace Chan, Christopher M Krahn, Elizabeth Utley Hagerty, Jeff Bailey, John Spanier, Lawrence Smith, Marcus A. Hopper, Pamela Robinson, Suwanty Mulia, Teresa Emery, William Loftis
- Engineers
- Elisabeth Allen (7), Rodolfo Bustos (4), Donald D. Dammen (3), Xuong Quach (3), Aaron J. Strauch (2), Brad Hollub (2), Edward Rivera (2), Jesus B Cabellon Jr (2), Kylie Lo (2), Alexander Joseph Pacheco, Amanda Garcia, Brian Shen, Carl Crizer, Craig Ristow, Dean Macy, Douglas Street, Habtom Nugusse Tewelde, Hugh King, Ivano Russo, Jimmy Lau, Joelle Rosander, Kevin Christensen, Kevin Kinoshita, Nathan Tremblay, Paul Kiley, Ryann Menges, Sargon Ishaya M.S., Saul Villanueva, Stanley H Lew, Thomas L. Bevans, Vasilio Artemiou, Zhen Chao Xiong
- Designers
- Peter Mchugh (5), Johnson Controls Fire (4), Acco Engineered Systems Inc., Lahue And Associat, Pioneer Fire Inc., Robert Buckley
- Pmt consultant/expediters
- Donald D. Dammen
Find contractors for work like this