Permits filed here
151 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 11, 2026 | In progress filed Sep 2026, not yet issued | 101 Spear St | site permit to enable peer review. full seismic retroift to (e) building to conform to 2025 sfbc section 304.3.2 for risk category ii using asce 41-23 nonlinear dynamic procedure. remodel of (e) seismic support structures as required for seismic work. remove & replace (e) walls & finishes to allowDetails
site permit to enable peer review. full seismic retroift to (e) building to conform to 2025 sfbc section 304.3.2 for risk category ii using asce 41-23 nonlinear dynamic procedure. remodel of (e) seismic support structures as required for seismic work. remove & replace (e) walls & finishes to allow | $15,000,000 | |
| Aug 14, 2026 | In progress filed Aug 2026, not yet issued | 101 Spear St | 3 exploratory excavation pit to deterine fondation size and existing pile conditions. no structural work.Details
3 exploratory excavation pit to deterine fondation size and existing pile conditions. no structural work. | $2,000 | |
| Jan 26, 2024 | In progress issued Jan 2024 | 101 Spear St | City Mechanical Inc | installation of water source heat pumps, ductwork and diffusers in the atriumDetails
installation of water source heat pumps, ductwork and diffusers in the atrium | $40,000 |
| Jan 10, 2024 | In progress issued May 2024 | 101 Spear St | Sabah International Incorporated | 1/f: provide modification of existing fire alarm system to accommodate new mechanical water source heat pumps at the 1st flr atrium. no architectural changes associated to the mechanical. ref permit 202401264727Details
1/f: provide modification of existing fire alarm system to accommodate new mechanical water source heat pumps at the 1st flr atrium. no architectural changes associated to the mechanical. ref permit 202401264727 | $11,269 |
| Jan 10, 2024 | In progress filed Jan 2024, not yet issued | 101 Spear St | Sabah International Incorporated | to unlock stairwell doors via the existing fire alarm sysem, system relays shall be added to unlock stairwell doors on 1st, 2nd and 3rd flrs. note: there is no building t.i. occuring.Details
to unlock stairwell doors via the existing fire alarm sysem, system relays shall be added to unlock stairwell doors on 1st, 2nd and 3rd flrs. note: there is no building t.i. occuring. | $10,469 |
| Jul 12, 2023 | Completed final sign-off Jul 2024 | 101 Spear St | Skyline Construction | ste 220: voluntary addition of structural glass guardrails at (e) balconies floors lvls 2,3,4 (e) steel guardrails (c.1988) are non-compliant w/respect to cbc 1015.3 height (42"min) & cbc 1015.4 opening limitations; (n) glass railings shall comply w/these requirements. patch/repair impacted finishesDetails
ste 220: voluntary addition of structural glass guardrails at (e) balconies floors lvls 2,3,4 (e) steel guardrails (c.1988) are non-compliant w/respect to cbc 1015.3 height (42"min) & cbc 1015.4 opening limitations; (n) glass railings shall comply w/these requirements. patch/repair impacted finishes | $465,000 |
| Jun 8, 2023 | Expired or cancelled cancelled Jan 2026 | 101 Spear St | Novo Construction Inc | seismic anchorage for phone booths on the 4th and 5th floors. fire sprinkler under separate permitDetails
seismic anchorage for phone booths on the 4th and 5th floors. fire sprinkler under separate permit | $75,000 |
| Nov 10, 2022 | Completed final sign-off Aug 2023 | 101 Spear St | Sabah International Incorporated | tenant improvement, fire alarm changes to modify/add fire alarms system.Details
tenant improvement, fire alarm changes to modify/add fire alarms system. | $40,865 |
| Aug 17, 2022 | Completed final sign-off Jul 2023 | 101 Spear St | R L H Fire Protection Inc | t.i. of the (e) fire sprinkler system; 50 (n) concealed heads (vertical sidewall) 07 (n) concealed heads (pendent)Details
t.i. of the (e) fire sprinkler system; 50 (n) concealed heads (vertical sidewall) 07 (n) concealed heads (pendent) | $5,000 |
| Feb 28, 2022 | Completed final sign-off Jun 2022 | 101 Spear St | Novo Construction Inc | 4th floor fire only permit to obatain assembly permit required stamps for flex work 0457/lounge 0403/roof deck 0456. ref pa #202105140410 and 202108267170Details
4th floor fire only permit to obatain assembly permit required stamps for flex work 0457/lounge 0403/roof deck 0456. ref pa #202105140410 and 202108267170 | |
| Feb 25, 2022 | Completed final sign-off Jun 2022 | 101 Spear St | Novo Construction Inc | 5th fl: fire only permit to obtain assembly permit required stamps for game room 0502 / flex work 0536 / break room 0551 / solarium 0552.Details
5th fl: fire only permit to obtain assembly permit required stamps for game room 0502 / flex work 0536 / break room 0551 / solarium 0552. | |
| Feb 16, 2022 | Completed final sign-off Sep 2022 | 101 Spear St | Marchetti Group | gr floor interior dmeo for 1 vacant retail space. demolish e suspended ceiling and carpet. patch e drywall walls and ceiling and paint. polish e concrete floor. no other work.Details
gr floor interior dmeo for 1 vacant retail space. demolish e suspended ceiling and carpet. patch e drywall walls and ceiling and paint. polish e concrete floor. no other work. | $10,000 |
| Dec 16, 2021 | Completed final sign-off Feb 2024 | 101 Spear St | Marchetti Group | revisionto pa 202010035855/r1 minor architectural revisions & aluminum frame; storefront glazing system structural engineering, mep engineering & title 24 energy compliance for warm shell gr fl vacant office spaces. disabled access restroom & path of travel compliances is documented and approved.Details
revisionto pa 202010035855/r1 minor architectural revisions & aluminum frame; storefront glazing system structural engineering, mep engineering & title 24 energy compliance for warm shell gr fl vacant office spaces. disabled access restroom & path of travel compliances is documented and approved. | $125,000 |
| Sep 14, 2021 | Expired or cancelled cancelled Jan 2026 | 101 Spear St | Marchetti Group | revision to existing permit # 2020-5310-6671 and 2020-0922-4736 to keep e temporary barricade walls as permanentDetails
revision to existing permit # 2020-5310-6671 and 2020-0922-4736 to keep e temporary barricade walls as permanent | $5,000 |
| Aug 26, 2021 | Completed final sign-off Mar 2022 | 101 Spear St | Novo Construction Inc | revision to 202105180510 to modify card readers per field inspectorDetails
revision to 202105180510 to modify card readers per field inspector | |
| Aug 26, 2021 | Completed final sign-off Mar 2022 | 101 Spear St | Novo Construction Inc | 4th fl - revision to 2021-0514-0410 per field inspector to modify card readers and obtain an assembly permit for existing roof deckDetails
4th fl - revision to 2021-0514-0410 per field inspector to modify card readers and obtain an assembly permit for existing roof deck | |
| Jul 26, 2021 | Never finaled issued Jul 2021, no final | 101 Spear St | Sabah International Incorporated | 4th & 5th flr-add:(2) dual input module,(4) output module,(5) control relay, (20 interllgent smk det. (3)photo duct smk det. (4) dooster pwr supply,(32) speaker ceiling stobes & (4) speaker/strobe. ref#202105140410/05180510/06212849/06182772Details
4th & 5th flr-add:(2) dual input module,(4) output module,(5) control relay, (20 interllgent smk det. (3)photo duct smk det. (4) dooster pwr supply,(32) speaker ceiling stobes & (4) speaker/strobe. ref#202105140410/05180510/06212849/06182772 | $68,613 |
| Jun 30, 2021 | Completed final sign-off Aug 2021 | 101 Spear St | Ayoob & Peery Plumbing Co Inc | 4th fl: add (9) changeout (9), relocate (3) sprinklers per t.i. pa #202105140410. 5th fl: add (9) changeout (9), relocate (13) sprinklers per t.i. pa #202105180510.Details
4th fl: add (9) changeout (9), relocate (3) sprinklers per t.i. pa #202105140410. 5th fl: add (9) changeout (9), relocate (13) sprinklers per t.i. pa #202105180510. | $18,900 |
| Jun 21, 2021 | Completed final sign-off Feb 2022 | 101 Spear St | Novo Construction Inc | 4/f: mechanical & electrical work for t.i. ref bpa#202105140410Details
4/f: mechanical & electrical work for t.i. ref bpa#202105140410 | |
| Jun 18, 2021 | Completed final sign-off Feb 2022 | 101 Spear St | Novo Construction Inc | 5th fl - mech and mech-e work for ti. ref pa 2021-0518-0510Details
5th fl - mech and mech-e work for ti. ref pa 2021-0518-0510 | |
| May 25, 2021 | Expired or cancelled expired Dec 2024 | 101 Spear St | Corporate Sign Systems | erect 2 electric single faced wall signs permit: "rincon" (2)totalDetails
erect 2 electric single faced wall signs permit: "rincon" (2)total | $3,500 |
| May 25, 2021 | Expired or cancelled cancelled Sep 2023 | 101 Spear St | Corporate Sign Systems | sign d: install 1 non-illuminated single face canopy sign. for "tenant xyz"Details
sign d: install 1 non-illuminated single face canopy sign. for "tenant xyz" | $1,000 |
| May 25, 2021 | Expired or cancelled cancelled Sep 2023 | 101 Spear St | Corporate Sign Systems | erect a non-electric single wall faced sign permit. "rincon center"Details
erect a non-electric single wall faced sign permit. "rincon center" | $3,000 |
| May 25, 2021 | Expired or cancelled withdrawn May 2023 | 101 Spear St | Corporate Sign Systems | sign a: install 2 illuminated double-faced projecting blade sign. "rincon"Details
sign a: install 2 illuminated double-faced projecting blade sign. "rincon" | $4,000 |
| May 25, 2021 | Expired or cancelled expired Dec 2024 | 101 Spear St | Corporate Sign Systems | erect a non-electric, wall single faced sign. "spear street"Details
erect a non-electric, wall single faced sign. "spear street" | $1,000 |
| May 25, 2021 | Expired or cancelled cancelled Sep 2023 | 101 Spear St | Corporate Sign Systems | sign c: install 2 illuminated double-faced projecting blade sign. for "tenant xyz rincon center"Details
sign c: install 2 illuminated double-faced projecting blade sign. for "tenant xyz rincon center" | $1,000 |
| May 25, 2021 | Completed final sign-off May 2024 | 101 Spear St | Corporate Sign Systems | install 1 non electric single faced wall sign: "office elevators"Details
install 1 non electric single faced wall sign: "office elevators" | $1,000 |
| May 25, 2021 | Expired or cancelled cancelled Sep 2023 | 101 Spear St | Corporate Sign Systems | erect an electric, single faced wall sign. "rincon" (4) totalDetails
erect an electric, single faced wall sign. "rincon" (4) total | $3,000 |
| May 25, 2021 | Completed final sign-off May 2024 | 101 Spear St | Corporate Sign Systems | install 1 electric single faced wall sign: "parking"Details
install 1 electric single faced wall sign: "parking" | $2,000 |
| May 20, 2021 | Completed final sign-off Apr 2024 | 101 Spear St | Corporate Sign Systems | replace extg 1-non illuminated single-faced wall sign "one rincon center"Details
replace extg 1-non illuminated single-faced wall sign "one rincon center" | $3,000 |
| May 20, 2021 | Expired or cancelled withdrawn May 2023 | 101 Spear St | Corporate Sign Systems | sign typae a- retail blade id qty 13. fabricate and install primary id blade, internally illuminated; wall mounting. signage is within "transit center special sign district" to have dimmable transformer. in line dimmer switch, dedicated and timers by othersDetails
sign typae a- retail blade id qty 13. fabricate and install primary id blade, internally illuminated; wall mounting. signage is within "transit center special sign district" to have dimmable transformer. in line dimmer switch, dedicated and timers by others | $1,600 |
| May 18, 2021 | Completed final sign-off Mar 2022 | 101 Spear St | Novo Construction Inc | 5th fl: demolition of select bnon-structural partitions, acoustical ceiling finishes, etc. provide new non-structural partitions and finishes. mep under sep. permit.Details
5th fl: demolition of select bnon-structural partitions, acoustical ceiling finishes, etc. provide new non-structural partitions and finishes. mep under sep. permit. | $1,445,000 |
| May 14, 2021 | Completed final sign-off Mar 2022 | 101 Spear St | Novo Construction Inc | 4th fl: demoliton of select non-structural partitions, acoustical ceilings, finishes, etc.. provide new non-structural partitions & finishes. electrical under separate permit.Details
4th fl: demoliton of select non-structural partitions, acoustical ceilings, finishes, etc.. provide new non-structural partitions & finishes. electrical under separate permit. | $1,305,000 |
| Jan 28, 2021 | Completed final sign-off Mar 2021 | 101 Spear St | Sabah International Incorporated | as-built for permit # 2020-0206-5443. relocate ceiling devices to wall mouted in open ceiling areas and provide additional devices in restrooms per inspector request. added fan coil units 1-6 and 1-7 to drawings. added additional window openers.Details
as-built for permit # 2020-0206-5443. relocate ceiling devices to wall mouted in open ceiling areas and provide additional devices in restrooms per inspector request. added fan coil units 1-6 and 1-7 to drawings. added additional window openers. | |
| Oct 3, 2020 | Completed final sign-off May 2022 | 101 Spear St | administrative permit to memorialize occii motions authorizing 23,224.88 gsf of office use to be flexibly configured @ ground fl.no construction under this permit, permit establishes that a change of use occupancy is approved for future tenant improvement.Details
administrative permit to memorialize occii motions authorizing 23,224.88 gsf of office use to be flexibly configured @ ground fl.no construction under this permit, permit establishes that a change of use occupancy is approved for future tenant improvement. | ||
| Oct 3, 2020 | Completed final sign-off Feb 2024 | 101 Spear St | ground fl construction of aluminum frame storefront glazing partition system & glass doors. new corridor partition wall & doors for all access to (e) restrooms. proposed office spaces to remain vacant & disabled access is preferred per ab-017Details
ground fl construction of aluminum frame storefront glazing partition system & glass doors. new corridor partition wall & doors for all access to (e) restrooms. proposed office spaces to remain vacant & disabled access is preferred per ab-017 | $65,000 | |
| Sep 22, 2020 | Completed final sign-off Sep 2022 | 101 Spear St | Marchetti Group | 1st fl - temporary barricades and egress path per inspector's request. ref to pa 2020 0310 6671.Details
1st fl - temporary barricades and egress path per inspector's request. ref to pa 2020 0310 6671. | $8,000 |
| Jun 11, 2020 | Never finaled issued Jun 2020, no final | 101 Spear St | street spaceDetails
street space | ||
| Mar 10, 2020 | Completed final sign-off Sep 2021 | 101 Spear St | Marchetti Group | renovation of existing elevator lobby space, including ceiling, lighting, and new reception desk area.Details
renovation of existing elevator lobby space, including ceiling, lighting, and new reception desk area. | $350,000 |
| Mar 10, 2020 | Completed final sign-off Aug 2021 | 101 Spear St | Marchetti Group | revision to pa #2019-0806-7976: omission of scope including raised platform area at spear st. entry including associated finish work, and elevator lift.Details
revision to pa #2019-0806-7976: omission of scope including raised platform area at spear st. entry including associated finish work, and elevator lift. | |
| Mar 3, 2020 | Never finaled issued Mar 2020, no final | 101 Spear St | street spaceDetails
street space | ||
| Feb 28, 2020 | Never finaled issued Mar 2020, no final | 101 Spear St | Marchetti Group | revision to pa #201911278338 for local equivalency of existing verical grase ducts.Details
revision to pa #201911278338 for local equivalency of existing verical grase ducts. | |
| Feb 26, 2020 | Completed final sign-off Mar 2021 | 101 Spear St | Sabah International Incorporated | ref pa# 201908279939; modify (e) fire alarm system, relocate (e) annunciator add(6) input/output modules, (12) dual input modules, (1) synch output module,(6) high power control relays, (2) smoke detectors, (8) duct smoke detectors, (4) interior relays, (2) booster power supplies, 38 speaker strobesDetails
ref pa# 201908279939; modify (e) fire alarm system, relocate (e) annunciator add(6) input/output modules, (12) dual input modules, (1) synch output module,(6) high power control relays, (2) smoke detectors, (8) duct smoke detectors, (4) interior relays, (2) booster power supplies, 38 speaker strobes | $88,758 |
| Jan 30, 2020 | Completed final sign-off Oct 2022 | 101 Spear St | Marchetti Group | revision to pa #2019-0806-7976: temporary fire assembly occupancy calculations for atrium spaces previously approved to be used as exhibit as part of sffd assembly/operational permit.Details
revision to pa #2019-0806-7976: temporary fire assembly occupancy calculations for atrium spaces previously approved to be used as exhibit as part of sffd assembly/operational permit. | |
| Jan 7, 2020 | Completed final sign-off Aug 2021 | 101 Spear St | R L H Fire Protection Inc | fire sprinkler permit for 1st fl: install 137 upright sprinklers and 71 pendents for the atrium remodel. ref ti #201908067976.Details
fire sprinkler permit for 1st fl: install 137 upright sprinklers and 71 pendents for the atrium remodel. ref ti #201908067976. | $92,000 |
| Dec 6, 2019 | Never finaled issued Dec 2019, no final | 101 Spear St | street spaceDetails
street space | ||
| Dec 3, 2019 | Completed final sign-off May 2020 | 101 Spear St | Novo Construction Inc | revision 2019-0610-2983 and 2019-0524-1693 to change furniture layout in employee break area on level 1 & 2Details
revision 2019-0610-2983 and 2019-0524-1693 to change furniture layout in employee break area on level 1 & 2 | |
| Nov 27, 2019 | Completed final sign-off Sep 2021 | 101 Spear St | Marchetti Group | ref# 201908279939 & 201908067976: deferred mep including grease exhaust fans&ducts, general exhaust & type 2 exhaust ducts. motorized operable windows for smoke control, restroom exhasut and rebalance existing restroom exhaust floor 2-5.Details
ref# 201908279939 & 201908067976: deferred mep including grease exhaust fans&ducts, general exhaust & type 2 exhaust ducts. motorized operable windows for smoke control, restroom exhasut and rebalance existing restroom exhaust floor 2-5. | |
| Nov 15, 2019 | Completed final sign-off Mar 2021 | 101 Spear St | Marchetti Group | project scope includes the installation of atrium doors assembly structural frame support framing on ground level slab. reference pa# 2019-0828-0119Details
project scope includes the installation of atrium doors assembly structural frame support framing on ground level slab. reference pa# 2019-0828-0119 | $25,000 |
| Nov 6, 2019 | Completed final sign-off Mar 2020 | 101 Spear St | Martinelli Environmental Graph | evacuation signs on floors 1,2, & 3.Details
evacuation signs on floors 1,2, & 3. | $3,500 |
| Nov 5, 2019 | Completed final sign-off Mar 2020 | 101 Spear St | Sabah International Incorporated | modification of f.a. system. reusing (e) heat pumps and fire device. add (9) new heat pumps with duct det and shut downs. adding (1) new fsd and replacing (151) speaker strobes. ref app#201906254311Details
modification of f.a. system. reusing (e) heat pumps and fire device. add (9) new heat pumps with duct det and shut downs. adding (1) new fsd and replacing (151) speaker strobes. ref app#201906254311 | $48,000 |
| Nov 4, 2019 | Never finaled issued Nov 2019, no final | 101 Spear St | Marchetti Group | project scope includes the construction of raised platforms withtin the atrium of rincon center located at 121 spear street. referece pa 2019-0806-7976Details
project scope includes the construction of raised platforms withtin the atrium of rincon center located at 121 spear street. referece pa 2019-0806-7976 | |
| Oct 28, 2019 | Completed final sign-off Mar 2021 | 101 Spear St | Marchetti Group | reference app#201908280119. structural work only. install new stair at egress corridor.Details
reference app#201908280119. structural work only. install new stair at egress corridor. | $18,000 |
| Oct 28, 2019 | Completed final sign-off Mar 2020 | 101 Spear St | Sabah International Incorporated | basement: voluntary fire alarm changes to accomodate tei project @ basement fl. add 1 single input monitor module & 1 dual input monitor module for fire kpump test loop tampers. maher n/a.Details
basement: voluntary fire alarm changes to accomodate tei project @ basement fl. add 1 single input monitor module & 1 dual input monitor module for fire kpump test loop tampers. maher n/a. | $13,868 |
| Oct 2, 2019 | Never finaled issued Oct 2019, no final | 101 Spear St | street spaceDetails
street space | ||
| Oct 2, 2019 | Never finaled issued Oct 2019, no final | 101 Spear St | street spaceDetails
street space | ||
| Sep 17, 2019 | Completed final sign-off May 2020 | 101 Spear St | Novo Construction Inc | revision to 201905241699 2nd flr & 201906254311 3rd flr. add roll down door at elevator lobby. roll down door approved on application listed above, this is for the strucutral approval with calcsDetails
revision to 201905241699 2nd flr & 201906254311 3rd flr. add roll down door at elevator lobby. roll down door approved on application listed above, this is for the strucutral approval with calcs | $5,000 |
| Aug 28, 2019 | Completed final sign-off Sep 2021 | 101 Spear St | Marchetti Group | revision to app#201809129816. remove portion of extg interior fl slab at extg service entry. remove portion of extg rated transfer corridor & extg egress stair. remove extg walls,doors, ceilings, & lighting at new proposed public entry lobby. install new slabs, rated partitions & openings, stairs,Details
revision to app#201809129816. remove portion of extg interior fl slab at extg service entry. remove portion of extg rated transfer corridor & extg egress stair. remove extg walls,doors, ceilings, & lighting at new proposed public entry lobby. install new slabs, rated partitions & openings, stairs, | $645,620 |
| Aug 27, 2019 | Never finaled issued Sep 2019, no final | 101 Spear St | Novo Construction Inc | 3rd flr ti deferred mep. ref pa 201906254311Details
3rd flr ti deferred mep. ref pa 201906254311 | $1,300,000 |
| Aug 27, 2019 | Expired or cancelled cancelled Sep 2021 | 101 Spear St | Marchetti Group | ground flr interior tenant improvements for 9 food service commercial kitchens and support spaces incl common food storage area, common employee lockers & changing rms, janitorial closets & common refuse rm. (n) partitions, finishes and kitchen equipment. mep under separate permitsDetails
ground flr interior tenant improvements for 9 food service commercial kitchens and support spaces incl common food storage area, common employee lockers & changing rms, janitorial closets & common refuse rm. (n) partitions, finishes and kitchen equipment. mep under separate permits | $975,000 |
| Aug 26, 2019 | Completed final sign-off Oct 2019 | 101 Spear St | R L H Fire Protection Inc | fire sprinklers install 90 new upright sprinklers for atrium demo ref 201803274706Details
fire sprinklers install 90 new upright sprinklers for atrium demo ref 201803274706 | $18,000 |
| Aug 22, 2019 | Never finaled issued Oct 2019, no final | 101 Spear St | Sabah International Incorporated | fire alarm modify existing system. add 1 dual signature driver controller, 2 20 control relay, 1 input/0utput module , 2 optical smk detector, 17 photosmk det, 6 booster power supply 158 speaker strobes, 70 v and 5 speaker strobes and 5 speaker strobes wp. ref pa#2019-0524-1699.**maher n/a**Details
fire alarm modify existing system. add 1 dual signature driver controller, 2 20 control relay, 1 input/0utput module , 2 optical smk detector, 17 photosmk det, 6 booster power supply 158 speaker strobes, 70 v and 5 speaker strobes and 5 speaker strobes wp. ref pa#2019-0524-1699.**maher n/a** | $101,509 |
| Aug 8, 2019 | Completed final sign-off Mar 2021 | 101 Spear St | Marchetti Group | revision to 201809129816. as construction will be going on for months, the fire inspector has requested a temporary egress path to be constructed.Details
revision to 201809129816. as construction will be going on for months, the fire inspector has requested a temporary egress path to be constructed. | $3,812,400 |
| Aug 6, 2019 | Completed final sign-off Sep 2021 | 101 Spear St | Marchetti Group | revision to pa 2018-0327-4706 to include (n) raised platforms, (n) all gender neutral restrooms, removal of non-historic windows, & install (n) actuating windows.Details
revision to pa 2018-0327-4706 to include (n) raised platforms, (n) all gender neutral restrooms, removal of non-historic windows, & install (n) actuating windows. | $200,000 |
| Aug 6, 2019 | Completed final sign-off Oct 2019 | 101 Spear St | Ayoob & Peery Plumbing Co Inc | 2nd flr, fire sprinklers. tenant improvement - add 136, relocate 107 sprinklers. ref 201905241699Details
2nd flr, fire sprinklers. tenant improvement - add 136, relocate 107 sprinklers. ref 201905241699 | $95,475 |
| Aug 6, 2019 | Completed final sign-off Sep 2019 | 101 Spear St | Ayoob & Peery Plumbing Co Inc | 1st flr, fire sprinklers. tenant improvement - add 34, relocate 27 sprinklers. ref 201906102983Details
1st flr, fire sprinklers. tenant improvement - add 34, relocate 27 sprinklers. ref 201906102983 | $23,925 |
| Aug 6, 2019 | Completed final sign-off Feb 2020 | 101 Spear St | Ayoob & Peery Plumbing Co Inc | 3rd flr, fire sprinklers. tenant improvement - add 52, relocate 30 sprinklers. ref 201906254311Details
3rd flr, fire sprinklers. tenant improvement - add 52, relocate 30 sprinklers. ref 201906254311 | $34,050 |
| Aug 1, 2019 | Completed final sign-off May 2020 | 101 Spear St | Novo Construction Inc | deferred mep for first floor ti ref 201906102983Details
deferred mep for first floor ti ref 201906102983 | |
| Jul 15, 2019 | Completed final sign-off Jun 2020 | 101 Spear St | Novo Construction Inc | 2nd floor:mep: relocate extg heat pumps, 17 new heat pumps, install 2 new exhaust fans, install 1 new f.s.p. install low pressure duct work. install condenser water per plans. n/a for maherDetails
2nd floor:mep: relocate extg heat pumps, 17 new heat pumps, install 2 new exhaust fans, install 1 new f.s.p. install low pressure duct work. install condenser water per plans. n/a for maher | $100,000 |
| Jun 25, 2019 | Never finaled issued Jun 2019, no final | 101 Spear St | street spaceDetails
street space | ||
| Jun 25, 2019 | Completed final sign-off May 2020 | 101 Spear St | Novo Construction Inc | 3rd flr. interior tenant improvement of approx 63,000 sq ft, located on level 3. improvements incl open offices, pantry, employee break room and conference roomsDetails
3rd flr. interior tenant improvement of approx 63,000 sq ft, located on level 3. improvements incl open offices, pantry, employee break room and conference rooms | $1,500,000 |
| Jun 10, 2019 | Completed final sign-off May 2020 | 101 Spear St | Novo Construction Inc | 1st fl - interior ti of approximately 12,000 sq ft on level 1. improvements include reception, pantry, game area, fitness room, employee break rooms, unisex and showerDetails
1st fl - interior ti of approximately 12,000 sq ft on level 1. improvements include reception, pantry, game area, fitness room, employee break rooms, unisex and shower | $1,550,000 |
| May 24, 2019 | Completed final sign-off Jun 2020 | 101 Spear St | Novo Construction Inc | interor soft demo of approx .23,150 sf located on level 3Details
interor soft demo of approx .23,150 sf located on level 3 | $120,000 |
| May 24, 2019 | Completed final sign-off May 2020 | 101 Spear St | Novo Construction Inc | interior t.i. of approx. 65,228 sf on level 2 & mezz improvements include open office, pantry employee, break rooms, conference rooms, unisex restroomsDetails
interior t.i. of approx. 65,228 sf on level 2 & mezz improvements include open office, pantry employee, break rooms, conference rooms, unisex restrooms | $5,900,000 |
| Apr 8, 2019 | Completed final sign-off May 2020 | 101 Spear St | Novo Construction Inc | demo of non structural partitions and finishes on 1st & 2nd floors ab 0.17Details
demo of non structural partitions and finishes on 1st & 2nd floors ab 0.17 | $10,000 |
| Mar 12, 2019 | Never finaled issued May 2019, no final | 101 Spear St | Richlen Construction | relocation of existing door at salesforce/twilio tenant suite on the 1st floor/ accessible upgrades per form c allowanceDetails
relocation of existing door at salesforce/twilio tenant suite on the 1st floor/ accessible upgrades per form c allowance | $10,000 |
| Sep 12, 2018 | Completed final sign-off Sep 2021 | 101 Spear St | Marchetti Group | remove portions of (e) interior & exterior slab at (e) service entry, portions of (e) rated transfer corridor & egress stair & associated walls, door, ceiling & lighting. install new floor slab & exterior landing & door, rated partitions, openings & stairs. accessible lift, ceiling & lightingDetails
remove portions of (e) interior & exterior slab at (e) service entry, portions of (e) rated transfer corridor & egress stair & associated walls, door, ceiling & lighting. install new floor slab & exterior landing & door, rated partitions, openings & stairs. accessible lift, ceiling & lighting | $645,620 |
| Jun 7, 2018 | Expired or cancelled withdrawn Sep 2018 | 101 Spear St | remove portion of existing interior fl slab 2 existing service entry, portion of existing rated transfer corridor & egress stair, existing walls, doors ceilings, lighting, entry,elevator lobby. install new slabs, stairs, ceilings, lighting, rated construction @ new public lobby and elevator lobbyDetails
remove portion of existing interior fl slab 2 existing service entry, portion of existing rated transfer corridor & egress stair, existing walls, doors ceilings, lighting, entry,elevator lobby. install new slabs, stairs, ceilings, lighting, rated construction @ new public lobby and elevator lobby | $645,620 | |
| Apr 4, 2018 | Expired or cancelled cancelled Jul 2024 | 101 Spear St | rehabilitation of 5 windows opening & 1 entrance @ the steuart street facade of the landmark post oppice bldg, including the removal of non-historic louvers. the installation of new glazing in (e) frams, updated louvers in one window, new entrance doors & surround. ** maher: n/a **Details
rehabilitation of 5 windows opening & 1 entrance @ the steuart street facade of the landmark post oppice bldg, including the removal of non-historic louvers. the installation of new glazing in (e) frams, updated louvers in one window, new entrance doors & surround. ** maher: n/a ** | $1,500,000 | |
| Mar 27, 2018 | Never finaled issued Mar 2019, no final | 101 Spear St | Marchetti Group | renovation of extg atrium space at rincon tower one: remove some extg int. food service tenant spaces, including most storefronts, flooring, ceilings, lighting in non-historic lobby & atrium spaces. install new retail storefronts and retail signage, new flooring, ceiling & lighting.Details
renovation of extg atrium space at rincon tower one: remove some extg int. food service tenant spaces, including most storefronts, flooring, ceilings, lighting in non-historic lobby & atrium spaces. install new retail storefronts and retail signage, new flooring, ceiling & lighting. | $2,500,000 |
| Apr 10, 2017 | Completed final sign-off May 2017 | 101 Spear St | Red Hawk Fire & Security Ca Llc | fire alarm ti on 4th fl salesforce. add 42 speaker strobes, 333 smoke det for atrium perimeter, 20 duct detectors, with relays for hp unints. 2 pendent smoke , 1 duct detector for fsds and 1 new loop controller cord ref 201612094519Details
fire alarm ti on 4th fl salesforce. add 42 speaker strobes, 333 smoke det for atrium perimeter, 20 duct detectors, with relays for hp unints. 2 pendent smoke , 1 duct detector for fsds and 1 new loop controller cord ref 201612094519 | $55,560 |
| Mar 7, 2017 | Never finaled issued Mar 2017, no final | 101 Spear St | Golden Gate Fire Protection Inc | 4th floor fire sprinkler - relocate 119 pendent sprinkler heads, relocate 114 upright sprinklers. upgrade end of line bracing & earthquake bracing. ref pa #201612094619. n/a maher ordinanceDetails
4th floor fire sprinkler - relocate 119 pendent sprinkler heads, relocate 114 upright sprinklers. upgrade end of line bracing & earthquake bracing. ref pa #201612094619. n/a maher ordinance | $98,175 |
| Dec 9, 2016 | Completed final sign-off Nov 2017 | 101 Spear St | Hathaway Dinwiddie Co. | partial floor interior tenant improvement for single tenant on 4th flr including mep demo work filed under 201612024025. n/a maher ord. 155-13Details
partial floor interior tenant improvement for single tenant on 4th flr including mep demo work filed under 201612024025. n/a maher ord. 155-13 | $2,000,000 |
| Dec 6, 2016 | Completed final sign-off Mar 2017 | 101 Spear St | Golden Gate Fire Protection Inc | fire sprinklers; relocate 28 upright sprinklers on the 4th floor. maher naDetails
fire sprinklers; relocate 28 upright sprinklers on the 4th floor. maher na | $5,600 |
| Dec 2, 2016 | Completed final sign-off Nov 2017 | 101 Spear St | Hathaway Dinwiddie Co. | 4th flr: interior non-structural demo work only. partial existing high rise building fully sprinklered, t.i. scope of work filed under separate permit.all demo work to comply with ab-017; maher n/aDetails
4th flr: interior non-structural demo work only. partial existing high rise building fully sprinklered, t.i. scope of work filed under separate permit.all demo work to comply with ab-017; maher n/a | $24,347 |
| Jun 6, 2016 | Completed final sign-off Aug 2016 | 101 Spear St | Hathaway Dinwiddie Co. | revision to pa 2014-0626-9637 for infield design modifications including open seating layout, electrical lighting and plumbingDetails
revision to pa 2014-0626-9637 for infield design modifications including open seating layout, electrical lighting and plumbing | |
| Jun 3, 2016 | Completed final sign-off Aug 2016 | 101 Spear St | Red Hawk Fire & Security Ca Llc | 2nd floor fire alarm for t.i. - add (101) new speaker/strobes, (16) strobes, (1) speaker, (40) smoke detectors, (64) duct detectors, (69) control relays, (3) booster supplies. ref #20140626963. n/a maher ordinanceDetails
2nd floor fire alarm for t.i. - add (101) new speaker/strobes, (16) strobes, (1) speaker, (40) smoke detectors, (64) duct detectors, (69) control relays, (3) booster supplies. ref #20140626963. n/a maher ordinance | $40,000 |
| Apr 22, 2016 | Completed final sign-off Apr 2016 | 101 Spear St | K Bali Construction | revision to app#201603020962. project under construction. remove ansul from drawings and provide fire protection per ab-005. n/a maherDetails
revision to app#201603020962. project under construction. remove ansul from drawings and provide fire protection per ab-005. n/a maher | |
| Apr 19, 2016 | Never finaled issued Apr 2016, no final | 101 Spear St | Hathaway Dinwiddie Co. | 2nd fl: revision to ref pa 2014-0626-9637: revised work includes new pantry, millwork layout, elevator lobby, new horizontal exit location & mep design. fire alarm & sprinkler deferred. compliance with maher ordinance no 155-13 not required.Details
2nd fl: revision to ref pa 2014-0626-9637: revised work includes new pantry, millwork layout, elevator lobby, new horizontal exit location & mep design. fire alarm & sprinkler deferred. compliance with maher ordinance no 155-13 not required. | $90,000 |
| Mar 21, 2016 | Completed final sign-off Jun 2016 | 101 Spear St | Golden Gate Fire Protection Inc | 2nd floor fire sprinklers - relocate 155 pendent sprinklers, relocate 183 upright sprinklers heads, upgrade end of line & earthquake bracing. ref t.i. #201511122392.Details
2nd floor fire sprinklers - relocate 155 pendent sprinklers, relocate 183 upright sprinklers heads, upgrade end of line & earthquake bracing. ref t.i. #201511122392. | $174,070 |
| Mar 16, 2016 | Never finaled issued Mar 2016, no final | 101 Spear St | street spaceDetails
street space | ||
| Mar 2, 2016 | Never finaled issued Dec 2016, no final | 101 Spear St | street spaceDetails
street space | ||
| Mar 2, 2016 | Completed final sign-off Apr 2016 | 101 Spear St | K Bali Construction | minor non-structural remodel to existing restaurant to include changes to customer serving area. changes to prep room adjacent to serving area. maher naDetails
minor non-structural remodel to existing restaurant to include changes to customer serving area. changes to prep room adjacent to serving area. maher na | $35,250 |
| Feb 5, 2016 | Completed final sign-off May 2016 | 101 Spear St | suite 400: demolition of (e) non-structural partitions, millwork and ceiling. removal of (e) mep distribution. re-suport lights throughout. maher naDetails
suite 400: demolition of (e) non-structural partitions, millwork and ceiling. removal of (e) mep distribution. re-suport lights throughout. maher na | $96,000 | |
| Nov 12, 2015 | Never finaled issued Mar 2016, no final | 101 Spear St | Hathaway Dinwiddie Co. | revision to pa#201406269637 for 2/f, partial office level t.i., revision include mezzanine, turnstiles & corresponding mechanical. n/a ordinance #155-13Details
revision to pa#201406269637 for 2/f, partial office level t.i., revision include mezzanine, turnstiles & corresponding mechanical. n/a ordinance #155-13 | |
| Aug 19, 2015 | Completed final sign-off Aug 2016 | 101 Spear St | Hathaway Dinwiddie Co. | interior non-structural soft demolition at 2nd floor: demo per ab-017. t.i. under appl, # 2014.06.26.9637 (under review). maher n/a.Details
interior non-structural soft demolition at 2nd floor: demo per ab-017. t.i. under appl, # 2014.06.26.9637 (under review). maher n/a. | $15,000 |
| Aug 14, 2015 | Never finaled issued Aug 2015, no final | 101 Spear St | street spaceDetails
street space | ||
| Jun 19, 2015 | Never finaled issued Jun 2015, no final | 101 Spear St | K Bali Construction | 1st floor suite a2: hair salon t.i. including electrical for new configuration of interior finishes, remove utility sink, new lighting and fixtures. maher n/a.Details
1st floor suite a2: hair salon t.i. including electrical for new configuration of interior finishes, remove utility sink, new lighting and fixtures. maher n/a. | $50,000 |
| Jan 12, 2015 | Completed final sign-off Mar 2015 | 101 Spear St | Red Hawk Fire & Security Ca Llc | 5th flr: fire alarm ref. appn. 201405166024 including: 72 speaker/strobes, 11 strobes, 4 smoke detectors, 50 duct detectors, 13 monitor modules, 45 relays; maher n/aDetails
5th flr: fire alarm ref. appn. 201405166024 including: 72 speaker/strobes, 11 strobes, 4 smoke detectors, 50 duct detectors, 13 monitor modules, 45 relays; maher n/a | $23,000 |
| Jan 8, 2015 | Expired or cancelled cancelled Jan 2026 | 101 Spear St | ste a-10: plumbing sink install, electrical re-position of sockets, window install; maher n/aDetails
ste a-10: plumbing sink install, electrical re-position of sockets, window install; maher n/a | ||
| Nov 18, 2014 | Completed final sign-off Mar 2015 | 101 Spear St | Hathaway Dinwiddie Co. | 5th flr: revision to elevator lobby doors on 5th flr, reference 201405166024; maher n/aDetails
5th flr: revision to elevator lobby doors on 5th flr, reference 201405166024; maher n/a | $8,000 |
| Nov 18, 2014 | Completed final sign-off Mar 2015 | 101 Spear St | Hathaway Dinwiddie Co. | 4th flr: revision to elevator lobby doors on 4th flr, ref. pa 201406300127 and pa 201311131835; maher n/aDetails
4th flr: revision to elevator lobby doors on 4th flr, ref. pa 201406300127 and pa 201311131835; maher n/a | $4,000 |
| Nov 12, 2014 | Completed final sign-off Dec 2014 | 101 Spear St | Red Hawk Fire & Security Ca Llc | 4th floor: as built of fire alarm t.i. revision appl. 2014.1029.0154. maher n/a.Details
4th floor: as built of fire alarm t.i. revision appl. 2014.1029.0154. maher n/a. | |
| Nov 10, 2014 | Never finaled issued Nov 2014, no final | 101 Spear St | street space permitDetails
street space permit | ||
| Nov 7, 2014 | Never finaled issued Nov 2014, no final | 101 Spear St | Golden Gate Fire Protection Inc | relocate 202 pendent sprinkler heads, relocate 113 upright sprinklers heads, upgrade end of line bracing and earthquake bracing. t.i. pa#201405166024. n/a ordinance #155-13Details
relocate 202 pendent sprinkler heads, relocate 113 upright sprinklers heads, upgrade end of line bracing and earthquake bracing. t.i. pa#201405166024. n/a ordinance #155-13 | $162,225 |
| Oct 29, 2014 | Completed final sign-off Dec 2014 | 101 Spear St | Red Hawk Fire & Security Ca Llc | fire alarm ti on 4th fl 1 power supply, 1 pull station, 2 strobes, 1 smoke detector, 44 speaker strobes, 20 duct detectors, 18 relaysDetails
fire alarm ti on 4th fl 1 power supply, 1 pull station, 2 strobes, 1 smoke detector, 44 speaker strobes, 20 duct detectors, 18 relays | $10,000 |
| Oct 23, 2014 | Never finaled issued Oct 2014, no final | 101 Spear St | street spaceDetails
street space | ||
| Oct 9, 2014 | Completed final sign-off Mar 2015 | 101 Spear St | Hathaway Dinwiddie Co. | 1st flr: training room, revise exiting and add door, as indicated in plans for office t.i. on 1st flr; maher n/aDetails
1st flr: training room, revise exiting and add door, as indicated in plans for office t.i. on 1st flr; maher n/a | $1,000 |
| Aug 21, 2014 | Never finaled issued Aug 2014, no final | 101 Spear St | Golden Gate Fire Protection Inc | 4th floor fire sprinkler - relocate 82 pendent sprinkler heads, relcoate 52 upright sprinkler heads, upgrade end of line bracing & earthquake bracing. ref ti #2013.1113.1835.Details
4th floor fire sprinkler - relocate 82 pendent sprinkler heads, relcoate 52 upright sprinkler heads, upgrade end of line bracing & earthquake bracing. ref ti #2013.1113.1835. | $69,010 |
| Aug 14, 2014 | Expired or cancelled withdrawn Sep 2014 | 101 Spear St | 1st flr t.i. (ref.201310240182); existing office space, mep included, fire alarm & sprinkler under separate permit for fire review only.building & mep approved under 201310240182; maher n/aDetails
1st flr t.i. (ref.201310240182); existing office space, mep included, fire alarm & sprinkler under separate permit for fire review only.building & mep approved under 201310240182; maher n/a | $1,530,000 | |
| Jul 14, 2014 | Completed final sign-off Feb 2015 | 101 Spear St | Hathaway Dinwiddie Co. | to erect non-electrical sign on bldg wall in courtyard. n/a for the maher ordinance #155-13Details
to erect non-electrical sign on bldg wall in courtyard. n/a for the maher ordinance #155-13 | $3,000 |
| Jul 14, 2014 | Completed final sign-off Feb 2015 | 101 Spear St | Hathaway Dinwiddie Co. | to erect non-electrical directional sign in courtyard entry. n/a for the maher ordinance #155-13Details
to erect non-electrical directional sign in courtyard entry. n/a for the maher ordinance #155-13 | $800 |
| Jul 14, 2014 | Completed final sign-off Feb 2015 | 101 Spear St | Hathaway Dinwiddie Co. | to erect non-electrical and non illuminated panel signage on extg projected blade sign on spear street and steurt street . n/a for the maher ordinance #155-13Details
to erect non-electrical and non illuminated panel signage on extg projected blade sign on spear street and steurt street . n/a for the maher ordinance #155-13 | $5,000 |
| Jul 14, 2014 | Completed final sign-off Feb 2015 | 101 Spear St | Hathaway Dinwiddie Co. | to erect electrical sign above main entrance door way. n/a for the maher ordinance #155-13Details
to erect electrical sign above main entrance door way. n/a for the maher ordinance #155-13 | $20,000 |
| Jun 30, 2014 | Completed final sign-off Mar 2015 | 101 Spear St | Hathaway Dinwiddie Co. | partail interior t.i. on 4th floor. fully sprinklered building. mep under separate permit. maher n/a. revision appl 201311131835.Details
partail interior t.i. on 4th floor. fully sprinklered building. mep under separate permit. maher n/a. revision appl 201311131835. | $20,000 |
| Jun 26, 2014 | Completed final sign-off Aug 2016 | 101 Spear St | Hathaway Dinwiddie Co. | 2nd floor tenant improvement on existing office space (partial floor t.i.), new mep work. n/a maher ordinanceDetails
2nd floor tenant improvement on existing office space (partial floor t.i.), new mep work. n/a maher ordinance | $1,528,688 |
| Jun 18, 2014 | Completed final sign-off Oct 2014 | 101 Spear St | Westower Communications | remove antenas, coax and conduit, and radio equipment. (nextel) n/a for the maher ordinance #155-13Details
remove antenas, coax and conduit, and radio equipment. (nextel) n/a for the maher ordinance #155-13 | $10,000 |
| May 16, 2014 | Completed final sign-off Apr 2015 | 101 Spear St | tenanat improvement on the 5th floor, existing office space, new mechanical, electrical, & plumbing work n//a maherDetails
tenanat improvement on the 5th floor, existing office space, new mechanical, electrical, & plumbing work n//a maher | $1,528,688 | |
| Apr 30, 2014 | Completed final sign-off Oct 2014 | 101 Spear St | Hathaway Dinwiddie Co. | revision to 201310240182. 1st fl partial tenant improvement. reconfigure 1st fl to include new food service area; compliance with ord 155-13 not requiredDetails
revision to 201310240182. 1st fl partial tenant improvement. reconfigure 1st fl to include new food service area; compliance with ord 155-13 not required | $500,000 |
| Apr 29, 2014 | Never finaled issued Apr 2014, no final | 101 Spear St | street spaceDetails
street space | ||
| Apr 28, 2014 | Never finaled issued Apr 2014, no final | 101 Spear St | Martinelli Environmental Graph | 3rd floor - installation of six evacuation maps. compliance with ordinance # 155-13 n/aDetails
3rd floor - installation of six evacuation maps. compliance with ordinance # 155-13 n/a | $600 |
| Apr 2, 2014 | Completed final sign-off Jul 2014 | 101 Spear St | Golden Gate Fire Protection Inc | 1st floor - relocate 86 pendent sprinklers, relcoate 56 upright sprinklers, upgrade end of line bracing & earthquake bracing. ref #2013.1024.0182. compliance with ordinance #155-13 not requiredDetails
1st floor - relocate 86 pendent sprinklers, relcoate 56 upright sprinklers, upgrade end of line bracing & earthquake bracing. ref #2013.1024.0182. compliance with ordinance #155-13 not required | $73,130 |
| Mar 5, 2014 | Completed final sign-off May 2014 | 101 Spear St | Golden Gate Fire Protection Inc | relocate 232 pendent sprinkler heads on the 3rd fl. relocate 267 upright sprinkler heads. upgrade end of line and earthquake bracing. add new preaction cabinet. mahar ordiance not required.Details
relocate 232 pendent sprinkler heads on the 3rd fl. relocate 267 upright sprinkler heads. upgrade end of line and earthquake bracing. add new preaction cabinet. mahar ordiance not required. | $256,985 |
| Feb 18, 2014 | Completed final sign-off Aug 2014 | 101 Spear St | Red Hawk Fire & Security Ca Llc | fire alarm ti 1st and 3rd fl: 5 booster panels, 3 control modules, 2 manual pulls, 151 speaker strobes, 3 strobes, 8 speakers, 62 smoke detectors, 65 duct detectors, 274 relays. compliance with ordinance no. 155-13 not required.Details
fire alarm ti 1st and 3rd fl: 5 booster panels, 3 control modules, 2 manual pulls, 151 speaker strobes, 3 strobes, 8 speakers, 62 smoke detectors, 65 duct detectors, 274 relays. compliance with ordinance no. 155-13 not required. | $30,000 |
| Feb 14, 2014 | Completed final sign-off Jun 2014 | 101 Spear St | Intelligent Technologies & Services Inc | 3rd floor: mdf pre-action detection and notification. 6 smoke and 1 bell. ref app#201310240183. n/a for the maher ordinance #155-13Details
3rd floor: mdf pre-action detection and notification. 6 smoke and 1 bell. ref app#201310240183. n/a for the maher ordinance #155-13 | $3,200 |
| Nov 6, 2012 | Completed final sign-off Apr 2013 | 101 Spear St | scope of work. unit a7. change of use only from flower shop to fast food restaurant/retail. changes sink basin. no change to plumbing. no construction.Details
scope of work. unit a7. change of use only from flower shop to fast food restaurant/retail. changes sink basin. no change to plumbing. no construction. | $200 | |
| Jul 9, 2012 | Expired or cancelled cancelled Jan 2026 | 101 Spear St | revision to bpa#2012-0406-7789 to add demising walls to tenant improvement. 1 one hour rated & 1 two hr rated wall at elevator shaft and stair.Details
revision to bpa#2012-0406-7789 to add demising walls to tenant improvement. 1 one hour rated & 1 two hr rated wall at elevator shaft and stair. | $5,000 | |
| Jun 29, 2012 | Expired or cancelled cancelled Jun 2014 | 101 Spear St | Signtech Electrical Advertising Inc. | install (1) non-electric, projecting, double-faced, non-illuminated, new sign for "chase"Details
install (1) non-electric, projecting, double-faced, non-illuminated, new sign for "chase" | $500 |
| Jun 29, 2012 | Expired or cancelled cancelled Jun 2014 | 101 Spear St | Signtech Electrical Advertising Inc. | install (4) electric, wall, single-faced, direct, new soffit band sign for "chase"Details
install (4) electric, wall, single-faced, direct, new soffit band sign for "chase" | $8,000 |
| Jun 29, 2012 | Expired or cancelled cancelled Jun 2014 | 101 Spear St | Signtech Electrical Advertising Inc. | install (2) electric, single-faced, window, direct, new sign on building interior for "chase".Details
install (2) electric, single-faced, window, direct, new sign on building interior for "chase". | $3,000 |
| Jun 29, 2012 | Expired or cancelled cancelled Jun 2014 | 101 Spear St | Signtech Electrical Advertising Inc. | install electric, wall, single-faced, direct, illuminated atm sign for "chase"Details
install electric, wall, single-faced, direct, illuminated atm sign for "chase" | $2,000 |
| Apr 6, 2012 | Expired or cancelled cancelled Jan 2026 | 101 Spear St | tenant improvement of existing leased space for a branch bank. work includes 2 atms, non structural partitions, ceilings, soffits, finishes, furniture and related hvac, elec, plumbing workDetails
tenant improvement of existing leased space for a branch bank. work includes 2 atms, non structural partitions, ceilings, soffits, finishes, furniture and related hvac, elec, plumbing work | $466,302 | |
| Apr 6, 2012 | Never finaled issued May 2012, no final | 101 Spear St | Howard S. Wright Constructors Lp | tenant improvement of existing leased space for a branch bank. work includes 2 atms, non structural partitions, ceilings, soffits, finishes, furniture and related hvac, elec, and plumbingDetails
tenant improvement of existing leased space for a branch bank. work includes 2 atms, non structural partitions, ceilings, soffits, finishes, furniture and related hvac, elec, and plumbing | $466,302 |
| Mar 27, 2012 | Completed final sign-off Apr 2012 | 101 Spear St | Aura Fire Safety Inc | ground floor-upgrade fire system for hood & duct in the kitchen area to meet ul-300 standardsDetails
ground floor-upgrade fire system for hood & duct in the kitchen area to meet ul-300 standards | $1,500 |
| Jan 13, 2012 | Completed final sign-off Feb 2012 | 101 Spear St | Skyline Construction | 4th floor-revision to pa# 2011-0614-8065 to add 2 fire smoke dampers. refer to pa# 2011-0310-1803Details
4th floor-revision to pa# 2011-0614-8065 to add 2 fire smoke dampers. refer to pa# 2011-0310-1803 | $450 |
| Jul 21, 2011 | Completed final sign-off Feb 2012 | 101 Spear St | Skyline Construction | revision to 201103101803: change server room to telephone closet. elec, lightingDetails
revision to 201103101803: change server room to telephone closet. elec, lighting | $125,000 |
| Jun 17, 2011 | Completed final sign-off Feb 2012 | 101 Spear St | Red Hawk Fire & Security Ca Llc | 4th floor fire alarm t.i. - intrax: (1) input/output modules for fsd & new fan; (1) control relay for fan overide; (1) duct detector for fan, (2) ceiling strobes, (49) ceiling speaker strobes. ref arch pa #201103101803.Details
4th floor fire alarm t.i. - intrax: (1) input/output modules for fsd & new fan; (1) control relay for fan overide; (1) duct detector for fan, (2) ceiling strobes, (49) ceiling speaker strobes. ref arch pa #201103101803. | $10,827 |
| Jun 14, 2011 | Completed final sign-off Feb 2012 | 101 Spear St | Skyline Construction | 4th fl - mechanical work for tenant improvment on the 4th floor including lowver. landmark 107 rincon annex post officeDetails
4th fl - mechanical work for tenant improvment on the 4th floor including lowver. landmark 107 rincon annex post office | $120,000 |
| May 12, 2010 | Expired or cancelled cancelled Jan 2026 | 101 Spear St | Aura Safety & Associates | install fire suppression for hood & duct with ul-300 standardsDetails
install fire suppression for hood & duct with ul-300 standards | |
| May 12, 2010 | Never finaled issued May 2010, no final | 101 Spear St | Aura Safety & Associates | unit #a-15-install fire suppression for hood & duct with ul-300 standardsDetails
unit #a-15-install fire suppression for hood & duct with ul-300 standards | $4,500 |
| Apr 30, 2010 | Completed final sign-off Apr 2011 | 101 Spear St | Aura Safety & Associates | install fire suppression system in a restaurant. upgrade to ul 300Details
install fire suppression system in a restaurant. upgrade to ul 300 | $3,500 |
| Sep 11, 2009 | Never finaled issued Sep 2009, no final | 101 Spear St | Aaa Restaurant Fire Control/Dba Aaa Fire | ground floor-furnish & install 1 ansul r-102 fire suppression system in the main kitchen area on the ground floor.Details
ground floor-furnish & install 1 ansul r-102 fire suppression system in the main kitchen area on the ground floor. | $2,000 |
| Apr 14, 2009 | Never finaled issued Apr 2009, no final | 101 Spear St | Exxell Corp. Dba Exxell Fire Systems | ul300 upgrade of fire suppression system.Details
ul300 upgrade of fire suppression system. | $4,000 |
| Mar 31, 2009 | Never finaled issued Mar 2009, no final | 101 Spear St | Terra Nova Industries | remove some non-bearing wall & ceiling, grid and tile carpet remove and safty off, electrical in walls removed, work on first floor only. exception ada requirments per ab-017. life safety under separate permits.Details
remove some non-bearing wall & ceiling, grid and tile carpet remove and safty off, electrical in walls removed, work on first floor only. exception ada requirments per ab-017. life safety under separate permits. | $5,000 |
| Jun 16, 2008 | Completed final sign-off Sep 2008 | 101 Spear St | Ayoob & Peery Plumbing Co Inc | relocate sprinkler heads per t.i. improvements. total of 33 heads.Details
relocate sprinkler heads per t.i. improvements. total of 33 heads. | $4,845 |
| Apr 4, 2008 | Never finaled issued Apr 2008, no final | 101 Spear St | Rcm Fire Protection Inc. | relocate 165 sprinkler heads for tenant improvement.(e) protection @ above ceiling to remain , areas where exposed to deck above.Details
relocate 165 sprinkler heads for tenant improvement.(e) protection @ above ceiling to remain , areas where exposed to deck above. | $24,000 |
| Jun 19, 2007 | Never finaled issued Jun 2007, no final | 101 Spear St | R L H Fire Protection Inc | 2nd floor - t. i. upgrade of fire sprinkler system. relocate 2 sprinkler heads and added 1 sprinkler head.Details
2nd floor - t. i. upgrade of fire sprinkler system. relocate 2 sprinkler heads and added 1 sprinkler head. | $4,392 |
| Feb 12, 2004 | Completed final sign-off Jul 2004 | 101 Spear St | building a wood rack in storage space s-2 for storage of table tops-reference pa 9906205Details
building a wood rack in storage space s-2 for storage of table tops-reference pa 9906205 | $1,000 | |
| Jan 22, 2004 | Expired or cancelled expired Jan 2005 | 101 Spear St | install 1 18" omni antenna & relocate 1 (e) antenna to top of railDetails
install 1 18" omni antenna & relocate 1 (e) antenna to top of rail | $15,000 | |
| Oct 14, 2003 | Completed final sign-off Dec 2003 | 101 Spear St | Rudolph Commercial Interiors Inc, Rci | oti-2,2nd floor-el, me, spDetails
oti-2,2nd floor-el, me, sp | $69,000 |
| Aug 22, 2003 | Completed final sign-off Dec 2003 | 101 Spear St | Rudolph Commercial Interiors Inc, Rci | oti-1 el,me,ls,spDetails
oti-1 el,me,ls,sp | $115,000 |