Dorel Anghel
- Listed as
- engineer
- Firm
- Mechanical Deisgn Studio
- Based in
- Walnut Creek
- On San Francisco permits
- Jan 2005 to Sep 2026
59 permits since 2000 (engineer on 59 permits): 39 completed, 4 in progress, 11 never finaled, 5 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 29, 2026 | In progress issued Sep 2026 | 600 Townsend St | Kr Johnston Construction Inc | modify hvac ductwork for new layout. add electrical outlets. modify lighting. ref pa# 202605070870Details
modify hvac ductwork for new layout. add electrical outlets. modify lighting. ref pa# 202605070870 | $20,000 |
| Aug 28, 2026 | In progress issued Aug 2026 | 3 Embarcadero Center | Vulcan Construction Inc | ste 2350- mep deferred for bpa: 202607104811. new lights, new outlets, new floor monuments, new vav to supply new offices.Details
ste 2350- mep deferred for bpa: 202607104811. new lights, new outlets, new floor monuments, new vav to supply new offices. | $75,000 |
| Aug 28, 2026 | In progress issued Aug 2026 | 1945 Irving St | Matrix Hg Inc | replacement of four rooftop package a/c units with gas heating. same location of roofDetails
replacement of four rooftop package a/c units with gas heating. same location of roof | $47,000 |
| Aug 28, 2026 | In progress issued Aug 2026 | 2485 San Bruno Av | Matrix Hg Inc | replacement of three rooftop package a/c units with gas heating.Details
replacement of three rooftop package a/c units with gas heating. | $31,000 |
| Jun 3, 2026 | Completed final sign-off Aug 2026 | 3 Embarcadero Center | Vulcan Construction Inc | 8/f: installing transfer grills and replacing lights. (deferred mep for pa# 202603107215)Details
8/f: installing transfer grills and replacing lights. (deferred mep for pa# 202603107215) | $75,000 |
| May 15, 2026 | Completed final sign-off Jun 2026 | 2300 Harrison St | Matrix Hg Inc | 2/f: restroom exhaust fan, ductwork, and outlets. one vav box relocation. ref permit 202604139302Details
2/f: restroom exhaust fan, ductwork, and outlets. one vav box relocation. ref permit 202604139302 | $15,000 |
| May 6, 2026 | Completed final sign-off Jun 2026 | 77 Federal St | Ewsf Inc. | 1/f and basement: revision to 202602035133. add (1) office room, (2) phone room and (1) idf room on level 1. new soffit and (2) closets at break area l1. bottle filler devices added to break area 4 and basement.Details
1/f and basement: revision to 202602035133. add (1) office room, (2) phone room and (1) idf room on level 1. new soffit and (2) closets at break area l1. bottle filler devices added to break area 4 and basement. | $6,000 |
| Feb 3, 2026 | Completed final sign-off Jun 2026 | 77 Federal St | Ewsf Inc. | 1st fl & basement improvement: new non structural walls & partitions. new interior finishes, two new bathrooms, one new mother's room with sink, two new sink counters. mep modification. change of use from retail space (gym) to business service b. no exterior, structural or demo work.Details
1st fl & basement improvement: new non structural walls & partitions. new interior finishes, two new bathrooms, one new mother's room with sink, two new sink counters. mep modification. change of use from retail space (gym) to business service b. no exterior, structural or demo work. | $300,000 |
| Aug 29, 2025 | Completed final sign-off Feb 2026 | 315 Montgomery St | Matrix Hg Inc | 5th fl - replacement of (1) 3 ton water source heat pump. the equipment is above ceiling & serves a 5th l iof closetDetails
5th fl - replacement of (1) 3 ton water source heat pump. the equipment is above ceiling & serves a 5th l iof closet | $15,000 |
| Jun 26, 2025 | Completed final sign-off Mar 2026 | 1500 16th St | Ewsf Inc. | 1500 16th st was gym, now change of use as #201/2nd fl to business services. 1st/f #101 to be whole sale . 1st fl/#102,103,104,105,106,107 to be whole sale. demo e) wall & partitions. construct n) walls,partitions,ada ramps, restrooms,skylights. replace exterior windows & storefronts.n)lights/panelsDetails
1500 16th st was gym, now change of use as #201/2nd fl to business services. 1st/f #101 to be whole sale . 1st fl/#102,103,104,105,106,107 to be whole sale. demo e) wall & partitions. construct n) walls,partitions,ada ramps, restrooms,skylights. replace exterior windows & storefronts.n)lights/panels | $320,000 |
| Mar 31, 2025 | Completed final sign-off Aug 2025 | 77 Federal St | Ewsf Inc. | floor 4 and 5: office t.i (10,524 sf) each floor. demo of (e) non-bearing partition walls, new walls for meeting room and offices, new finishes (flooring, ceiling, lighting). modify mechanical and electrical design based on new layout. t-24 compliance. no plumbing. no change of use.Details
floor 4 and 5: office t.i (10,524 sf) each floor. demo of (e) non-bearing partition walls, new walls for meeting room and offices, new finishes (flooring, ceiling, lighting). modify mechanical and electrical design based on new layout. t-24 compliance. no plumbing. no change of use. | $420,000 |
| May 22, 2024 | Completed final sign-off May 2025 | 1333 Bush St | C B 2 Builders Incorporated | ti of existing commercial kitchen. addition of new two compartment prep sinks, relocate existing station, addition of two gfci receptacles in existing dry storage room and associated breakers in existing electrical panels. replace finishes as needed.Details
ti of existing commercial kitchen. addition of new two compartment prep sinks, relocate existing station, addition of two gfci receptacles in existing dry storage room and associated breakers in existing electrical panels. replace finishes as needed. | $20,000 |
| Sep 9, 2022 | Completed final sign-off Jun 2023 | 55 Francisco St | Swinerton Builders | mechanical only work to floors 5,6,7. demo fan coils and connect duct risers to ductwork distribution systems to be servied by hav under 202203291063Details
mechanical only work to floors 5,6,7. demo fan coils and connect duct risers to ductwork distribution systems to be servied by hav under 202203291063 | $45,000 |
| Jul 6, 2022 | Completed final sign-off Jul 2022 | 1686 Market St | Emcor Services/Mesa Energy Systems Inc | revision to bpa 201905090211. as-built: revise access doors on ductwork.Details
revision to bpa 201905090211. as-built: revise access doors on ductwork. | |
| Aug 22, 2019 | Completed final sign-off May 2020 | 44 Montgomery St | Swinerton Builders | g/f suite 140: demo non-structural partitions, doors, millwork, finishes. construct (n) partitions, install (n) doors, millwork, lights, modify mech to accomodate new layout.Details
g/f suite 140: demo non-structural partitions, doors, millwork, finishes. construct (n) partitions, install (n) doors, millwork, lights, modify mech to accomodate new layout. | $118,000 |
| Aug 1, 2019 | Never finaled issued Aug 2019, no final | 655 Beach St | Trans Bay Air | install 2-ton split system heating pump to service the learning center. connect to (e) ductwork located above steetrock ceiling.Details
install 2-ton split system heating pump to service the learning center. connect to (e) ductwork located above steetrock ceiling. | $15,500 |
| May 22, 2019 | Completed final sign-off Sep 2022 | 1 Front St | Swinerton Builders | 18th fl: demo non structural partitions, doors, lights, finishes. construct new - partitions, doors, frames, millwork, lights. reconfigure mech to fit in new layout & new finishes. maher naDetails
18th fl: demo non structural partitions, doors, lights, finishes. construct new - partitions, doors, frames, millwork, lights. reconfigure mech to fit in new layout & new finishes. maher na | $80,500 |
| May 3, 2019 | Never finaled issued May 2019, no final | 111 Pine St | Western Allied Mechanical Inc. | 3/f: furnish & install (1) water source heat pump and associated duct & piping on 3rd fl. maher n/a.Details
3/f: furnish & install (1) water source heat pump and associated duct & piping on 3rd fl. maher n/a. | $40,000 |
| Aug 16, 2018 | Completed final sign-off Apr 2019 | 135 Post St | Emcor Services/Mesa Energy Systems Inc | rooftop: a/c unit replacements, like for like, in-kind (2xa/c + 2 condensors). maher n/a.Details
rooftop: a/c unit replacements, like for like, in-kind (2xa/c + 2 condensors). maher n/a. | $35,000 |
| May 30, 2018 | Completed final sign-off Aug 2019 | 1 Front St | Swinerton Builders | 15th fl: demo of (e) structural partitions, doors, cabinets, lights, finishes, mech, construct (n) partitions, install new lights, mechanical, finishes & (n) single use toilet. maher naDetails
15th fl: demo of (e) structural partitions, doors, cabinets, lights, finishes, mech, construct (n) partitions, install new lights, mechanical, finishes & (n) single use toilet. maher na | $750,000 |
| Mar 1, 2018 | Completed final sign-off Apr 2018 | 25 Van Ness Av | Emcor Services/Mesa Energy Systems Inc | like for like replacement of 11 heat pumps in basement. ref. 201612165160, pp20130401543, pm20130401544. n/a maherDetails
like for like replacement of 11 heat pumps in basement. ref. 201612165160, pp20130401543, pm20130401544. n/a maher | $11,800 |
| Dec 13, 2017 | Completed final sign-off May 2018 | 1354 Castro St | Swinerton Builders | demo (e) non structural partitions & finishes, construct (n) non structural partitions, doors, millwork, finishes, electrical to accomodate (n) layout & mechanical.Details
demo (e) non structural partitions & finishes, construct (n) non structural partitions, doors, millwork, finishes, electrical to accomodate (n) layout & mechanical. | $85,000 |
| Oct 31, 2017 | Never finaled issued Oct 2017, no final | 250 04th St | Fuel Oil System | no additional work will be performed based on inspectors' comments. new changes in details of drawings have been encorporated. ref pa# 201306280802 (s-9).Details
no additional work will be performed based on inspectors' comments. new changes in details of drawings have been encorporated. ref pa# 201306280802 (s-9). | |
| Oct 27, 2017 | Completed final sign-off Dec 2018 | 875 Howard St | Emcor Services/Mesa Energy Systems Inc | install new 65-ton self contained, water cooled a/c unit.Details
install new 65-ton self contained, water cooled a/c unit. | $178,600 |
| Oct 6, 2017 | Never finaled issued Oct 2017, no final | 650 Townsend St | Emcor Services/Mesa Energy Systems Inc | 4th fl: install one (1) 3-ton cooling only split system. maher naDetails
4th fl: install one (1) 3-ton cooling only split system. maher na | $26,438 |
| Oct 6, 2017 | Never finaled issued Oct 2017, no final | 5 The Embarcadero | Emcor Services/Mesa Energy Systems Inc | replace and remove (2) air handler units. one at street level & one at intermediate level. maher maDetails
replace and remove (2) air handler units. one at street level & one at intermediate level. maher ma | $42,302 |
| Oct 6, 2017 | Completed final sign-off Aug 2018 | 444 De Haro St | Emcor Services/Mesa Energy Systems Inc | replace boiler & circulating pump with (2) new high efficiency condensing boilers. maher naDetails
replace boiler & circulating pump with (2) new high efficiency condensing boilers. maher na | $201,437 |
| Oct 6, 2017 | Completed final sign-off Aug 2018 | 444 De Haro St | Emcor Services/Mesa Energy Systems Inc | new garage exhaust fans, new co monitoring control system. maher naDetails
new garage exhaust fans, new co monitoring control system. maher na | $89,421 |
| Jun 30, 2017 | Completed final sign-off Mar 2018 | 1 Front St | Skender Construction Llc | new type 2 kitchen hood, makeup air unit and associated duct work, piping air outlets and controlsDetails
new type 2 kitchen hood, makeup air unit and associated duct work, piping air outlets and controls | $150,000 |
| May 23, 2017 | Never finaled issued May 2017, no final | 1 Front St | Swinerton Builders | 4/f- demo non structural partitions, lights, ceilings, finishes. construct (n) non structural partitions, doors, ceilings, finishes, install lights, mech to accommodate (n) lauyout. n/a ordinance #155-13. life safety deferred.Details
4/f- demo non structural partitions, lights, ceilings, finishes. construct (n) non structural partitions, doors, ceilings, finishes, install lights, mech to accommodate (n) lauyout. n/a ordinance #155-13. life safety deferred. | $550,000 |
| Jan 30, 2017 | Completed final sign-off Nov 2017 | 111 Pine St | Swinerton Builders | 6/f- demo (e) non-structural partitions, construct (n) non structural partitions, install new doors, millwork, carpet, paint, finishes, lights, accommodate mechanic for (n) wall layout. n/a ordinance #155-13Details
6/f- demo (e) non-structural partitions, construct (n) non structural partitions, install new doors, millwork, carpet, paint, finishes, lights, accommodate mechanic for (n) wall layout. n/a ordinance #155-13 | $625,000 |
| Oct 27, 2016 | Completed final sign-off Feb 2017 | 266 Sutter St | Harrow Construction Corporation | 4/f- t.i. beauty /hair salon to accommodate 4 relocated shampoo bowls and bathroom retrofit for d.a. new exhaust system and intake, new bigger water heater, lighting only. n/a ordinance #133-15Details
4/f- t.i. beauty /hair salon to accommodate 4 relocated shampoo bowls and bathroom retrofit for d.a. new exhaust system and intake, new bigger water heater, lighting only. n/a ordinance #133-15 | $20,000 |
| May 9, 2016 | Completed final sign-off Dec 2016 | 3325 Sacramento St | Oakstone Construction Inc. | ti- new interior non-bearing partitions, suspended ceilings, millwork, mechanical, plumbing and electrical. restore (e) cleverstory window, new store front. accessible entrance.Details
ti- new interior non-bearing partitions, suspended ceilings, millwork, mechanical, plumbing and electrical. restore (e) cleverstory window, new store front. accessible entrance. | $288,000 |
| Dec 15, 2015 | Completed final sign-off Aug 2017 | 10 Hawthorne St | Herrero Builders Incorporated | mechanical work for t.i. pa# 201512084388 on 1/f, 2/f & basement.Details
mechanical work for t.i. pa# 201512084388 on 1/f, 2/f & basement. | $98,000 |
| Dec 8, 2015 | Completed final sign-off Aug 2017 | 10 Hawthorne St | Herrero Builders Incorporated | ti to convert vacant space to a gallery, 2 floors & basement. some structure, mep. defered total 10,080 sfDetails
ti to convert vacant space to a gallery, 2 floors & basement. some structure, mep. defered total 10,080 sf | $735,000 |
| Dec 8, 2015 | Completed final sign-off Jun 2017 | 10 Hawthorne St | Herrero Builders Incorporated | demo onlyDetails
demo only | $25,000 |
| Sep 11, 2015 | Never finaled issued Sep 2015, no final | 100 California St | Swinerton Builders | ground floor lobby - install new ductwork to existing zones, install new supply/return air diffusers, isntall new space heater. install (2) new fire dampers ref #201508043281. n/a maher ordinanceDetails
ground floor lobby - install new ductwork to existing zones, install new supply/return air diffusers, isntall new space heater. install (2) new fire dampers ref #201508043281. n/a maher ordinance | $20,000 |
| Sep 11, 2015 | Never finaled issued Sep 2015, no final | 100 California St | Acco Engineered Systems Inc. Dba Acco En | basement - install make-up air & exhaust systems for bike storage & shower/locker room areas. ref #201508043283. n/a meher ordinanceDetails
basement - install make-up air & exhaust systems for bike storage & shower/locker room areas. ref #201508043283. n/a meher ordinance | $106,000 |
| Nov 25, 2014 | Never finaled issued Dec 2014, no final | 1912 Lombard St | San Francisco Investment Development | mep to install high efficiecy gas furnace and ventilation system. ref. appl.# 201407070556 & revise architectural plans to match hvac & revise to one bathroom unisex.Details
mep to install high efficiecy gas furnace and ventilation system. ref. appl.# 201407070556 & revise architectural plans to match hvac & revise to one bathroom unisex. | $20,000 |
| Aug 22, 2014 | Completed final sign-off Oct 2014 | 2180 Harrison St | Matrix Hg Inc | install one new split air conditioning system. new fire and smoke dampers at elevator machine room walls. maher n/a.Details
install one new split air conditioning system. new fire and smoke dampers at elevator machine room walls. maher n/a. | $15,000 |
| Jun 30, 2014 | Completed final sign-off Oct 2014 | 180 Montgomery St | Matrix Hg Inc | demo (12) vav boxes, 42 sq registers, 8 ra/exh registers, 1 fire damper, associated low press ducting, install new 12 vav boxes, 54 sa registers, 21 ra/exh registers, associated low press ducting, 1 fan coil unit, relocate 12 t-stats, ref. 201406118134Details
demo (12) vav boxes, 42 sq registers, 8 ra/exh registers, 1 fire damper, associated low press ducting, install new 12 vav boxes, 54 sa registers, 21 ra/exh registers, associated low press ducting, 1 fan coil unit, relocate 12 t-stats, ref. 201406118134 | $27,500 |
| Jun 26, 2014 | Expired or cancelled cancelled Jan 2026 | 595 Market St | Gci, Inc | mechanical work for tenant improvement. ref. arch #201405064972Details
mechanical work for tenant improvement. ref. arch #201405064972 | $5,000 |
| Jun 26, 2014 | Expired or cancelled cancelled Jan 2026 | 595 Market St | Gci, Inc | mechanical work for tenant improvement. ref. arch #201405064975Details
mechanical work for tenant improvement. ref. arch #201405064975 | $5,000 |
| Apr 20, 2012 | Completed final sign-off Dec 2012 | 1271 Mission St | Aspen Building Group Inc | partial demo of existing ductwork. new ductwork. new furnace on 1st fl, replace e furnace in basement. remove front security gate/sign/marble wainsoat. re stucco wainscoat & paint front of bldg.Details
partial demo of existing ductwork. new ductwork. new furnace on 1st fl, replace e furnace in basement. remove front security gate/sign/marble wainsoat. re stucco wainscoat & paint front of bldg. | $98,550 |
| Sep 8, 2008 | Never finaled issued Sep 2008, no final | 409 Illinois St | Fuel Oil System | revision to permit #200802084320. change piping to double contained with spill pans at main tank.Details
revision to permit #200802084320. change piping to double contained with spill pans at main tank. | |
| Aug 19, 2008 | Expired or cancelled cancelled May 2009 | 550 California St | Fuel Oil System | installation of wall mounted remote fill station for purpose of filling a new 500 gallon generator belly tank serving new 450kw gen (by others) ref pa# 2008/07/02/5895Details
installation of wall mounted remote fill station for purpose of filling a new 500 gallon generator belly tank serving new 450kw gen (by others) ref pa# 2008/07/02/5895 | $25,000 |
| Jul 2, 2008 | Completed final sign-off Feb 2009 | 303 02nd St | ti for new wells fargo bank branch on the ground floor. new interior store front, tellerline, equipmt rm, atm rm,ceiling, new finishes, paint, carpet and new furnitures.Details
ti for new wells fargo bank branch on the ground floor. new interior store front, tellerline, equipmt rm, atm rm,ceiling, new finishes, paint, carpet and new furnitures. | $100,000 | |
| Apr 4, 2008 | Completed final sign-off Jul 2009 | 1390 Mission St | Fuel Oil System | revision to pa# 2006-0614-4078/s7-revision to change secondary piping to 40" sch 10 astm, additional leak detectors.Details
revision to pa# 2006-0614-4078/s7-revision to change secondary piping to 40" sch 10 astm, additional leak detectors. | |
| Dec 5, 2007 | Completed final sign-off Apr 2008 | 4045 24th St | Hathaway Dinwiddie Co. | remove existing partitions, counters, ceiling grid within space, new partitions, doors, glazing, light fixtures, millwork & finishes for new office layout. provive new restroom to meet accessability req, provide new elec outlets for new office, provive new hvac ducts w/support w/supply return as reqDetails
remove existing partitions, counters, ceiling grid within space, new partitions, doors, glazing, light fixtures, millwork & finishes for new office layout. provive new restroom to meet accessability req, provide new elec outlets for new office, provive new hvac ducts w/support w/supply return as req | $325,187 |
| Nov 9, 2007 | Never finaled issued Dec 2007, no final | 4045 24th St | change of use from retail phramacy to financial institution( wells fargo bank).(n) storefront, awning, 2 atms, lighting and exterior wall tile. interior work includes tellerline area, atms, pantry,restrm and equipment rm.(n) 1hr rated corridor to ext. and power data. sprinkler under separate paDetails
change of use from retail phramacy to financial institution( wells fargo bank).(n) storefront, awning, 2 atms, lighting and exterior wall tile. interior work includes tellerline area, atms, pantry,restrm and equipment rm.(n) 1hr rated corridor to ext. and power data. sprinkler under separate pa | $125,000 | |
| Sep 26, 2007 | Expired or cancelled expired Jul 2009 | 923 Folsom St | installation of mechanical system. plumbing and electrical with ref. to pa#2006/12/08/9526.Details
installation of mechanical system. plumbing and electrical with ref. to pa#2006/12/08/9526. | $65,000 | |
| Feb 2, 2007 | Completed final sign-off Mar 2007 | 405 Howard St | Fuel Oil System | install 2-1200 gallon storage tanks, 2 pump sets & 2 remote fill panels.Details
install 2-1200 gallon storage tanks, 2 pump sets & 2 remote fill panels. | $65,000 |
| Jan 20, 2006 | Expired or cancelled withdrawn Feb 2007 | 640 Bryant St | mechanical, electrical, lighting.Details
mechanical, electrical, lighting. | $35,000 | |
| Jan 20, 2006 | Completed final sign-off Jul 2007 | 640 Bryant St | Novo Construction Inc | demolish (e) interior walls, install new interior walls. office partitions, electrical, lighting, finishes. new lights, spray booth.Details
demolish (e) interior walls, install new interior walls. office partitions, electrical, lighting, finishes. new lights, spray booth. | $150,000 |
| Oct 27, 2005 | Completed final sign-off Dec 2005 | 600 Harrison St | Gci, Inc | oti-5 3rd floor meDetails
oti-5 3rd floor me | $175,000 |
| Jun 28, 2005 | Completed final sign-off Mar 2006 | 600 Stockton St | Carrier Corporation | modify (e) chilled water plant to expand with addition of pure comfort cogeneration system.Details
modify (e) chilled water plant to expand with addition of pure comfort cogeneration system. | $175,000 |
| Apr 5, 2005 | Completed final sign-off Sep 2005 | 525 Market St | Novo Construction Inc | oti-2 4/f el meDetails
oti-2 4/f el me | $250,000 |
| Jan 20, 2005 | Completed final sign-off Mar 2005 | 1 Sansome St | oti-2 32nd floor, el, meDetails
oti-2 32nd floor, el, me | $50,000 | |
| Jan 20, 2005 | Completed final sign-off Mar 2005 | 1 Sansome St | oti-1 32nd floor, el, me, ls, spDetails
oti-1 32nd floor, el, me, ls, sp | $125,000 |