Block 0834, lot 004
27 Van Ness Ave
- City’s use
- Commercial Office
- Built
- 1911
- Stories
- 8
- Rooms
- 15 bathrooms
- Lot
- 19,740 sq ft
- Zoning
- C3G
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
88 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 2, 2025 | Completed final sign-off May 2025 | 27 Van Ness Av | Signawest Systems Inc | fire alarm as built drawing submission re: fire alarm permit 202412036033Details
fire alarm as built drawing submission re: fire alarm permit 202412036033 | $27,000 |
| Apr 15, 2025 | Completed final sign-off Jul 2025 | 27 Van Ness Av | Chiang C M Construction Inc. | revision to pa 202207138394, install a new door actuator, card reader and video intercom at the base of column to serve the public entry doors and related elec workDetails
revision to pa 202207138394, install a new door actuator, card reader and video intercom at the base of column to serve the public entry doors and related elec work | $4,000 |
| Dec 12, 2024 | Completed final sign-off Dec 2024 | 25 Van Ness Av | Signawest Systems Inc | rev to pa# 20240206530: fire alarm as built drawing for review/approval 7th fl.Details
rev to pa# 20240206530: fire alarm as built drawing for review/approval 7th fl. | |
| Dec 3, 2024 | Completed final sign-off May 2025 | 27 Van Ness Av | Signawest Systems Inc | fire alarm tenant improvement works for new aitc clinic/office on 1st fl ref pa 202207138394Details
fire alarm tenant improvement works for new aitc clinic/office on 1st fl ref pa 202207138394 | $27,100 |
| Nov 19, 2024 | Completed final sign-off Jul 2025 | 27 Van Ness Av | Arch Plumbing Inc | relocate sprinkler heads on the 1st fl ref# 202207138394Details
relocate sprinkler heads on the 1st fl ref# 202207138394 | $10,000 |
| Sep 19, 2024 | In progress issued Sep 2025 | 25 Van Ness Av | project consists exclusively of elevator modernization of two traction elevators (elevators #1 and #2) and one hydraulic elevator (#3) at 25 van ness aveDetails
project consists exclusively of elevator modernization of two traction elevators (elevators #1 and #2) and one hydraulic elevator (#3) at 25 van ness ave | ||
| Mar 28, 2024 | Completed final sign-off Aug 2024 | 25 Van Ness Av | Arch Plumbing Inc | relocate 7 fire sprinkler heads or add 3 new fire sprinkler heads.Details
relocate 7 fire sprinkler heads or add 3 new fire sprinkler heads. | $5,000 |
| Feb 6, 2024 | Completed final sign-off Dec 2024 | 25 Van Ness Av | Signawest Systems Inc | retrofit of (e) fire alarm system to install additional notifiction appliannces for the 7th fl. t.i.Details
retrofit of (e) fire alarm system to install additional notifiction appliannces for the 7th fl. t.i. | $15,500 |
| Nov 17, 2022 | Never finaled issued Jan 2023, no final | 25 Van Ness Av | Mik Construction Inc | remove and replace damaged sections of sidewalk, sidewalk is over an occupied basement.Details
remove and replace damaged sections of sidewalk, sidewalk is over an occupied basement. | $26,000 |
| Nov 3, 2022 | Completed final sign-off Mar 2025 | 25 Van Ness Av | 7/f: selective demolition of interior partitions, construction of new partitions, new lighting, new finishes, new plumbing in breakroom, ada upgrades in restrooms, new power and data receptacles.Details
7/f: selective demolition of interior partitions, construction of new partitions, new lighting, new finishes, new plumbing in breakroom, ada upgrades in restrooms, new power and data receptacles. | $1,275,000 | |
| Jul 13, 2022 | Completed final sign-off Jul 2025 | 27 Van Ness Av | Chiang C M Construction Inc. | tenant improvement of 27 van ness suite with demolition and construction scope for wall partitions, flooring, ceilings, finishes, as well as related mechanical, plumbing, fire protection, and electrical work.Details
tenant improvement of 27 van ness suite with demolition and construction scope for wall partitions, flooring, ceilings, finishes, as well as related mechanical, plumbing, fire protection, and electrical work. | $1,750,000 |
| Nov 20, 2020 | Never finaled issued Nov 2020, no final | 25 Van Ness Av | Mik Construction Inc | grindings of sidewalk pavement and re-apply waterproofing on sidewalk to protect basement rooms. (non structural pavement only)Details
grindings of sidewalk pavement and re-apply waterproofing on sidewalk to protect basement rooms. (non structural pavement only) | $250,000 |
| Nov 1, 2019 | Completed final sign-off Apr 2022 | 25 Van Ness Av | convert existing men&women restrooms on the 8th floor to two multi-user all-gender restrooms. one of which will be made fully accessible. all compartments will have privacy partitions and door. work includes demo of a urinal. install new partitions grab bar changing table and signage.Details
convert existing men&women restrooms on the 8th floor to two multi-user all-gender restrooms. one of which will be made fully accessible. all compartments will have privacy partitions and door. work includes demo of a urinal. install new partitions grab bar changing table and signage. | $12,000 | |
| Mar 26, 2019 | Completed final sign-off Dec 2019 | 25 Van Ness Av | Wells Electrical, Inc | this project will be adding one anchor at a location specified on drawings. the anchors will be at a minimum 18' above grade and include a 1/2" hilti kwik bolt embedded 4" into the buildings concrete facade to hold up string lights over hickory alley.Details
this project will be adding one anchor at a location specified on drawings. the anchors will be at a minimum 18' above grade and include a 1/2" hilti kwik bolt embedded 4" into the buildings concrete facade to hold up string lights over hickory alley. | $5,000 |
| Mar 1, 2018 | Completed final sign-off Apr 2018 | 25 Van Ness Av | Emcor Services/Mesa Energy Systems Inc | like for like replacement of 11 heat pumps in basement. ref. 201612165160, pp20130401543, pm20130401544. n/a maherDetails
like for like replacement of 11 heat pumps in basement. ref. 201612165160, pp20130401543, pm20130401544. n/a maher | $11,800 |
| Dec 16, 2016 | Completed final sign-off Mar 2018 | 25 Van Ness Av | Pacific Auxiliary Fire Alarm | basement: ref pp20130401543, m20130401544, e201304019636 - 11 heat pump (in e) were replace by other. from meeting minntes it was determined that the heat pump was a air moving system renging duct smoke detector on each and global shut down maher naDetails
basement: ref pp20130401543, m20130401544, e201304019636 - 11 heat pump (in e) were replace by other. from meeting minntes it was determined that the heat pump was a air moving system renging duct smoke detector on each and global shut down maher na | $17,838 |
| Nov 4, 2016 | Never finaled issued Dec 2016, no final | 25 Van Ness Av | voluntary barrier removal. elevator only. see exemption by disablity access coord. area of work 191 sq ft. n/a for maherDetails
voluntary barrier removal. elevator only. see exemption by disablity access coord. area of work 191 sq ft. n/a for maher | $25,000 | |
| Sep 21, 2016 | Never finaled issued Sep 2016, no final | 25 Van Ness Av | Rodda Electric Inc | electrical title 24 add 18 light fixtures, 16 receptacles, and 10 data raceways with no cabling.Details
electrical title 24 add 18 light fixtures, 16 receptacles, and 10 data raceways with no cabling. | $45,000 |
| Aug 24, 2016 | Completed final sign-off Aug 2016 | 25 Van Ness Av | Lincoln Air Conditioning | basement level mech set- relocate diffusers & ductwork, like for like. no new ducting ref pa #201606301291. n/a maher ordinanceDetails
basement level mech set- relocate diffusers & ductwork, like for like. no new ducting ref pa #201606301291. n/a maher ordinance | $3,500 |
| Aug 22, 2016 | Expired or cancelled cancelled Jan 2026 | 25 Van Ness Av | replace sub side walk basement roof at sw corner of van ness and oak st nw corner of hickory and van nessDetails
replace sub side walk basement roof at sw corner of van ness and oak st nw corner of hickory and van ness | $200,000 | |
| Aug 8, 2016 | Completed final sign-off Sep 2016 | 25 Van Ness Av | Aa Fire Systems Inc. | relocate (10) automatic fire sprinklers in remodeled theater lobby as required per nfpa 13. t.i. pa#201606301291. n/a ordinance #155-13Details
relocate (10) automatic fire sprinklers in remodeled theater lobby as required per nfpa 13. t.i. pa#201606301291. n/a ordinance #155-13 | $1,200 |
| Jun 30, 2016 | Completed final sign-off Sep 2016 | 25 Van Ness Av | Cobuild Construction Services Inc | minor renovation of extg theater lobby to include new paint, carpet, furnishings, replace lighting and repair sprinklers. minor partition adjustment.Details
minor renovation of extg theater lobby to include new paint, carpet, furnishings, replace lighting and repair sprinklers. minor partition adjustment. | $149,312 |
| Dec 30, 2014 | Never finaled issued Dec 2014, no final | 25 Van Ness Av | Bullard's Heating & Air Inc. | #210: replace existing ac equipment (water source heat pumps); add new duct work; new duct smoke detectors in each unit- fiere alarm connection separate permit. maher n/aDetails
#210: replace existing ac equipment (water source heat pumps); add new duct work; new duct smoke detectors in each unit- fiere alarm connection separate permit. maher n/a | $48,000 |
| Oct 28, 2014 | Never finaled issued Oct 2014, no final | 25 Van Ness Av | mta onlyDetails
mta only | ||
| Oct 21, 2014 | Never finaled issued Oct 2014, no final | 25 Van Ness Av | street space permitDetails
street space permit | ||
| Jan 11, 2013 | Completed final sign-off Jun 2013 | 25 Van Ness Av | Starlite Electric Inc. | 2nd floor -install (1) smoke, (1) control module and one sti "push to exit" button on existing fire alarm system for re-entry door to second floor office from egress stairway.Details
2nd floor -install (1) smoke, (1) control module and one sti "push to exit" button on existing fire alarm system for re-entry door to second floor office from egress stairway. | $3,000 |
| Jan 11, 2013 | Completed final sign-off Jun 2013 | 25 Van Ness Av | Starlite Electric Inc. | roof (8th floor) -install (1) smoke, (1) control module on existing fire alarm system, and one sti "push to exit" button on existing fire alarm system for access to required egress stairway.Details
roof (8th floor) -install (1) smoke, (1) control module on existing fire alarm system, and one sti "push to exit" button on existing fire alarm system for access to required egress stairway. | $3,000 |
| Jan 9, 2013 | Never finaled issued Jan 2013, no final | 25 Van Ness Av | street space and mtaDetails
street space and mta | ||
| Oct 2, 2012 | Completed final sign-off Mar 2013 | 25 Van Ness Av | Starlite Electric Inc. | install 1 smoke detector & 1 control relay module (4th floor) for 2 door release buttons on 3rd floor- door release under separate permit-Details
install 1 smoke detector & 1 control relay module (4th floor) for 2 door release buttons on 3rd floor- door release under separate permit- | $2,000 |
| Jul 6, 2012 | Never finaled issued Jul 2012, no final | 25 Van Ness Av | street spaceDetails
street space | ||
| May 31, 2012 | Never finaled issued Jun 2012, no final | 25 Van Ness Av | Signawest Systems Inc | 1st floor - to upgrade existing fire alarm control panel to notifier nf2-3030 w/digital voice command. existing facp's location will remain in sffd control room at first floor. replace annunicator panel at the lobby.Details
1st floor - to upgrade existing fire alarm control panel to notifier nf2-3030 w/digital voice command. existing facp's location will remain in sffd control room at first floor. replace annunicator panel at the lobby. | $24,525 |
| May 30, 2012 | Expired or cancelled cancelled Jan 2026 | 25 Van Ness Av | remove (e) chain link fenced bike storage in corridor & replace with rated bike storage room under ab-005. provide relocated sprinkler headDetails
remove (e) chain link fenced bike storage in corridor & replace with rated bike storage room under ab-005. provide relocated sprinkler head | $10,000 | |
| May 7, 2012 | Completed final sign-off Jan 2013 | 25 Van Ness Av | Pribuss Engineering Inc | 1st/3rd,5th,6th floors-fire sprinkler t.i-1st fl-relocate 84, add 2 & delete 31. 3rd fl-relocate 26, delete11. 5th fl-relocate 15, delete 8. 6th fl-relocate 7, delete 1 & change out 1Details
1st/3rd,5th,6th floors-fire sprinkler t.i-1st fl-relocate 84, add 2 & delete 31. 3rd fl-relocate 26, delete11. 5th fl-relocate 15, delete 8. 6th fl-relocate 7, delete 1 & change out 1 | $69,474 |
| Apr 26, 2012 | Never finaled issued Apr 2012, no final | 25 Van Ness Av | Signawest Systems Inc | revision to fire alarm pa# 201202073670. adding 18 fire smoke damper duct smoke detectors to exisiting fire alarm panel on floors 1, 3, 5, 6. supervisory only.Details
revision to fire alarm pa# 201202073670. adding 18 fire smoke damper duct smoke detectors to exisiting fire alarm panel on floors 1, 3, 5, 6. supervisory only. | $13,350 |
| Feb 7, 2012 | Never finaled issued Feb 2012, no final | 25 Van Ness Av | Turner Construction Co | extend existing fire alarm and voice evac system to new tenant improvement (soar) sf office of aids renovationDetails
extend existing fire alarm and voice evac system to new tenant improvement (soar) sf office of aids renovation | $7,665 |
| Dec 22, 2011 | Never finaled issued Dec 2011, no final | 25 Van Ness Av | street space & mta parking meterDetails
street space & mta parking meter | ||
| May 12, 2011 | Completed final sign-off Jun 2012 | 25 Van Ness Av | comply comp 201045296(pid). accessibility improvement to existing restrooms on 1st, 3rd, 5th & 6th floors. work includes new flooring, relocation of plumbing fixtures, and reconfiguration of bathroom status.Details
comply comp 201045296(pid). accessibility improvement to existing restrooms on 1st, 3rd, 5th & 6th floors. work includes new flooring, relocation of plumbing fixtures, and reconfiguration of bathroom status. | $88,000 | |
| May 12, 2011 | Completed final sign-off May 2013 | 25 Van Ness Av | Turner Construction Co | t.i of the 1st, 3rd, 5th & 6th flrs of 25 van ness ave.interior alternation/renovation including architecture, structural, mechanical, plumbings and electrical work.Details
t.i of the 1st, 3rd, 5th & 6th flrs of 25 van ness ave.interior alternation/renovation including architecture, structural, mechanical, plumbings and electrical work. | $4,488,000 |
| Jul 22, 2010 | Never finaled issued Sep 2010, no final | 25 Van Ness Av | Mina-Tree Signs, Inc | install 2 banners 36" x 96" , thickness .020, weight 16 oz, service area 24 sqft, double sided.Details
install 2 banners 36" x 96" , thickness .020, weight 16 oz, service area 24 sqft, double sided. | $8,000 |
| Apr 21, 2010 | Completed final sign-off Jan 2011 | 25 Van Ness Av | 1st fl - tenant improvement work to house. offices for sfmta and hsa.Details
1st fl - tenant improvement work to house. offices for sfmta and hsa. | $100,000 | |
| Nov 12, 2009 | Never finaled issued Dec 2009, no final | 25 Van Ness Av | permanent cooling for 3 servers rooms. furnish and install 3 water cooled heat pumps to provide permanent cooling to meet the process heating loads on the 3rd, 4th, and 5th floor server rooms.Details
permanent cooling for 3 servers rooms. furnish and install 3 water cooled heat pumps to provide permanent cooling to meet the process heating loads on the 3rd, 4th, and 5th floor server rooms. | $150,000 | |
| Oct 22, 2009 | Never finaled issued Dec 2009, no final | 25 Van Ness Av | installation of mechancial ducts @ basement per ab-019.Details
installation of mechancial ducts @ basement per ab-019. | $60,000 | |
| Oct 22, 2009 | Never finaled issued Nov 2009, no final | 25 Van Ness Av | installation of a trash compactor & secured bicycle area by fence.Details
installation of a trash compactor & secured bicycle area by fence. | $60,000 | |
| Oct 21, 2009 | Expired or cancelled cancelled Aug 2022 | 25 Van Ness Av | to obtain final inspection for work approved under 200606214600. all work is complete.Details
to obtain final inspection for work approved under 200606214600. all work is complete. | ||
| Sep 3, 2009 | Never finaled issued Sep 2009, no final | 25 Van Ness Av | International Fire Equip | add (1) sprinkler head at 2nd floorDetails
add (1) sprinkler head at 2nd floor | $800 |
| Jul 29, 2009 | Never finaled issued Sep 2009, no final | 27 Van Ness Av | request additional addressDetails
request additional address | ||
| Dec 9, 2008 | Never finaled issued Dec 2008, no final | 25 Van Ness Av | street space permit only.Details
street space permit only. | ||
| Oct 10, 2007 | Never finaled issued Oct 2007, no final | 25 Van Ness Av | Potter Fire Protection | relocate 1 (one) fire sprinkler, 7th floor.Details
relocate 1 (one) fire sprinkler, 7th floor. | $850 |
| Aug 10, 2007 | Completed final sign-off Nov 2012 | 25 Van Ness Av | Pacific Auxiliary Fire Alarm | 5th and 7 th floor tenant improvment adding strobes, speakers, and door holder and smoke detectorsDetails
5th and 7 th floor tenant improvment adding strobes, speakers, and door holder and smoke detectors | $30,000 |
| Feb 28, 2007 | Never finaled issued May 2007, no final | 25 Van Ness Av | oti-1 7th floor el, l/s (suite #700)Details
oti-1 7th floor el, l/s (suite #700) | ||
| Feb 28, 2007 | Never finaled issued May 2007, no final | 25 Van Ness Av | demolition of coffee station casework, sliding door and patching of adjacent finished, construction of new glazed partition, painting new and weexsiting walls and soffits, constuction of new cross corridor dorrs (oti-1=6th floor, el, lsDetails
demolition of coffee station casework, sliding door and patching of adjacent finished, construction of new glazed partition, painting new and weexsiting walls and soffits, constuction of new cross corridor dorrs (oti-1=6th floor, el, ls | ||
| Nov 22, 2006 | Never finaled issued Nov 2006, no final | 25 Van Ness Av | street space permitDetails
street space permit | ||
| Sep 11, 2006 | Expired or cancelled expired Mar 2009 | 25 Van Ness Av | Tony Ng Plumbing Co | work @ suite# 220 & suite# 230 only. relocate 11 (e) sprinkler heads. 2nd floor.Details
work @ suite# 220 & suite# 230 only. relocate 11 (e) sprinkler heads. 2nd floor. | $3,000 |
| Aug 22, 2006 | Expired or cancelled expired Mar 2009 | 25 Van Ness Av | G C Electric | install (4) fire strobes and (1) fire speaker - tie into (e) system. fire alarmDetails
install (4) fire strobes and (1) fire speaker - tie into (e) system. fire alarm | $750 |
| Aug 9, 2006 | Completed final sign-off Sep 2007 | 25 Van Ness Av | Western Roofing Service | installation of new roof. higher than 0.70 reflectance, higher than 0.75 thermal emittanceDetails
installation of new roof. higher than 0.70 reflectance, higher than 0.75 thermal emittance | $610,000 |
| Aug 2, 2006 | Never finaled issued Nov 2006, no final | 25 Van Ness Av | replace drinking fountains with new accessible hi-low drinking fountains - widen alcoves on 6th floor only. 1 per level. new accessible signage at various locations along common area paths. alteration / accessibility improvements of (e) restrooms. pair per level. includes 1 new power assist to (e)Details
replace drinking fountains with new accessible hi-low drinking fountains - widen alcoves on 6th floor only. 1 per level. new accessible signage at various locations along common area paths. alteration / accessibility improvements of (e) restrooms. pair per level. includes 1 new power assist to (e) | ||
| Aug 2, 2006 | Never finaled issued Nov 2006, no final | 25 Van Ness Av | replace drinking fountains w/new accessible hi-low drinking fountains-widen alcoves-1 per level.new accessible signage at var loc along common area paths.alter/access improv of (e) restrooms.pair per level.replace wall sconces at var loc along common area paths.adj door timing at (e)elevator landingDetails
replace drinking fountains w/new accessible hi-low drinking fountains-widen alcoves-1 per level.new accessible signage at var loc along common area paths.alter/access improv of (e) restrooms.pair per level.replace wall sconces at var loc along common area paths.adj door timing at (e)elevator landing | ||
| Jul 19, 2006 | Expired or cancelled expired Mar 2009 | 25 Van Ness Av | demo 1 demising wall to combine 2 suites into 1.demo 2 offices, partition between work area.const offices, coffee station,reception counter,conference room & file room. const a server room(nec 645 does not apply). const accessable ramp&painting of (n) &(e) walls,soffit.Details
demo 1 demising wall to combine 2 suites into 1.demo 2 offices, partition between work area.const offices, coffee station,reception counter,conference room & file room. const a server room(nec 645 does not apply). const accessable ramp&painting of (n) &(e) walls,soffit. | $100,000 | |
| Jun 21, 2006 | Expired or cancelled expired Mar 2009 | 25 Van Ness Av | access features for suite# 200 at 2nd floor. work includes: replacement of (e) drinking fountains on 1st & 2nd floors. barrier removal at 2 passage archway awing corr. path at 2nd floor. replace lavatory at accessible lavatories in both men & women's restroom at 2nd floor.Details
access features for suite# 200 at 2nd floor. work includes: replacement of (e) drinking fountains on 1st & 2nd floors. barrier removal at 2 passage archway awing corr. path at 2nd floor. replace lavatory at accessible lavatories in both men & women's restroom at 2nd floor. | ||
| Jun 21, 2006 | Never finaled issued Jul 2006, no final | 25 Van Ness Av | tenant improvement for suite# 200 at 2nd floor. incluces: demolition of 1 office & 2 - 48" high partitions. new construction of partially enclosed meeting area. new wire mech partition with sliding door in (e) storage room. painting of new & (e) walls & soffits.Details
tenant improvement for suite# 200 at 2nd floor. incluces: demolition of 1 office & 2 - 48" high partitions. new construction of partially enclosed meeting area. new wire mech partition with sliding door in (e) storage room. painting of new & (e) walls & soffits. | ||
| Dec 28, 2004 | Completed final sign-off Jan 2005 | 25 Van Ness Av | Pacific Auxiliary Fire Alarm | installation of a monitoring module on the 2nd flr to monitor the suppression systemDetails
installation of a monitoring module on the 2nd flr to monitor the suppression system | $4,000 |
| Nov 4, 2004 | Completed final sign-off Jan 2005 | 25 Van Ness Av | Sabah International Incorporated | 2/f- design/install/test & final fm200 fire suppression system,1 control panel,1 abort,1 nozzle,Details
2/f- design/install/test & final fm200 fire suppression system,1 control panel,1 abort,1 nozzle, | $14,000 |
| Aug 25, 2004 | Never finaled issued Oct 2004, no final | 25 Van Ness Av | revisions to 200308051274: tenant improvements in suite 210Details
revisions to 200308051274: tenant improvements in suite 210 | ||
| Jul 29, 2004 | Completed final sign-off Apr 2005 | 25 Van Ness Av | new carpet, new fixed auditorium seating, ada improvementsDetails
new carpet, new fixed auditorium seating, ada improvements | $47,500 | |
| Jul 21, 2004 | Completed final sign-off Apr 2005 | 25 Van Ness Av | remove carpet, removed auditorium seating, ada improvements to be under separate permit app & spaceDetails
remove carpet, removed auditorium seating, ada improvements to be under separate permit app & space | $7,000 | |
| Jul 6, 2004 | Never finaled issued Jul 2004, no final | 25 Van Ness Av | streetspaceDetails
streetspace | ||
| Mar 9, 2004 | Expired or cancelled expired Sep 2008 | 25 Van Ness Av | Swinerton Builders | underpin adjacent wall to 50 oak st, project to facilitate construction of 50 oak st.Details
underpin adjacent wall to 50 oak st, project to facilitate construction of 50 oak st. | $16,000 |
| Nov 24, 2003 | Never finaled issued Nov 2003, no final | 25 Van Ness Av | California Suppresion Dba Calif. Protect | renew permit 200307280484Details
renew permit 200307280484 | $3,285 |
| Sep 18, 2003 | Never finaled issued Oct 2003, no final | 25 Van Ness Av | Peninsula Air Condition | replace 1 cooling tower/condenses water pump/1 boiled with like model/1 siesmic restraint system perDetails
replace 1 cooling tower/condenses water pump/1 boiled with like model/1 siesmic restraint system per | $6,000 |
| Aug 15, 2003 | Never finaled issued Aug 2003, no final | 25 Van Ness Av | Peninsula Air Condition | replace 1 cooling tower, 1 condenser water pump, 1 boiler with like made & model, install 1 new freqDetails
replace 1 cooling tower, 1 condenser water pump, 1 boiler with like made & model, install 1 new freq | $93,000 |
| Aug 5, 2003 | Never finaled issued Sep 2003, no final | 25 Van Ness Av | installation of large screen video display system, operator consoles, equipment racks, floor jacksDetails
installation of large screen video display system, operator consoles, equipment racks, floor jacks | ||
| Jul 28, 2003 | Never finaled issued Jul 2003, no final | 25 Van Ness Av | California Suppresion Dba Calif. Protect | rm #320- furnish & install (3) new strobes, tie-in to (e) circuit #1Details
rm #320- furnish & install (3) new strobes, tie-in to (e) circuit #1 | $3,285 |
| Jul 16, 2003 | Never finaled issued Jul 2003, no final | 25 Van Ness Av | Pacific Auxiliary Fire Alarm | adding 1 smoke detector to (e) fire alarm system to provide special elevator recall of upgraded elevDetails
adding 1 smoke detector to (e) fire alarm system to provide special elevator recall of upgraded elev | $6,000 |
| Jun 5, 2003 | Completed final sign-off Jul 2003 | 25 Van Ness Av | dpw will install 2x4" conduits entering 25 van ness ave. from oak st. to the 2nd dlr (ste210) work wDetails
dpw will install 2x4" conduits entering 25 van ness ave. from oak st. to the 2nd dlr (ste210) work w | $57,393 | |
| Apr 24, 2003 | Completed final sign-off Jun 2003 | 25 Van Ness Av | wall partitions, paintingDetails
wall partitions, painting | ||
| May 2, 2002 | Expired or cancelled expired Jun 2003 | 25 Van Ness Av | California Suppresion Dba Calif. Protect | install (1) smoke detector in suite#220. (1) fire/life safety speaker. (1) strobe & perform functionDetails
install (1) smoke detector in suite#220. (1) fire/life safety speaker. (1) strobe & perform function | $6,985 |
| Apr 11, 2002 | Expired or cancelled expired Jun 2003 | 25 Van Ness Av | demo interior non structural construcion/restaurant equip suteis 120/150 disable access separate perDetails
demo interior non structural construcion/restaurant equip suteis 120/150 disable access separate per | $28,000 | |
| Aug 6, 2001 | Expired or cancelled expired Feb 2002 | 25 Van Ness Av | Ayoob & Peery Plumbing Co Inc | remove existing central c-1a fire sprinkler heads install new central model bv-qr fire sprinkler heaDetails
remove existing central c-1a fire sprinkler heads install new central model bv-qr fire sprinkler hea | $16,000 |
| Jul 13, 2001 | Expired or cancelled expired Jul 2002 | 25 Van Ness Av | Carli Construction, Inc. | oti-1 4th floor, el, me, ls, & sp.Details
oti-1 4th floor, el, me, ls, & sp. | $55,000 |
| Jul 11, 2001 | Expired or cancelled expired Jan 2002 | 25 Van Ness Av | California Suppresion Dba Calif. Protect | fire alarm tenant improvement 4th floor locationDetails
fire alarm tenant improvement 4th floor location | $6,250 |
| Jul 11, 2001 | Expired or cancelled expired Jan 2002 | 25 Van Ness Av | California Suppresion Dba Calif. Protect | fire alarm tenant improvement 4th floorDetails
fire alarm tenant improvement 4th floor | $8,739 |
| Jun 13, 2001 | Completed final sign-off Sep 2001 | 25 Van Ness Av | Carli Construction, Inc. | oti-2 2nd fl ltg,mech,ls,sprDetails
oti-2 2nd fl ltg,mech,ls,spr | $120,000 |
| May 1, 2001 | Expired or cancelled expired Sep 2001 | 25 Van Ness Av | California Suppresion Dba Calif. Protect | "as built" revisions to drawings submitted under pa#9920461Details
"as built" revisions to drawings submitted under pa#9920461 | |
| Feb 15, 2001 | Expired or cancelled expired Sep 2001 | 25 Van Ness Av | California Suppresion Dba Calif. Protect | furnish & install 9 new alarm strobes, 7 new fire life/safety spearkers, 3 new pho. electric smoke dDetails
furnish & install 9 new alarm strobes, 7 new fire life/safety spearkers, 3 new pho. electric smoke d | $7,000 |
| Feb 5, 2001 | Expired or cancelled expired Jun 2001 | 25 Van Ness Av | Potter Fire Protection | relocate (19) fire sprinkler to accomodate the new wall & ceiling construction in an office tenant iDetails
relocate (19) fire sprinkler to accomodate the new wall & ceiling construction in an office tenant i | $3,200 |
| Sep 6, 2000 | Completed final sign-off Oct 2001 | 25 Van Ness Av | Carli Construction, Inc. | oti-1, basement-el, spDetails
oti-1, basement-el, sp | $37,000 |
| Aug 25, 2000 | Completed final sign-off Sep 2001 | 25 Van Ness Av | Carli Construction, Inc. | oti-1, 2nd floor, el, me, ls, spDetails
oti-1, 2nd floor, el, me, ls, sp | $130,000 |
| Feb 22, 2000 | Expired or cancelled expired Mar 2001 | 25 Van Ness Av | voluntary building fire alarm system upgradeDetails
voluntary building fire alarm system upgrade | $45,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- California Suppresion Dba Calif. Protect (7), Carli Construction, Inc. (4), Pacific Auxiliary Fire Alarm (4), Signawest Systems Inc (3), Signawest Systems Inc (3), Starlite Electric Inc. (3), Arch Plumbing Inc (2), Chiang C M Construction Inc. (2), Mik Construction Inc (2), Peninsula Air Condition (2), Potter Fire Protection (2), Turner Construction Co (2), Aa Fire Systems Inc., Ayoob & Peery Plumbing Co Inc, Bullard's Heating & Air Inc., Cobuild Construction Services Inc, Emcor Services/Mesa Energy Systems Inc, G C Electric, International Fire Equip, Lincoln Air Conditioning, Mina-Tree Signs, Inc, Pribuss Engineering Inc, Rodda Electric Inc, Sabah International Incorporated, Swinerton Builders, Tony Ng Plumbing Co, Wells Electrical, Inc, Western Roofing Service
- Architects
- Gordon Hoy (8), Ignatius Tsang (2), Mitchell Joe (2), Glenn Hunt, Irene U. Aquino, Jane Chan Architecture, Paul Cooper, Richard Gee
- Engineers
- Ramid Arbabaraghi (2), Dorel Anghel, Edward Rivera, Gary Hanna, Joseph Chan, Lincoln Air Eng Installed Svc, Nejla Bamshad-Alavi, Shahla Saiidnia
- Authorized agent-otherss
- Tony Leung
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.