Block 3783, lot 009
699 08th St
The 200 most recent permits filed for this property.
CompletedIn progressNever finaledExpired or cancelled
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 6, 2026 | In progress issued Jul 2026 | 699 08th St | B N Builders Inc | 4/f: revision to pa# 202604099181- revised scope to include converting an existing conference room and open office area into a work room with fenced area for new equipment. occupant load is decreasing as part of the scope. revised electrical and structrual included. | $50,000 |
| Apr 9, 2026 | In progress issued May 2026 | 699 08th St | B N Builders Inc | partial tenant improvement at (e) 4/f suite, (n) equipment at idf & mdf rooms, (n) fence @ mdf room, remove & replace (e) card readers, (n) mechanical units for idf and mdf @ roof. accessibility upgrades @ all gender room, 1st flr entry and roof parking. | $110,029 |
| Mar 5, 2025 | Completed final sign-off Mar 2025 | 650 Townsend St | Fire Detection Unlimited | fire alarm as built for pa # 2023-0428-6730 | |
| Jul 23, 2024 | Completed final sign-off Nov 2024 | 650 Townsend St | Fire Detection Unlimited | ti to existing fire alarm system. reuse (3) existing & (2) new addressable monitor module for new fire pump controller (by others) points: pump running power failure, phase reversal, transfer switch in emergency, emergency isolation switch open | $9,424 |
| Mar 20, 2024 | Completed final sign-off May 2024 | 650 Townsend St | Western Waterproofing/Brisk Wp | re-paint 13 windows ledges using gacoflex urethane coating. | $2,000 |
| Mar 20, 2024 | In progress filed Mar 2024, not yet issued | 650 Townsend St | Western Waterproofing/Brisk Wp | re-paint 13 window ledges using gacoflex urethane coating. | $2,000 |
| Jul 11, 2023 | Completed final sign-off Jan 2024 | 699 08th St | Matrix Hg Inc | replace (e) fuel oil pipe with new. | $179,620 |
| May 23, 2023 | Never finaled filed May 2023, never issued | 650 Townsend St | installation of canopy with solar on parking structure. | $500,000 | |
| Apr 28, 2023 | Completed final sign-off Mar 2025 | 650 Townsend St | Fire Detection Unlimited | like for like replace of an (e) fire alarm system with a (n) auto call 4100es. replace all (e) fire alarm control units & transponders. replace (e) pull stations, smoke & heat detector heads only. | $405,572 |
| Mar 10, 2023 | Completed final sign-off Jul 2023 | 650 Townsend St | Coil Inc | installation of 2 tritium 50kw ev chargers. | $138,600 |
| Dec 8, 2022 | Completed final sign-off Sep 2023 | 699 08th St | Weidner Architectural Signage | (1) nonilluminated exterior sidewalk directional sign, wall mounted | $600 |
| Dec 8, 2022 | Completed final sign-off Sep 2023 | 699 08th St | Weidner Architectural Signage | (1) set illuminated exterior signage "699 townsend center" | $28,700 |
| Dec 8, 2022 | Completed final sign-off Sep 2023 | 699 08th St | Weidner Architectural Signage | (1) illuminated exterior sign "townsend center" | $14,200 |
| Aug 4, 2022 | Completed final sign-off Nov 2023 | 650 Townsend St | Bevilacqua & Sons | infilling an abandoned elevator pit under an existing hallway elevator pit is not visible from street view. | $48,000 |
| Jan 24, 2022 | Completed final sign-off Feb 2022 | 650 Townsend St | Johnson Controls Fire | as-built to pa# 202102184953-r1. modify (e) fire alarm system. | |
| Nov 18, 2021 | Completed final sign-off Mar 2022 | 650 Townsend St | Clune Construction Company L P | revision to pa# 202011209346. ste 160 & 180. revise scope of demolition. add finishes to existing corridor. modify existing non-building steel structure. | |
| Oct 6, 2021 | Completed final sign-off Nov 2021 | 650 Townsend St | Johnson Controls Fire | suite 160: modify (e) fire alarm system, submit "as built" to approved fire permit #202105069961 | |
| Oct 4, 2021 | Completed final sign-off Oct 2021 | 699 08th St | Johnson Controls Fire | submit revised approved fire alarm system. modification plans to app# 202104138395 | |
| Sep 14, 2021 | Expired or cancelled cancelled Jan 2026 | 650 Townsend St | Clune Construction Company L P | revision to pa. 202011209346. add 1 hr rated,wall details, to existing stairwell, no changes. | $250,000 |
| Sep 8, 2021 | Completed final sign-off Sep 2021 | 650 Townsend St | Ayoob & Peery Plumbing Co Inc | suite 180: add (9) relocate (88) sprinklers per t.i. reference bpa #2020/1120/9346 | $23,285 |
| Aug 30, 2021 | Completed final sign-off Nov 2021 | 650 Townsend St | Johnson Controls Fire | fire alarm system modification: provide new devices, relocate and demo (e) devices. adding (9) ceiling mount speakers/strobes. ref pa201912200153. | $6,700 |
| Jul 1, 2021 | Never finaled issued Jul 2021, no final | 699 08th St | Clune Construction Company L P | deferred structural to approved permit 2020-1207-0374 | $50,000 |
| Jul 1, 2021 | Completed final sign-off Jul 2025 | 699 08th St | Anderson, Rowe & Buckley, Inc. | fire sprinkler only - 3 relocated sprinker head for 3rd fl for wow door at zynga. | $1,500 |
| Jun 23, 2021 | Never finaled filed Jun 2021, never issued | 650 Townsend St | Johnson Controls Fire | as-built: modify existing fire alarm system. install (2) relays, (21) speaker strobes amd (4) strobes. revision to approved pa # 2020-0121-3035 (as-built) | |
| Jun 21, 2021 | Never finaled issued Jul 2021, no final | 699 08th St | Clune Construction Company L P | 3rd floor: revision to egress plans on app#202101132623 | |
| May 17, 2021 | Completed final sign-off Sep 2021 | 650 Townsend St | Ayoob & Peery Plumbing Co Inc | concourse: add (12), relocate (14) and change out (11) sprinklers per ti. ref #: 2020-1120-7346, job #: 21-625 | $9,450 |
| May 6, 2021 | Completed final sign-off Nov 2021 | 650 Townsend St | Johnson Controls Fire | modify existing fire alarm system. | |
| Apr 13, 2021 | Completed final sign-off Oct 2021 | 699 08th St | Johnson Controls Fire | ti ref revised arch plan #2021-0621-2873 modify existing fire alarm system, 3rd floor, for won door wall | $1,500 |
| Mar 30, 2021 | Expired or cancelled withdrawn May 2021 | 650 Townsend St | Johnson Controls Fire | ref t.i. # 2020-0822-2362 modify fire alarm system (existing) add: (2) smoke detectors (1) relay iam device at 3rd floor | $1,500 |
| Mar 4, 2021 | Expired or cancelled cancelled Jul 2023 | 650 Townsend St | Johnson Controls Fire | modify existing fire alarm system in elevator machine rooms, 1 & 2, 3 & 4, 5 & 6, and 7 & 8 as shown on drawings - provide (10) relay modules. - remove/replace (4) smoke detections. ref ti # 2020-0622-2362 | $10,500 |
| Mar 4, 2021 | Completed final sign-off May 2021 | 699 08th St | Anderson, Rowe & Buckley, Inc. | apn 2020-12-07-0374; tenant improvements to existing fire spkr. syst. 5 added, 45 relocated & 8 removed sprinklers. | $25,000 |
| Feb 18, 2021 | Never finaled issued Jun 2021, no final | 650 Townsend St | Johnson Controls Fire | "asbuilt", modify existin fire alarm. zynga concourse; approved fa permit # 2021-0121-3035; "install (2) relays, (21) speaker strobes, (4) strobes" | |
| Jan 26, 2021 | Never finaled issued Mar 2021, no final | 699 08th St | Ayoob & Peery Plumbing Co Inc | concourse: add (2) and relocate (4) sprinklers to conform with the new wall/ceiling layout of the tenant improvement. ref # 2020-0218-4755 | $1,950 |
| Jan 21, 2021 | Completed final sign-off Mar 2025 | 650 Townsend St | Johnson Controls Fire | modify existing fire alarm system, install (36) smoke detectors, (6) relays, (20) speaker strobes and (1) nac panel. mep ref permit: 2019-1220-0153 | $25,000 |
| Jan 21, 2021 | Completed final sign-off Mar 2021 | 650 Townsend St | R L H Fire Protection Inc | fire sprinkler permit. remove all fire sprinklers from machine rooms top of shafts, and pits of elevators 3-8, delete 18 uprights & 4 sidewalls. relocated 2 and add 2 sprinklers for new walls on the 3rd floor. t.i. # 2020-0822-2362. | $5,000 |
| Jan 13, 2021 | Completed final sign-off Oct 2021 | 699 08th St | Clune Construction Company L P | 3/f: voluntary addition of operable fire partition at 3rd floor atrium breakroom. | $100,000 |
| Dec 28, 2020 | Completed final sign-off Feb 2022 | 650 Townsend St | Johnson Controls Fire | fire alarm system smoke control programming per approved smoke control report and mechanical consultant memo, no new devices, no removed devices. programming only - fire alarm only - no associated permit. | $20,000 |
| Dec 24, 2020 | Completed final sign-off Mar 2025 | 650 Townsend St | Johnson Controls Fire | modify existing fire alarm system. | $1,500 |
| Dec 21, 2020 | Completed final sign-off May 2021 | 650 Townsend St | City Mechanical Inc | suite 150c: mechanical improvements. (reference) maher n/a. | $190,000 |
| Dec 7, 2020 | Completed final sign-off Jul 2022 | 699 08th St | Clune Construction Company L P | concourse: interior commercial office tenant improvement. minor demolition. construction of non-bearing interior partitions. | $2,382,895 |
| Nov 20, 2020 | Completed final sign-off Feb 2022 | 650 Townsend St | Clune Construction Company L P | ste 160 & 180: demolish non-structural elements including partitions, doors, equipment & finishes. construction of demising wall. replace lights and minimal flooring. mep under separate permit. ref pa# 201912200153 | $935,000 |
| Oct 26, 2020 | Completed final sign-off Mar 2021 | 699 08th St | R L H Fire Protection Inc | fire sprinkler permit. relocate 8, add 25 sprinklers on the 2nd floor. t.i. #2019-1030-5929. | $15,000 |
| Sep 28, 2020 | Completed final sign-off Nov 2020 | 699 08th St | Certified Fire And Safety | upgrade existing ul300 ansul fire system to protect kitchen hoods & cooking equipment. | $5,000 |
| Sep 28, 2020 | Completed final sign-off Nov 2020 | 650 Townsend St | Johnson Controls Fire | suite 150: modify (e) fire alarm system. install 1 nac panel, 13 smoke detctors, 1 duct dector, 3 strobes and 24 speaker strobes. ref ti #201912200153. maher n/a. | $1,500 |
| Sep 4, 2020 | Never finaled issued Sep 2020, no final | 650 Townsend St | C B F Inc | suite #150c: new power, new lighting, office ti, only electrical work. ti permit #2019-1220-0153 | $250,000 |
| Aug 22, 2020 | Never finaled issued Sep 2020, no final | 650 Townsend St | Mitsubishi Electric Us Inc | barrier removal, accessible upgrades to 2 ( e ) elevators | $125,000 |
| Aug 18, 2020 | Completed final sign-off Mar 2021 | 699 08th St | Clune Construction Company L P | mechanical deferred submittal to 2019.1030.5929 1. re-use existing vav boxes and ductwork as shown 2. provide new duct, vav boxes, and grilles as required 3. air balance area of work | $500,000 |
| Aug 18, 2020 | Never finaled issued Oct 2020, no final | 699 08th St | Clune Construction Company L P | deferred structural submittal to 2019.1030.5929 structural support system for modernfold door system | $10,000 |
| Aug 5, 2020 | Completed final sign-off Mar 2021 | 699 08th St | Novo Construction Inc | 6/f: t.i. of (e) office: add single door and glazing to storage room and double door to replace (e) door on exit pathway. replace solid door with full lite door at receptaion. fire and life safety system to remain intact and operation. | $70,000 |
| Jul 19, 2020 | Completed final sign-off Nov 2021 | 699 08th St | R L H Fire Protection Inc | fire sprinkler permit. add 1 fire sprinkler for new restroom on the 4th floor. ref. t.i. #2019/1230/0928. | $1,000 |
| Mar 16, 2020 | Expired or cancelled cancelled Jan 2026 | 650 Townsend St | 4th & 5th fl - interior soft demo for future ti. demo of non-load bearing partitions, doors & frames, ceiling systems, lights, millwork of (e) vacant offices spaces | $10,000 | |
| Feb 18, 2020 | Completed final sign-off Feb 2021 | 699 08th St | Clune Construction Company L P | bakery relocation - minor demolition of non-bearing interior partitions. | $235,302 |
| Feb 13, 2020 | Completed final sign-off Aug 2020 | 650 Townsend St | R L H Fire Protection Inc | suite 150c: fire sprinkler permit. relocate 11, add 35 and delete 19 sprinklers in the basement level . t.i. #201912200153 | $20,000 |
| Feb 3, 2020 | Completed final sign-off Apr 2020 | 699 08th St | R L H Fire Protection Inc | 4th floor- t.i# 201906103001: fire sprinkler: revision to permit# 201908239648. drawings changed to accurately show field conditions. sprinkler scope reduced to 47 pendent sprinklers and 28 upright sprinklers. | $1,000 |
| Feb 3, 2020 | Completed final sign-off Apr 2020 | 699 08th St | R L H Fire Protection Inc | 3rd floor: t.i# 2019-0610-2944: as built revision to permit# 2019-0823-9651: drawing changed to accuratey showed field conditions. sprinkler scope reduced to 45 pendent sprinklers and 35 upright sprinklers. | $1,000 |
| Jan 21, 2020 | Completed final sign-off Mar 2021 | 699 08th St | Novo Construction Inc | 6/f: ref pa# 201908128489: interior t.i. of (e) reception area, demo of door and partion of wall, construction includes new gas related glazing, deluge sprinklers (deferred submittal, hav) new stroage room/closet, and miner finish changes | $156,000 |
| Dec 30, 2019 | Completed final sign-off Oct 2020 | 699 08th St | Clune Construction Company L P | 4th floor: add one single all gender restroom. demo & partition permit under separate pa# 2019-0516-0883 & 2019-0610-3001 | $50,000 |
| Dec 30, 2019 | Completed final sign-off Oct 2020 | 699 08th St | Clune Construction Company L P | 3rd floor: add one single all gneder restroom. demo & construction under separate pa# 2019-0516-0883 & 2019-0610-2944 | $50,000 |
| Dec 30, 2019 | Completed final sign-off Mar 2021 | 650 Townsend St | Clune Construction Company L P | install one 24/7 cooling only dx spot system | $60,000 |
| Dec 20, 2019 | Completed final sign-off May 2021 | 650 Townsend St | Bevilacqua & Sons | basement - interior ti includes demo of (e) partitions, floor finishes, ceiling & lighting. (n) partitions, doors, poiwer & tele/data, lighting & millwork. mep deferred | $1,750,000 |
| Nov 5, 2019 | Never finaled issued Nov 2019, no final | 650 Townsend St | United California Glass And Door | installation of security metal fence along the perimeter of the loading dock area of the basement and ground nfloor levels. a roll-up grille & pedestrian gate will be installed at bottom of vehicular ramp | $187,745 |
| Oct 30, 2019 | Completed final sign-off Mar 2021 | 699 08th St | Clune Construction Company L P | 2nd floor: minor demolition and construction of non-bearing interior partitions in currently vacant suite for new open office and meeting rooms and add one single use all gender restroom. n/a for maher | $1,500,000 |
| Oct 4, 2019 | Completed final sign-off Aug 2020 | 699 08th St | Johnson Controls Fire | fire alarm tenant improvement to 5th and 6th fl 20 speaker and strobes ref 201908128488 and 201908128489 | $15,500 |
| Oct 2, 2019 | Never finaled issued Dec 2019, no final | 650 Townsend St | Hathaway Dinwiddie Co. | assembly permit revision, update furniture plans, revise egress plan, change atrium assembly use to a-2 space ref pa 2018-0530-0538, 2018-0530-0539 | |
| Oct 1, 2019 | Completed final sign-off Jul 2020 | 650 Townsend St | Ayoob & Peery Plumbing Co Inc | 6th flr - add 6 relocate 25 sprinklers to conform with ti 201908128489 | $8,775 |
| Oct 1, 2019 | Completed final sign-off Oct 2019 | 650 Townsend St | Ayoob & Peery Plumbing Co Inc | 5th flr - add 8 relocate 2 sprinklers to conform with ti 201908128488 | $4,650 |
| Sep 5, 2019 | Completed final sign-off Jul 2020 | 699 08th St | Johnson Controls Fire | remodel 3rd & 4th floor. demo of (e) notification device in the area of work & install new notification devices. 140 new notification install in the scope of work. ** maher: n/a ** | $90,933 |
| Aug 23, 2019 | Completed final sign-off Jul 2020 | 699 08th St | R L H Fire Protection Inc | 4th flr - fire sprinklers install 36 pendent sprinklers and 120 upright ti 201806103001 | $32,000 |
| Aug 23, 2019 | Completed final sign-off Mar 2020 | 699 08th St | R L H Fire Protection Inc | 3rd flr - fire sprinklers install 40 pendent sprinklers and 50 upright ti 201906102944 | $20,000 |
| Aug 23, 2019 | Completed final sign-off Apr 2021 | 650 Townsend St | Clune Construction Company L P | mep to permits 201906102944 & 201906103001 | |
| Aug 12, 2019 | Completed final sign-off Mar 2021 | 699 08th St | Skyline Construction, Novo Construction Inc | 5th floor: interior tenant improvement of existing built out office space ont he 6th floor. construction to include new partitions, finishes, lighting and pantry. | $1,075,000 |
| Aug 12, 2019 | Completed final sign-off Mar 2021 | 699 08th St | Novo Construction Inc | 6th floor: interior tenant improvement of existing built out office space ont he 6th floor. construction to include new partitions, finishes, lighting and pantry. | $3,150,000 |
| Jun 26, 2019 | Never finaled issued Jun 2019, no final | 699 08th St | Novo Construction Inc | 5th and 6th flr, demo. demo non-structural partions millwork, finishes, plumbing fixtures, lighting and ceilings | $70,000 |
| Jun 24, 2019 | Completed final sign-off Oct 2020 | 699 08th St | Clune Construction Company L P | upgrade to existing lobby that includes and not limited to new reception desk, new paint, new flooring, new lighting maher not req | $41,000 |
| Jun 10, 2019 | Completed final sign-off Oct 2020 | 699 08th St | Clune Construction Company L P | 4th fl - minor demo pa 2019-0516-0883 construction of non-bearing interior partitions in vacant suite for new open and meeting rooms | $5,000,000 |
| Jun 10, 2019 | Completed final sign-off Oct 2020 | 699 08th St | Clune Construction Company L P | 3rd flr - minor demo - construction of non bearing interior partitions in vacant suite for new opn office and meeting rooms | $4,250,112 |
| Jun 4, 2019 | Completed final sign-off Aug 2019 | 650 Townsend St | Johnson Controls Fire | 6th floor. fire alarm as-built record drawing for permit app 201902223617 | |
| Jun 4, 2019 | Completed final sign-off Nov 2019 | 650 Townsend St | Johnson Controls Fire | 3rd floor. fire alarm as-built record drawing for pa# 201902223615 | |
| Jun 4, 2019 | Completed final sign-off Aug 2019 | 650 Townsend St | Johnson Controls Fire | 2nd floor. fire alarm as-built record drawing for permit app 201902223612 | |
| May 16, 2019 | Completed final sign-off Mar 2021 | 699 08th St | Clune Construction Company L P | 1st flr, 3rd flr & 4th flr. minor demo of non-load bearing interior partitions in vacant suite. | $100,000 |
| May 8, 2019 | Completed final sign-off Aug 2019 | 650 Townsend St | Johnson Controls Fire | fire alarm system improvement per approved pa #2018-0530-0538. the system added (82) smokes, (9) ducts, (10) relays, (5) strobes and (55) speaker strobes.**maher n/a** | $108,993 |
| May 6, 2019 | Completed final sign-off Jun 2019 | 650 Townsend St | Aaa Restaurant Fire Control/Dba Aaa Fire | 2/f: as built for pa #201902263782, f/a system for ansul system. maher n/a. | |
| Apr 4, 2019 | Completed final sign-off Aug 2019 | 650 Townsend St | Pribuss Engineering Inc | revise for permit #201811145814. relocate speinklers = 81, added sprinklers =21. total 102. | $15,934 |
| Mar 29, 2019 | Never finaled issued Mar 2019, no final | 650 Townsend St | street space only | ||
| Mar 11, 2019 | Never finaled issued Mar 2019, no final | 650 Townsend St | Hathaway Dinwiddie Co. | smoke control matrix for 2nd, 3rd, 4th floors & atrium ti's revised matrix for pa 2018-0523-9943 | |
| Mar 8, 2019 | Never finaled issued Apr 2019, no final | 650 Townsend St | Hathaway Dinwiddie Co. | defeerred submittal under pa 201803073080 s/s1 for bluxome st. entrance curtain wall construction details. demo and removal of 2 levels of glass, structurally install of new curtain wall windows and doors system. | $20,000 |
| Feb 26, 2019 | Completed final sign-off Jun 2019 | 650 Townsend St | Aaa Restaurant Fire Control/Dba Aaa Fire | 2nd fl - furnish and install 2 ansul fire systems in the kitchen ref pa 2018-0530-0539; 6th fl - furnish and install 1 ansul fire system in the kitchen ref pa 2018-0615-1971; furnish and install 3 ansul fire system in the pcu's on the roof | $18,500 |
| Feb 22, 2019 | Completed final sign-off Nov 2019 | 650 Townsend St | Johnson Controls Fire | fire alarm t.i. on 3rd fl. provide new devices, relocate & demo existing devices. addition of new devices,19 smoke sensors,10 duct smoke sensors, 8 monitor modules, 5 relays modules,12 relays, 9 relay & monitor device,2 6 point modules, 115 speaker/strobes. ref pa #2018/0615/1975 | $94,300 |
| Feb 22, 2019 | Never finaled issued Mar 2019, no final | 650 Townsend St | Johnson Controls Fire | fire alarm t.i. at 6 floor. addition of new devices, 20 smoke sensors,6 duct smoke sensors, 5 monitor modules, 5 relay modules,7 relays, 6 relay & monitor module device, 2 6 point module, 125 speaker/strobes. ref bpa#2018/0615/1971 | $93,000 |
| Feb 22, 2019 | Never finaled issued Mar 2019, no final | 650 Townsend St | Johnson Controls Fire | fire alarm t.i. on 2nd floor. provide new devices, relocate and demo existing devices. 35 smoke sensors, 11 duct smoke sensors, 11 monitor modules, 5 relay modules,22 relays, 2 speakers, 4 strobes, 63 speaker/strobes. ref pa# 2018/0530/0539 | $82,700 |
| Feb 11, 2019 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | revision to pa #201805300539 - to add fds schedule to show fsd smoke control operation, includes updated mechanical drawings. 2nd fl minor architectual udates for design layouts. | |
| Feb 11, 2019 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | revision to pa #201806151971 - to update smoke control sequencing, includes updated mechanical drawings. 6th fl | |
| Feb 11, 2019 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | revision to pa #201806151975 - to update smoke control sequencing, includes updated mechanical drawings. 3rd fl | |
| Jan 23, 2019 | Expired or cancelled cancelled Jan 2026 | 650 Townsend St | Hathaway Dinwiddie Co. | gas line routing. additoinal plumbing scope to 201805300539 | $250,000 |
| Jan 4, 2019 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | 2/f: revision to 201805300339 to replace (e) non structural shaft liner w/structural floor. maher n/a. | $2,000 |
| Nov 14, 2018 | Completed final sign-off Apr 2019 | 650 Townsend St | Pribuss Engineering Inc | f/s: modify (e) 2nd fl fire sprinkler system for ti. add 134 heads, relocate 168 heads, total 302. ref ti #201805300539. | $155,228 |
| Nov 14, 2018 | Completed final sign-off Aug 2019 | 650 Townsend St | Pribuss Engineering Inc | fire sprinkler modification of (e) 1st thru 6th fls fire sprinkler systems for new ti. add 96 heads, relocate 358, total 452. ref ti #201805239943. | $232,328 |
| Nov 9, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | unstrut structural suppot for theatre equipment in atrium. ref pa #201805300538 for approved interior work. | $65,000 |
| Oct 10, 2018 | Completed final sign-off Mar 2019 | 650 Townsend St | Pribuss Engineering Inc | 3rd fl - includes modifying the existing 3rd fl fire sprinklers system to accomodate new ti. relocate 152, added 40. total 192. ttl head in the project 584 inclduing (e) heads, 192 heads being touched ref pa 2018-0615-1975 | $98,688 |
| Sep 25, 2018 | Completed final sign-off Mar 2019 | 650 Townsend St | Pribuss Engineering Inc | 6th fl - includes modifying the existing 6th fl fire sprinkler to accomodate ti. 179 relocates, 61 adds total 240. ref pa 2018-0615-1971 n/a for maher | $123,360 |
| Aug 15, 2018 | Never finaled issued Sep 2018, no final | 650 Townsend St | Hathaway Dinwiddie Co. | revision to pa # 201805239943 for core & shell. smoke control boundary to show (n) rated enclosures, fsd, smoke control matrix, compliance letter. maher n/a. floors 2nd, 3rd and 5th | $10,000 |
| Jul 18, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | revision to structural design of slab infill on 3rd fl due to infield conditions. ref 201804035411 | |
| Jun 28, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | interior soft demo of extg partitions and soffits, stage and ramp, and finishes in atrium. ab-017 | $50,000 |
| Jun 15, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | ti work in vacant office space on 3rd fl. work includeds partitions, cieling installations, light fixtures, doors, frames, millwork & finishes. maher na | $5,900,000 |
| Jun 15, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | 6th floor - ti work in vacant 6th fl office space. work includes partitions, ceiling installations, light fixtures, doors, frames, millwork, finishes & micro-kitchen with dining & servery area. maher na | $6,000,000 |
| May 30, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | this is an atrium improvement project. work includes (n) interior partitions, doors/frames, finishes, ada lifts, stairs, ramp, lighting & mep work. reference pa #2018-0307-3080 for approved exterior work. smoke control update. | $2,500,000 |
| May 30, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | ti work on 2nd flr: partitions, ceilings,doors & frames,millwrok finishes & mep work for office spaces, kitchen w/ dining & servery area & auditorium w/ fixed seating. other minor work on 1st flr, concourse & roof lvl for bicycle storage, grease equipment & (n) roof top equipment. | $8,000,000 |
| May 23, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | core and shell improvement for construction of 1 hr atrium, boundry walls, doors, frames, non-doors, frames, non-door & window systems on floors 2,3 & 6. other work includes bathroom renovations, and associated selective demo | $453,600 |
| Apr 3, 2018 | Completed final sign-off Oct 2020 | 650 Townsend St | Hathaway Dinwiddie Co. | new concrete infill slab of (e) floor opening on 3rd. renovate mens & women's restroom on 3rd flr. install smoke curtain to (e) elevator on 4th flr. temp barricades on 2nd & 3rd flr. selective demo of partitions, doors, lighting millwork to (e) vacant floor space on 2nd, 3rd & 6th maher na | $800,000 |
| Mar 7, 2018 | Never finaled issued Jun 2018, no final | 650 Townsend St | Hathaway Dinwiddie Co. | modification to a portion of the north (bluxome street) facade for (n) entry doors, windows & ada access ramp. (n) interior stairs, non load bearing partiions & inteiror finishes. no change of use. ** maher: n/a ** | $350,000 |
| Oct 6, 2017 | Never finaled issued Oct 2017, no final | 650 Townsend St | Emcor Services/Mesa Energy Systems Inc | 4th fl: install one (1) 3-ton cooling only split system. maher na | $26,438 |
| Aug 4, 2017 | Completed final sign-off Apr 2018 | 650 Townsend St | Johnson Controls Fire | provide new 8 relay iams for disconnecting the existing bms signal to 8 new vfd's at the atrium fans and 8 idnet iam with t-sense for control & monitoring atrium fan ufd located on the roof | $5,000 |
| May 26, 2017 | Completed final sign-off Nov 2022 | 650 Townsend St | Johnson Controls Fire | 4th floor - ti consist of adding (3) new speaker/strobes. remove & replace existing 2 speaker/strobes with new. demo exsiting devices as shown on pa 2017-0130-8186. maher na | $4,000 |
| May 18, 2017 | Completed final sign-off Jun 2017 | 699 08th St | Pioneer Fire Inc. | 4/f-relocate 10 pendents, add 2 pendents ref 201704143984 | $6,613 |
| May 10, 2017 | Completed final sign-off Jul 2017 | 699 08th St | Gci, Inc | 4/f- electrical, new power & branch. ref. pa#201704143984. na maher | $85,000 |
| Apr 17, 2017 | Completed final sign-off Oct 2018 | 650 Townsend St | Swinerton Builders | roof level- remove and replace existing waterproofing membrane and concrete topping slab at roof level, restripe parking layout, non structural work, no interior modifications. n/a ordinance #155-13 | $6,000,000 |
| Apr 14, 2017 | Completed final sign-off Jul 2017 | 699 08th St | Gci, Inc | 4th floor: suite 480 + 475 - demo and construction of non-structural interior partitions, new meeting rooms & renovated restroom fixtures & finishes on 4th floor. | $180,000 |
| Mar 31, 2017 | Never finaled issued Mar 2017, no final | 650 Townsend St | Johnson Controls Fire | 4th fl ti consists of adding 2 speaker strobes, 2 smoke detectors, 1 relay as shown drawings | $4,000 |
| Mar 7, 2017 | Never finaled issued Mar 2017, no final | 699 08th St | Novo Construction Inc | minor demo of perimeter glazed wall, existing prtitoins interior rooms and millwork. new open work area, pantry conference rooms. new suite entry with blazed oors, new partitions ceiling millwork and pantry. mep sep permit maher not req | $650,000 |
| Jan 30, 2017 | Completed final sign-off May 2017 | 650 Townsend St | Gci, Inc | tenant improvement - new multi tenant hallway on 4th flr. new gyp board partition around opening of (e) 5 story atrium. maher na | $25,000 |
| Jan 13, 2017 | Never finaled issued Jan 2017, no final | 650 Townsend St | Terra Visual Inc | install 1 electric single faced wall sign | $10,000 |
| Jan 12, 2017 | Completed final sign-off Feb 2017 | 650 Townsend St | Pioneer Fire Inc. | 2nd & 3rd flr: return system to shell condition ti 201612054144 maher na | $23,570 |
| Dec 5, 2016 | Completed final sign-off Feb 2017 | 650 Townsend St | Gci, Inc | 2nd flr: demo only-non-structural, remove carpet, wood flooring, millwork, act, storefront window, concrete block; maher n/a | $60,000 |
| Dec 5, 2016 | Completed final sign-off Feb 2017 | 650 Townsend St | Gci, Inc | 3rd flr: demo only-non structurarl remove carpet, act, wood flooring, millwork, storefront window, concrete block wall; maher n/a | $70,000 |
| Oct 21, 2016 | Completed final sign-off Oct 2016 | 650 Townsend St | Pioneer Fire Inc. | 6th floor - remove pre-action system & piping. restore to original conditoin with sprinklers installed in existing wet sprinkler piping. ref pa #201610119912. n/a maher ordinance | $9,657 |
| Oct 11, 2016 | Completed final sign-off Feb 2017 | 650 Townsend St | Gci, Inc | 6/f- partial demo, not touching ceiling, removal of hvac unit, raised floor, per ab-17 | $25,000 |
| Aug 9, 2016 | Completed final sign-off Aug 2016 | 699 08th St | Johnson Controls Fire | 4th floor - provide & install new (3) monitor modules, (1) speaker/strobe, (1) relay module, (3) smoke detectors & (4) duct detectors. ref t.i.# 2016-0412-4540 and 2016-0804-4147 | $7,500 |
| Aug 4, 2016 | Never finaled issued Aug 2016, no final | 699 08th St | Intelligent Technologies & Services Inc | provide parts amd smarts for 4th flr mdf room pre action detection. fire alarm wiring and installation under separate permit. sprinkler ref pa 201607212928, arch ref pa 201504124540. 6 detectors | $7,500 |
| Jul 21, 2016 | Completed final sign-off Aug 2016 | 699 08th St | Pioneer Fire Inc. | install new pre-action system with a total of 12 fire sprinklers. ref pa 2016-042-4540. maher na | $12,000 |
| Jul 20, 2016 | Never finaled issued Jul 2016, no final | 699 08th St | Gci, Inc | revision to ref pa 2016 0412 4540: 4th flr, suite 476 - floor lighting & power systems. connecting power to new or relocated light fixtures, power outlets and tenant equipment. connections to base bld (e) panels. | |
| Jul 12, 2016 | Never finaled issued Jul 2016, no final | 699 08th St | Gci, Inc | revision to pa 2016 0412 4540: addition of electrical room in (e) office space, suite 476 | |
| Jul 12, 2016 | Never finaled issued Jul 2016, no final | 699 08th St | Gci, Inc | revision to ref pa 2016 0412 4540: provide split system for cooling in the mdf room. 4th flr, suite 476 | $7,000 |
| Apr 12, 2016 | Never finaled issued Apr 2016, no final | 650 Townsend St | Gci, Inc | suite # 476: demo and construct non-bearing inteiror partitions in currently vacant suite for new fire rated mdf/ it room and associated work room. n/a for maher | $40,000 |
| Mar 16, 2016 | Completed final sign-off Oct 2016 | 699 08th St | Metropolitan Electrical Construction, Mastec Network Solutions Inc | install (1) new e-911 omni-directional antenna, (1) new equipment cabinet and (1) new gps/weather sensor unit on rooftop. equipment will use existing electrical panel. *nextnav e-911 | $5,000 |
| Mar 3, 2016 | Completed final sign-off Mar 2016 | 699 08th St | Swinerton Builders | #2d- interior t.i. including demo of non-structural partitions, new millwork and finishes. mep. and life safety/sprinklers under seperate permit. n/a ordinance #155-13 | $160,000 |
| Oct 29, 2015 | Completed final sign-off Nov 2015 | 650 Townsend St | Pribuss Engineering Inc | fire sprinkler ti,add 4 dry pendent sprinklers for new coolers. maher na | $7,205 |
| Sep 4, 2015 | Completed final sign-off Nov 2015 | 650 Townsend St | Johnson Controls Fire | fire alarm ti for concourse level. relcoate (e) speaker/strobe to new location. maher na | $1,000 |
| May 19, 2015 | Expired or cancelled cancelled Aug 2023 | 650 Townsend St | 44 new evacuation signage through 6 floors including concourse as needed. n/a maher ordinance | $3,400 | |
| May 8, 2015 | Completed final sign-off Jun 2015 | 650 Townsend St | Johnson Controls Fire | 4th floor: fire alarm t.i. consist of relocation existing 1 speaker/strobe. add new 3 speaker/strobes. ref. t.i. 2015.0306.0148. maher n/a. | $2,500 |
| Apr 9, 2015 | Never finaled issued Apr 2015, no final | 650 Townsend St | H & M Fire Protection, Inc. | #425-: fire sprinkler - relocate 9, add 3 ref pa# 2015 0306 0148. n/a ordinance #155-13 t.i. 201503060148 | $3,600 |
| Mar 6, 2015 | Completed final sign-off Jun 2015 | 650 Townsend St | Conscious Construction | partial ti suite 425. the scope inculdes addition of non load bearing partitions, soft seating, finishes and millwork. no structural work. maher - not req'd | $203,040 |
| Oct 20, 2014 | Never finaled issued Jan 2015, no final | 650 Townsend St | Structural & Refrigeration Mechanicalref | install customer supplied chiller. pumps, reconnect existing pipes to same. repipe existing heat exchanger. install 2 control values. life safety under separate permit. | $190,000 |
| Aug 1, 2014 | Never finaled issued Aug 2014, no final | 650 Townsend St | Ad Art Inc. | erect illuminated single faced wall sign; maher n/a | $8,000 |
| May 8, 2014 | Completed final sign-off Jul 2014 | 650 Townsend St | Johnson Controls Fire | 4th floor suite 410 - relocate (3) speaker/strobes, add (18) speaker/strobes & (3) duct detectors for the t.i. ref #2014.0320.1221. compliance with ordinance #155-13 not required | $10,000 |
| Apr 29, 2014 | Completed final sign-off May 2014 | 650 Townsend St | Johnson Controls Fire | #450: relocate 5 existing speaker/strobes to a new location. add 2 new speaker strobes as shown on drawings. ref app# 2014 0320 1221. n/a ordinance #155-13 | $5,000 |
| Apr 18, 2014 | Completed final sign-off Mar 2015 | 650 Townsend St | Johnson Controls Fire | #500- remove and replace extg 20 ceiling mount strobes with new ceiling mount speaker/srobes. add 4 new ceiling mount speaker/strobes, 2 wall mount speaker/strobes, 3 relays, 3 smoke detectors, 6 duct detectors as shown on the drawings. ref app#201401287227. n/a for the maher ordinance #155-13 | $17,000 |
| Apr 8, 2014 | Completed final sign-off May 2014 | 699 08th St | Anderson, Rowe & Buckley, Inc. | existing fire sprinkler system - tenant improvement, 4th floor: adding - 49 sprinklers. compliance with ordinance #155-13 not required. ref bpa#201403070162 | $24,500 |
| Apr 7, 2014 | Never finaled issued Apr 2014, no final | 650 Townsend St | Novo Construction Inc | 5th floor:revision to app#201401287227 to modify previously approved prep pantry. change conference room 548 to yoga room 548. modify pantry area 540,pantry area 533, pantry area 587 and pf store 553/board room.n/a for the maher ordinance#155-13 | |
| Apr 4, 2014 | Completed final sign-off May 2014 | 650 Townsend St | Anderson, Rowe & Buckley, Inc. | fire sprinkler system. tenant improvements. 52 added, 60 removed. ref 201403201221. 4th and 5th floors. | $26,000 |
| Mar 20, 2014 | Completed final sign-off Mar 2015 | 650 Townsend St | Novo Construction Inc | t.i. consisting of non structural demolition of existing office partitions, new construction to include partitions, glazing, doors, millwork, electrical & mechanical included. na ordinance #155-13 | $625,000 |
| Mar 7, 2014 | Completed final sign-off Mar 2015 | 699 08th St | Novo Construction Inc | ste #450: 4th flr: project consists of demo of select existing partitions. new conference rooms, storage rooms, private offices. suite is currently unoccupied. mech, ele, life safety, sprinklers system modification under this permit. comp with ord 155-13 not required | $614,000 |
| Feb 20, 2014 | Completed final sign-off Mar 2014 | 650 Townsend St | Novo Construction Inc | #305:renovation of extg office space at suite #305. convert open office into a conference room.n/a for the maher ordinance #155-13 | $50,000 |
| Jan 28, 2014 | Completed final sign-off Mar 2015 | 650 Townsend St | Novo Construction Inc | tenant improvement consisting of non-structural demolition of existing offices, new construction to include partitions, glazing, door, millwork, lighting, electrical & mechanical. | $1,200,000 |
| May 17, 2013 | Completed final sign-off Jun 2013 | 650 Townsend St | Dome Construction Corp | revision to 201303263089; t.i. wall layout change at room 304. | $6,000 |
| May 7, 2013 | Completed final sign-off Mar 2025 | 650 Townsend St | Simplexgrinnell Lp. | ground floor (zynga) -provide & install 1 new relay for (e) turnstile gate | $3,500 |
| Apr 29, 2013 | Completed final sign-off Jun 2013 | 650 Townsend St | Dome Construction Corp | suite 305 -added two (2) smoke fire dampers & added two (2) vav boxes. | $7,400 |
| Apr 24, 2013 | Never finaled issued Apr 2013, no final | 650 Townsend St | street space and sidewalk repair | ||
| Apr 22, 2013 | Completed final sign-off May 2013 | 650 Townsend St | Orr Protection Systems Inc | as builts to correct drawings - original pa# 201303071715; remove preaction system detection and releasing devices sprinkler work to be performed by superior sprinkler (201302220743) | $12,000 |
| Apr 19, 2013 | Completed final sign-off Jun 2013 | 650 Townsend St | Simplexgrinnell Lp. | 3rd floor-t.i. consist of adding 4 wall mount speaker/strobes, 1 wall mount & 2 duct detectors. ti 2013-0326-3089 | $3,000 |
| Apr 16, 2013 | Completed final sign-off May 2013 | 650 Townsend St | Golden Gate Fire Protection Inc | relocate 3 upright heads on 3/f. ti #20303263089. | $1,545 |
| Mar 26, 2013 | Completed final sign-off May 2013 | 650 Townsend St | Dome Construction Corp | 3rd floor suite #305 - interior tenant improvement including demolitoin, new partitions, furring 1 wall, ceiling work & new carpet. combining 2 offices into 1 office. | $100,000 |
| Mar 20, 2013 | Completed final sign-off Nov 2022 | 650 Townsend St | Simplexgrinnell Lp. | fire alarm to second floor. adding 1 monitor modole for sprinkler waterflow. refer to app. 201303071715. | $800 |
| Mar 7, 2013 | Completed final sign-off Apr 2013 | 650 Townsend St | Orr Protection Systems Inc | the existing pre-action system-zone 3 is to remain in place w/ the make up piping removed. a flow switch is to ge installed and the existing pre-action piping is to be filled making it wet. the riser will remain attached to the standpipe w/ new water flow swithch and tamper sprinkler pa#201302220743 | $12,000 |
| Mar 7, 2013 | Never finaled issued Mar 2013, no final | 650 Townsend St | Structural & Refrigeration Mechanicalref | remove 3 cooling towers and replace with 2 new cooling towers. | $250,000 |
| Feb 22, 2013 | Completed final sign-off Apr 2013 | 650 Townsend St | Superior Automatic Sprinkler | 2nd floor - convert pre-action (valve 1) to wet pipe | $8,000 |
| Dec 27, 2012 | Never finaled issued Feb 2013, no final | 650 Townsend St | Structural & Refrigeration Mechanicalref | change out chiller and 2 pumps | $450,000 |
| Dec 4, 2012 | Never finaled issued Dec 2012, no final | 699 08th St | Novo Construction Inc | revision to app#201209149743 electrical and mechanical work associated with 2 new roof boilers. no new fsd's are being added. | |
| Sep 14, 2012 | Never finaled issued Sep 2012, no final | 699 08th St | Novo Construction Inc | new lightweight housekeeping pad. elec and mech work associated with 2 new roof boilers, 2 new roof pumps, 1 air separator and 1 expansion tank. new chemical treatement system. no new fsds being added | $10,000 |
| Jul 16, 2012 | Completed final sign-off Jul 2012 | 699 08th St | Ayoob & Peery Plumbing Co Inc | 4th floor-add & relocate fire sprinkler heads per tenant improvement. 11 add, 111 relocate for ste 425 & 410 | $62,708 |
| Jul 9, 2012 | Completed final sign-off Jul 2012 | 699 08th St | Ayoob & Peery Plumbing Co Inc | 6th floor - relocate (7) fire sprinkler heads per tenant improvement. | $3,598 |
| Jun 27, 2012 | Expired or cancelled cancelled Apr 2013 | 699 08th St | Novo Construction Inc | ti 6th fl southeast consists of minor demolition of new non load bearing walls, doors, frames, light fixutres and finishes. mep. lifesafety under seperate permit. | $200,000 |
| Jun 26, 2012 | Completed final sign-off Jul 2012 | 699 08th St | Simplexgrinnell Lp. | 6th floor tenant improvement - remove & cover (2) strobes & (1) speaker. remove & replace (2) existing speaker/strobes. provide new (4) ceiling mount speaker/strobes. | $6,500 |
| Jun 26, 2012 | Completed final sign-off Nov 2012 | 699 08th St | Simplexgrinnell Lp. | 4th floor suite 425 & 410 - remove /replace & cover existing speaker/strobes for t.i. provide new (1) manual pull station, (2) smoke detectors, (1) duct detector, (78) ceiling mount speaker/strobes & (2) signal circuit card for (e) nac panels. | $17,500 |
| Jun 15, 2012 | Expired or cancelled cancelled Apr 2021 | 650 Townsend St | to erect sign | $8,000 | |
| Jun 12, 2012 | Expired or cancelled cancelled May 2013 | 699 08th St | Novo Construction Inc | commericial ti, demo existing offices, walls, doors, ceiling, and finishes. new non load bearing walls, doors, light fixtures, millwork, restroom fixtures, and finishes. no structural work. mech, elec, fire life sarfety separate permit. | $200,000 |
| May 24, 2012 | Completed final sign-off Dec 2012 | 699 08th St | Novo Construction Inc | revision to pa# 2012-0509-0121-upgrd (e) preumatic system to ddc controls, (e) duct to be removed. adding duct static pressure sensors power poles light fixtures. 44 new vav boxes & 2 new fan coil units | |
| May 9, 2012 | Completed final sign-off Jan 2013 | 699 08th St | Novo Construction Inc | 6th floor-minor demolition of non load bearing partitions, new partitions, doors/frames, light fixtures & finishes. new restroom fixtures & finishes. m.e.p & life safety under seperate | $200,000 |
| May 9, 2012 | Completed final sign-off Dec 2012 | 699 08th St | Novo Construction Inc | 4th floor-mechanical & electrical for tenant improvement for suite #425 & 410 to include 9 new vav boxes, 3 fan powered boxes, 2 fan coil units & lighting. | $600,000 |
| Apr 30, 2012 | Completed final sign-off Dec 2012 | 699 08th St | Novo Construction Inc | tenant improvement modifications to 4th suites 425 and 410 . open office spaces private offices, conference rooms copy rooms and break room mep under sep permits | $1,055,000 |
| Apr 3, 2012 | Expired or cancelled cancelled Apr 2013 | 699 08th St | Novo Construction Inc | modifications to (e) street level exterior side walk on the 8th st. side. it will include demo of planter boxes, extending a gas line & installation of a guardrail & weather guard.area for employees. | $200,000 |
| Mar 30, 2012 | Completed final sign-off Apr 2012 | 699 08th St | Anderson, Rowe & Buckley, Inc. | 6th floor:extg fire sprinkler system. t.i. 28 added sprinklers, 18 removed sprinklers, 20 relocated sprinklers. | $24,000 |
| Mar 29, 2012 | Completed final sign-off Oct 2012 | 650 Townsend St | Ad Art Inc. | to erect non-illuminated single face wall sign. | $9,000 |
| Mar 16, 2012 | Completed final sign-off Apr 2012 | 699 08th St | Simplexgrinnell Lp. | 6th floor-t.i fire alarm system consist of following: remove/repl & cover (e) speaker/strobes. provide 1 new wall mount strobe, 1 ceiling mount strobe, 4 wall mount speaker/strobes, 18 ceiling mount speaker/strobes & 1 signal circuit card for (e) nac panel | $10,000 |
| Mar 8, 2012 | Completed final sign-off Feb 2013 | 699 08th St | Novo Construction Inc | replacement of pendant fixtures, new power for work stations, new restroom lighting and 2 new panels for work stations only. duct distribution per new layout. 4 new vav, 4 new fan coil units, 1 new cooled chiller, 1 new pump, 1 expansion tank, chemical treatment sytem. no new fsd's | $250,000 |
| Feb 23, 2012 | Completed final sign-off Jan 2013 | 699 08th St | Novo Construction Inc | 6th floor partial demolition of existing offices, new non-load bearing walls, doors/frames, acoustical ceiling tile/grid, & related finishes. mep & life safety under separate permit. | $100,000 |
| Jan 17, 2012 | Completed final sign-off Apr 2012 | 699 08th St | Novo Construction Inc | 5th floor-mechanical & electrical work for t.i. refer to arch pa# 2011-1027-7755 | $450,000 |
| Jan 13, 2012 | Completed final sign-off Mar 2012 | 699 08th St | Simplexgrinnell Lp. | 5th floor fire alarm system update includes the modification of existing notifications circuits east side only includes the additoin of (37) visuals only, (72) speaker/visuals, (1) speaker only, & (1) heat detector. | $37,500 |
| Nov 30, 2011 | Completed final sign-off Jan 2012 | 650 Townsend St | Pribuss Engineering Inc | 1st floor unit #90:fire sprinkler t.i.. add one sprinkler x 514.62 | $515 |
| Nov 18, 2011 | Completed final sign-off Jan 2012 | 650 Townsend St | Simplex Grinnell | provide & install 1 (n) strobe, 1(n) smoke detector, 1 (n) relay iam | $5,000 |
| Nov 4, 2011 | Completed final sign-off Mar 2012 | 699 08th St | Simplexgrinnell Lp. | submit as built drawings per inspectors request. reference p/a#201102109985. field verify original plans vs. as-builts. | |
| Oct 27, 2011 | Never finaled issued Oct 2011, no final | 650 Townsend St | Occidental Express | replacing 20 deteriorated anchors at parapet 3/4" @ diamteter @ side of property + front | $3,500 |
| Oct 27, 2011 | Never finaled issued Nov 2011, no final | 699 08th St | Novo Construction Inc | 5th floor - ti consists of demo of existing offices, non-load bearing walls, doors/frames, acoustical ceiling tile/grid and finishes. new interior non load bearing walls, doors, light fixtures, new millwork. mep and fire life safety under separate permit. | $975,000 |
| Oct 21, 2011 | Expired or cancelled cancelled Aug 2012 | 650 Townsend St | Simplex Grinnell | install 3 new ceiling mount speakers/strobes for 2nd fl tenant suite 246 | $4,000 |
| Oct 20, 2011 | Completed final sign-off Jul 2012 | 699 08th St | revision to pa# 2011.08.25.3216. fire dept. assembly permit/ verification of assembly areas w/ occupant loads ( max. per dwgs) 3 areas of assembly: ground fl. private cafeteria; basement auditorium; basement gaming/dining. | ||
| Oct 20, 2011 | Completed final sign-off Oct 2011 | 699 08th St | Pribuss Engineering Inc | fire sprinkler ti. 16 fire sprinklers. | $8,234 |
| Aug 30, 2011 | Expired or cancelled cancelled Jan 2026 | 699 08th St | 1st floor:construction of steel frame and metal fence to demarcate exterior seating for tenant. structural scope included. extg mechanical electrical life safety not included in permit. | $30,000 | |
| Aug 25, 2011 | Completed final sign-off Jul 2012 | 699 08th St | Plant Construction Company Lp | fire department assembly permit verification of assembly areas with maximum occupant loads(per drawings). ground floor private cafeteria and basement auditorium | |
| Aug 17, 2011 | Completed final sign-off Dec 2011 | 650 Townsend St | Plant Construction Company Lp | 1st floor ste 90 - construction of (1) unisex accessible restroom at (e) office space. | $60,000 |
| Aug 15, 2011 | Never finaled issued Aug 2011, no final | 650 Townsend St | Occidental Express | re-roofing; re-flashing parapet and sheathing. | $15,000 |
| Aug 12, 2011 | Expired or cancelled cancelled Jan 2026 | 650 Townsend St | structural attachment upgrade of business sign. | $8,000 |