Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 13, 2021 | Completed final sign-off Oct 2021 | 699 08th St | Clune Construction Company L P | 3/f: voluntary addition of operable fire partition at 3rd floor atrium breakroom.Details
3/f: voluntary addition of operable fire partition at 3rd floor atrium breakroom. | $100,000 |
| Dec 7, 2020 | Completed final sign-off Jul 2022 | 699 08th St | Clune Construction Company L P | concourse: interior commercial office tenant improvement. minor demolition. construction of non-bearing interior partitions.Details
concourse: interior commercial office tenant improvement. minor demolition. construction of non-bearing interior partitions. | $2,382,895 |
| Jun 24, 2019 | Completed final sign-off Oct 2020 | 699 08th St | Clune Construction Company L P | upgrade to existing lobby that includes and not limited to new reception desk, new paint, new flooring, new lighting maher not reqDetails
upgrade to existing lobby that includes and not limited to new reception desk, new paint, new flooring, new lighting maher not req | $41,000 |
| Jun 4, 2019 | Completed final sign-off Nov 2019 | 555 Montgomery St | Peacock Construction | 14/f: revision to pa 201903195603 to document change to egress plan on g1.0. maher n/a.Details
14/f: revision to pa 201903195603 to document change to egress plan on g1.0. maher n/a. | |
| May 14, 2019 | Completed final sign-off Dec 2019 | 1 Embarcadero Center | Principal Builders Inc. | 16/f: revision to app#201904160087 to remove rating at common corridor. not required by cbc 10.20.1 n/a for maherDetails
16/f: revision to app#201904160087 to remove rating at common corridor. not required by cbc 10.20.1 n/a for maher | |
| Apr 16, 2019 | Completed final sign-off Dec 2019 | 1 Embarcadero Center | Principal Builders Inc. | 16th flr. new partitions, doors, millwork, finishes, glazing and mechanical systems, lighting & power. sprinklers & life safety to be submitted separately.Details
16th flr. new partitions, doors, millwork, finishes, glazing and mechanical systems, lighting & power. sprinklers & life safety to be submitted separately. | $2,179,928 |
| Mar 19, 2019 | Completed final sign-off Nov 2019 | 555 Montgomery St | Peacock Construction | 14/f: removal of non-structural partition, relocate electrical and data outlets, suspended decorative panals and finishesDetails
14/f: removal of non-structural partition, relocate electrical and data outlets, suspended decorative panals and finishes | $10,400 |