Permit GraphShortlistSan Francisco building permits since 2000

Marc Penninger

License
C27880
Architect or Civil engineer: both boards write C before the number, and the roles on the permits do not settle which
About the two boards
Look the license up with the state (Architects Board)
Look up C27880 at the Board for Professional Engineers
Listed as
architect, authorized agent-others, designer, engineer
Firm
Studios Architecture
Based in
San Francisco
On San Francisco permits
Jul 2003 to Nov 2026

99 permits since 2000 (architect on 96 permits, engineer on 2 permits, authorized agent-others on 1 permit, designer on 1 permit): 62 completed, 22 in progress, 11 never finaled, 4 expired or cancelled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records

Worked with

Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.

Contractors
Bcci Construction Company (35), Novo Construction Inc (22), Dpr Construction (6), Skyline Construction (6), Truebeck Construction (6), Principal Builders Inc. (4), Field Construction Inc. (2), Hathaway Dinwiddie Co. (2), Sc Builders, Inc (2), B N Builders Inc, Dpr Construction Inc, Metropolitan Electrical Construction, Source Planning And Construction Inc
Architects
Byron Kwong
Engineers
Amit Wadhwa (11), Levi G. Abarte (9), Philip Tapia (3), Aaron Strauch (2), Dennis Cheung (2), Joe Gulden (2), Laura Weyl (2), Mark Koenigs (2), Blake Dilsworth, Carl Ludwig Schroeder, Christopher Jordan Malabed, David Johnson, David Zenor Heinzerling, Dean Macy, Joe Gulden, Joshua Mcmahan, Laura Weyl, Paul Littler, Tim Heiman, Valeria Balderramos
Authorized agents
Paul Littler (2)

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Nov 5, 2026In progress
issued Nov 2026
300 Howard StNovo Construction Inc9th fl: mdf room ti. mechanical and electrical included, no plumbing
Details
Permit
202611050385
Permit issued
Nov 10, 2026

9th fl: mdf room ti. mechanical and electrical included, no plumbing

Open the permit page

$50,000
Oct 16, 2026In progress
filed Oct 2026, not yet issued
300 Howard Stbasement level 1,2,3 & 1,2,3/f: service elevator - structural improvements to accommodate elevator shaft modifications. mechanical & electrical tie in to accommodate new service elevator.
Details
Permit
202610169538

basement level 1,2,3 & 1,2,3/f: service elevator - structural improvements to accommodate elevator shaft modifications. mechanical & electrical tie in to accommodate new service elevator.

Open the permit page

$593,938
Oct 8, 2026In progress
issued Oct 2026
300 Howard StNovo Construction Incbasement level 1: mpoe permit, mchanical & electrical only, no arch under this permit
Details
Permit
202610089180
Permit issued
Oct 27, 2026

basement level 1: mpoe permit, mchanical & electrical only, no arch under this permit

Open the permit page

$56,897
Oct 2, 2026In progress
filed Oct 2026, not yet issued
1089 03rd Stproj-26-0643: mou port - deferred submittal for atrium audio-visual diplay piers (reference pa# 202511079166 & b-2025-025
Details
Permit
202609218439

proj-26-0643: mou port - deferred submittal for atrium audio-visual diplay piers (reference pa# 202511079166 & b-2025-025

Open the permit page

Sep 30, 2026In progress
filed Sep 2026, not yet issued
300 Howard St16th floor: dining and servery t.i. includes interior wall, ceiling, millwork and finishes.
Details
Permit
202609308836

16th floor: dining and servery t.i. includes interior wall, ceiling, millwork and finishes.

Open the permit page

$6,048,657
Sep 23, 2026In progress
filed Sep 2026, not yet issued
300 Howard St14th fl: dining and servery. ti includes interior walls, ceilkings, millwork, finishes.
Details
Permit
202609238502

14th fl: dining and servery. ti includes interior walls, ceilkings, millwork, finishes.

Open the permit page

$9,172,090
Sep 15, 2026In progress
filed Sep 2026, not yet issued
300 Howard StNovo Construction Inc2/f: tenant improvements: in existing office building. improvements to include, architectural, mechanical, electrical and plumbing to accommodate new tenant build out. mep scope to support kitchen build-out and updated restrooms.
Details
Permit
202608186764

2/f: tenant improvements: in existing office building. improvements to include, architectural, mechanical, electrical and plumbing to accommodate new tenant build out. mep scope to support kitchen build-out and updated restrooms.

Open the permit page

$8,061,217
Sep 1, 2026In progress
filed Sep 2026, not yet issued
300 Howard St15th floor: t.i. including new interior walls, ceilings, millwork & finishes
Details
Permit
202609017538

15th floor: t.i. including new interior walls, ceilings, millwork & finishes

Open the permit page

$8,361,087
Aug 28, 2026Completed
final sign-off Nov 2026
345 Spear StB N Builders Incground fl ste 118-120: addition of partition wall to divide (e) lounge space into (2) individual enclosed rooms. (arch/mep)
Details
Permit
202608287381
Permit issued
Sep 18, 2026
Final sign-off
Nov 17, 2026

ground fl ste 118-120: addition of partition wall to divide (e) lounge space into (2) individual enclosed rooms. (arch/mep)

Open the permit page

$100,000
Aug 25, 2026In progress
issued Nov 2026
300 Howard St2nd fl - ti to existing office. includes improvements to arch, mech, electrical and plumbing
Details
Permit
202608257157
Permit issued
Nov 6, 2026

2nd fl - ti to existing office. includes improvements to arch, mech, electrical and plumbing

Open the permit page

$6,048,657
Aug 24, 2026In progress
issued Sep 2026
300 Howard StNovo Construction Inc14th/f: structural upgrade to accommodate future t.i.
Details
Permit
202608247057
Permit issued
Sep 10, 2026

14th/f: structural upgrade to accommodate future t.i.

Open the permit page

$165,000
Aug 20, 2026In progress
issued Sep 2026
300 Howard StNovo Construction Inc15th f/l: structural upgrades to accomodate future tenant buildout.
Details
Permit
202608206933
Permit issued
Sep 10, 2026

15th f/l: structural upgrades to accomodate future tenant buildout.

Open the permit page

$165,000
Aug 17, 2026In progress
issued Sep 2026
300 Howard StNovo Construction Inc7th & 8th floors: t.i. including new interior walls, ceiling, milkwork and finishes.
Details
Permit
202608176690
Permit issued
Sep 24, 2026

7th & 8th floors: t.i. including new interior walls, ceiling, milkwork and finishes.

Open the permit page

$15,451,442
Jul 7, 2026In progress
issued Jul 2026
300 Howard StNovo Construction Inc9/f: structural upgrades to accommodate future tenant buildout.
Details
Permit
202607074613
Permit issued
Jul 27, 2026

9/f: structural upgrades to accommodate future tenant buildout.

Open the permit page

$135,000
Jul 6, 2026In progress
issued Aug 2026
300 Howard StNovo Construction Inc16th fl: structural upgrades to accommodate future tenant buildout
Details
Permit
202607064589
Permit issued
Aug 24, 2026

16th fl: structural upgrades to accommodate future tenant buildout

Open the permit page

$165,000
Jun 23, 2026In progress
issued Aug 2026
300 Howard StNovo Construction Inc2 : structural upgrades to accommodate future tenant buildout
Details
Permit
202606233762
Permit issued
Aug 10, 2026

2 : structural upgrades to accommodate future tenant buildout

Open the permit page

$200,000
Jun 18, 2026Completed
final sign-off Nov 2026
555 Market StBcci Construction Companydeferred submittal for pa#: 202512121719 for review of climbing walls.
Details
Permit
202606183561
Permit issued
Jul 23, 2026
Final sign-off
Nov 3, 2026

deferred submittal for pa#: 202512121719 for review of climbing walls.

Open the permit page

May 27, 2026Completed
final sign-off Oct 2026
1 Harrison StTruebeck Construction6/fl- revisoin 202410173107 to include adding guardrail to 6th floor roof deck plan north parapet. in response to as built discovery that the parapet is less than 42" at roof deck
Details
Permit
202605271940
Permit issued
May 29, 2026
Final sign-off
Oct 20, 2026

6/fl- revisoin 202410173107 to include adding guardrail to 6th floor roof deck plan north parapet. in response to as built discovery that the parapet is less than 42" at roof deck

Open the permit page

Apr 7, 2026Completed
final sign-off Oct 2026
1 Harrison StTruebeck Constructionrevision to 202410082583 and 202507020012. update 5 columns at level 1 from frp strengthening to steel tube strengthening.
Details
Permit
202604079048
Permit issued
Apr 13, 2026
Final sign-off
Oct 20, 2026

revision to 202410082583 and 202507020012. update 5 columns at level 1 from frp strengthening to steel tube strengthening.

Open the permit page

Mar 30, 2026In progress
issued Apr 2026
199 Fremont StNovo Construction Incfloor 1,3, 8, 11, 12, 17, 18, 20, 21, 22. interior non-strucutural demo of (e) unoccupied floors include removal of walls, ceilings, millworks, finishes, doors, light fixture per ab-017.
Details
Permit
202603308510
Permit issued
Apr 7, 2026

floor 1,3, 8, 11, 12, 17, 18, 20, 21, 22. interior non-strucutural demo of (e) unoccupied floors include removal of walls, ceilings, millworks, finishes, doors, light fixture per ab-017.

Open the permit page

$1,500,000
Mar 11, 2026Completed
final sign-off Oct 2026
1 Harrison StTruebeck Constructiondefferred green living wall submission associated with approved pa #202410173107
Details
Permit
202603117374
Permit issued
Mar 17, 2026
Final sign-off
Oct 20, 2026

defferred green living wall submission associated with approved pa #202410173107

Open the permit page

$10,000
Dec 18, 2025Completed
final sign-off Jan 2026
2 Harrison Stref 202506108301- documentation only for path of travel compliance of (e) high rise office buidling from street access and basement parking to first floor. scope does not inlcude levels above 1st floor. no work to be done and drawings record as built conditions complaint with cbc accessiblity
Details
Permit
202512182168
Permit issued
Dec 18, 2025
Final sign-off
Jan 7, 2026

ref 202506108301- documentation only for path of travel compliance of (e) high rise office buidling from street access and basement parking to first floor. scope does not inlcude levels above 1st floor. no work to be done and drawings record as built conditions complaint with cbc accessiblity

Open the permit page

Dec 12, 2025In progress
issued Feb 2026
555 Market StBcci Construction Company1/fl- (n) amenity bar/restaurant space, basketball court, lounge area, includes (n) conference rooms, countertop bar and island, seating, restrooms, finishes, and lighting throughout. 2/fl (n) lighting, ceilings, and finishes throughout. (n) pickleball court, fitness area, fitness, classroom, new
Details
Permit
202512121719
Permit issued
Feb 25, 2026

1/fl- (n) amenity bar/restaurant space, basketball court, lounge area, includes (n) conference rooms, countertop bar and island, seating, restrooms, finishes, and lighting throughout. 2/fl (n) lighting, ceilings, and finishes throughout. (n) pickleball court, fitness area, fitness, classroom, new

Open the permit page

$8,361,781
Oct 24, 2025In progress
issued Oct 2025
500 Howard StNovo Construction Inc1/f: change of occupancy from retail to office.
Details
Permit
202510248135
Permit issued
Oct 29, 2025

1/f: change of occupancy from retail to office.

Open the permit page

Oct 10, 2025In progress
filed Oct 2025, not yet issued
1089 03rd Stproj#25-0621-mou port: alteration to existing floor plates on level 6,7,& 8.demo existing slab & create floor openings as shown, for future tenant improvements.provide temporary code compliance with smoke control report.
Details
Permit
202509266165

proj#25-0621-mou port: alteration to existing floor plates on level 6,7,& 8.demo existing slab & create floor openings as shown, for future tenant improvements.provide temporary code compliance with smoke control report.

Open the permit page

$1,750,000
Sep 24, 2025In progress
issued Jan 2026
222 02nd StNovo Construction Inc18th floor: installation of 3 phone booths.
Details
Permit
202509246022
Permit issued
Jan 22, 2026

18th floor: installation of 3 phone booths.

Open the permit page

$15,000
Jun 10, 2025Completed
final sign-off Nov 2025
2 Harrison StSkyline Constructionbarrier removal improvements in high rise office bldg. bring basement floor parking accessibility up to current code. bring publicly accessible restrooms on 1st fl of 2 harrison & 345 spear up to current code
Details
Permit
202506108301
Permit issued
Aug 22, 2025
Final sign-off
Nov 21, 2025

barrier removal improvements in high rise office bldg. bring basement floor parking accessibility up to current code. bring publicly accessible restrooms on 1st fl of 2 harrison & 345 spear up to current code

Open the permit page

$150,000
May 29, 2025Completed
final sign-off Oct 2026
1 Harrison StTruebeck Constructionrevision to pa# 202410082583: misc structural updates.
Details
Permit
202505297523
Permit issued
Jul 1, 2025
Final sign-off
Oct 20, 2026

revision to pa# 202410082583: misc structural updates.

Open the permit page

May 28, 2025In progress
issued Sep 2025
500 Howard StNovo Construction Incground floor:t.i. to existing retail space consisting of 2 new interior doors, curtains, privacy film and applied finish treatments, repairs to existing conditions. signage replacements where room names changed mech/electrical included.
Details
Permit
202505287350
Permit issued
Sep 24, 2025

ground floor:t.i. to existing retail space consisting of 2 new interior doors, curtains, privacy film and applied finish treatments, repairs to existing conditions. signage replacements where room names changed mech/electrical included.

Open the permit page

$75,000
Mar 31, 2025Completed
final sign-off Jan 2026
500 Howard StNovo Construction Inc5th fl: interior ti. include paint throughout. removal of existing walls, ceilings and finishes. new interior construction of walls, new wall & floor finishes. mechanical, electrical ,plumbing & structural included
Details
Permit
202503313350
Permit issued
Jun 20, 2025
Final sign-off
Jan 23, 2026

5th fl: interior ti. include paint throughout. removal of existing walls, ceilings and finishes. new interior construction of walls, new wall & floor finishes. mechanical, electrical ,plumbing & structural included

Open the permit page

$5,416,864
Feb 26, 2025Completed
final sign-off Feb 2026
500 Howard StNovo Construction Inc3rd fl -ti to include new nonstructural partitions, paint, wall covering on, privacy glass film; repairs to existing conditions. mep included
Details
Permit
202502261131
Permit issued
May 15, 2025
Final sign-off
Feb 26, 2026

3rd fl -ti to include new nonstructural partitions, paint, wall covering on, privacy glass film; repairs to existing conditions. mep included

Open the permit page

$4,721,444
Feb 24, 2025Completed
final sign-off Dec 2025
500 Howard StNovo Construction Inc5th fl- removal of (e) walls, ceilings, millwork and finishes ab017
Details
Permit
202502240917
Permit issued
Feb 25, 2025
Final sign-off
Dec 1, 2025

5th fl- removal of (e) walls, ceilings, millwork and finishes ab017

Open the permit page

$175,000
Feb 21, 2025Completed
final sign-off Feb 2026
500 Howard StNovo Construction Inc3rd floor: non-structural demolition of office space. addition of prep kitchen to include walk -in cooler, cooking hood, dish clean, & misc. equipment. ancillary storage for mechanical equipment, grease interceptor & water heaters.
Details
Permit
202502210777
Permit issued
May 21, 2025
Final sign-off
Feb 26, 2026

3rd floor: non-structural demolition of office space. addition of prep kitchen to include walk -in cooler, cooking hood, dish clean, & misc. equipment. ancillary storage for mechanical equipment, grease interceptor & water heaters.

Open the permit page

$986,000
Feb 21, 2025Completed
final sign-off May 2025
500 Howard StNovo Construction Inc8th fl- revision to pa #202412237306 to add selective new demo for new exhaust duct, new environmental exhuast louver added hand and prep sink, added power, new hot water pump. new exhaust fan, under floor terminal unit and equipment anchorage
Details
Permit
202502210769
Permit issued
Mar 21, 2025
Final sign-off
May 6, 2025

8th fl- revision to pa #202412237306 to add selective new demo for new exhaust duct, new environmental exhuast louver added hand and prep sink, added power, new hot water pump. new exhaust fan, under floor terminal unit and equipment anchorage

Open the permit page

$75,000
Jan 10, 2025Completed
final sign-off Aug 2025
500 Howard StNovo Construction Inc4th floor: selective demo of millwork, finshes and wall penetrations, mew carpet, paint and acoustic panels, new exterior window louver alteration of drinking fountain niche, mep included
Details
Permit
202501108111
Permit issued
Feb 10, 2025
Final sign-off
Aug 6, 2025

4th floor: selective demo of millwork, finshes and wall penetrations, mew carpet, paint and acoustic panels, new exterior window louver alteration of drinking fountain niche, mep included

Open the permit page

$325,000
Dec 23, 2024Completed
final sign-off May 2025
500 Howard StNovo Construction Inc8/fl- ti to convert storage to pantry to include (n) refrigator, freezer, food storage and sinks. mep included.
Details
Permit
202412237306
Permit issued
Jan 16, 2025
Final sign-off
May 6, 2025

8/fl- ti to convert storage to pantry to include (n) refrigator, freezer, food storage and sinks. mep included.

Open the permit page

$250,000
Nov 14, 2024Completed
final sign-off Oct 2026
1 Harrison StTruebeck Constructionhorizontal infill of (e) terraces at levels 2-5, (n) marquee. architectural and mep core and shell updates at all floors, and (n) interior & exterior assembly amenity spaces at level 6. soft demo, interior tenant improvements, and voluntary seismic upgrade to be done under separate permits.
Details
Permit
202410173107
Permit issued
Jul 24, 2025
Final sign-off
Oct 20, 2026

horizontal infill of (e) terraces at levels 2-5, (n) marquee. architectural and mep core and shell updates at all floors, and (n) interior & exterior assembly amenity spaces at level 6. soft demo, interior tenant improvements, and voluntary seismic upgrade to be done under separate permits.

Open the permit page

$13,300,000
Oct 28, 2024Completed
final sign-off May 2025
500 Howard StNovo Construction Incselect demo of built in seating and tables, addition of new mobile food service severy carts new shelving and wall mounted dish drying rack new stainless steel finishes around t/r/ dish drop are enlarge waste opening paint one wall in barista area
Details
Permit
202410283845
Permit issued
Nov 26, 2024
Final sign-off
May 6, 2025

select demo of built in seating and tables, addition of new mobile food service severy carts new shelving and wall mounted dish drying rack new stainless steel finishes around t/r/ dish drop are enlarge waste opening paint one wall in barista area

Open the permit page

$195,000
Oct 8, 2024Completed
final sign-off Oct 2026
1 Harrison StTruebeck Constructionphase 2: voluntary structural seismic upgrade on all floors: soft demo and architecture under separate permit. see 202410173107.
Details
Permit
202410082583
Permit issued
May 16, 2025
Final sign-off
Oct 20, 2026

phase 2: voluntary structural seismic upgrade on all floors: soft demo and architecture under separate permit. see 202410173107.

Open the permit page

$6,545,000
Oct 4, 2024Completed
final sign-off May 2025
500 Howard StNovo Construction Incbarrier removal path of travel compliance for parking level floors 1,2,3,5, and 8
Details
Permit
202410042322
Permit issued
Dec 4, 2024
Final sign-off
May 2, 2025

barrier removal path of travel compliance for parking level floors 1,2,3,5, and 8

Open the permit page

$288,991
Aug 1, 2024Completed
final sign-off Sep 2024
2 Harrison StBcci Construction Company7/f: demo of partitions and ceilings. ref sprinkler 202407297491
Details
Permit
202408017763
Permit issued
Aug 7, 2024
Final sign-off
Sep 18, 2024

7/f: demo of partitions and ceilings. ref sprinkler 202407297491

Open the permit page

$45,000
May 7, 2024In progress
issued May 2024
444 De Haro StSkyline Constructioninstallation and relocation of 12 phone booths and relocate 4.
Details
Permit
202405071536
Permit issued
May 28, 2024

installation and relocation of 12 phone booths and relocate 4.

Open the permit page

$100,000
Mar 23, 2021Completed
final sign-off Dec 2021
2 Harrison StSource Planning And Construction Inc4th floor: renovation of an (e) coffee bar and storage room, permit includes electrical and plumbing n/a maher
Details
Permit
202103237109
Permit issued
Aug 19, 2021
Final sign-off
Dec 3, 2021

4th floor: renovation of an (e) coffee bar and storage room, permit includes electrical and plumbing n/a maher

Open the permit page

$100,000
Jan 27, 2021Never finaled
issued Apr 2021, no final
303 02nd StSkyline Construction7th fl tenant improvement to include new non-structural partitions, multi purpose room expansion, all gender restrooms, upgrades to mens & womens restrooms, interior finishes.
Details
Permit
202101273430
Permit issued
Apr 30, 2021

7th fl tenant improvement to include new non-structural partitions, multi purpose room expansion, all gender restrooms, upgrades to mens & womens restrooms, interior finishes.

Open the permit page

$1,250,000
Jan 21, 2021Never finaled
issued Mar 2021, no final
303 02nd StSkyline Construction7/f: partial demolition of existing construction for future tenant improvement in compliance to ab-017. maher n/a. eniter 7th floor is vacant
Details
Permit
202101212977
Permit issued
Mar 15, 2021

7/f: partial demolition of existing construction for future tenant improvement in compliance to ab-017. maher n/a. eniter 7th floor is vacant

Open the permit page

$85,000
Jan 19, 2021Completed
final sign-off Mar 2023
303 02nd StSkyline Construction6th fl partial demolition of existing construction for future tenant improvement. ab-017. entire 6th floor is vacant.
Details
Permit
202101192929
Permit issued
Mar 15, 2021
Final sign-off
Mar 3, 2023

6th fl partial demolition of existing construction for future tenant improvement. ab-017. entire 6th floor is vacant.

Open the permit page

$65,000
Oct 18, 2019Completed
final sign-off Oct 2020
2 Harrison StBcci Construction Company3rd fl - alterations include new non rated partitions. new conference rooms, new editing room & storage. ref pa 2019-0123-0979
Details
Permit
201910184899
Permit issued
Nov 6, 2019
Final sign-off
Oct 16, 2020

3rd fl - alterations include new non rated partitions. new conference rooms, new editing room & storage. ref pa 2019-0123-0979

Open the permit page

$410,000
Mar 11, 2019Never finaled
issued Apr 2019, no final
345 Spear StBcci Construction Company6th floor - construction of a new catering kitchen and office space. new grease trap that runs from the 5th flooor through the 7th fl. 8th fl and roof equipment included in scope. structural deferred for grease interceptors & 8th floor rooftop anchorage. n/a for maher.
Details
Permit
201903114864
Permit issued
Apr 17, 2019

6th floor - construction of a new catering kitchen and office space. new grease trap that runs from the 5th flooor through the 7th fl. 8th fl and roof equipment included in scope. structural deferred for grease interceptors & 8th floor rooftop anchorage. n/a for maher.

Open the permit page

$2,800,000
Jan 23, 2019Completed
final sign-off Aug 2019
2 Harrison StBcci Construction Company4th floor: revision to previously approved architectural and m.e.p permits. change door and partition in coffee tasting room. adding new hand sink. ref: 201810193678.
Details
Permit
201901230980
Permit issued
Mar 20, 2019
Final sign-off
Aug 21, 2019

4th floor: revision to previously approved architectural and m.e.p permits. change door and partition in coffee tasting room. adding new hand sink. ref: 201810193678.

Open the permit page

$100,000
Dec 10, 2018Never finaled
issued Dec 2018, no final
121 Spear StBcci Construction Companyroo: replace the existing roof gate with a new gate at east tower of building. maher n/a.
Details
Permit
201812107848
Permit issued
Dec 10, 2018

roo: replace the existing roof gate with a new gate at east tower of building. maher n/a.

Open the permit page

$15,000
Oct 31, 2018Never finaled
issued Nov 2018, no final
121 Spear StBcci Construction Company2nd fl - fire only. permit for a-3 occupancy assembly. ref pa #201711093681. occupant load 91 and 94
Details
Permit
201810314670
Permit issued
Nov 7, 2018

2nd fl - fire only. permit for a-3 occupancy assembly. ref pa #201711093681. occupant load 91 and 94

Open the permit page

Oct 31, 2018Never finaled
issued Nov 2018, no final
121 Spear StBcci Construction Company5th fl - fire only. permit for a-2 assembly. ref pa #201711164136. barisita and deck occupant load 149
Details
Permit
201810314667
Permit issued
Nov 7, 2018

5th fl - fire only. permit for a-2 assembly. ref pa #201711164136. barisita and deck occupant load 149

Open the permit page

Oct 31, 2018Never finaled
issued Nov 2018, no final
121 Spear StBcci Construction Company6th floor- fire only permit for a3 occupancy assembly. ref: 2017-1212-6270 ol concentrated 276. ol unconcentrated 14 lb.
Details
Permit
201810314668
Permit issued
Nov 7, 2018

6th floor- fire only permit for a3 occupancy assembly. ref: 2017-1212-6270 ol concentrated 276. ol unconcentrated 14 lb.

Open the permit page

Oct 19, 2018Completed
final sign-off Mar 2021
2 Harrison StBcci Construction Company3th fl - office ti includes new partitions, kitchen & a-2 assembly area. room 300. mep deferred. structural drawings for walls.
Details
Permit
201810193680
Permit issued
Dec 27, 2018
Final sign-off
Mar 4, 2021

3th fl - office ti includes new partitions, kitchen & a-2 assembly area. room 300. mep deferred. structural drawings for walls.

Open the permit page

$980,000
Oct 19, 2018Completed
final sign-off Mar 2021
2 Harrison StBcci Construction Company4th fl - office ti includes new partitions, gender neutral restrooms. as assembly area, room 401. mep deferred. also includes kitchen & coffee tasting area.
Details
Permit
201810193678
Permit issued
Dec 27, 2018
Final sign-off
Mar 4, 2021

4th fl - office ti includes new partitions, gender neutral restrooms. as assembly area, room 401. mep deferred. also includes kitchen & coffee tasting area.

Open the permit page

$980,000
Jun 26, 2018Completed
final sign-off Jun 2019
121 Spear StBcci Construction Company6th fl revision to approved ti. relocate hand sink inpantry. clarify to utilize floor mop sink. update cove base finish in restroom. ref #201803163850. maher na
Details
Permit
201806262936
Permit issued
Jul 10, 2018
Final sign-off
Jun 21, 2019

6th fl revision to approved ti. relocate hand sink inpantry. clarify to utilize floor mop sink. update cove base finish in restroom. ref #201803163850. maher na

Open the permit page

Dec 12, 2017Completed
final sign-off Jun 2019
121 Spear StBcci Construction Company2nd flr: office space including partition, event rooms & horizontal exit. maher n/a
Details
Permit
201712126227
Permit issued
Jan 3, 2018
Final sign-off
Jun 25, 2019

2nd flr: office space including partition, event rooms & horizontal exit. maher n/a

Open the permit page

$2,000,000
Dec 12, 2017Completed
final sign-off Jun 2019
121 Spear StBcci Construction Company6th flr office ti with mep. new partitions, horizontal exit & finishes. this permit is to be completed together with permit #9.
Details
Permit
201712126270
Permit issued
Mar 15, 2018
Final sign-off
Jun 25, 2019

6th flr office ti with mep. new partitions, horizontal exit & finishes. this permit is to be completed together with permit #9.

Open the permit page

$5,000,000
Dec 12, 2017Completed
final sign-off Jun 2019
121 Spear StBcci Construction Company3rd flr office ti with mep. new partitions, horizontal exit & finishes.
Details
Permit
201712126276
Permit issued
Mar 7, 2018
Final sign-off
Jun 25, 2019

3rd flr office ti with mep. new partitions, horizontal exit & finishes.

Open the permit page

$4,500,000
Nov 21, 2017Completed
final sign-off Jun 2019
121 Spear StBcci Construction Company5th fl - tenant improvement including build out of workstations, partitions a/meps. also work on 3rd floor mdf room. fire under separate permits. maher na
Details
Permit
201711214496
Permit issued
Feb 6, 2018
Final sign-off
Jun 21, 2019

5th fl - tenant improvement including build out of workstations, partitions a/meps. also work on 3rd floor mdf room. fire under separate permits. maher na

Open the permit page

$6,000,000
Nov 20, 2017Completed
final sign-off Jun 2019
121 Spear StBcci Construction Companyon 2nd through 5th floors- new interconnecting stair & stair openings for ti project. ** maher: n/a **
Details
Permit
201711204399
Permit issued
Feb 5, 2018
Final sign-off
Jun 21, 2019

on 2nd through 5th floors- new interconnecting stair & stair openings for ti project. ** maher: n/a **

Open the permit page

$1,100,000
Nov 9, 2017Completed
final sign-off Jun 2019
121 Spear StBcci Construction Companyamep. level 3, office - kitchen dishroom & servery, seating areas. grease trap on level 2 & shafts that run from level 3 to roof. mep included. (n) 2 hrs shaft, fire assembly area- two way communication, ul 300, sprinklers and fire alarm separate permit.
Details
Permit
201711093681
Permit issued
Apr 12, 2018
Final sign-off
Jun 26, 2019

amep. level 3, office - kitchen dishroom & servery, seating areas. grease trap on level 2 & shafts that run from level 3 to roof. mep included. (n) 2 hrs shaft, fire assembly area- two way communication, ul 300, sprinklers and fire alarm separate permit.

Open the permit page

$6,000,000
Jul 26, 2017Completed
final sign-off Jun 2019
345 Spear StBcci Construction Company6th floor remodel, (e) tech talk room, conference rooms 9 fire doors
Details
Permit
201707263017
Permit issued
Aug 22, 2017
Final sign-off
Jun 27, 2019

6th floor remodel, (e) tech talk room, conference rooms 9 fire doors

Open the permit page

$1,215,000
Jul 24, 2017Completed
final sign-off Jun 2019
121 Spear StBcci Construction Companydemolition of floors 2,3,4,5 & 6 interior only selective areas on each floor to be demolished. n/a maher
Details
Permit
201707242790
Permit issued
Aug 1, 2017
Final sign-off
Jun 21, 2019

demolition of floors 2,3,4,5 & 6 interior only selective areas on each floor to be demolished. n/a maher

Open the permit page

$100,000
Jun 26, 2017Never finaled
issued Jun 2017, no final
2 Harrison StBcci Construction Company2nd floor - new partitions, ceilings and finishes. n/a for maher.
Details
Permit
201706260334
Permit issued
Jun 27, 2017

2nd floor - new partitions, ceilings and finishes. n/a for maher.

Open the permit page

$300,000
Feb 7, 2017Never finaled
issued Feb 2017, no final
1 Embarcadero CenterPrincipal Builders Inc.30th floor - revision to pa #201607132253 to show guardrail at 30th floor.
Details
Permit
201702078847
Permit issued
Feb 9, 2017

30th floor - revision to pa #201607132253 to show guardrail at 30th floor.

Open the permit page

Jan 18, 2017Completed
final sign-off Feb 2017
188 The EmbarcaderoDpr Constructionrevision to 201606291145 ti permit to update da checklist. no new construction, administrative only
Details
Permit
201701187352
Permit issued
Jan 18, 2017
Final sign-off
Feb 14, 2017

revision to 201606291145 ti permit to update da checklist. no new construction, administrative only

Open the permit page

Sep 12, 2016Completed
final sign-off Feb 2017
188 The EmbarcaderoDpr Construction1st floor - administrative purposes to document a-3 assembly space 114 and 118 in office bldg. t.i. portion is under a separate permit #201606291145.
Details
Permit
201609127369
Permit issued
Sep 12, 2016
Final sign-off
Feb 15, 2017

1st floor - administrative purposes to document a-3 assembly space 114 and 118 in office bldg. t.i. portion is under a separate permit #201606291145.

Open the permit page

Jun 29, 2016Completed
final sign-off Feb 2017
188 The EmbarcaderoDpr Constructioninterior alterations including walls, ceilings, flooring and casework. mech, elec, plumbing to support new interior space. demo under 201602119345 maher not req
Details
Permit
201606291145
Permit issued
Jul 12, 2016
Final sign-off
Feb 14, 2017

interior alterations including walls, ceilings, flooring and casework. mech, elec, plumbing to support new interior space. demo under 201602119345 maher not req

Open the permit page

$2,400,000
Apr 22, 2016Completed
final sign-off Jun 2017
345 Spear StBcci Construction Company4th floor -demolition of (17) existing offices to create open office space & a single occupancy unisex ada restroom to be built to provide full accessibility and associated mep; n/a maher ord. # 155-13
Details
Permit
201604225525
Permit issued
Apr 25, 2016
Final sign-off
Jun 2, 2017

4th floor -demolition of (17) existing offices to create open office space & a single occupancy unisex ada restroom to be built to provide full accessibility and associated mep; n/a maher ord. # 155-13

Open the permit page

$494,160
Mar 24, 2016Completed
final sign-off Oct 2016
188 The EmbarcaderoDpr Constructionrevision to pa #201509116686 - revisions include additoinal t. i. by means of new conference rooms, open office & re-routing of mechanical duct work, to supply new open office area. n/a maher ordinance
Details
Permit
201603242951
Permit issued
Apr 15, 2016
Final sign-off
Oct 12, 2016

revision to pa #201509116686 - revisions include additoinal t. i. by means of new conference rooms, open office & re-routing of mechanical duct work, to supply new open office area. n/a maher ordinance

Open the permit page

$500,000
Dec 28, 2015Completed
final sign-off Oct 2017
345 Spear StBcci Construction Company5th flr: partial floor t.i. including minor demolition,new partitions,finishes & associated mep, fire ls under separate permit; maher n/a
Details
Permit
201512285994
Permit issued
Jan 7, 2016
Final sign-off
Oct 4, 2017

5th flr: partial floor t.i. including minor demolition,new partitions,finishes & associated mep, fire ls under separate permit; maher n/a

Open the permit page

$795,000
Nov 12, 2015Completed
final sign-off Jan 2016
22 04th StSc Builders, Inc12th flr: revision to 201509177337; added two new room, changed some lighting fixtures etc. meps under separate permit; maher n/a
Details
Permit
201511122448
Permit issued
Dec 3, 2015
Final sign-off
Jan 26, 2016

12th flr: revision to 201509177337; added two new room, changed some lighting fixtures etc. meps under separate permit; maher n/a

Open the permit page

$25,000
Nov 5, 2015Completed
final sign-off Jul 2016
345 Spear StSkyline Constructiondemolition of existing concrete fountain related fountain equipment on level b1 to be removed. $20,000 to be deferred to construction permit application. compliance with maher ordinance no 155-13 not required.
Details
Permit
201511051782
Permit issued
Nov 5, 2015
Final sign-off
Jul 18, 2016

demolition of existing concrete fountain related fountain equipment on level b1 to be removed. $20,000 to be deferred to construction permit application. compliance with maher ordinance no 155-13 not required.

Open the permit page

$20,000
Nov 3, 2015Completed
final sign-off Aug 2016
188 The EmbarcaderoDpr Construction Incinterior alterations to floor 6. renovations include dining, food prep and meeting areas that are an accessory use. maher not req. life safety/type 1 hood deferred submittals.
Details
Permit
201511031646
Permit issued
Dec 8, 2015
Final sign-off
Aug 8, 2016

interior alterations to floor 6. renovations include dining, food prep and meeting areas that are an accessory use. maher not req. life safety/type 1 hood deferred submittals.

Open the permit page

$2,000,000
Oct 21, 2015Completed
final sign-off Oct 2016
188 The EmbarcaderoDpr Constructionmodification of (e) cellular phone equipment and platform. raising of equipment on roof. compliance with maher ordinance not required.
Details
Permit
201510210369
Permit issued
Oct 27, 2015
Final sign-off
Oct 13, 2016

modification of (e) cellular phone equipment and platform. raising of equipment on roof. compliance with maher ordinance not required.

Open the permit page

$24,000
Sep 22, 2015Expired or cancelled
cancelled Jan 2026
22 04th Stfloor 3, 6, 10 tenant improvement - upgrade lobbies access control door devices only, and toilet patition door at womens ada restroom door n/a maher ordinance
Details
Permit
201509227687

floor 3, 6, 10 tenant improvement - upgrade lobbies access control door devices only, and toilet patition door at womens ada restroom door n/a maher ordinance

Open the permit page

$10,000
Sep 17, 2015Completed
final sign-off Jan 2016
22 04th StSc Builders, Incupgrade elevator lobby area, reception area, conference rooms & upgrade existing door access control, scope of work to include demolition of partitions at open office area, elevator lobby. n/a ordinance #155-13
Details
Permit
201509177337
Permit issued
Sep 30, 2015
Final sign-off
Jan 26, 2016

upgrade elevator lobby area, reception area, conference rooms & upgrade existing door access control, scope of work to include demolition of partitions at open office area, elevator lobby. n/a ordinance #155-13

Open the permit page

$200,000
Jul 30, 2015Never finaled
filed Jul 2015, never issued
188 The EmbarcaderoDpr Construction8th flr: deferred submittal to permit 201506048095; for decorative ceiling trellis on 8th flr; maher n/a
Details
Permit
201507302907

8th flr: deferred submittal to permit 201506048095; for decorative ceiling trellis on 8th flr; maher n/a

Open the permit page

Jul 10, 2015Completed
final sign-off May 2016
2 Harrison StBcci Construction Company2nd floor suite #200: interior t.i. including new partitions, ceiling, finishes and associated mechanical and electrical. fire life safety under separate permit. maher n/a.
Details
Permit
201507101229
Permit issued
Jul 20, 2015
Final sign-off
May 27, 2016

2nd floor suite #200: interior t.i. including new partitions, ceiling, finishes and associated mechanical and electrical. fire life safety under separate permit. maher n/a.

Open the permit page

$1,416,000
Jul 2, 2015Completed
final sign-off Jan 2016
22 04th StMetropolitan Electrical Construction6th floor: tenant improvement for lighting upgrade. n/a for maher ordinance. ref #201504224272
Details
Permit
201507020521
Permit issued
Jul 2, 2015
Final sign-off
Jan 22, 2016

6th floor: tenant improvement for lighting upgrade. n/a for maher ordinance. ref #201504224272

Open the permit page

$30,000
May 18, 2015Completed
final sign-off Jun 2016
345 Spear StBcci Construction Company2nd flr: interior non-structural pre construction demo. work done under sfab-017. floor to remain unoccupied
Details
Permit
201505186555
Permit issued
May 18, 2015
Final sign-off
Jun 6, 2016

2nd flr: interior non-structural pre construction demo. work done under sfab-017. floor to remain unoccupied

Open the permit page

$248,000
Jan 27, 2015Completed
final sign-off May 2016
2 Harrison StBcci Construction Company3rd floor suite 350 tenant improvement including minor demolition, new partitions, finishes & associated mechanical & electrical. n/a maher ordinance. life safety deferred. structural for tube steel support under separate permit
Details
Permit
201501276745
Permit issued
Feb 3, 2015
Final sign-off
May 27, 2016

3rd floor suite 350 tenant improvement including minor demolition, new partitions, finishes & associated mechanical & electrical. n/a maher ordinance. life safety deferred. structural for tube steel support under separate permit

Open the permit page

$678,000
Jan 23, 2015Completed
final sign-off Nov 2016
345 Spear StBcci Construction Company7th floor: ti. include demo, refurbishing of (e) restrooms, new partitions & new ceilings. mep, fire alarm and sprinklers under separate permit. new occupant loads and pavers on roof. sffd assembly permit required.** maher: compliance with ordinance no# 155-13 not required **
Details
Permit
201501236545
Permit issued
Mar 16, 2015
Final sign-off
Nov 29, 2016

7th floor: ti. include demo, refurbishing of (e) restrooms, new partitions & new ceilings. mep, fire alarm and sprinklers under separate permit. new occupant loads and pavers on roof. sffd assembly permit required.** maher: compliance with ordinance no# 155-13 not required **

Open the permit page

$3,100,000
Nov 19, 2014Completed
final sign-off Jun 2016
345 Spear StBcci Construction Company3rd floor - revision to appl #2014.0818.4059 to reconfigure work spaces & to eliminate the demolitoin of the interconnecting staircase. mechanical & electrical work under separate permit.
Details
Permit
201411191892
Permit issued
Nov 19, 2014
Final sign-off
Jun 6, 2016

3rd floor - revision to appl #2014.0818.4059 to reconfigure work spaces & to eliminate the demolitoin of the interconnecting staircase. mechanical & electrical work under separate permit.

Open the permit page

Aug 18, 2014Expired or cancelled
cancelled Jul 2016
345 Spear StBcci Construction Companyinterior demolition of convenient stair connecting levels 2 to 3 floor & 3 to 4 floor. demolition of associated partitions. structural infill of openings on levels 3 to 4 floor. n/a ordinance #155-13
Details
Permit
201408184050
Permit issued
Aug 28, 2014

interior demolition of convenient stair connecting levels 2 to 3 floor & 3 to 4 floor. demolition of associated partitions. structural infill of openings on levels 3 to 4 floor. n/a ordinance #155-13

Open the permit page

$250,000
Aug 18, 2014Completed
final sign-off Jan 2015
345 Spear StBcci Construction Companycafe 3rd floor - revision to appl #2014.0611.8144 establish occupancy load. sffd assembly permit required. to reflect changes in food service plan. n/a maher ordinance
Details
Permit
201408184058
Permit issued
Sep 17, 2014
Final sign-off
Jan 6, 2015

cafe 3rd floor - revision to appl #2014.0611.8144 establish occupancy load. sffd assembly permit required. to reflect changes in food service plan. n/a maher ordinance

Open the permit page

Jul 16, 2014Expired or cancelled
cancelled Sep 2015
345 Spear StBcci Construction Company7th floor: phase 1 of 2 interior t.i. including new partitions and finishes, mechanical and electrical and fire alarm and sprinkler under seperate permit. work includes new horizontal exit & reviseing smoke control report. ** maher: compliance with ordinance no# 155-13 not required **
Details
Permit
201407161418
Permit issued
Jul 31, 2014

7th floor: phase 1 of 2 interior t.i. including new partitions and finishes, mechanical and electrical and fire alarm and sprinkler under seperate permit. work includes new horizontal exit & reviseing smoke control report. ** maher: compliance with ordinance no# 155-13 not required **

Open the permit page

$1,900,000
Jun 11, 2014Completed
final sign-off Dec 2014
345 Spear StBcci Construction Companycafe 3rd floor: minor demolition, new wall, kitchen equipment and mechanical & electrical. installing new hortzontial exit. ls & sprinklers under seperate permit. n/a ordinance #155-13-per pre-application mtg 7-3-14- phase i- temp exiting corridor- sealing convience stair. occupant load.
Details
Permit
201406118144
Permit issued
Jul 31, 2014
Final sign-off
Dec 22, 2014

cafe 3rd floor: minor demolition, new wall, kitchen equipment and mechanical & electrical. installing new hortzontial exit. ls & sprinklers under seperate permit. n/a ordinance #155-13-per pre-application mtg 7-3-14- phase i- temp exiting corridor- sealing convience stair. occupant load.

Open the permit page

$1,400,000
May 13, 2014Never finaled
issued May 2014, no final
345 Spear StBcci Construction Companytenant improvement on the 5th fl. new partitions, willwork, finishes. associated mep and sprinklers and life safety under separate permit.
Details
Permit
201405135585
Permit issued
May 13, 2014

tenant improvement on the 5th fl. new partitions, willwork, finishes. associated mep and sprinklers and life safety under separate permit.

Open the permit page

$3,000,000
Apr 1, 2014Completed
final sign-off Sep 2014
345 Spear StBcci Construction Companyinterior, non-structural pre construction demo under sfab 017 area to remain unoccupied. n/a to ordinance#155-13.
Details
Permit
201404012199
Permit issued
Apr 2, 2014
Final sign-off
Sep 30, 2014

interior, non-structural pre construction demo under sfab 017 area to remain unoccupied. n/a to ordinance#155-13.

Open the permit page

$215,460
Oct 5, 2011Completed
final sign-off Mar 2012
4 Embarcadero CenterField Construction Inc.25th floor tenant improvement of existing space, consisting primarily of the installation of new gypsum board walls, floor covering, wall & ceiling finishes, suspended act & lighting. also misc work in bathrooms. mep, sprinkler and fire alarm under separate applications
Details
Permit
201110056130
Permit issued
Oct 28, 2011
Final sign-off
Mar 7, 2012

25th floor tenant improvement of existing space, consisting primarily of the installation of new gypsum board walls, floor covering, wall & ceiling finishes, suspended act & lighting. also misc work in bathrooms. mep, sprinkler and fire alarm under separate applications

Open the permit page

$155,474
Oct 5, 2011Expired or cancelled
cancelled Jan 2026
4 Embarcadero CenterField Construction Inc.24th floor tenant improvement of existing space, consisting primarily of the installation of new gypsum board walls, floor covering, wall & ceiling finishes, suspended act & lighting. misc. restroom upgrades. mep, life safety separate.
Details
Permit
201110056128

24th floor tenant improvement of existing space, consisting primarily of the installation of new gypsum board walls, floor covering, wall & ceiling finishes, suspended act & lighting. misc. restroom upgrades. mep, life safety separate.

Open the permit page

$129,685
Jul 21, 2011Completed
final sign-off Sep 2011
333 Bush StPrincipal Builders Inc.30th floor - new partitions, new millwork, new doors, frames & hardward, new sink @ break room, re-wrap fabric panels, new electrical floor boxes, new lighting, rework mechanical zones, repaint all walls. life safety & sprinkler under separate permit.
Details
Permit
201107210690
Permit issued
Jul 25, 2011
Final sign-off
Sep 20, 2011

30th floor - new partitions, new millwork, new doors, frames & hardward, new sink @ break room, re-wrap fabric panels, new electrical floor boxes, new lighting, rework mechanical zones, repaint all walls. life safety & sprinkler under separate permit.

Open the permit page

$115,001
Jun 27, 2011Completed
final sign-off Sep 2011
333 Bush StPrincipal Builders Inc.27th & 28th floor mechanical, electrical & plumbing modifications, arch pa #201106027295. life safety & sprinklers to be under separate permit.
Details
Permit
201106278958
Permit issued
Jun 27, 2011
Final sign-off
Sep 20, 2011

27th & 28th floor mechanical, electrical & plumbing modifications, arch pa #201106027295. life safety & sprinklers to be under separate permit.

Open the permit page

$230,000
Jun 2, 2011Completed
final sign-off Sep 2011
333 Bush StPrincipal Builders Inc.new ceiling and walls for 27th nad 28th floors. demo under 201105176217- mep, sp & ls separate permits-
Details
Permit
201106027295
Permit issued
Jun 13, 2011
Final sign-off
Sep 20, 2011

new ceiling and walls for 27th nad 28th floors. demo under 201105176217- mep, sp & ls separate permits-

Open the permit page

$534,066
Mar 10, 2010Completed
final sign-off May 2010
1 Market StHathaway Dinwiddie Co.5th floor tenant improvement involving removal of an existing glass partition & addition of (2) new partitions dividing existing conf. room into (2) new offices. fire sprinklers & life safety & mep under separate permit.
Details
Permit
201003107933
Permit issued
Mar 10, 2010
Final sign-off
May 17, 2010

5th floor tenant improvement involving removal of an existing glass partition & addition of (2) new partitions dividing existing conf. room into (2) new offices. fire sprinklers & life safety & mep under separate permit.

Open the permit page

$28,000
Mar 1, 2007Completed
final sign-off Jul 2007
1 Market StHathaway Dinwiddie Co.sedgwick, deiert moran arnold- oti-2, 11th floor, el, me.
Details
Permit
200703015206
Permit issued
Apr 4, 2007
Final sign-off
Jul 30, 2007

sedgwick, deiert moran arnold- oti-2, 11th floor, el, me.

Open the permit page

$112,000
Jul 22, 2003Completed
final sign-off Nov 2003
219 King St1st time t.i. for ice cream store, work includes (n)partitions (n)casework (n)finishes (n)ducts
Details
Permit
200307220112
Permit issued
Jul 22, 2003
Final sign-off
Nov 13, 2003

1st time t.i. for ice cream store, work includes (n)partitions (n)casework (n)finishes (n)ducts

Open the permit page

$90,000