Block 3721, lot 119
500 Howard St
- City’s use
- Commercial Office
- Built
- 2003
- Stories
- 10
- Building
- 232,801 sq ft
- Lot
- 32,189 sq ft
- Zoning
- C3O
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
120 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 20, 2026 | In progress issued Jul 2026 | 500 Howard St | floors: 2, 4, 6, 7: anchoring of (e) modules phone booths in (e) office.Details
floors: 2, 4, 6, 7: anchoring of (e) modules phone booths in (e) office. | $135,000 | |
| Oct 24, 2025 | In progress issued Oct 2025 | 500 Howard St | Novo Construction Inc | 1/f: change of occupancy from retail to office.Details
1/f: change of occupancy from retail to office. | |
| Sep 9, 2025 | Completed final sign-off Oct 2025 | 500 Howard St | Edison Fire Extinguisher Company Inc | ul 300 fire system installation.Details
ul 300 fire system installation. | $19,500 |
| Aug 27, 2025 | Completed final sign-off Oct 2025 | 500 Howard St | Everon Llc | fire alarm t.i. on 5th floor. add 5 speaker, 51 speaker strobes, 1 smoke detector, 4 duct detectors for fcu and 5 control relay for fcu. ref#: 202503313350Details
fire alarm t.i. on 5th floor. add 5 speaker, 51 speaker strobes, 1 smoke detector, 4 duct detectors for fcu and 5 control relay for fcu. ref#: 202503313350 | $45,000 |
| Aug 27, 2025 | Completed final sign-off Sep 2025 | 500 Howard St | Everon Llc | 3/fl- ti 202502210777 for kitchen area to add (5) control relays for kitchen fans (mva,tf,khe,gef) shutdown, add (1) input module for kitchen suppression system and (3) duct for fansDetails
3/fl- ti 202502210777 for kitchen area to add (5) control relays for kitchen fans (mva,tf,khe,gef) shutdown, add (1) input module for kitchen suppression system and (3) duct for fans | $10,000 |
| Aug 27, 2025 | Completed final sign-off Sep 2025 | 500 Howard St | Everon Llc | fire alarm t.i. on 3rd flr - office space. add 1 control relay for uft. 1 dual module for fsd monitoring 1 duct detector for fsd, 19 speaker and 57 speaker strobes. ref: 202502261131Details
fire alarm t.i. on 3rd flr - office space. add 1 control relay for uft. 1 dual module for fsd monitoring 1 duct detector for fsd, 19 speaker and 57 speaker strobes. ref: 202502261131 | $38,000 |
| Aug 21, 2025 | In progress issued Aug 2025 | 500 Howard St | Pioneer Fire Inc. | 5th floor. relocate (123) pendents, (25) uprights relocate (e) hose valve cabinet, install new hose valve cabinetDetails
5th floor. relocate (123) pendents, (25) uprights relocate (e) hose valve cabinet, install new hose valve cabinet | $37,000 |
| Jun 11, 2025 | Completed final sign-off Sep 2025 | 500 Howard St | Pioneer Fire Inc. | 3rd floor: relocate 119 pendents, 41 uprights, add 2 pendents. gcti#202502210777 and 202502261131Details
3rd floor: relocate 119 pendents, 41 uprights, add 2 pendents. gcti#202502210777 and 202502261131 | $30,000 |
| May 28, 2025 | In progress issued Sep 2025 | 500 Howard St | Novo Construction Inc | ground floor:t.i. to existing retail space consisting of 2 new interior doors, curtains, privacy film and applied finish treatments, repairs to existing conditions. signage replacements where room names changed mech/electrical included.Details
ground floor:t.i. to existing retail space consisting of 2 new interior doors, curtains, privacy film and applied finish treatments, repairs to existing conditions. signage replacements where room names changed mech/electrical included. | $75,000 |
| Mar 31, 2025 | Completed final sign-off Jan 2026 | 500 Howard St | Novo Construction Inc | 5th fl: interior ti. include paint throughout. removal of existing walls, ceilings and finishes. new interior construction of walls, new wall & floor finishes. mechanical, electrical ,plumbing & structural includedDetails
5th fl: interior ti. include paint throughout. removal of existing walls, ceilings and finishes. new interior construction of walls, new wall & floor finishes. mechanical, electrical ,plumbing & structural included | $5,416,864 |
| Mar 14, 2025 | Completed final sign-off Mar 2025 | 500 Howard St | Pioneer Fire Inc. | 8th fl ref pa 2024-1223-7306 add 6 pendentsDetails
8th fl ref pa 2024-1223-7306 add 6 pendents | $1,500 |
| Feb 26, 2025 | Completed final sign-off Feb 2026 | 500 Howard St | Novo Construction Inc | 3rd fl -ti to include new nonstructural partitions, paint, wall covering on, privacy glass film; repairs to existing conditions. mep includedDetails
3rd fl -ti to include new nonstructural partitions, paint, wall covering on, privacy glass film; repairs to existing conditions. mep included | $4,721,444 |
| Feb 24, 2025 | Completed final sign-off Dec 2025 | 500 Howard St | Novo Construction Inc | 5th fl- removal of (e) walls, ceilings, millwork and finishes ab017Details
5th fl- removal of (e) walls, ceilings, millwork and finishes ab017 | $175,000 |
| Feb 21, 2025 | Completed final sign-off Feb 2026 | 500 Howard St | Novo Construction Inc | 3rd floor: non-structural demolition of office space. addition of prep kitchen to include walk -in cooler, cooking hood, dish clean, & misc. equipment. ancillary storage for mechanical equipment, grease interceptor & water heaters.Details
3rd floor: non-structural demolition of office space. addition of prep kitchen to include walk -in cooler, cooking hood, dish clean, & misc. equipment. ancillary storage for mechanical equipment, grease interceptor & water heaters. | $986,000 |
| Feb 21, 2025 | Completed final sign-off May 2025 | 500 Howard St | Novo Construction Inc | 8th fl- revision to pa #202412237306 to add selective new demo for new exhaust duct, new environmental exhuast louver added hand and prep sink, added power, new hot water pump. new exhaust fan, under floor terminal unit and equipment anchorageDetails
8th fl- revision to pa #202412237306 to add selective new demo for new exhaust duct, new environmental exhuast louver added hand and prep sink, added power, new hot water pump. new exhaust fan, under floor terminal unit and equipment anchorage | $75,000 |
| Jan 31, 2025 | Completed final sign-off Dec 2025 | 500 Howard St | Novo Construction Inc | non structural demo of interior office space with exception of mother's room and all gender restrooms. ab 017.Details
non structural demo of interior office space with exception of mother's room and all gender restrooms. ab 017. | $125,000 |
| Jan 10, 2025 | Completed final sign-off Aug 2025 | 500 Howard St | Novo Construction Inc | 4th floor: selective demo of millwork, finshes and wall penetrations, mew carpet, paint and acoustic panels, new exterior window louver alteration of drinking fountain niche, mep includedDetails
4th floor: selective demo of millwork, finshes and wall penetrations, mew carpet, paint and acoustic panels, new exterior window louver alteration of drinking fountain niche, mep included | $325,000 |
| Dec 23, 2024 | Completed final sign-off May 2025 | 500 Howard St | Novo Construction Inc | 8/fl- ti to convert storage to pantry to include (n) refrigator, freezer, food storage and sinks. mep included.Details
8/fl- ti to convert storage to pantry to include (n) refrigator, freezer, food storage and sinks. mep included. | $250,000 |
| Oct 28, 2024 | Completed final sign-off May 2025 | 500 Howard St | Novo Construction Inc | select demo of built in seating and tables, addition of new mobile food service severy carts new shelving and wall mounted dish drying rack new stainless steel finishes around t/r/ dish drop are enlarge waste opening paint one wall in barista areaDetails
select demo of built in seating and tables, addition of new mobile food service severy carts new shelving and wall mounted dish drying rack new stainless steel finishes around t/r/ dish drop are enlarge waste opening paint one wall in barista area | $195,000 |
| Oct 4, 2024 | Completed final sign-off May 2025 | 500 Howard St | Novo Construction Inc | barrier removal path of travel compliance for parking level floors 1,2,3,5, and 8Details
barrier removal path of travel compliance for parking level floors 1,2,3,5, and 8 | $288,991 |
| Aug 2, 2024 | Expired or cancelled cancelled Aug 2024 | 500 Howard St | Novo Construction Inc | 5th floor: demolition of interior non structural partitions ceilings and existing finishes. ab-017.Details
5th floor: demolition of interior non structural partitions ceilings and existing finishes. ab-017. | $45,000 |
| May 14, 2024 | Completed final sign-off May 2024 | 500 Howard St | Edison Fire Extinguisher Company Inc | hood and duct system installationDetails
hood and duct system installation | $5,000 |
| Feb 12, 2024 | In progress filed Feb 2024, not yet issued | 500 Howard St | Acco Engineered Systems Inc. Dba Acco En | replace (e) underlfloor fan powered booster units. disconnect & reconnect (e) power & controls. new duct transitions from booter units to (e) linked plenums. air balance new booster units to (e) cfm's.Details
replace (e) underlfloor fan powered booster units. disconnect & reconnect (e) power & controls. new duct transitions from booter units to (e) linked plenums. air balance new booster units to (e) cfm's. | $150,000 |
| Mar 28, 2023 | Never finaled issued Mar 2023, no final | 500 Howard St | Gci, Inc | administrative permit to pa# 2018-1016-3273, 3/f, to document work under this permit, supersededs work performed under pa# 2015-0828-5499. ok to cancel p.a. 201508285499Details
administrative permit to pa# 2018-1016-3273, 3/f, to document work under this permit, supersededs work performed under pa# 2015-0828-5499. ok to cancel p.a. 201508285499 | |
| Oct 13, 2022 | Completed final sign-off Nov 2022 | 500 Howard St | R L H Fire Protection Inc | voluntary modernization to sprinkler system remove eight sprinklers from machine room. no other work.Details
voluntary modernization to sprinkler system remove eight sprinklers from machine room. no other work. | $1,000 |
| Jul 22, 2022 | Completed final sign-off Jul 2023 | 500 Howard St | Everon Llc | fa ti for elevator modernization. add (2) control relays for service and passenger elevators fire fighter flashing helmet light function. remove (1) control relay and (1) monitoring module for shout trip. remove (8) heat detectors in associated machine room due to removal of sprinkler heads.Details
fa ti for elevator modernization. add (2) control relays for service and passenger elevators fire fighter flashing helmet light function. remove (1) control relay and (1) monitoring module for shout trip. remove (8) heat detectors in associated machine room due to removal of sprinkler heads. | $5,000 |
| Sep 24, 2021 | Never finaled filed Sep 2021, never issued | 500 Howard St | maximum occupancy signage to be posted.requested by fire for operational permit.Details
maximum occupancy signage to be posted.requested by fire for operational permit. | ||
| Jul 23, 2021 | Completed final sign-off Dec 2024 | 500 Howard St | Sc Builders, Inc | revision to 201810163273 reduced area of work from original permit only. additional gender neutral restrooms, new training room, new mother room, storage, upgrade core restrooms, new finishes lightingDetails
revision to 201810163273 reduced area of work from original permit only. additional gender neutral restrooms, new training room, new mother room, storage, upgrade core restrooms, new finishes lighting | |
| Aug 7, 2020 | Completed final sign-off Oct 2020 | 500 Howard St | Sc Builders, Inc | rev to pa 201907226543, suite 100 & 101: revise language to include door exiting requirements per 1010.1.9.0 for inspector request.Details
rev to pa 201907226543, suite 100 & 101: revise language to include door exiting requirements per 1010.1.9.0 for inspector request. | |
| Jun 1, 2020 | Completed final sign-off Sep 2020 | 500 Howard St | Martin Sign Co Inc. | erect single faced non-electric signDetails
erect single faced non-electric sign | $3,280 |
| Jan 6, 2020 | Never finaled issued Jan 2020, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | 1 floor: fire alarm as built drawing for pa# 2019-1224-0469: to reflect control relay for securty interfaceDetails
1 floor: fire alarm as built drawing for pa# 2019-1224-0469: to reflect control relay for securty interface | |
| Dec 24, 2019 | Completed final sign-off Dec 2020 | 500 Howard St | Red Hawk Fire & Security Ca Llc | ref# 2019-0722-6543: fire alarm t.i. on 1st floor. add 1 speaker strobs and 1 speaker.Details
ref# 2019-0722-6543: fire alarm t.i. on 1st floor. add 1 speaker strobs and 1 speaker. | $1,200 |
| Oct 23, 2019 | Never finaled issued Oct 2019, no final | 500 Howard St | Custom Contracting Services | install non-electric wall double faced signDetails
install non-electric wall double faced sign | $4,000 |
| Oct 23, 2019 | Never finaled issued Oct 2019, no final | 500 Howard St | Custom Contracting Services | install non-electric single faced door window "workspace"Details
install non-electric single faced door window "workspace" | $1,000 |
| Sep 18, 2019 | Completed final sign-off Mar 2020 | 500 Howard St | Pribuss Engineering Inc | ref pa# 201907226543; fire sprinkler t.i. on the 1st fl. 23 total sprinklers this projectDetails
ref pa# 201907226543; fire sprinkler t.i. on the 1st fl. 23 total sprinklers this project | $11,822 |
| Aug 9, 2019 | Never finaled issued Aug 2019, no final | 500 Howard St | street space w/mtaDetails
street space w/mta | ||
| Aug 2, 2019 | Never finaled issued Aug 2019, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm ti on 3rd flr - add 4 speaker strobes & relocate (e) smk det as shown ref 201810163273Details
fire alarm ti on 3rd flr - add 4 speaker strobes & relocate (e) smk det as shown ref 201810163273 | $2,000 |
| Jul 22, 2019 | Completed final sign-off Oct 2020 | 500 Howard St | Sc Builders, Inc | 1st fl suite 100 & 101 - demo of non-structural partition lighting finishes doors/frames, construction of non-structural partitions finishes lighting ceiling, mep (struct/fire/life safety & exterior signs under sep permit). replace front door with double door & removing window film from storefronts.Details
1st fl suite 100 & 101 - demo of non-structural partition lighting finishes doors/frames, construction of non-structural partitions finishes lighting ceiling, mep (struct/fire/life safety & exterior signs under sep permit). replace front door with double door & removing window film from storefronts. | $500,000 |
| Jun 5, 2019 | Completed final sign-off Aug 2019 | 500 Howard St | Anderson, Rowe & Buckley, Inc. | 3rd fl: existing fire sprinkler system - t.i. 20 aded sprinklers. ach #201810163273.Details
3rd fl: existing fire sprinkler system - t.i. 20 aded sprinklers. ach #201810163273. | $10,000 |
| Apr 19, 2019 | Never finaled issued May 2019, no final | 500 Howard St | Sc Builders, Inc | addition of non structural fence partitions and electrified security hardware in stairwellDetails
addition of non structural fence partitions and electrified security hardware in stairwell | $18,285 |
| Feb 26, 2019 | Completed final sign-off Apr 2019 | 500 Howard St | Sc Builders, Inc | rev to pa# 201805078381; to remove coffee bar, millwork & associated plumbingDetails
rev to pa# 201805078381; to remove coffee bar, millwork & associated plumbing | |
| Jan 31, 2019 | Completed final sign-off Feb 2019 | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm t.i. on 3rd fl. remove (2) ceiling speakers, (2) wall mount strobes, (2) wall mount speaker strobes, add (5) speaker strobes & (2) speakers only, replace (e) power supplyDetails
fire alarm t.i. on 3rd fl. remove (2) ceiling speakers, (2) wall mount strobes, (2) wall mount speaker strobes, add (5) speaker strobes & (2) speakers only, replace (e) power supply | $6,000 |
| Jan 18, 2019 | Never finaled issued Jan 2019, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm as built for 201812077754Details
fire alarm as built for 201812077754 | |
| Jan 18, 2019 | Completed final sign-off Apr 2019 | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm as built drawing for 201807104148Details
fire alarm as built drawing for 201807104148 | |
| Jan 11, 2019 | Never finaled issued Jan 2019, no final | 500 Howard St | Anderson, Rowe & Buckley, Inc. | existing fire sprinkler system-t.i. 6 relocated sprinkler- pendent. 4 relocated sprinkler upright. ref# 2018-1016-3273Details
existing fire sprinkler system-t.i. 6 relocated sprinkler- pendent. 4 relocated sprinkler upright. ref# 2018-1016-3273 | $5,000 |
| Dec 27, 2018 | Expired or cancelled cancelled Jan 2026 | 500 Howard St | Sc Builders, Inc | demo of bike parking fence. construction of new dtorage space with non structural partitions/doors/frame/hardware/lights/drywall/finishes. ele, fire sprinkler and life safety under sep permit. maher naDetails
demo of bike parking fence. construction of new dtorage space with non structural partitions/doors/frame/hardware/lights/drywall/finishes. ele, fire sprinkler and life safety under sep permit. maher na | $43,820 |
| Dec 18, 2018 | Completed final sign-off Apr 2019 | 500 Howard St | Sc Builders, Inc | on 8th floor - revision to 201805078386 egress and occupant load only. fire onlyDetails
on 8th floor - revision to 201805078386 egress and occupant load only. fire only | |
| Dec 14, 2018 | Completed final sign-off Jul 2019 | 500 Howard St | Yesco Signs Llc | revision to existing sign permits to reflect new logo and sign sizes, letters weights and areas unchanged, attachment and engineering are unchanged: 201801118361, 201801118362, 201801118363.Details
revision to existing sign permits to reflect new logo and sign sizes, letters weights and areas unchanged, attachment and engineering are unchanged: 201801118361, 201801118362, 201801118363. | |
| Dec 7, 2018 | Completed final sign-off Feb 2019 | 500 Howard St | Red Hawk Fire & Security Ca Llc | 8th fl - fire alarm ti add dual monitoring modules for fsd; 20 smoke detecors 3 duct detectors for fsds, 7 control relays for fsd, fans & kitchen suppression system. 3 ceiling speakers; 23 speaker strobes, 5 strobes & 1 monitoring module for ansul system. ref pa 2018-0808-6775 and 2018-0507-8386Details
8th fl - fire alarm ti add dual monitoring modules for fsd; 20 smoke detecors 3 duct detectors for fsds, 7 control relays for fsd, fans & kitchen suppression system. 3 ceiling speakers; 23 speaker strobes, 5 strobes & 1 monitoring module for ansul system. ref pa 2018-0808-6775 and 2018-0507-8386 | $18,000 |
| Nov 29, 2018 | Never finaled issued Nov 2018, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | as built fa plans for pa 201811297067.Details
as built fa plans for pa 201811297067. | |
| Nov 19, 2018 | Never finaled issued Nov 2018, no final | 500 Howard St | Martin Sign Co Inc. | installation of evacuation maps for 1, 4, 8 and 9th floorsDetails
installation of evacuation maps for 1, 4, 8 and 9th floors | $1,649 |
| Nov 2, 2018 | Completed final sign-off Mar 2019 | 500 Howard St | Sc Builders, Inc | revision to 201808086775 and 201805078386 to include barista bar, trash, recycle, compost locations for dph review and grease trap locationsDetails
revision to 201808086775 and 201805078386 to include barista bar, trash, recycle, compost locations for dph review and grease trap locations | |
| Oct 16, 2018 | Completed final sign-off Dec 2024 | 500 Howard St | Sc Builders, Inc | 3rd fl: amep full floor ti -demo of non-structural partitions, ceilings, finishes. construction of non-structural partitions, ceilings, finishes, millwork, acoustic ceiling, mechanical, electrical & plumbing. two new assembly spaces- break/lounge area 50 occ, training room (74or99 occ). maher naDetails
3rd fl: amep full floor ti -demo of non-structural partitions, ceilings, finishes. construction of non-structural partitions, ceilings, finishes, millwork, acoustic ceiling, mechanical, electrical & plumbing. two new assembly spaces- break/lounge area 50 occ, training room (74or99 occ). maher na | $3,772,797 |
| Sep 27, 2018 | Never finaled issued Dec 2018, no final | 500 Howard St | Sc Builders, Inc | installation of type 1 hood for in office food service. reference bpa# 2018/10808/6775. building is fully sprinkled/alarmed**maher n/a**Details
installation of type 1 hood for in office food service. reference bpa# 2018/10808/6775. building is fully sprinkled/alarmed**maher n/a** | $5,000 |
| Sep 26, 2018 | Completed final sign-off Dec 2018 | 500 Howard St | Aaa Restaurant Fire Control/Dba Aaa Fire | ref pa# 201808086775; furnish & install (1) ansul r-102 fire system in the kitchen hood. n/a maherDetails
ref pa# 201808086775; furnish & install (1) ansul r-102 fire system in the kitchen hood. n/a maher | $4,000 |
| Aug 29, 2018 | Never finaled issued Sep 2018, no final | 500 Howard St | Ayoob & Peery Plumbing Co Inc | add 2 sprinklers in order to conform to the new wall/ceiling layout of the to ref 201711214532 maher naDetails
add 2 sprinklers in order to conform to the new wall/ceiling layout of the to ref 201711214532 maher na | $450 |
| Aug 29, 2018 | Never finaled issued Sep 2018, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm - 1st flr - suite 100 & 101 add 4 duct detectors w/control for heat pump, 1 control relay for fsd, 1 smk det, 5 speaker/strobes ref 201806151997 mah ernDetails
fire alarm - 1st flr - suite 100 & 101 add 4 duct detectors w/control for heat pump, 1 control relay for fsd, 1 smk det, 5 speaker/strobes ref 201806151997 mah ern | $8,000 |
| Aug 22, 2018 | Completed final sign-off Nov 2018 | 500 Howard St | Pribuss Engineering Inc | 9th fl. ref pa# 20180578390; fire sprinkler tenant improvent relocated sprinklers (54), added sprinklers (29), total (83)Details
9th fl. ref pa# 20180578390; fire sprinkler tenant improvent relocated sprinklers (54), added sprinklers (29), total (83) | $43,176 |
| Aug 22, 2018 | Completed final sign-off Dec 2018 | 500 Howard St | Pribuss Engineering Inc | 8th fl - fire sprinkler ti, 8th fl - relocate 86 sprinklers, add 20 sprinklers. ref pa 2018-0507-8386Details
8th fl - fire sprinkler ti, 8th fl - relocate 86 sprinklers, add 20 sprinklers. ref pa 2018-0507-8386 | $34,438 |
| Aug 8, 2018 | Completed final sign-off Aug 2018 | 500 Howard St | Pribuss Engineering Inc | 1st flr - fire sprinkler ti - relocated 15, add 2 total 17Details
1st flr - fire sprinkler ti - relocated 15, add 2 total 17 | $10,794 |
| Aug 8, 2018 | Completed final sign-off Mar 2019 | 500 Howard St | Sc Builders, Inc | 8th flr. interior improvements to include non-structural partitions, frames, finishes, mep, kitchen area. fire and life safety under separate permit. rooms 837, 838, & 839 only.Details
8th flr. interior improvements to include non-structural partitions, frames, finishes, mep, kitchen area. fire and life safety under separate permit. rooms 837, 838, & 839 only. | $228,000 |
| Jul 31, 2018 | Completed final sign-off Jan 2019 | 500 Howard St | Sc Builders, Inc | 1st flr - mep for ti. 2 new fire/smoke damper. ref 201806151997Details
1st flr - mep for ti. 2 new fire/smoke damper. ref 201806151997 | $40,000 |
| Jul 26, 2018 | Completed final sign-off Nov 2018 | 500 Howard St | Pribuss Engineering Inc | 4th flr fire sprinkler ti relocated 53, add 67; ref pa 201605078383Details
4th flr fire sprinkler ti relocated 53, add 67; ref pa 201605078383 | $61,166 |
| Jul 20, 2018 | Completed final sign-off Apr 2019 | 500 Howard St | Sc Builders, Inc | revision to 10th fl 2017-0320-4098 to revise smoke barrier around slab opening to include non structural partitions and relocation of exit signsDetails
revision to 10th fl 2017-0320-4098 to revise smoke barrier around slab opening to include non structural partitions and relocation of exit signs | |
| Jul 10, 2018 | Never finaled issued Jul 2018, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | 4th flr fa ti - add 49 speakers/strobes, relocate 2 (e) speakers. add 16 speakers only, add 6 smk det, 4 control relays ref 201805078383 maher naDetails
4th flr fa ti - add 49 speakers/strobes, relocate 2 (e) speakers. add 16 speakers only, add 6 smk det, 4 control relays ref 201805078383 maher na | $36,000 |
| Jul 10, 2018 | Never finaled issued Oct 2018, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | 9th flr fa ti - add 35 speaker storbes, add 8 speakers add 4 smk det and 2 control relays. ref 201805078390 maher naDetails
9th flr fa ti - add 35 speaker storbes, add 8 speakers add 4 smk det and 2 control relays. ref 201805078390 maher na | $25,000 |
| Jul 10, 2018 | Completed final sign-off Apr 2019 | 500 Howard St | Red Hawk Fire & Security Ca Llc | 1st flr fa ti - add 1 for security door release and 7 speakers/strobes ref 201805078381 maher naDetails
1st flr fa ti - add 1 for security door release and 7 speakers/strobes ref 201805078381 maher na | $4,100 |
| Jun 15, 2018 | Never finaled issued Jun 2018, no final | 500 Howard St | Sc Builders, Inc | 1st fl: demo of non-structural partitions ceiling fixtures & equipment full sprinklered building.maher n/a.Details
1st fl: demo of non-structural partitions ceiling fixtures & equipment full sprinklered building.maher n/a. | $30,000 |
| Jun 15, 2018 | Completed final sign-off Jan 2019 | 500 Howard St | Sc Builders, Inc | 1st fl: retail ti to include (n) non-structural partitions, doors, millwork. fully sprinklered. mep & fire under sep permit. maher naDetails
1st fl: retail ti to include (n) non-structural partitions, doors, millwork. fully sprinklered. mep & fire under sep permit. maher na | $400,950 |
| Jun 14, 2018 | Completed final sign-off Sep 2018 | 500 Howard St | Pribuss Engineering Inc | fire spprinkler ti on 1st fl, total 23 sprinklers ($514.00)Details
fire spprinkler ti on 1st fl, total 23 sprinklers ($514.00) | $11,822 |
| May 31, 2018 | Expired or cancelled cancelled Jan 2026 | 500 Howard St | administrative correction to 201711143931, 201804045458 to confirm review and approval of change of occupancy from extg b to b/a-2 occupancyDetails
administrative correction to 201711143931, 201804045458 to confirm review and approval of change of occupancy from extg b to b/a-2 occupancy | ||
| May 25, 2018 | Completed final sign-off Jun 2018 | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm t.i. suite 100a, add (6) speaker strobesDetails
fire alarm t.i. suite 100a, add (6) speaker strobes | $3,000 |
| May 25, 2018 | Never finaled issued May 2018, no final | 500 Howard St | Sc Builders, Inc | admin. correction to pa #201711143931 & 201804245458 to include - a-2 assembly occupancy listing on 5th floorDetails
admin. correction to pa #201711143931 & 201804245458 to include - a-2 assembly occupancy listing on 5th floor | |
| May 9, 2018 | Completed final sign-off Jun 2018 | 500 Howard St | R L H Fire Protection Inc | 1st floor - fire sprinkler permi install 10 pendents & delete 1 ref 201804116032 maher naDetails
1st floor - fire sprinkler permi install 10 pendents & delete 1 ref 201804116032 maher na | $6,000 |
| May 7, 2018 | Completed final sign-off Feb 2019 | 500 Howard St | Sc Builders, Inc | 4th fl work includes construction of non structural partitions, doors, frames, hardware, mi9llwork, drywall, ceilings, finishes, mep. fire sprinkler under sep permitDetails
4th fl work includes construction of non structural partitions, doors, frames, hardware, mi9llwork, drywall, ceilings, finishes, mep. fire sprinkler under sep permit | $3,772,797 |
| May 7, 2018 | Completed final sign-off Apr 2019 | 500 Howard St | Sc Builders, Inc | 8th fl ti work includes construction of non structural paritions, door,/frames, hardware, millwork, drywall, ceilings, finishes, mep fire sprinkler under sep permit food service rooms 837,838,839 under sep permit maher not reqDetails
8th fl ti work includes construction of non structural paritions, door,/frames, hardware, millwork, drywall, ceilings, finishes, mep fire sprinkler under sep permit food service rooms 837,838,839 under sep permit maher not req | $2,275,110 |
| May 7, 2018 | Completed final sign-off Feb 2019 | 500 Howard St | Sc Builders, Inc | 9th fl work includes construction of on structural partitions, door frames, hardware, millwork, drywall, ceilings, finishes, mep. fire sprinkler under seperate permitDetails
9th fl work includes construction of on structural partitions, door frames, hardware, millwork, drywall, ceilings, finishes, mep. fire sprinkler under seperate permit | $2,274,603 |
| May 7, 2018 | Completed final sign-off Jun 2019 | 500 Howard St | Sc Builders, Inc | first floor: work includes construction of non-structural partitions, doors/frames/hardware, millwork, drywall, cieling, finishes and mep. fire sprinker under sep permit. no exterior changes. maher naDetails
first floor: work includes construction of non-structural partitions, doors/frames/hardware, millwork, drywall, cieling, finishes and mep. fire sprinker under sep permit. no exterior changes. maher na | $148,298 |
| May 2, 2018 | Completed final sign-off Jun 2018 | 500 Howard St | Martin Sign Co Inc. | fabrication of evac maps with digital print graphics. in stallation of 16 evac mapsDetails
fabrication of evac maps with digital print graphics. in stallation of 16 evac maps | $1,600 |
| Apr 16, 2018 | Completed final sign-off Mar 2019 | 500 Howard St | Sc Builders, Inc | 4th & 8th floor: non-structural demo of partitions, millwork, and mep. n/a for maherDetails
4th & 8th floor: non-structural demo of partitions, millwork, and mep. n/a for maher | $10,000 |
| Apr 12, 2018 | Completed final sign-off Dec 2018 | 500 Howard St | Pribuss Engineering Inc | 1st, 4th,8th, & 9th floors: fire sprinkler t.i. total of sprinklers heads modified = 18 at 514.00. n/a for maher no t.i.Details
1st, 4th,8th, & 9th floors: fire sprinkler t.i. total of sprinklers heads modified = 18 at 514.00. n/a for maher no t.i. | $60,652 |
| Apr 11, 2018 | Completed final sign-off Jun 2018 | 500 Howard St | Richlen Construction | partial remodel of extg retail suite #100 for retail manager. new non-structural walls, finishes, casework, power data, ceiling and lighting. under separate permit: elect, mech, fire life safety. n/a for maherDetails
partial remodel of extg retail suite #100 for retail manager. new non-structural walls, finishes, casework, power data, ceiling and lighting. under separate permit: elect, mech, fire life safety. n/a for maher | $90,000 |
| Apr 4, 2018 | Never finaled issued Apr 2018, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | 5th floor: fire alarm as built for app#201803214219. n/a for maherDetails
5th floor: fire alarm as built for app#201803214219. n/a for maher | |
| Apr 4, 2018 | Completed final sign-off Jul 2018 | 500 Howard St | Sc Builders, Inc | revision to permit# 201711143931 removal of ramp to dining platform areaDetails
revision to permit# 201711143931 removal of ramp to dining platform area | $500 |
| Apr 3, 2018 | Completed final sign-off Apr 2018 | 500 Howard St | Red Hawk Fire & Security Ca Llc | parking level /1st floor: fire alarm t.i. to add 5 speaker strobes. replace 1 power supply and add 7 speaker strobes on 1st floor ref# 201712206951, n/a for maherDetails
parking level /1st floor: fire alarm t.i. to add 5 speaker strobes. replace 1 power supply and add 7 speaker strobes on 1st floor ref# 201712206951, n/a for maher | $8,000 |
| Apr 2, 2018 | Completed final sign-off Jul 2019 | 500 Howard St | Yesco Signs Llc | revise permits #201801118362 and 201801118363 to change the proposed location, no other changes are proposed. n/a maherDetails
revise permits #201801118362 and 201801118363 to change the proposed location, no other changes are proposed. n/a maher | |
| Mar 21, 2018 | Completed final sign-off Mar 2018 | 500 Howard St | Red Hawk Fire & Security Ca Llc | 5th fl l- 49 speaker/strobes, 8 speakers, add 7 relay modules, add 17 smoke detectors, add 2 duct detectorsDetails
5th fl l- 49 speaker/strobes, 8 speakers, add 7 relay modules, add 17 smoke detectors, add 2 duct detectors | $10,000 |
| Mar 20, 2018 | Completed final sign-off Apr 2019 | 500 Howard St | Sc Builders, Inc | demo e structural slab. new stair under separate permit. mep and fire under sep permitDetails
demo e structural slab. new stair under separate permit. mep and fire under sep permit | $25,000 |
| Mar 7, 2018 | Completed final sign-off Mar 2018 | 500 Howard St | Ayoob & Peery Plumbing Co Inc | basement & 1st flr ti: add 2 and relocate 6 sprinklers to 1st. relocate 2 sprinklers in order to conform with the new wall/ceiling layout of ti ref 201712206951 maher naDetails
basement & 1st flr ti: add 2 and relocate 6 sprinklers to 1st. relocate 2 sprinklers in order to conform with the new wall/ceiling layout of ti ref 201712206951 maher na | $2,321 |
| Feb 5, 2018 | Completed final sign-off Apr 2019 | 500 Howard St | Sc Builders, Inc | 10th flr - ti at 500 howard st base bkd connection for arch tube steel "peaks" at the 10th flr stair is the mezzanine level. ref pa 201711214532 maher naDetails
10th flr - ti at 500 howard st base bkd connection for arch tube steel "peaks" at the 10th flr stair is the mezzanine level. ref pa 201711214532 maher na | $5,000 |
| Jan 30, 2018 | Completed final sign-off Mar 2018 | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm ti on 7th fl: add 62 speaker strobes, 13 speakers, & replace 1 existing power supply with new. ref #201710252250. maher naDetails
fire alarm ti on 7th fl: add 62 speaker strobes, 13 speakers, & replace 1 existing power supply with new. ref #201710252250. maher na | $37,500 |
| Jan 30, 2018 | Completed final sign-off Jul 2018 | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm ti on 10th fl: add 31 speaker strobes & 5 speakers. ref #201711214532. maher naDetails
fire alarm ti on 10th fl: add 31 speaker strobes & 5 speakers. ref #201711214532. maher na | $18,000 |
| Jan 30, 2018 | Completed final sign-off Apr 2018 | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm ti on 2nd fl: add 43 speaker strobes, 1 speakers, & replace 1 existing power supply with new. ref pa #201710312742. maher naDetails
fire alarm ti on 2nd fl: add 43 speaker strobes, 1 speakers, & replace 1 existing power supply with new. ref pa #201710312742. maher na | $27,000 |
| Jan 30, 2018 | Completed final sign-off Mar 2018 | 500 Howard St | Red Hawk Fire & Security Ca Llc | fire alarm ti on 6th fl: add 54 speaker strobes, 8 speakers, & replace 1 existing power supply with new. ref #201710252245. maher naDetails
fire alarm ti on 6th fl: add 54 speaker strobes, 8 speakers, & replace 1 existing power supply with new. ref #201710252245. maher na | $31,000 |
| Jan 11, 2018 | Completed final sign-off Jul 2019 | 500 Howard St | Yesco Signs Llc | install 1 illuminated wall signDetails
install 1 illuminated wall sign | $6,000 |
| Jan 11, 2018 | Completed final sign-off Jul 2019 | 500 Howard St | Yesco Signs Llc | install 1 illuminated projecting signDetails
install 1 illuminated projecting sign | $2,000 |
| Jan 11, 2018 | Completed final sign-off Apr 2018 | 500 Howard St | Ayoob & Peery Plumbing Co Inc | 5th flr- revision to 201712146455; install 2 new fire hose cabinet tp conform with the new wall/ceiling layout of the ti - ref 201711143931 maher naDetails
5th flr- revision to 201712146455; install 2 new fire hose cabinet tp conform with the new wall/ceiling layout of the ti - ref 201711143931 maher na | |
| Jan 11, 2018 | Completed final sign-off Jul 2019 | 500 Howard St | Yesco Signs Llc | install 1 non illuminated wall signDetails
install 1 non illuminated wall sign | $2,000 |
| Dec 20, 2017 | Completed final sign-off Jul 2018 | 500 Howard St | Sc Builders, Inc | basement & 1st floor - construction of non-sttructural partitions, doors/frames/hardware, millwrok, drywall & acoustic ceiling grid/tile. finishes, mechanical, electrical & plumbing. fire sprinklers & life safety under separate permit.Details
basement & 1st floor - construction of non-sttructural partitions, doors/frames/hardware, millwrok, drywall & acoustic ceiling grid/tile. finishes, mechanical, electrical & plumbing. fire sprinklers & life safety under separate permit. | $90,150 |
| Dec 14, 2017 | Completed final sign-off Apr 2018 | 500 Howard St | Ayoob & Peery Plumbing Co Inc | 10th flr: add 19, relocate 40 and plug 1 sprinkler in order to conform with the new ti ref 201711214532 maher naDetails
10th flr: add 19, relocate 40 and plug 1 sprinkler in order to conform with the new ti ref 201711214532 maher na | $18,575 |
| Dec 14, 2017 | Never finaled issued Dec 2017, no final | 500 Howard St | Ayoob & Peery Plumbing Co Inc | 5th flr: add 29, relocate 62 and plug 6 sprinkler in order to conform with the new ti ref 201711143931 maher naDetails
5th flr: add 29, relocate 62 and plug 6 sprinkler in order to conform with the new ti ref 201711143931 maher na | $28,555 |
| Nov 21, 2017 | Completed final sign-off Sep 2019 | 500 Howard St | Sc Builders, Inc | 10th flr: construction of non structural partitions, structural partitions. mezzanine, non-egres stairs, doors, frames, hardware, millwork, drywall, acoustic ceiling grid/tile, finishes, mech, elec, plumb, fire sprinkler & life saftey under deffered submittal. arch features under. separate permit.Details
10th flr: construction of non structural partitions, structural partitions. mezzanine, non-egres stairs, doors, frames, hardware, millwork, drywall, acoustic ceiling grid/tile, finishes, mech, elec, plumb, fire sprinkler & life saftey under deffered submittal. arch features under. separate permit. | $2,264,084 |
| Nov 16, 2017 | Completed final sign-off Feb 2018 | 500 Howard St | Ayoob & Peery Plumbing Co Inc | 7th floor: add 45, relocate 96 sprinklers in order to conform with the new wall ceiling layout of the t.i. ref app#201710252250. n/a for maherDetails
7th floor: add 45, relocate 96 sprinklers in order to conform with the new wall ceiling layout of the t.i. ref app#201710252250. n/a for maher | $45,225 |
| Nov 16, 2017 | Completed final sign-off Jan 2018 | 500 Howard St | Ayoob & Peery Plumbing Co Inc | 6th floor: add 23, relocate 96 and plug 3 sprinklers in order to conform with the new wall ceiling layout of the t.i. ref app#201710252245. n/a for maherDetails
6th floor: add 23, relocate 96 and plug 3 sprinklers in order to conform with the new wall ceiling layout of the t.i. ref app#201710252245. n/a for maher | $33,675 |
| Nov 16, 2017 | Completed final sign-off Jul 2018 | 500 Howard St | Ayoob & Peery Plumbing Co Inc | 2nd floor: add 41, relocate 51 and plug 2 sprinklers in order to conform with the new wall/ceiling layout of the t.i. ref app#201710312742. n/a for maherDetails
2nd floor: add 41, relocate 51 and plug 2 sprinklers in order to conform with the new wall/ceiling layout of the t.i. ref app#201710312742. n/a for maher | $33,000 |
| Nov 14, 2017 | Completed final sign-off Jul 2018 | 500 Howard St | Sc Builders, Inc | construction of non structural partitions, doors/frames/hardware, millwork, drywall, acoustic ceiling/ grid finishes, horizontal exit,mech, elec, plumbing structural platforms fire sprinkler and life safety under deferred submittal. n/a for maher.Details
construction of non structural partitions, doors/frames/hardware, millwork, drywall, acoustic ceiling/ grid finishes, horizontal exit,mech, elec, plumbing structural platforms fire sprinkler and life safety under deferred submittal. n/a for maher. | $3,772,797 |
| Oct 31, 2017 | Completed final sign-off Jul 2018 | 500 Howard St | Sc Builders, Inc | 2nd fl: construction of non-structural partitions, door/frames/hardware, millwork, drywall and acoustic ceiling grid/tile, finishes, mechanical, electrical and plumbing. structural platforms. fire sprinkler & life safety under deferred submittal. maher n/a.Details
2nd fl: construction of non-structural partitions, door/frames/hardware, millwork, drywall and acoustic ceiling grid/tile, finishes, mechanical, electrical and plumbing. structural platforms. fire sprinkler & life safety under deferred submittal. maher n/a. | $3,225,407 |
| Oct 25, 2017 | Completed final sign-off Jul 2018 | 500 Howard St | Sc Builders, Inc | construction of non-structural partitions, door/frames/hardware, millwork, drywall and acoustic ceiling grid/tile, finishes, mechanical, electrical and plumbing. structural platforms. fire sprinkler & life safety under deferred submittal. maher n/a.Details
construction of non-structural partitions, door/frames/hardware, millwork, drywall and acoustic ceiling grid/tile, finishes, mechanical, electrical and plumbing. structural platforms. fire sprinkler & life safety under deferred submittal. maher n/a. | $3,704,357 |
| Oct 25, 2017 | Completed final sign-off Jul 2018 | 500 Howard St | Sc Builders, Inc | construction of non-structural partitions, door/frames/hardware, millwork, drywall and acoustic ceiling grid/tile, finishes, mechanical, electrical and plumbing. structural platforms. fire sprinkler & life safety under deferred submittal. maher n/a.Details
construction of non-structural partitions, door/frames/hardware, millwork, drywall and acoustic ceiling grid/tile, finishes, mechanical, electrical and plumbing. structural platforms. fire sprinkler & life safety under deferred submittal. maher n/a. | $3,797,131 |
| Jul 24, 2017 | Completed final sign-off Nov 2017 | 500 Howard St | Sc Builders, Inc | ceiling demo associated with pa 2017-0627-0448 and sprinkler pa 2017-0717-2073 flr lobby, 1, 2, 5, 6, 7 and 10Details
ceiling demo associated with pa 2017-0627-0448 and sprinkler pa 2017-0717-2073 flr lobby, 1, 2, 5, 6, 7 and 10 | |
| Jul 17, 2017 | Completed final sign-off Sep 2017 | 500 Howard St | Pribuss Engineering Inc | 1,2,5,6,7,10/f- fire sprinklers t.i. under pa#201706270448, relocate 180 sprinklers. n/a ordinance #155-13Details
1,2,5,6,7,10/f- fire sprinklers t.i. under pa#201706270448, relocate 180 sprinklers. n/a ordinance #155-13 | $93,118 |
| Jun 27, 2017 | Completed final sign-off Nov 2017 | 500 Howard St | Sc Builders, Inc | floors -basement, 1, 2, 5, 6,7,10 : demo of non-structural partitoins, doors/frames, hardware, millwork, ceilings, finishes, mechanical, electrical & plumbing. ti under separate permits. all proposed work areas are under 1 tenant. n/a maher ordinanceDetails
floors -basement, 1, 2, 5, 6,7,10 : demo of non-structural partitoins, doors/frames, hardware, millwork, ceilings, finishes, mechanical, electrical & plumbing. ti under separate permits. all proposed work areas are under 1 tenant. n/a maher ordinance | $200,000 |
| Sep 23, 2016 | Completed final sign-off Mar 2018 | 500 Howard St | Ayoob & Peery Plumbing Co Inc | 8th floor: add (3), relocate (5) sprinklers to conform with the new wall/ceiling layout of the ti. ref pa 2016-0808-4476Details
8th floor: add (3), relocate (5) sprinklers to conform with the new wall/ceiling layout of the ti. ref pa 2016-0808-4476 | $2,592 |
| Aug 8, 2016 | Completed final sign-off Jan 2017 | 500 Howard St | Novo Construction Inc | arch only tenant improvement to (e) occupied office space. limited demolition of non-structural partitions, doors, ceiling & seating. new construction of non-structural partitions, doors, ceiling and finishes, mep and fire deferredDetails
arch only tenant improvement to (e) occupied office space. limited demolition of non-structural partitions, doors, ceiling & seating. new construction of non-structural partitions, doors, ceiling and finishes, mep and fire deferred | $387,500 |
| Aug 28, 2015 | Expired or cancelled cancelled Apr 2023 | 500 Howard St | Gci, Inc | 3rd floor: t.i. includes demo of non-structural partitions. all new or revised hvac, electrical, plmbg, life safety and sprinklers work will be design build and submitted for permit separately. bldg fully sprinkler. n/a for maher.Details
3rd floor: t.i. includes demo of non-structural partitions. all new or revised hvac, electrical, plmbg, life safety and sprinklers work will be design build and submitted for permit separately. bldg fully sprinkler. n/a for maher. | $68,943 |
| Apr 18, 2014 | Never finaled issued Apr 2014, no final | 500 Howard St | Red Hawk Fire & Security Ca Llc | ground floor: add 2 new speakers and 3 new speaker/strobes. t.i. app#201404072569. n/a for the maher ordinance #155-13Details
ground floor: add 2 new speakers and 3 new speaker/strobes. t.i. app#201404072569. n/a for the maher ordinance #155-13 | $6,100 |
| Apr 7, 2014 | Completed final sign-off Jun 2014 | 500 Howard St | Novo Construction Inc | ground floor: interior t.i. new non-structural partitions, millwork and finishes. mep, life safety and fire sprinkler under seperate permit. n/a for the maher ordinance #155-13Details
ground floor: interior t.i. new non-structural partitions, millwork and finishes. mep, life safety and fire sprinkler under seperate permit. n/a for the maher ordinance #155-13 | $25,000 |
| Sep 13, 2013 | Completed final sign-off Oct 2013 | 500 Howard St | Red Hawk Fire & Security Ca Llc | 3rd floor- fire alarm ti, add 18 new speakers and 14 new speaker/strobesDetails
3rd floor- fire alarm ti, add 18 new speakers and 14 new speaker/strobes | $16,000 |
| Aug 23, 2013 | Completed final sign-off Oct 2013 | 500 Howard St | R L H Fire Protection Inc | add, relocate & remove fire sprinkler heads per t.i. - 7 add, 10 relocate & 14 remove.Details
add, relocate & remove fire sprinkler heads per t.i. - 7 add, 10 relocate & 14 remove. | $8,738 |
| Aug 14, 2013 | Completed final sign-off Oct 2013 | 500 Howard St | Denham-Blythe Company Inc | suite 450:1)add entry doors. 2)add interior doors. 3)add one private office.Details
suite 450:1)add entry doors. 2)add interior doors. 3)add one private office. | $150,000 |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.