45 permits since 2000 (engineer on 43 permits, architect on 1 permit, authorized agent-others on 1 permit): 24 completed, 21 in progress.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 30, 2026 | In progress filed Sep 2026, not yet issued | 350 Bush St | B N Builders Inc | deferred mep for ref pa 202608136550Details
deferred mep for ref pa 202608136550 | $350,000 |
| Sep 30, 2026 | In progress filed Sep 2026, not yet issued | 815 Powell St | deferred bpa 202311090505 reconfiguration of existing ductwork for the recommising of an existing split system fan coilDetails
deferred bpa 202311090505 reconfiguration of existing ductwork for the recommising of an existing split system fan coil | $20,000 | |
| Sep 10, 2026 | In progress issued Sep 2026 | 1 California St | Singular Builders | mechanical and electrical work for t.i. at suite 1825. ref: 202606223639Details
mechanical and electrical work for t.i. at suite 1825. ref: 202606223639 | $82,000 |
| Sep 10, 2026 | In progress issued Sep 2026 | 101 02nd St | Source Planning And Construction Inc | 8/f suite 800: deferred mep for ref pa 202607144969. electrical - office t.i retrofit: lighting with associated circuits and controls, power and signal with associated circuits and wiring. mechanical - demo of ceiling diffusers in open area. install of ductwork where required. new sidewall diffusersDetails
8/f suite 800: deferred mep for ref pa 202607144969. electrical - office t.i retrofit: lighting with associated circuits and controls, power and signal with associated circuits and wiring. mechanical - demo of ceiling diffusers in open area. install of ductwork where required. new sidewall diffusers | $92,450 |
| Sep 3, 2026 | In progress issued Sep 2026 | 353 Sacramento St | Bcci Construction Company | 22nd fl: mep submittal to support approved pa: 202606253937 - new hvac and ductwork for new office layout. new lighting and power.Details
22nd fl: mep submittal to support approved pa: 202606253937 - new hvac and ductwork for new office layout. new lighting and power. | $600,000 |
| Aug 28, 2026 | In progress issued Sep 2026 | 345 Spear St | B N Builders Inc | ground fl ste 118-120: addition of partition wall to divide (e) lounge space into (2) individual enclosed rooms. (arch/mep)Details
ground fl ste 118-120: addition of partition wall to divide (e) lounge space into (2) individual enclosed rooms. (arch/mep) | $100,000 |
| Aug 12, 2026 | In progress issued Aug 2026 | 1 California St | Singular Builders | #1850: mechanical and electrical work to tenant improvement ref 202605261889Details
#1850: mechanical and electrical work to tenant improvement ref 202605261889 | $60,000 |
| Jul 20, 2026 | In progress issued Aug 2026 | 350 Rhode Island St | B N Builders Inc | 3/fl- construction of (n) full height non load bearing paritions, doors, glazing millwork, finishes, plumbing, associated electrical power lighting distruction associated mep and fixtures.Details
3/fl- construction of (n) full height non load bearing paritions, doors, glazing millwork, finishes, plumbing, associated electrical power lighting distruction associated mep and fixtures. | $6,000,000 |
| Jun 29, 2026 | In progress issued Jun 2026 | 415 Kearny St | Novo Construction Inc | 4/f: mechanical work for tenant improvement. ref arch permit 202603137502 and 202604109248.Details
4/f: mechanical work for tenant improvement. ref arch permit 202603137502 and 202604109248. | $75,000 |
| Jun 29, 2026 | In progress issued Jun 2026 | 415 Kearny St | Novo Construction Inc | 3/f: mechanical work for tenant improvement. ref arch permit 202603137505 and 202604139310.Details
3/f: mechanical work for tenant improvement. ref arch permit 202603137505 and 202604139310. | $75,000 |
| May 27, 2026 | In progress issued Jun 2026 | 1100 Ellis St | Guzman Construction Group Inc. | 1/fl-revision 202604179653- m/p modifications. existing base building system is not in scope and is to remain.Details
1/fl-revision 202604179653- m/p modifications. existing base building system is not in scope and is to remain. | $100,000 |
| May 26, 2026 | In progress issued May 2026 | 706 Sansome St | M C S Construction Services | deferred elec and mech. 202505216975 and 202604230002 mech 3 new exhaust fans replacement,3 new fire smoke dampers. new ductwork as needed.reconfig ductwork,air dist ddc controls and air balance. elec lighting w assoc circuits and controls, power and signal w ass circuits and wiringDetails
deferred elec and mech. 202505216975 and 202604230002 mech 3 new exhaust fans replacement,3 new fire smoke dampers. new ductwork as needed.reconfig ductwork,air dist ddc controls and air balance. elec lighting w assoc circuits and controls, power and signal w ass circuits and wiring | $150,000 |
| May 1, 2026 | Completed final sign-off Aug 2026 | 353 Sacramento St | Bcci Construction Company | 12th/f: mep submittal to t.i. 202603057008, new ductwork & lighting for new office layoutDetails
12th/f: mep submittal to t.i. 202603057008, new ductwork & lighting for new office layout | $250,000 |
| Apr 15, 2026 | Completed final sign-off Sep 2026 | 1 Sansome St | Skyline Construction | 33rd & 35th revision to pa 202511129396 food service scope including finishes, equipment and environmental health notes. revision includes additional locakers, drinking fountaint, ceiling and soffit modificationsDetails
33rd & 35th revision to pa 202511129396 food service scope including finishes, equipment and environmental health notes. revision includes additional locakers, drinking fountaint, ceiling and soffit modifications | |
| Apr 15, 2026 | Completed final sign-off Sep 2026 | 1 Sansome St | revision to pa 202511129399 30-31floor - food service scope includes finishes, equipments and environmental health notes. revision includes additional lockers, drinking fountain, ceiling and soffit modificationsDetails
revision to pa 202511129399 30-31floor - food service scope includes finishes, equipments and environmental health notes. revision includes additional lockers, drinking fountain, ceiling and soffit modifications | ||
| Apr 8, 2026 | Completed final sign-off May 2026 | 353 Sacramento St | Bcci Construction Company | new fire smoke dampers and power ref approved mech permit: 202602236308.Details
new fire smoke dampers and power ref approved mech permit: 202602236308. | $50,000 |
| Mar 20, 2026 | In progress issued Mar 2026 | 353 Sacramento St | Bcci Construction Company | 16th floor - mep submittal to support approved architectural permit. new vav boxes, ductwork, lighting and power. ref # 202512222377Details
16th floor - mep submittal to support approved architectural permit. new vav boxes, ductwork, lighting and power. ref # 202512222377 | $250,000 |
| Feb 23, 2026 | Completed final sign-off May 2026 | 353 Sacramento St | Bcci Construction Company | 2nd fl ref pa #2025-1215-1741: mep permit to add new lighting, power, air & ducts.Details
2nd fl ref pa #2025-1215-1741: mep permit to add new lighting, power, air & ducts. | $450,000 |
| Feb 12, 2026 | In progress issued Mar 2026 | 201 03rd St | Skyline Construction | 5th/f - revison to approved permit# 2025-1126-0530. demo of moveable wall. construct new wall, new door and upgrade to mechanical electrical equipement due to new room.Details
5th/f - revison to approved permit# 2025-1126-0530. demo of moveable wall. construct new wall, new door and upgrade to mechanical electrical equipement due to new room. | $50,000 |
| Feb 4, 2026 | In progress issued Feb 2026 | 1 Sansome St | Skyline Construction | 38/f: deferred mep for permit 202512101393.Details
38/f: deferred mep for permit 202512101393. | $1,158,696 |
| Jan 21, 2026 | Completed final sign-off Sep 2026 | 1 Sansome St | Skyline Construction | level 33,35 deferred mep for 202511129396Details
level 33,35 deferred mep for 202511129396 | $2,333,160 |
| Jan 21, 2026 | Completed final sign-off Sep 2026 | 1 Sansome St | Skyline Construction | l30-31 deferred mep for 202511129399Details
l30-31 deferred mep for 202511129399 | $2,347,776 |
| Dec 12, 2025 | In progress issued Feb 2026 | 201 03rd St | Skyline Construction | 7th fl - interior ti demo includes of non-structural partitions construction includes millwork, finishes, ceiling, mech & elec upgradesDetails
7th fl - interior ti demo includes of non-structural partitions construction includes millwork, finishes, ceiling, mech & elec upgrades | $425,000 |
| Nov 26, 2025 | In progress issued Dec 2025 | 201 03rd St | Skyline Construction | 5/f: office tenant improvement. removal of non-structural walls, finishes, and lighting. new construction of non-structural walls, finishes, millwork, ceiling. mechanical and electrical upgradesDetails
5/f: office tenant improvement. removal of non-structural walls, finishes, and lighting. new construction of non-structural walls, finishes, millwork, ceiling. mechanical and electrical upgrades | $725,000 |
| Nov 4, 2025 | Completed final sign-off Feb 2026 | 430 California St | Novo Construction Inc | 11/f: demolition of interior partitions to create open office. minor lighting and power. new finishes.Details
11/f: demolition of interior partitions to create open office. minor lighting and power. new finishes. | $193,000 |
| Oct 2, 2025 | Completed final sign-off Mar 2026 | 650 Davis St | Field Construction Inc. | unit 175: mechanical- 3 new water sources, 2 new outside air fans, 1 new transfer exhaust fan. electrical power, lighting and signal. ref #202504073829Details
unit 175: mechanical- 3 new water sources, 2 new outside air fans, 1 new transfer exhaust fan. electrical power, lighting and signal. ref #202504073829 | $153,000 |
| Aug 6, 2025 | Completed final sign-off Dec 2025 | 4 Embarcadero Center | Field Construction Inc. | suite 3120 31st fl ref pa # 202505287367. remove heatpump & pumpDetails
suite 3120 31st fl ref pa # 202505287367. remove heatpump & pump | |
| Aug 5, 2025 | Completed final sign-off Sep 2025 | 580 California St | Skyline Construction | 20th fl, ste 2000 mechanical and electricl work for ti ref pa 202505086068Details
20th fl, ste 2000 mechanical and electricl work for ti ref pa 202505086068 | $120,000 |
| May 28, 2025 | Completed final sign-off Dec 2025 | 4 Embarcadero Center | Field Construction Inc. | suite 3120 ref pa # 2025-0411-4228: mech- new single duct vav boxes, new water source heat pump, new circulation condenser water pump & new ductwork & air distribution . electrical- power, lighting & signalDetails
suite 3120 ref pa # 2025-0411-4228: mech- new single duct vav boxes, new water source heat pump, new circulation condenser water pump & new ductwork & air distribution . electrical- power, lighting & signal | $150,000 |
| May 5, 2025 | Completed final sign-off Nov 2025 | 615 Battery St | Hathaway Dinwiddie Co. | 6/f: deferred mep submittal for building permit 202503212723 includes mechanical, electrical, and plumbing.Details
6/f: deferred mep submittal for building permit 202503212723 includes mechanical, electrical, and plumbing. | $384,260 |
| Apr 22, 2025 | Completed final sign-off Jul 2025 | 1 Post St | Peacock Construction | (ste #400) deffered mechanical/electrical. ref pa# 202502140413Details
(ste #400) deffered mechanical/electrical. ref pa# 202502140413 | $90,000 |
| Apr 17, 2025 | Completed final sign-off Oct 2025 | 601 California St | Peacock Construction | 14th fl suite 1450 ref pa# 2024-1224-7361: new vav @ meeting & arbitration room, new ductwork, new supply & return diffusers, new exhaust fan at copy room, relocate thermostats, air balanceDetails
14th fl suite 1450 ref pa# 2024-1224-7361: new vav @ meeting & arbitration room, new ductwork, new supply & return diffusers, new exhaust fan at copy room, relocate thermostats, air balance | $75,000 |
| Apr 11, 2025 | In progress issued Apr 2025 | 69 Green St | Novo Construction Inc | 1st and 2nd fl ref 202502210827 deferred mechanical and electrical work for tenant improvementDetails
1st and 2nd fl ref 202502210827 deferred mechanical and electrical work for tenant improvement | $45,000 |
| Mar 4, 2025 | Completed final sign-off May 2025 | 2 Embarcadero Center | M C S Construction Services | suite 1630: deferred mechanical & electrical permit ref pa 202502079849 mech- mech modifications to accommodate arch layout changes, new dual duct rav box & new ductwork as needed. reconfigure of (e) ductwork & air dist. electrical- new power & signal devices throughout space new title 24.Details
suite 1630: deferred mechanical & electrical permit ref pa 202502079849 mech- mech modifications to accommodate arch layout changes, new dual duct rav box & new ductwork as needed. reconfigure of (e) ductwork & air dist. electrical- new power & signal devices throughout space new title 24. | $100,000 |
| Jan 23, 2025 | Completed final sign-off Mar 2025 | 101 California St | Hp Build | mechanical and electrical work (ste 1925/19th fl) ref 2024.1121.5485Details
mechanical and electrical work (ste 1925/19th fl) ref 2024.1121.5485 | $105,000 |
| Jan 6, 2025 | Completed final sign-off Jun 2025 | 221 Main St | Novo Construction Inc | 16th floor: partial floor and ceiling demolition of existing tenant space. new interior partitios, ceilings, and finishes. mechanical and electrical work included.Details
16th floor: partial floor and ceiling demolition of existing tenant space. new interior partitios, ceilings, and finishes. mechanical and electrical work included. | $1,086,562 |
| Jan 6, 2025 | In progress issued Jan 2025 | 235 Montgomery St | Anderson, Rowe & Buckley, Inc. | 22nd floor: interior ti to restrooms. scope of work includes install 2 new exhaust fans, installl ductwork to new exhaust grilles, install return/transfer grilles, air balance. reference arch app # 202411265757Details
22nd floor: interior ti to restrooms. scope of work includes install 2 new exhaust fans, installl ductwork to new exhaust grilles, install return/transfer grilles, air balance. reference arch app # 202411265757 | $35,000 |
| Oct 16, 2024 | Completed final sign-off Jan 2025 | 1 Market St | Source Planning And Construction Inc | basement lvl ref pa # 2024-0820-9023 mechanical demo of existing duct & install new fsdDetails
basement lvl ref pa # 2024-0820-9023 mechanical demo of existing duct & install new fsd | $25,000 |
| Oct 2, 2024 | Completed final sign-off Apr 2025 | 222 02nd St | Plant Construction Co, Lp | 3rd fl - replacement of existing kitchen equipment in pot wash room. 20% ada restroom upgrades. no change in fixture quantities; occupant load calculations or path of travelDetails
3rd fl - replacement of existing kitchen equipment in pot wash room. 20% ada restroom upgrades. no change in fixture quantities; occupant load calculations or path of travel | $30,000 |
| Aug 1, 2024 | Completed final sign-off Oct 2024 | 735 Montgomery St | M C S Construction Services | 4th floor: deferred mechanical, electrical, plumbing permit for office t.i. project. ref pa#202403208278.Details
4th floor: deferred mechanical, electrical, plumbing permit for office t.i. project. ref pa#202403208278. | $148,000 |
| Apr 23, 2024 | In progress issued Apr 2024 | 221 Main St | Principal Builders Inc. | 8th floor- rev 202403137701- minor mechanical changeDetails
8th floor- rev 202403137701- minor mechanical change | $5,000 |
| Mar 13, 2024 | In progress issued Mar 2024 | 221 Main St | Principal Builders Inc. | 8th floor: revision to 202311019990. mechanical only.Details
8th floor: revision to 202311019990. mechanical only. | |
| Sep 28, 2023 | Completed final sign-off Mar 2024 | 425 California St | M C S Construction Services | deferred mech and electrical. ref 202307252868 202308315717. mech, demo install newduct annd hvac equip, dual ductboxes, exhaust fans, ddc controls, air balance. ele new power and data new lighting and controlsDetails
deferred mech and electrical. ref 202307252868 202308315717. mech, demo install newduct annd hvac equip, dual ductboxes, exhaust fans, ddc controls, air balance. ele new power and data new lighting and controls | $150,000 |
| May 23, 2023 | Completed final sign-off Oct 2023 | 45 Fremont St | Principal Builders Inc. | deferred mep for 202304286752Details
deferred mep for 202304286752 | $1,453,000 |
| Mar 22, 2023 | Completed final sign-off Jul 2023 | 322 Ritch St | Principal Builders Inc. | install new gas furnace and new roof exhaust fanDetails
install new gas furnace and new roof exhaust fan | $40,000 |