Jahandar Yadegar
- Listed as
- architect, engineer
- Firm
- John Yadegar & Assoc.
- Based in
- San Francisco
- On San Francisco permits
- Jun 2001 to Sep 2025
164 permits since 2000 (engineer on 147 permits, architect on 17 permits): 126 completed, 15 never finaled, 23 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 164.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 5, 2025 | Completed final sign-off Feb 2026 | 1133 Fell St | Steelcore Builders Inc | revision to pa #202507150822 addiitonal and remove and replace the dryrotted beam with the same and modify foundation to accept the column's base plate in the garage.Details
revision to pa #202507150822 addiitonal and remove and replace the dryrotted beam with the same and modify foundation to accept the column's base plate in the garage. | $5,000 |
| Jun 24, 2022 | Completed final sign-off Nov 2022 | 1145 Green St | Mulhall Construction Inc. | revision to 202201186135. new grade beam detail, new footing detail, no change in scope.Details
revision to 202201186135. new grade beam detail, new footing detail, no change in scope. | |
| Feb 23, 2022 | Completed final sign-off Sep 2022 | 561 Sanchez St | Alpha Restoration & Wateproof | new gate at front entry.Details
new gate at front entry. | $2,000 |
| Jan 20, 2022 | Never finaled issued Feb 2022, no final | 1490 Willard St | Steelcore Builders Inc | revision to pa 2021-1209-4035 & 2021-0309-6206 include replacement of deck @ 2nd fl & updating the steel strong wall toward strong wall @ 2nd fl along grid line h & gDetails
revision to pa 2021-1209-4035 & 2021-0309-6206 include replacement of deck @ 2nd fl & updating the steel strong wall toward strong wall @ 2nd fl along grid line h & g | |
| Jan 18, 2022 | Completed final sign-off Nov 2022 | 1145 Green St | Mulhall Construction Inc. | voluntary seismic strengthing.Details
voluntary seismic strengthing. | $40,000 |
| Jul 2, 2021 | Never finaled issued Jul 2021, no final | 1490 Willard St | Steelcore Builders Inc | revision to app#202012020076. add plywood to cripple wall and replace hand dug with drilled piers.Details
revision to app#202012020076. add plywood to cripple wall and replace hand dug with drilled piers. | |
| May 20, 2021 | Completed final sign-off Dec 2021 | 168 Palm Av | Lordan Construction | seismic strengthening to comply with sf soft story ordinance design per iebc appendix a-4.Details
seismic strengthening to comply with sf soft story ordinance design per iebc appendix a-4. | $120,000 |
| Apr 26, 2021 | Never finaled issued May 2021, no final | 468 Jersey St | Madden Construction | new internal stair from 2nd to 1st fl. remodel existing powder room, relocate laundry & sink.Details
new internal stair from 2nd to 1st fl. remodel existing powder room, relocate laundry & sink. | $80,000 |
| Apr 14, 2021 | Completed final sign-off Feb 2022 | 23 Baker St | Restoration Workshop Ltd | revision to pa# 201905029521. foundation design change.Details
revision to pa# 201905029521. foundation design change. | $100 |
| Feb 18, 2021 | Completed final sign-off Jul 2022 | 549 Jersey St | J5 Real Estate Development Co | renovation of existing 200 sqft shed in rear yard. permitted and constructed in 1942. remove existing full bath & provide new half bath & wet bar to confirm to zoning administrator bulletin #1. all work at main dwelling under pa# 201812188681.Details
renovation of existing 200 sqft shed in rear yard. permitted and constructed in 1942. remove existing full bath & provide new half bath & wet bar to confirm to zoning administrator bulletin #1. all work at main dwelling under pa# 201812188681. | $20,000 |
| Jan 22, 2021 | Completed final sign-off Apr 2021 | 530 Lake St | Sft Construction Corp | reinforcement of bay windowsDetails
reinforcement of bay windows | $40,000 |
| Jan 6, 2021 | Never finaled issued Feb 2021, no final | 36 Parnassus Av | Trush Construction Company Inc. | construction of (n) staircase to connect rooms down at 1st fl to 2nd fl through interior of unit.Details
construction of (n) staircase to connect rooms down at 1st fl to 2nd fl through interior of unit. | $7,500 |
| Dec 23, 2020 | Completed final sign-off Aug 2022 | 1871 43rd Av | Trim Fit Constr. - O'reilly Engineering | convert part of garage into conditioned space - add bedroom, bathroom, family room. remove 1 stair. remodel 2nd flr bathroom- replace fixtures and finishes. restore front yard landscaping and permeable surfaceDetails
convert part of garage into conditioned space - add bedroom, bathroom, family room. remove 1 stair. remodel 2nd flr bathroom- replace fixtures and finishes. restore front yard landscaping and permeable surface | $125,000 |
| Aug 15, 2020 | Completed final sign-off May 2023 | 1522 Howard St | Jing Hua Construction Corp | application for adu in existing ground floor space. new work to include new kitchen, remodel of existing bathroom, and new doors and window out to rear yard. mep, and any required title 24 calcs, permitted separately. per ord 162-16.Details
application for adu in existing ground floor space. new work to include new kitchen, remodel of existing bathroom, and new doors and window out to rear yard. mep, and any required title 24 calcs, permitted separately. per ord 162-16. | $50,000 |
| May 13, 2020 | Completed final sign-off Apr 2021 | 2541 Washington St | Lyons Building & Associates Inc. | 1st flr - repairs due to flood damage. remodel kitchen and bathroom.Details
1st flr - repairs due to flood damage. remodel kitchen and bathroom. | $50,000 |
| Feb 5, 2020 | Never finaled issued Feb 2020, no final | 430 Bush St | Paradigm General Contractors | construction of 32'w x 12'h art installation @ existing office at g/f. installation of structural hanging display bridge.Details
construction of 32'w x 12'h art installation @ existing office at g/f. installation of structural hanging display bridge. | $12,000 |
| Dec 26, 2019 | Completed final sign-off May 2021 | 1018 Valencia St | 1018 valencia - voluntary upgrades to vacant ground fl commercial tenant space including demolition of non-conforming mezzanine; upgrade of restroom & entry for ada-compliance; repair & replacemtn of windows, door, & interior stairs. 1018-1020 valencia - voluntary soft story upgrade.Details
1018 valencia - voluntary upgrades to vacant ground fl commercial tenant space including demolition of non-conforming mezzanine; upgrade of restroom & entry for ada-compliance; repair & replacemtn of windows, door, & interior stairs. 1018-1020 valencia - voluntary soft story upgrade. | $161,000 | |
| Dec 20, 2019 | Expired or cancelled expired Feb 2024 | 972 Mission St | Modern Construction Inc | barrier removal project to include: removal of elevator and enlargement of elevator shaft in preparation for new elevator, work also includes new finishes and lighting at elevator lobby, mep, title 24 energy calcs, fire sprinklers and life safety under separate permitDetails
barrier removal project to include: removal of elevator and enlargement of elevator shaft in preparation for new elevator, work also includes new finishes and lighting at elevator lobby, mep, title 24 energy calcs, fire sprinklers and life safety under separate permit | $100,000 |
| Dec 9, 2019 | Completed final sign-off Jul 2020 | 59 Rosewood Dr | Steelcore Builders Inc | new deck at rear yardDetails
new deck at rear yard | $35,000 |
| Nov 12, 2019 | Never finaled issued Apr 2021, no final | 468 Jersey St | Madden Construction | remodel kitchen & breakfast room; rework lower room ceiling for new deck above; relocate (new) under 10' spiral stair with 45% setback. not extending building footprint.Details
remodel kitchen & breakfast room; rework lower room ceiling for new deck above; relocate (new) under 10' spiral stair with 45% setback. not extending building footprint. | $150,000 |
| Jul 31, 2019 | Completed final sign-off Dec 2019 | 1671 Lombard St | Sft Construction Corp | revision to pa 201710201838, soft-story. retrofit to comply w/ sf soft-story ordinance complaint # 201714512Details
revision to pa 201710201838, soft-story. retrofit to comply w/ sf soft-story ordinance complaint # 201714512 | $50,000 |
| May 16, 2019 | Completed final sign-off Aug 2024 | 1820 Anza St | Add A Garage Inc. | soil permeation grouting along property line of adjacent property at 1812 anza as req'd by pa# 201711154103 s1Details
soil permeation grouting along property line of adjacent property at 1812 anza as req'd by pa# 201711154103 s1 | $5,000 |
| Jan 30, 2019 | Completed final sign-off Jun 2023 | 29 Hattie St | Ccsf Design Build | revison to previously approved pa #201712227255. revision poured forms to be shotcrete.Details
revison to previously approved pa #201712227255. revision poured forms to be shotcrete. | |
| Dec 18, 2018 | Completed final sign-off Dec 2022 | 549 Jersey St | J5 Real Estate Development Co | addition of 3rd floor master suite & remodel of 2nd floor kitchen, bath. guestroom @ 1st floor.Details
addition of 3rd floor master suite & remodel of 2nd floor kitchen, bath. guestroom @ 1st floor. | $250,000 |
| Nov 29, 2018 | Completed final sign-off Nov 2020 | 307 03rd Av | Pacific Engineering & Construction Inc. | seismic strengthening measures to comply with sf soft story ordinance. design per iebc app a4 (residential)Details
seismic strengthening measures to comply with sf soft story ordinance. design per iebc app a4 (residential) | $100,000 |
| Oct 9, 2018 | Completed final sign-off Jan 2022 | 230 Oak St | Steelcore Builders Inc | ref 201608054353 structural work onlyDetails
ref 201608054353 structural work only | |
| Oct 4, 2018 | Completed final sign-off May 2019 | 254 Moreland St | Blue Mountain Construction Services Inc | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. | $40,000 |
| Sep 14, 2018 | Completed final sign-off Jul 2020 | 3476 19th St | Pacific Engineering & Construction Inc. | commercial soft-story retrofit to comply w/ sf ordinance design per 2016 iebc appendix a-4. ref residential soft story 201809140221. maher n/aDetails
commercial soft-story retrofit to comply w/ sf ordinance design per 2016 iebc appendix a-4. ref residential soft story 201809140221. maher n/a | $75,000 |
| Sep 14, 2018 | Completed final sign-off Jul 2020 | 793 Valencia St | Pacific Engineering & Construction Inc. | residedential soft-story retrofit to comply w/ sf ordinance design per iebc appendix a-4. ref commercial soft story 201809140222. maher n/aDetails
residedential soft-story retrofit to comply w/ sf ordinance design per iebc appendix a-4. ref commercial soft story 201809140222. maher n/a | $75,000 |
| Aug 8, 2018 | Completed final sign-off Sep 2021 | 1822 42nd Av | addition of wall & entry door at 1st fl. remodel of kitchen, bathroom & powder room at 2nd fl. removal and addition of windows on side and rear of building.Details
addition of wall & entry door at 1st fl. remodel of kitchen, bathroom & powder room at 2nd fl. removal and addition of windows on side and rear of building. | $100,000 | |
| May 16, 2018 | Completed final sign-off Jan 2019 | 2090 Vallejo St | Upcycle Builders Inc. | interior renovation at all floors and minor reconfigurations for new owner move-in. maher naDetails
interior renovation at all floors and minor reconfigurations for new owner move-in. maher na | $124,841 |
| May 2, 2018 | Completed final sign-off Feb 2019 | 164 Bemis St | Blue Mountain Construction Services Inc | revision to 201609157824, change to footingDetails
revision to 201609157824, change to footing | |
| Apr 30, 2018 | Completed final sign-off Jun 2018 | 855 Howard St | Source Planning And Construction Inc | basement, 1st & 2nd flr - demo only - interior demo only ab-107. disabled access will be under tiDetails
basement, 1st & 2nd flr - demo only - interior demo only ab-107. disabled access will be under ti | $72,000 |
| Feb 14, 2018 | Expired or cancelled cancelled Jan 2026 | 2080 Gough St | revision to t201609157853. reduction of scope 2nd fl. building split level work strengthening 2nd fl walls incorrectly included. no req for soft story ordDetails
revision to t201609157853. reduction of scope 2nd fl. building split level work strengthening 2nd fl walls incorrectly included. no req for soft story ord | ||
| Feb 9, 2018 | Completed final sign-off Oct 2019 | 929 Ashbury St | removal of existing planters & replace with retaining walls and driveway to match existing. no work on back of house. re-paving less than 200 sq. ft. of driveway. (145 sq ft prevaving)Details
removal of existing planters & replace with retaining walls and driveway to match existing. no work on back of house. re-paving less than 200 sq. ft. of driveway. (145 sq ft prevaving) | $25,000 | |
| Jan 16, 2018 | Completed final sign-off Jul 2019 | 2535 Lyon St | Noa Construction Llc | interior remodel o1st, 2nd, 3 and 4th fl and removal of interior stair in unit 1 connecting 1st and 2nd floors. exterior work to include new windows at rear of buildingDetails
interior remodel o1st, 2nd, 3 and 4th fl and removal of interior stair in unit 1 connecting 1st and 2nd floors. exterior work to include new windows at rear of building | $250,000 |
| Dec 22, 2017 | Never finaled issued Dec 2017, no final | 2940 Lyon St | Jame L Kelly Construction | revision to pa #201710262355 - structural revision - remove & replace substandard framing at 2nd floor bay windows in kind. n/a maher ordinanceDetails
revision to pa #201710262355 - structural revision - remove & replace substandard framing at 2nd floor bay windows in kind. n/a maher ordinance | $5,000 |
| Nov 15, 2017 | Completed final sign-off Apr 2019 | 793 Clayton St | Steelcore Builders Inc | soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4 | $55,000 |
| Oct 20, 2017 | Completed final sign-off Sep 2019 | 1133 Fell St | Steelcore Builders Inc | seismic strenthening measure to comply with sf soft story ordinance 2016 cebc appendix a4.Details
seismic strenthening measure to comply with sf soft story ordinance 2016 cebc appendix a4. | $50,000 |
| Oct 20, 2017 | Completed final sign-off Dec 2019 | 1671 Lombard St | Steelcore Builders Inc, Sft Construction Corp | seismic strengthening measure to comply with sf soft story ordinance 2016 cebc appendix a4.Details
seismic strengthening measure to comply with sf soft story ordinance 2016 cebc appendix a4. | $70,000 |
| Oct 10, 2017 | Completed final sign-off May 2018 | 2630 Mission St | Embree Construction Group Inc | construction and installation of elevator & shaft between basemant & 1st floor of existing building. change of use from retail to dental clinic under permit #2017-1010-0775.Details
construction and installation of elevator & shaft between basemant & 1st floor of existing building. change of use from retail to dental clinic under permit #2017-1010-0775. | $80,000 |
| Sep 15, 2017 | Completed final sign-off Aug 2019 | 12 Rausch St | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $55,000 | |
| Sep 15, 2017 | Completed final sign-off Jul 2019 | 350 Arbor St | Blue Mountain Construction Services Inc | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $50,000 |
| Sep 15, 2017 | Completed final sign-off May 2019 | 112 Addison St | Blue Mountain Construction Services Inc | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $30,000 |
| Sep 15, 2017 | Completed final sign-off Aug 2019 | 1155 Howard St | soft story retrofit to comply with sf city ordinance per sfebc chapter 4d: 2016 cebc appendix a-4, plywood shear walls have been added or strenghthend & concrete foundation have been added where requiredDetails
soft story retrofit to comply with sf city ordinance per sfebc chapter 4d: 2016 cebc appendix a-4, plywood shear walls have been added or strenghthend & concrete foundation have been added where required | $91,000 | |
| Aug 30, 2017 | Completed final sign-off Oct 2018 | 420 Mason St | Arroyo Realty & Development Llc | demo int. non-struct. walls, lobby floor section for accessible entrance, lobby finishes, (e) service bars, (e) bathrm fixtures, finishes & (e) entry slide in preparation of new interior alteration. new basement work includes new lounge and restaurant seating, new bowling lanes, & int. finishes,Details
demo int. non-struct. walls, lobby floor section for accessible entrance, lobby finishes, (e) service bars, (e) bathrm fixtures, finishes & (e) entry slide in preparation of new interior alteration. new basement work includes new lounge and restaurant seating, new bowling lanes, & int. finishes, | $800,000 |
| Aug 25, 2017 | Completed final sign-off Aug 2019 | 1801 Hayes St | Steelcore Builders Inc | soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4. plywood shear walls are being added for lateral resistance. n/a for maherDetails
soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4. plywood shear walls are being added for lateral resistance. n/a for maher | $90,000 |
| Aug 25, 2017 | Completed final sign-off Feb 2020 | 1832 Franklin St | Steelcore Builders Inc | soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4. plywood shear walls are being added for lateral resistance with simpson special steel moment frames at garage concrete fdns where needed. n/a for maherDetails
soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4. plywood shear walls are being added for lateral resistance with simpson special steel moment frames at garage concrete fdns where needed. n/a for maher | $85,000 |
| Aug 15, 2017 | Completed final sign-off Oct 2019 | 20 Parker Av | Steelcore Builders Inc | soft story retrofit per sfebc chapter 4d per 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d per 2016 cebc appendix a-4 | $83,300 |
| Jun 20, 2017 | Expired or cancelled withdrawn May 2019 | 2760 Polk St | soft story retrofit per sfbc chapter 4b per 2016 cebc appendix a-4.Details
soft story retrofit per sfbc chapter 4b per 2016 cebc appendix a-4. | $80,000 | |
| Jun 14, 2017 | Completed final sign-off Jun 2020 | 929 Ashbury St | revision to 201705166719: new footing, sister to lvls. minor change to door jam in master bedrm on 3rd fl, non-load bearing.Details
revision to 201705166719: new footing, sister to lvls. minor change to door jam in master bedrm on 3rd fl, non-load bearing. | ||
| Jun 14, 2017 | Expired or cancelled withdrawn Dec 2017 | 550 Washington St | Northern Sun Associates | interior tenant improvement to (e) restaurant and adjacent retail space. (e) commercial kitchen to remain. scope includes new partitions, ceilings, finishes, build out bar, new dumbwaiter, minor structural work, mep under separate permit. no change build height or area, no exterior work. *maher:n/a*Details
interior tenant improvement to (e) restaurant and adjacent retail space. (e) commercial kitchen to remain. scope includes new partitions, ceilings, finishes, build out bar, new dumbwaiter, minor structural work, mep under separate permit. no change build height or area, no exterior work. *maher:n/a* | $515,000 |
| Jun 14, 2017 | Completed final sign-off Nov 2019 | 1642 Larkin St | Steelcore Builders Inc | soft story retrofit to comply w/sfebc chapter 4d. plywood shear walls & steel smfs added @ ground floor. conc. ftgs added as needed. 2016 cebc appendix a-4.Details
soft story retrofit to comply w/sfebc chapter 4d. plywood shear walls & steel smfs added @ ground floor. conc. ftgs added as needed. 2016 cebc appendix a-4. | $77,000 |
| Jun 7, 2017 | Completed final sign-off Dec 2019 | 495 03rd Av | Beyond The Horizon Construction | soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, add plywood shear walls & steel ordinary moment frames @ ground floor. add conc. footing as needed.Details
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, add plywood shear walls & steel ordinary moment frames @ ground floor. add conc. footing as needed. | $88,000 |
| Jun 7, 2017 | Completed final sign-off Nov 2019 | 3225 Laguna St | Mulhall Construction Inc. | soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, add plywood shear walls & steel ordinary moment frames @ ground floor. add concrete footing as needed.Details
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, add plywood shear walls & steel ordinary moment frames @ ground floor. add concrete footing as needed. | $86,500 |
| May 18, 2017 | Completed final sign-off Nov 2019 | 933 Dartmouth St | remove 2 load bearing walls at 2nd floor; 1st floor remove load bearing wallsDetails
remove 2 load bearing walls at 2nd floor; 1st floor remove load bearing walls | $5,000 | |
| May 18, 2017 | Completed final sign-off Nov 2019 | 933 Dartmouth St | replace 4 windows (2 of different size) & replace 2 sliding doors back of houseDetails
replace 4 windows (2 of different size) & replace 2 sliding doors back of house | $3,000 | |
| Apr 25, 2017 | Completed final sign-off Jul 2017 | 431 Noe St | Steelcore Builders Inc | front bldg - revision to 201611303801 - field revision to structural elements of existing permit.Details
front bldg - revision to 201611303801 - field revision to structural elements of existing permit. | $5,000 |
| Apr 18, 2017 | Completed final sign-off Jul 2018 | 555 Pine St | Building Services/System Maintenance Inc | architectural & electrical, plumbing & mechanical work to start preparing for a new it equipment room, including ada workDetails
architectural & electrical, plumbing & mechanical work to start preparing for a new it equipment room, including ada work | $139,000 |
| Apr 18, 2017 | Completed final sign-off May 2018 | 611 Folsom St | American Incorporated | freight elevator modernizationDetails
freight elevator modernization | $100,000 |
| Mar 7, 2017 | Never finaled issued Mar 2017, no final | 1275 02nd Av | Acme Builders | unit #2: removal of bearing wall between kitchen and hallway. stregthen joist above. add beams below,Details
unit #2: removal of bearing wall between kitchen and hallway. stregthen joist above. add beams below, | $13,750 |
| Mar 1, 2017 | Never finaled issued Mar 2017, no final | 1175 Francisco St | Acme Builders | 3rd floor unit #10: alterations remove wall, some kitchen workDetails
3rd floor unit #10: alterations remove wall, some kitchen work | $15,000 |
| Jan 20, 2017 | Never finaled issued Jan 2017, no final | 45 Henry St | William Gregory Clause | voluntary seismic upgrade at garage level for open garage front only.Details
voluntary seismic upgrade at garage level for open garage front only. | $12,000 |
| Jan 18, 2017 | Completed final sign-off Apr 2018 | 1360 Taylor St | seismic strengthening measures to comply with sf soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4.Details
seismic strengthening measures to comply with sf soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. | $161,730 | |
| Dec 1, 2016 | Completed final sign-off Mar 2017 | 165 Peralta Av | retrofit to sf soft story ord per sfbc ch34b, design per iebc appx a4Details
retrofit to sf soft story ord per sfbc ch34b, design per iebc appx a4 | $42,000 | |
| Nov 8, 2016 | Never finaled issued Nov 2016, no final | 101 Henry Adams St | C C I Commercial Construction & Improv | slab on grade related to app#201608034050 maher naDetails
slab on grade related to app#201608034050 maher na | $20,000 |
| Oct 21, 2016 | Completed final sign-off Oct 2017 | 2665 Chestnut St | A M Rocca Inc. | soft story retrofit per sfbc chapter 34b 2012 iebc appendix a-4. maher n/aDetails
soft story retrofit per sfbc chapter 34b 2012 iebc appendix a-4. maher n/a | $53,500 |
| Oct 18, 2016 | Completed final sign-off Apr 2017 | 333 Irving St | G-Max Construction | voluntary partial structural strengthening measures of the ground floor level. not intended to comply w/full seismic strengthening criteria. removal & remdeiation of brick veneer.Details
voluntary partial structural strengthening measures of the ground floor level. not intended to comply w/full seismic strengthening criteria. removal & remdeiation of brick veneer. | $40,000 |
| Sep 30, 2016 | Never finaled issued Jan 2017, no final | 2051 Broadway | Jetton Construction | interior remodel of two dwelling units uncluding voluntary selective structural strengthening at garage (ground) level & new den & full bathroom. new stair connected to 2nd floor unit to ground floor. replace bedroom windows on 2nd & 3rd flr unit. kitchen & 2 bathrooms remodel on 2nd & 3rd flr unitsDetails
interior remodel of two dwelling units uncluding voluntary selective structural strengthening at garage (ground) level & new den & full bathroom. new stair connected to 2nd floor unit to ground floor. replace bedroom windows on 2nd & 3rd flr unit. kitchen & 2 bathrooms remodel on 2nd & 3rd flr units | $800,000 |
| Sep 12, 2016 | Completed final sign-off Dec 2017 | 1 Cabrillo St | soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. work at ground level to add lateral resistance.Details
soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. work at ground level to add lateral resistance. | $117,000 | |
| Sep 8, 2016 | Expired or cancelled expired Dec 2020 | 2566 Washington St | Pagac & Co | soft story retrofit per sfbc chapter 34b engineering criteria 2012 iebc appendix a-4Details
soft story retrofit per sfbc chapter 34b engineering criteria 2012 iebc appendix a-4 | $37,000 |
| Aug 24, 2016 | Completed final sign-off Aug 2017 | 494 29th Av | Bai Construction | seismic strengthening meausres to comply with the sf soft story ordinance design per iebc appendiex a4Details
seismic strengthening meausres to comply with the sf soft story ordinance design per iebc appendiex a4 | $97,386 |
| Aug 5, 2016 | Completed final sign-off Jan 2022 | 230 Oak St | Steelcore Builders Inc | seismic stregthening measure to comply with the sf soft story ordinance. design per iebc appendix a4. maher naDetails
seismic stregthening measure to comply with the sf soft story ordinance. design per iebc appendix a4. maher na | $171,100 |
| Aug 4, 2016 | Completed final sign-off Jan 2024 | 211 Liberty St | A W Construction Company | soft stroy seismic retrofit per 2012 iebc appendix a-4Details
soft stroy seismic retrofit per 2012 iebc appendix a-4 | $99,000 |
| Jul 27, 2016 | Completed final sign-off Apr 2018 | 70 Sea View Tr | remodel south facade to incl new wood siding,stucco,windows,doors,extended deck& landscaping.new backsplash tile&lite in kitn&family rm.remodel 2/fl bath.propose deck ext not to exceed10'on grade.all st face windows&doors to wood/alum clad.no bldg extension.Details
remodel south facade to incl new wood siding,stucco,windows,doors,extended deck& landscaping.new backsplash tile&lite in kitn&family rm.remodel 2/fl bath.propose deck ext not to exceed10'on grade.all st face windows&doors to wood/alum clad.no bldg extension. | $80,000 | |
| May 25, 2016 | Expired or cancelled expired Sep 2019 | 112 Woodland Av | Stokely Marcus Construction Inc | replace existing perimeter foundationDetails
replace existing perimeter foundation | $60,000 |
| May 12, 2016 | Completed final sign-off Mar 2017 | 1511 Dolores St | revision to ref pa 2015 1210 4734: omit steel beams, reframe rear wall & roof of room at rear. repair & refinish stair as necessary. add warm floors at rear room & bathDetails
revision to ref pa 2015 1210 4734: omit steel beams, reframe rear wall & roof of room at rear. repair & refinish stair as necessary. add warm floors at rear room & bath | ||
| Apr 11, 2016 | Expired or cancelled cancelled Mar 2018 | 570 Indiana St | accessary use(resididential) within wood shop nsr. add dwelling. n/a for maher ordinance no. 155-13.Details
accessary use(resididential) within wood shop nsr. add dwelling. n/a for maher ordinance no. 155-13. | $9,000 | |
| Feb 3, 2016 | Completed final sign-off Aug 2016 | 1424 Filbert St | Steelcore Builders Inc | soft story retrofit per sfbc chapter 34b 2012 iebc appendix a-4. maher naDetails
soft story retrofit per sfbc chapter 34b 2012 iebc appendix a-4. maher na | $60,000 |
| Oct 7, 2015 | Completed final sign-off Jan 2016 | 3129 Folsom St | Steelcore Builders Inc | soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. epoxy anchors, install simpson clips, construct sheerwalls, construct grade beams for sheerwalls, install replacement sheetrock.Details
soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. epoxy anchors, install simpson clips, construct sheerwalls, construct grade beams for sheerwalls, install replacement sheetrock. | $81,040 |
| Mar 12, 2015 | Completed final sign-off Jul 2015 | 862 14th St | soft story programDetails
soft story program | $25,000 | |
| Feb 25, 2015 | Completed final sign-off Jun 2015 | 343 21st Av | San Francisco Earthquake Retrofitting | soft story seismic stregthening. new shearwall and anchors at perimeter and transverse walls. 2 new momentframes . 4 new grade beams. 2012 iebc appendix a-4Details
soft story seismic stregthening. new shearwall and anchors at perimeter and transverse walls. 2 new momentframes . 4 new grade beams. 2012 iebc appendix a-4 | $60,200 |
| Jan 15, 2015 | Completed final sign-off Feb 2018 | 542 Pennsylvania Av | Capron Construction, Takoma Carpentry & Remodeling | hori & vert addition. remodel (e) struct (n) construction to include pop-out @ rear & addition of master suite @ a (n) 3rd fl. footprint of bldg to remain unchanged. front facade material to be changed from (e) stucco to fiber reinforced concrete panels.Details
hori & vert addition. remodel (e) struct (n) construction to include pop-out @ rear & addition of master suite @ a (n) 3rd fl. footprint of bldg to remain unchanged. front facade material to be changed from (e) stucco to fiber reinforced concrete panels. | $600,000 |
| Dec 22, 2014 | Completed final sign-off Apr 2015 | 133 Alpine Tr | Trim Fit Constr. - O'reilly Engineering | remodel existing kitc hen, reduce 1st fl full bath to 1/2 bath, move full bath to 2nd fl, remodel master bath, reconfigure closets, update electrical.Details
remodel existing kitc hen, reduce 1st fl full bath to 1/2 bath, move full bath to 2nd fl, remodel master bath, reconfigure closets, update electrical. | $75,000 |
| Sep 8, 2014 | Completed final sign-off Dec 2014 | 444 De Haro St | Premier Structures Inc | infill of existing openings in slab located on ground floor. revision to pa#201405145691. n/a ordinance #155-13Details
infill of existing openings in slab located on ground floor. revision to pa#201405145691. n/a ordinance #155-13 | $10,000 |
| Aug 27, 2014 | Completed final sign-off May 2015 | 2245 Larkin St | soft story retrofit. maher n/aDetails
soft story retrofit. maher n/a | $10,000 | |
| Aug 12, 2014 | Completed final sign-off Jan 2015 | 139 Corbett Av | Preservation Trust Builder | remodel bath and kitchen. remove wall between dining and kitchen. install recessed lights in living room and dining room at top level, 2nd flDetails
remodel bath and kitchen. remove wall between dining and kitchen. install recessed lights in living room and dining room at top level, 2nd fl | $60,000 |
| Aug 8, 2014 | Completed final sign-off Apr 2015 | 215 Claremont Bl | revision appl. #2014.0613.8322. change structural beam type in rear of house. no change in use of space.Details
revision appl. #2014.0613.8322. change structural beam type in rear of house. no change in use of space. | $500 | |
| Jul 23, 2014 | Completed final sign-off Nov 2015 | 1692 Haight St | Jame L Kelly Construction | structural revisions to permit 201305318358, sheets s1.2, s2.0,s2.1Details
structural revisions to permit 201305318358, sheets s1.2, s2.0,s2.1 | $20,000 |
| Jul 16, 2014 | Completed final sign-off Feb 2015 | 39 Paramount Tr | E B W Builders Inc | revision to existing permit 201407010224. add beams in family roomDetails
revision to existing permit 201407010224. add beams in family room | $1,500 |
| May 14, 2014 | Completed final sign-off May 2015 | 444 De Haro St | Premier Structures Inc | new a.d.a. ramp addition, no future hvac, electrical of fire alarm required, sprinkler system under seperate permit. n/a ordinance #155-13.Details
new a.d.a. ramp addition, no future hvac, electrical of fire alarm required, sprinkler system under seperate permit. n/a ordinance #155-13. | $80,000 |
| Nov 8, 2013 | Completed final sign-off Feb 2016 | 1151 Castro St | Genuine Construction Inc. | proposed proj is a structural redesign of a previously approved proj. no changes to the previously approved proj 201305227661 arch design are proposed. jyasf has performed a complete structural design based on the current and proposed conditions at the site & those recommendations are described inDetails
proposed proj is a structural redesign of a previously approved proj. no changes to the previously approved proj 201305227661 arch design are proposed. jyasf has performed a complete structural design based on the current and proposed conditions at the site & those recommendations are described in | $30,000 |
| Oct 3, 2013 | Completed final sign-off Aug 2015 | 2320 Sutter St | Thompson Suskind L P | to erect 3 stories, no basement, medical office. (rear bldg).Details
to erect 3 stories, no basement, medical office. (rear bldg). | $600,000 |
| Mar 6, 2013 | Completed final sign-off Oct 2013 | 505 Beach St | Tritek Construction Inc., European Enterprises | new restaurant on basement level, raise interior floor to make level, new framing, plumbing, electrical, mechanical for interior. new outdoor dining area and excavation of existing soil at north east corner. new civil and landscape work for outdoor dining, sewer lateral tie in. new storefront,Details
new restaurant on basement level, raise interior floor to make level, new framing, plumbing, electrical, mechanical for interior. new outdoor dining area and excavation of existing soil at north east corner. new civil and landscape work for outdoor dining, sewer lateral tie in. new storefront, | $800,000 |
| Dec 21, 2012 | Completed final sign-off Nov 2014 | 105 Hoffman Av | Van Der Sterre Construction | add garage & bedrooms to an (e) basement & infill under an (e) deck. raise (e) 1st floor approx 2'-0" to accomodate the new garage slope & new stair to connect the (e) & new floors. work also includes add bath & laundry.Details
add garage & bedrooms to an (e) basement & infill under an (e) deck. raise (e) 1st floor approx 2'-0" to accomodate the new garage slope & new stair to connect the (e) & new floors. work also includes add bath & laundry. | $150,000 |
| Aug 14, 2012 | Completed final sign-off Mar 2014 | 101 Williams Av | Deca Construction | interior tenant improvement, domolitin select walls, windows, doors. remove 1119 sq ft slab, replace with new. attach new ducts to existing air handlers. service space heaters. new stair, some structural repairs, relocate and new lighting. mep & lighting under seperate permit.Details
interior tenant improvement, domolitin select walls, windows, doors. remove 1119 sq ft slab, replace with new. attach new ducts to existing air handlers. service space heaters. new stair, some structural repairs, relocate and new lighting. mep & lighting under seperate permit. | $250,000 |
| Nov 23, 2011 | Completed final sign-off Nov 2012 | 1100 26th St | Artcore Construction | building 'f' - voluntary seismic upgrade of building at army street mini storageDetails
building 'f' - voluntary seismic upgrade of building at army street mini storage | $40,000 |
| Nov 7, 2011 | Completed final sign-off Nov 2012 | 1100 26th St | Artcore Construction | building 'c'- voluntary seismic upgrade of building at army street mini storageDetails
building 'c'- voluntary seismic upgrade of building at army street mini storage | $40,000 |
| Oct 24, 2011 | Completed final sign-off Feb 2013 | 66 Potomac St | Design Line Construction | revision to pa# 2010/05/14/2529-s/r3. revisions include designation of new 3rd floor level. interior layout, structural revisions & clarification of total number of stories from (e)2 stories & basement/garage to 3 stories & basement/garageDetails
revision to pa# 2010/05/14/2529-s/r3. revisions include designation of new 3rd floor level. interior layout, structural revisions & clarification of total number of stories from (e)2 stories & basement/garage to 3 stories & basement/garage | |
| Apr 29, 2011 | Completed final sign-off Aug 2011 | 1 Montgomery St | Swinerton Builders | sidewalk - revision to pa#201011124800, replacement of deteriorated concrete slab and handicap ramp at sidewalk/basement roofDetails
sidewalk - revision to pa#201011124800, replacement of deteriorated concrete slab and handicap ramp at sidewalk/basement roof | $30,000 |