Block 3704, lot 021
972 Mission St
- City’s use
- Commercial Retail
- Built
- 1925
- Stories
- 5
- Units
- 2
- Rooms
- 9 bathrooms
- Building
- 60,000 sq ft
- Lot
- 12,000 sq ft
- Zoning
- C3G
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
28 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 30, 2025 | Completed final sign-off May 2025 | 972 Mission St | Innovative Technologies | installation of smoke detector in new electrical room in the basementDetails
installation of smoke detector in new electrical room in the basement | $5,000 |
| Apr 25, 2024 | Completed final sign-off May 2025 | 972 Mission St | Modern Construction Inc | construction of (n) electrical utlitly room located at basement. separate mep & fire/life safety permits will need to be obtained.Details
construction of (n) electrical utlitly room located at basement. separate mep & fire/life safety permits will need to be obtained. | $15,000 |
| Dec 29, 2023 | Completed final sign-off Feb 2024 | 972 Mission St | Modern Construction Inc | renew pa#201909252719 and pa#201912200109 and 202205033442 for final inspection all work complete.Details
renew pa#201909252719 and pa#201912200109 and 202205033442 for final inspection all work complete. | |
| Nov 28, 2022 | Completed final sign-off Feb 2024 | 972 Mission St | Innovative Technologies | provide elevator recall for elevator upgrade. installation of smoke detectors in elevator lobbies on each floor.Details
provide elevator recall for elevator upgrade. installation of smoke detectors in elevator lobbies on each floor. | $2,000 |
| May 31, 2022 | Completed final sign-off Aug 2022 | 972 Mission St | North Star Plumbing & Fire Protection | elevator lobby: adding 14 sprinkler heads.Details
elevator lobby: adding 14 sprinkler heads. | $12,800 |
| May 3, 2022 | Expired or cancelled expired Feb 2024 | 972 Mission St | Modern Construction Inc | lobby:add title 24 to permit application 201912200109. electrical compliance.Details
lobby:add title 24 to permit application 201912200109. electrical compliance. | |
| Sep 23, 2021 | Completed final sign-off Nov 2021 | 972 Mission St | to abate planning code violation 2020002839enf to 1. legalize office use on 5th fl (10, 107 gsf) 2. document light manufacturing uses on floors 1-3 are currently vacant, and 3. document continued use of 4th fl as light manufacturing. no work proposedDetails
to abate planning code violation 2020002839enf to 1. legalize office use on 5th fl (10, 107 gsf) 2. document light manufacturing uses on floors 1-3 are currently vacant, and 3. document continued use of 4th fl as light manufacturing. no work proposed | ||
| Dec 23, 2020 | Never finaled issued Jun 2021, no final | 972 Mission St | R & S Erection Of S F Inc | new security gates/grilles at storefront & mezzanine windows of ground floor tenant space.Details
new security gates/grilles at storefront & mezzanine windows of ground floor tenant space. | $7,500 |
| Dec 20, 2019 | Expired or cancelled expired Feb 2024 | 972 Mission St | Modern Construction Inc | barrier removal project to include: removal of elevator and enlargement of elevator shaft in preparation for new elevator, work also includes new finishes and lighting at elevator lobby, mep, title 24 energy calcs, fire sprinklers and life safety under separate permitDetails
barrier removal project to include: removal of elevator and enlargement of elevator shaft in preparation for new elevator, work also includes new finishes and lighting at elevator lobby, mep, title 24 energy calcs, fire sprinklers and life safety under separate permit | $100,000 |
| Sep 25, 2019 | Expired or cancelled expired Feb 2024 | 972 Mission St | Modern Construction Inc | barrier removal: replacement of (e) elevator with new larger elevator, work also includes new elevator machine room penthouse, to replace (e) mep, title 24 enerry calc, fire sprinklers, life safety, & elevator construction under separate permits: 201912200109.Details
barrier removal: replacement of (e) elevator with new larger elevator, work also includes new elevator machine room penthouse, to replace (e) mep, title 24 enerry calc, fire sprinklers, life safety, & elevator construction under separate permits: 201912200109. | $80,000 |
| Jun 14, 2019 | Never finaled issued Jun 2019, no final | 972 Mission St | street spaceDetails
street space | ||
| Jun 5, 2019 | Never finaled issued Jun 2019, no final | 972 Mission St | street spaceDetails
street space | ||
| Dec 13, 2018 | Completed final sign-off Jan 2019 | 972 Mission St | Innovative Technologies | correct (3) duct smoke detectors to the fire alarm systemDetails
correct (3) duct smoke detectors to the fire alarm system | $1,000 |
| Oct 30, 2018 | Completed final sign-off Jan 2019 | 972 Mission St | rev to pa# 201808157412; changes in ligting and power distribution, add 1 non-full height partitionDetails
rev to pa# 201808157412; changes in ligting and power distribution, add 1 non-full height partition | ||
| Oct 26, 2018 | Completed final sign-off Jan 2019 | 972 Mission St | Innovative Technologies | installation of 14 new notification devices. 12 strobes, 2 horn-strobes. all work on the 5th floor.Details
installation of 14 new notification devices. 12 strobes, 2 horn-strobes. all work on the 5th floor. | $6,500 |
| Oct 2, 2018 | Completed final sign-off Oct 2018 | 972 Mission St | Project Contractor Inc | ref pa# 201808157412: modification of fire sprinkler system per t.i. total added 10 new, 9 relocated. (5th fl)Details
ref pa# 201808157412: modification of fire sprinkler system per t.i. total added 10 new, 9 relocated. (5th fl) | $10,000 |
| Aug 15, 2018 | Completed final sign-off Jan 2019 | 972 Mission St | Modern Construction Inc | 5/f -demolish door, sidelite and portion of wall, construct new walls, doors,sidelites, ada case work, power outlet and light fixtures, extend kitchen with sink and dishwasher, install 3 hvac unitsDetails
5/f -demolish door, sidelite and portion of wall, construct new walls, doors,sidelites, ada case work, power outlet and light fixtures, extend kitchen with sink and dishwasher, install 3 hvac units | $350,000 |
| Nov 7, 2017 | Never finaled issued Nov 2017, no final | 972 Mission St | Econ Glass Company | street spaceDetails
street space | |
| Oct 24, 2017 | Completed final sign-off Aug 2019 | 972 Mission St | Econ Glass Company | replace existing steel shash windows in kind due to rust and deterioration with double insulated glazing. no interior workDetails
replace existing steel shash windows in kind due to rust and deterioration with double insulated glazing. no interior work | $60,000 |
| Jul 11, 2017 | Expired or cancelled cancelled Jan 2026 | 972 Mission St | new concrete reinforced slab for new sidewalk door, approx 50 sq ft sidewalk subbasement maher not reqDetails
new concrete reinforced slab for new sidewalk door, approx 50 sq ft sidewalk subbasement maher not req | $5,000 | |
| Aug 18, 2016 | Completed final sign-off Nov 2016 | 972 Mission St | Yes Construction | 5th floor: title 24 restroom area. ref pa 201608034080 maher na; building is type iii-b construction; instead of i-b.Details
5th floor: title 24 restroom area. ref pa 201608034080 maher na; building is type iii-b construction; instead of i-b. | $2,500 |
| Aug 3, 2016 | Completed final sign-off Nov 2016 | 972 Mission St | Yes Construction | 5th floor level only - barrier removal, remodel exisitng toilets & lunch room area & janitorial closet, kitchenette. n/a maher ordinanceDetails
5th floor level only - barrier removal, remodel exisitng toilets & lunch room area & janitorial closet, kitchenette. n/a maher ordinance | $40,000 |
| Oct 27, 2015 | Expired or cancelled cancelled Jan 2026 | 972 Mission St | replace (e) windows at front facade (e) steel shash to be replace with aluminum sections in kind due to rust & deteriorationDetails
replace (e) windows at front facade (e) steel shash to be replace with aluminum sections in kind due to rust & deterioration | $20,000 | |
| Jan 9, 2014 | Completed final sign-off Apr 2014 | 972 Mission St | Innovative Technologies | elevator recall system to be installed. excavation <50 cu.yd.per 2013 nfpa 13 and asme a17.1. compliance with ordinance #155-13 not required.Details
elevator recall system to be installed. excavation <50 cu.yd.per 2013 nfpa 13 and asme a17.1. compliance with ordinance #155-13 not required. | $10,000 |
| Oct 14, 2011 | Completed final sign-off Oct 2011 | 972 Mission St | Diamond Home Restoration | demolition only. extg occupancy to be addressed under seperate pemit per ab-017Details
demolition only. extg occupancy to be addressed under seperate pemit per ab-017 | $10,000 |
| Oct 20, 2008 | Expired or cancelled cancelled Aug 2022 | 972 Mission St | rmove extg steel windows and doors and installing new aluminum wndw in the same location. from 2nd through 5th floor on mission. visible from the streetDetails
rmove extg steel windows and doors and installing new aluminum wndw in the same location. from 2nd through 5th floor on mission. visible from the street | $106,000 | |
| Jan 31, 2001 | Expired or cancelled expired Mar 2002 | 972 Mission St | Richlen Construction | hvac sprinkler , electrical, construction - 2nd floor, 200009190947Details
hvac sprinkler , electrical, construction - 2nd floor, 200009190947 | $90,000 |
| Sep 19, 2000 | Expired or cancelled expired Sep 2001 | 972 Mission St | interior renovation of the 2nd floor/new office partitionDetails
interior renovation of the 2nd floor/new office partition | $107,000 |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.