Permit GraphShortlistSan Francisco building permits since 2000

Cortland Morgan

License
C25519
Architect
About the California Architects Board
Look the license up with the state (Architects Board)
Listed as
architect, authorized agent-others, pmt consultant/expediter
Firm
Cortland Morgan Arch.
Based in
Arlington
On San Francisco permits
Dec 2004 to Jul 2026

55 permits since 2000 (architect on 52 permits, pmt consultant/expediter on 2 permits, authorized agent-others on 1 permit): 37 completed, 3 in progress, 11 never finaled, 4 expired or cancelled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records

Worked with

Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.

Contractors
Gci, Inc (3), Crane Construction Company Inc. (2), J C O R Inc (2), Paradigm General Contractors (2), Richlen Construction (2), Teel Construction Inc. (2), Terra Nova Industries (2), A & E Construction Co, A2z Builders Inc, Alain Hirsch Construction Corp, Bcci Construction Company, Brodson Construction Inc, Construction One Inc., Embree Construction Group Inc, Fisher Development Inc, Hardesty And Associates, J Palmer Construction Inc, James Agresta Carpentry, James M Barb Construction Co, Jason Barber Construction Llc, Jkt Construction Inc Dba Corcon, Peacock Construction, R 3 Builders Inc., R T Stevens Construction Inc, Ryan Contractors Inc, Sd Design Construction Corp., Shawmut Woodworking & Supply Inc, T D S Commercial Constr. Inc., Vortex Industries Inc, W. Wong Construction Co. Inc., X S Industries Inc
Architects
Janet Crane
Engineers
Daniel Conrad, Donald Spencer, Jeff Elmendorf, Jillian P. Moritz, Matthew Case, Michael Howe, Pak Hui, Peter A. Leptuch, Richard Wells, Thomas Castle, Thomas Clapp
Authorized agents
James Dyer (2), Faisal Elhalis, Junjian Lao

Where they worked

One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jul 29, 2026In progress
issued Sep 2026
274 King StJ C O R Incti of a retail. mech & electrical upgrades. no structural work.
Details
Permit
202607295748
Permit issued
Sep 29, 2026

ti of a retail. mech & electrical upgrades. no structural work.

Open the permit page

$50,000
Jul 17, 2026In progress
issued Jul 2026
101 California StBcci Construction Company27th floor: renovation of the existing break room layout. 28th floor: new furniture and finishes throughout.
Details
Permit
202607175188
Permit issued
Jul 23, 2026

27th floor: renovation of the existing break room layout. 28th floor: new furniture and finishes throughout.

Open the permit page

$751,283
Feb 21, 2024Completed
final sign-off May 2024
2300 16th StJ C O R Incspace #255: tenant improvement. (n) hair color, hair care, beauty, nail supply. (this is not a salon service)
Details
Permit
202402216224
Permit issued
Mar 18, 2024
Final sign-off
May 9, 2024

space #255: tenant improvement. (n) hair color, hair care, beauty, nail supply. (this is not a salon service)

Open the permit page

$111,000
Nov 27, 2023In progress
issued Jan 2024
3998 18th StSd Design Construction Corp.interior alterations only: replacement of (e) ceiling; (n) subflooring w/ slab infill work; (n) flooring; (n) finishes; minor repair/replacement of (e) duct system; installation of coolers/freezers; bring unise toilet from ada to requirements; provide (e) electrical panel with (n) service;
Details
Permit
202311271433
Permit issued
Jan 12, 2024

interior alterations only: replacement of (e) ceiling; (n) subflooring w/ slab infill work; (n) flooring; (n) finishes; minor repair/replacement of (e) duct system; installation of coolers/freezers; bring unise toilet from ada to requirements; provide (e) electrical panel with (n) service;

Open the permit page

$225,000
Jun 20, 2023Completed
final sign-off Nov 2023
3251 20th AvJason Barber Construction Llc#155: interior alteration to an (e) tenant space to house retail occup. scope includes new finishes and fixtures, while reusing the (e) walls, stock area, and (1) full access. toilet rm & modifications & extensions of (e) mep systems. no exterior work. no change of use.
Details
Permit
202306200439
Permit issued
Aug 28, 2023
Final sign-off
Nov 3, 2023

#155: interior alteration to an (e) tenant space to house retail occup. scope includes new finishes and fixtures, while reusing the (e) walls, stock area, and (1) full access. toilet rm & modifications & extensions of (e) mep systems. no exterior work. no change of use.

Open the permit page

$89,000
Apr 27, 2023Completed
final sign-off Jun 2025
901 Market StA2z Builders Inclower lvl/ground flr: interior remodel of existing ross store-work area approx 29,131 sf, install merchndise racks, register counters and fitting rooms. no mep work.
Details
Permit
202304276570
Permit issued
May 23, 2025
Final sign-off
Jun 6, 2025

lower lvl/ground flr: interior remodel of existing ross store-work area approx 29,131 sf, install merchndise racks, register counters and fitting rooms. no mep work.

Open the permit page

$45,000
Dec 22, 2021Completed
final sign-off Jun 2022
90 New Montgomery StR 3 Builders Inc.ste 250. new carpet & ceiling grid, relocating heat pump and add new grills. relocate lights and add new occupancy sensors. demo of partition wall
Details
Permit
202112224877
Permit issued
Feb 14, 2022
Final sign-off
Jun 13, 2022

ste 250. new carpet & ceiling grid, relocating heat pump and add new grills. relocate lights and add new occupancy sensors. demo of partition wall

Open the permit page

$300,000
Oct 25, 2021Completed
final sign-off Aug 2022
101 California StConstruction One Inc.27/f suite 2700: t.i to reduce sq. ft of training room to create a small team room. minor demolition and construction. suite entry/egress doors and egress paths to remain. minor mechanical and electrical. scope on a-101. fire alarm/sprinkler/emer lighting on sep permits.
Details
Permit
202110251096
Permit issued
Nov 10, 2021
Final sign-off
Aug 10, 2022

27/f suite 2700: t.i to reduce sq. ft of training room to create a small team room. minor demolition and construction. suite entry/egress doors and egress paths to remain. minor mechanical and electrical. scope on a-101. fire alarm/sprinkler/emer lighting on sep permits.

Open the permit page

$280,480
Jan 19, 2021Completed
final sign-off Jun 2021
2056 Fillmore StVortex Industries Incinstall security gate at store entrance for "gorjana".
Details
Permit
202101192919
Permit issued
Apr 20, 2021
Final sign-off
Jun 2, 2021

install security gate at store entrance for "gorjana".

Open the permit page

$4,000
Aug 12, 2020Completed
final sign-off Mar 2022
71 Powell StGci, Increvision to bpa#201609268771. remove one(non-egress).entry door: new storefront color propose for powell & ellis st. all architecture revisions are solely on powell st. no architectural revisons on ellis
Details
Permit
202008121609
Permit issued
Nov 23, 2020
Final sign-off
Mar 3, 2022

revision to bpa#201609268771. remove one(non-egress).entry door: new storefront color propose for powell & ellis st. all architecture revisions are solely on powell st. no architectural revisons on ellis

Open the permit page

Oct 23, 2019Completed
final sign-off Aug 2020
2219 Chestnut StJ Palmer Construction Incbarrier removal front entry door access. to comply with accessible business entrance program
Details
Permit
201910235390
Permit issued
Nov 15, 2019
Final sign-off
Aug 16, 2020

barrier removal front entry door access. to comply with accessible business entrance program

Open the permit page

$5,000
Apr 15, 2019Never finaled
issued Apr 2019, no final
800 Market StPeacock Constructionrevision to pa 2018-0618-2124 and 2019-0304-4279 to reduce scope of work
Details
Permit
201904157969
Permit issued
Apr 15, 2019

revision to pa 2018-0618-2124 and 2019-0304-4279 to reduce scope of work

Open the permit page

Jan 11, 2019Never finaled
filed Jan 2019, never issued
240 Powell Stexpose original brickwork under (e) front stucco; removing (e) stucco finish on storefront; replace (e) security gate. maher n/a.
Details
Permit
201901110165

expose original brickwork under (e) front stucco; removing (e) stucco finish on storefront; replace (e) security gate. maher n/a.

Open the permit page

$40,000
Jan 11, 2019Never finaled
filed Jan 2019, never issued
240 Powell St1/f: tenant improvement: minor demo including ceiling, light fixtures, conduit and unised plumbing. new ceiling, lighting, cutwork, finishes.
Details
Permit
201901110163

1/f: tenant improvement: minor demo including ceiling, light fixtures, conduit and unised plumbing. new ceiling, lighting, cutwork, finishes.

Open the permit page

$425,000
Sep 5, 2018Never finaled
issued Jul 2019, no final
3 Embarcadero CenterEmbree Construction Group Incunit #3111a: shoe rack permit: removing extg furniture and installing new freestanding fixture being bolted into the ground. just a curved fixture being added. 300 sqft
Details
Permit
201809059196
Permit issued
Jul 15, 2019

unit #3111a: shoe rack permit: removing extg furniture and installing new freestanding fixture being bolted into the ground. just a curved fixture being added. 300 sqft

Open the permit page

$2,000
Feb 1, 2018Completed
final sign-off Aug 2018
3 Embarcadero CenterCrane Construction Company Inc.revision to pa 2017-1017-1431 space r3111a, relocate air handling unit, arch, mech & electrical work
Details
Permit
201802010130
Permit issued
Mar 20, 2018
Final sign-off
Aug 21, 2018

revision to pa 2017-1017-1431 space r3111a, relocate air handling unit, arch, mech & electrical work

Open the permit page

$300,000
Oct 17, 2017Completed
final sign-off Aug 2018
3 Embarcadero CenterCrane Construction Company Inc.space # r3111a: t.i. consisting of a build out of an extg mall. improvements include new flooring,wall finishes, new light fixtures, new display fixtures, & new g.w.b. ceilings. please refer to engineer drawing for mech, elec, & plmg scope of work. n/a for maher
Details
Permit
201710171431
Permit issued
Jan 5, 2018
Final sign-off
Aug 21, 2018

space # r3111a: t.i. consisting of a build out of an extg mall. improvements include new flooring,wall finishes, new light fixtures, new display fixtures, & new g.w.b. ceilings. please refer to engineer drawing for mech, elec, & plmg scope of work. n/a for maher

Open the permit page

$605,000
Jun 8, 2017Completed
final sign-off Aug 2017
125 Grant AvAlain Hirsch Construction Corpexisting interior tenant build out to be demolished. all egress stairs & fire protection system to remain. no exterior work. ti to be filed under separate permit per ab017
Details
Permit
201706088743
Permit issued
Jul 5, 2017
Final sign-off
Aug 21, 2017

existing interior tenant build out to be demolished. all egress stairs & fire protection system to remain. no exterior work. ti to be filed under separate permit per ab017

Open the permit page

$150,000
Jun 8, 2017Expired or cancelled
cancelled Jan 2026
125 Grant Avexisting exterior signs to be removed including glue on letters, glue on horse logos, pin mounted letters, blade sign & fabric awnings. purposed new signs to be filed under separate application
Details
Permit
201706088744

existing exterior signs to be removed including glue on letters, glue on horse logos, pin mounted letters, blade sign & fabric awnings. purposed new signs to be filed under separate application

Open the permit page

$10,000
Apr 7, 2017Completed
final sign-off Oct 2017
2086 Union StJames Agresta Carpentryinterior t/i including new interior partitions, new finishes, new electrical distribution partial replacement of existing hvac system. this follows a formula retail cu approved by motion #19848.
Details
Permit
201704073505
Permit issued
Jun 22, 2017
Final sign-off
Oct 11, 2017

interior t/i including new interior partitions, new finishes, new electrical distribution partial replacement of existing hvac system. this follows a formula retail cu approved by motion #19848.

Open the permit page

$200,000
Nov 30, 2016Completed
final sign-off Jul 2017
2060 Chestnut StR T Stevens Construction Incblue mercury retail cosmetics store. non-structural interior tenant improvement including (n) partitions, finishes, mechanical system, power plant lighting. n/a for maher ordinance no.155-13.
Details
Permit
201611303813
Permit issued
Feb 8, 2017
Final sign-off
Jul 31, 2017

blue mercury retail cosmetics store. non-structural interior tenant improvement including (n) partitions, finishes, mechanical system, power plant lighting. n/a for maher ordinance no.155-13.

Open the permit page

$140,000
Nov 17, 2016Completed
final sign-off Dec 2016
303 02nd StGci, Incsuite s-137 - revision to pa #201607253274 - modify sheet a5 (equipment plan) to indicate accessible seating areas at two loctions & clearance between shelving racks.
Details
Permit
201611173046
Permit issued
Nov 17, 2016
Final sign-off
Dec 20, 2016

suite s-137 - revision to pa #201607253274 - modify sheet a5 (equipment plan) to indicate accessible seating areas at two loctions & clearance between shelving racks.

Open the permit page

Sep 26, 2016Never finaled
issued Nov 2017, no final
71 Powell Stground flr, exterior alterations to (e) storefront. replace (e) 1st flr. exterior finishes with (n) panelized style facade, inserting (n) glazing system within (e) window openings
Details
Permit
201609268771
Permit issued
Nov 14, 2017

ground flr, exterior alterations to (e) storefront. replace (e) 1st flr. exterior finishes with (n) panelized style facade, inserting (n) glazing system within (e) window openings

Open the permit page

$100,000
Jul 12, 2016Completed
final sign-off Nov 2016
303 02nd StGci, Incste s-137 - demolish (e) non-load bearing walls, drop ceilings, (e) toilet room fixtures & finish ceramic tiles. remove mortar bed at & around (e) toilet room tile floors to (e) conc. slab in grade (per ab-017). space to remain vacant
Details
Permit
201607122165
Permit issued
Jul 15, 2016
Final sign-off
Nov 15, 2016

ste s-137 - demolish (e) non-load bearing walls, drop ceilings, (e) toilet room fixtures & finish ceramic tiles. remove mortar bed at & around (e) toilet room tile floors to (e) conc. slab in grade (per ab-017). space to remain vacant

Open the permit page

$10,000
Dec 8, 2015Completed
final sign-off Apr 2016
333 Jefferson StRyan Contractors Incnon structural demolition, new drywall partitions, new flooring, new nc accessible ramp, new drywall ceiling, new mopsink with wh, new lighting and power. n/a for maher.
Details
Permit
201512084488
Permit issued
Jan 15, 2016
Final sign-off
Apr 8, 2016

non structural demolition, new drywall partitions, new flooring, new nc accessible ramp, new drywall ceiling, new mopsink with wh, new lighting and power. n/a for maher.

Open the permit page

$170,000
Sep 16, 2014Completed
final sign-off Dec 2014
3251 20th AvT D S Commercial Constr. Inc.space #150: minor non-structurarl demo, new drywall partitions, new acoustic ceiling in stock room, new lighting, relocate hvac ducting, after existing restrooms to conform with title 24 disability access, doors, cabinetry, new flooring, stock room shelving.
Details
Permit
201409166434
Permit issued
Oct 9, 2014
Final sign-off
Dec 1, 2014

space #150: minor non-structurarl demo, new drywall partitions, new acoustic ceiling in stock room, new lighting, relocate hvac ducting, after existing restrooms to conform with title 24 disability access, doors, cabinetry, new flooring, stock room shelving.

Open the permit page

$100,000
Jul 16, 2014Never finaled
filed Jul 2014, never issued
1355 Market StTerra Nova Industriesrevision to pa# 2012/11/08/3877. build mezzanine for office & storage space on ground floor. mep under separate permit. ** maher: compliance with ordinance no# 155-13 not required **
Details
Permit
201407161426

revision to pa# 2012/11/08/3877. build mezzanine for office & storage space on ground floor. mep under separate permit. ** maher: compliance with ordinance no# 155-13 not required **

Open the permit page

$134,000
May 5, 2014Completed
final sign-off Feb 2015
1355 Market StTerra Nova Industriesinterior non-structural demolition at ground floor. t.i #2014.0128.7280. compliance with ordinance #155-13 not required
Details
Permit
201405054849
Permit issued
May 12, 2014
Final sign-off
Feb 6, 2015

interior non-structural demolition at ground floor. t.i #2014.0128.7280. compliance with ordinance #155-13 not required

Open the permit page

$5,000
Jan 28, 2014Expired or cancelled
cancelled Mar 2020
1355 Market Stexterior remodel to include (e) storefront (removal) between column lines, addition of (n) double doors at storefront, & addition of (n) fresh air intake at storefront. compliance with ordinance 3155-13 not required.
Details
Permit
201401287284

exterior remodel to include (e) storefront (removal) between column lines, addition of (n) double doors at storefront, & addition of (n) fresh air intake at storefront. compliance with ordinance 3155-13 not required.

Open the permit page

$30,000
Jan 28, 2014Completed
final sign-off Feb 2015
1355 Market StW. Wong Construction Co. Inc.ground floor interior remodel to include select areas of demolition, general retail tenant improvement, new handicap accessible toilet room. exterior & mep work under separate permits. ** maher: compliance with ordinance no# 155-13 not required **
Details
Permit
201401287280
Permit issued
Nov 19, 2014
Final sign-off
Feb 6, 2015

ground floor interior remodel to include select areas of demolition, general retail tenant improvement, new handicap accessible toilet room. exterior & mep work under separate permits. ** maher: compliance with ordinance no# 155-13 not required **

Open the permit page

$1,200,000
Oct 30, 2013Completed
final sign-off Jun 2014
77 Beale StParadigm General Contractorsplumbing electric scope f/(e) approved architectural, permit arch 201304184830. gr fl cafe
Details
Permit
201310300670
Permit issued
Dec 6, 2013
Final sign-off
Jun 10, 2014

plumbing electric scope f/(e) approved architectural, permit arch 201304184830. gr fl cafe

Open the permit page

$40,000
Sep 18, 2013Completed
final sign-off Dec 2013
201 Mission StRichlen Construction12th floor t.i.:make 7 offices from open area. finishes, paint, allocate lights, add 3 new lights and one heat pump added.includes mep- sprinkler and fire alarm separate permits
Details
Permit
201309187148
Permit issued
Sep 26, 2013
Final sign-off
Dec 9, 2013

12th floor t.i.:make 7 offices from open area. finishes, paint, allocate lights, add 3 new lights and one heat pump added.includes mep- sprinkler and fire alarm separate permits

Open the permit page

$102,000
Jul 9, 2013Completed
final sign-off Dec 2013
58 Geary StBrodson Construction Inct.i.include: new ceilings & partitions, new electrical including light fixtures, new floor ceiling finish, selective demo, new hvac, new plumbing, new ada lift, any exterior storefront change subject to minor permit to alter (historic planning) structural support framing for hvac will be under
Details
Permit
201307091416
Permit issued
Oct 9, 2013
Final sign-off
Dec 6, 2013

t.i.include: new ceilings & partitions, new electrical including light fixtures, new floor ceiling finish, selective demo, new hvac, new plumbing, new ada lift, any exterior storefront change subject to minor permit to alter (historic planning) structural support framing for hvac will be under

Open the permit page

$415,000
Apr 18, 2013Completed
final sign-off Jun 2014
77 Beale StParadigm General Contractorslobby. remodel (e) vacant cafe space within main lobby of pg & e building. project will entail minimal new drywall partitions, new millwork package, plumbing & electrical for coffee equipment & lighting
Details
Permit
201304184830
Permit issued
Dec 6, 2013
Final sign-off
Jun 23, 2014

lobby. remodel (e) vacant cafe space within main lobby of pg & e building. project will entail minimal new drywall partitions, new millwork package, plumbing & electrical for coffee equipment & lighting

Open the permit page

$101,848
Feb 22, 2013Completed
final sign-off Dec 2014
240 Powell StX S Industries Incerect/change a electric wall single faced sign.
Details
Permit
201302220775
Permit issued
Aug 20, 2014
Final sign-off
Dec 26, 2014

erect/change a electric wall single faced sign.

Open the permit page

$2,000
Jun 13, 2012Completed
final sign-off Nov 2012
201 Mission StRichlen Constructiont.i.- 12/fl: new/reloc lighting&basic elec. hvac:35 new supplys. 27 new interior return airgrills, vav boxes, 2-5 ion ac unit w/thermostat. plumbing:drinking fountain, plumbing. restroom: 2 new ada toilets, cosmetic renovates new finishes thruout. sprinklers and fire alarm
Details
Permit
201206132506
Permit issued
Jul 5, 2012
Final sign-off
Nov 7, 2012

t.i.- 12/fl: new/reloc lighting&basic elec. hvac:35 new supplys. 27 new interior return airgrills, vav boxes, 2-5 ion ac unit w/thermostat. plumbing:drinking fountain, plumbing. restroom: 2 new ada toilets, cosmetic renovates new finishes thruout. sprinklers and fire alarm

Open the permit page

$920,000
Mar 2, 2011Completed
final sign-off Jun 2011
101 Geary StTeel Construction Inc.swatch +. install two illuminated channel letters wall sign.
Details
Permit
201103021235
Permit issued
May 23, 2011
Final sign-off
Jun 27, 2011

swatch +. install two illuminated channel letters wall sign.

Open the permit page

$10,000
Dec 27, 2010Completed
final sign-off Nov 2011
350 Post StShawmut Woodworking & Supply Incminor remodel of a section of ti on 2nd floor in office area. partition,door jewerly case grab bars, ceiling, duct work & minor electrical
Details
Permit
201012277400
Permit issued
Mar 1, 2011
Final sign-off
Nov 1, 2011

minor remodel of a section of ti on 2nd floor in office area. partition,door jewerly case grab bars, ceiling, duct work & minor electrical

Open the permit page

$110,000
Sep 2, 2010Never finaled
issued Apr 2011, no final
101 Geary StTeel Construction Inc.interior ti of existing retail space
Details
Permit
201009020104
Permit issued
Apr 14, 2011

interior ti of existing retail space

Open the permit page

$65,000
Jul 23, 2010Completed
final sign-off Oct 2010
846 Market StJkt Construction Inc Dba Corconinterior remodel of existing retail store. work to include partition walls, plumbing, mechanical , electrical, sales fixtures, drywall, carpet and paint, and remodel for ada restroom. fire sprinkler and fire alarm under separate permit.
Details
Permit
201007237310
Permit issued
Aug 20, 2010
Final sign-off
Oct 15, 2010

interior remodel of existing retail store. work to include partition walls, plumbing, mechanical , electrical, sales fixtures, drywall, carpet and paint, and remodel for ada restroom. fire sprinkler and fire alarm under separate permit.

Open the permit page

$120,000
Jul 18, 2007Completed
final sign-off Nov 2007
865 Market Sttenant improvement: interior remodeling of an existing retail tenant space at san francisco centre (westfield mall).
Details
Permit
200707187153
Permit issued
Jul 19, 2007
Final sign-off
Nov 19, 2007

tenant improvement: interior remodeling of an existing retail tenant space at san francisco centre (westfield mall).

Open the permit page

$75,000
Jul 5, 2006Completed
final sign-off Aug 2006
22 04th Stinterior improvement of e office space: partial demolition, new partition, new doors, new ceiling. mech/elec and fire alarm and sprinkler modifications to existing. under sep permit
Details
Permit
200607055720
Permit issued
Jul 5, 2006
Final sign-off
Aug 22, 2006

interior improvement of e office space: partial demolition, new partition, new doors, new ceiling. mech/elec and fire alarm and sprinkler modifications to existing. under sep permit

Open the permit page

$81,242
Jun 7, 2006Completed
final sign-off Jan 2007
845 Market StA & E Construction Cocti-1, 2nd floor, el, me, ls, sp. martin & osa, #249.
Details
Permit
200606073430
Permit issued
Aug 4, 2006
Final sign-off
Jan 23, 2007

cti-1, 2nd floor, el, me, ls, sp. martin & osa, #249.

Open the permit page

$500,000
May 25, 2006Completed
final sign-off Jan 2007
845 Market Stcti-1, "j crew", #245, 2nd level, el, me, ls, sp.
Details
Permit
200605252528
Permit issued
Jun 22, 2006
Final sign-off
Jan 23, 2007

cti-1, "j crew", #245, 2nd level, el, me, ls, sp.

Open the permit page

$242,325
May 24, 2006Never finaled
issued Mar 2007, no final
150 Stockton Stfinish work and lighting for vendor areas on lower level (gucci) and 1st floor (chole & channel)new lighting for existing display windows on 1st floor. also vendors fendi, dior, guerlain.
Details
Permit
200605242360
Permit issued
Mar 13, 2007

finish work and lighting for vendor areas on lower level (gucci) and 1st floor (chole & channel)new lighting for existing display windows on 1st floor. also vendors fendi, dior, guerlain.

Open the permit page

$67,500
Feb 28, 2006Completed
final sign-off Dec 2006
845 Market StJames M Barb Construction Cospace# 422. cti-1, 4th floor, el, me, ls, sp. tenant improvement/store front, sprinkler modification, paint, metal fixtures and lighting/
Details
Permit
200602285638
Permit issued
Aug 17, 2006
Final sign-off
Dec 14, 2006

space# 422. cti-1, 4th floor, el, me, ls, sp. tenant improvement/store front, sprinkler modification, paint, metal fixtures and lighting/

Open the permit page

$22,000
Feb 28, 2006Completed
final sign-off Dec 2006
845 Market Stsunglass hut. cti-2, 4th floor, el, me.
Details
Permit
200602285645
Permit issued
Sep 5, 2006
Final sign-off
Dec 14, 2006

sunglass hut. cti-2, 4th floor, el, me.

Open the permit page

$30,750
Feb 10, 2006Never finaled
issued Feb 2006, no final
22 04th Stinterior remodel, add 3 new offices incl partiton ceiling, doors and finishes. new storage include partitions, doors, ceilings, finishes
Details
Permit
200602104419
Permit issued
Feb 10, 2006

interior remodel, add 3 new offices incl partiton ceiling, doors and finishes. new storage include partitions, doors, ceilings, finishes

Open the permit page

$51,424
Sep 27, 2005Completed
final sign-off Jun 2006
150 Stockton Stremodel of mens shoes area on basement level only. no structural work. interior work only.
Details
Permit
200509274031
Permit issued
Sep 27, 2005
Final sign-off
Jun 23, 2006

remodel of mens shoes area on basement level only. no structural work. interior work only.

Open the permit page

$60,000
Aug 4, 2005Completed
final sign-off Sep 2005
77 Battery Stinterior remodel of (e) office spaces at 2nd & 3rd floor. new partitions as indicated, doors.
Details
Permit
200508049469
Permit issued
Aug 4, 2005
Final sign-off
Sep 16, 2005

interior remodel of (e) office spaces at 2nd & 3rd floor. new partitions as indicated, doors.

Open the permit page

$97,000
Aug 4, 2005Completed
final sign-off Jun 2006
150 Stockton Stphase v vendor improvement on lower level for loro piana & armani.vendor improvement on 2/f for
Details
Permit
200508049509
Permit issued
Aug 4, 2005
Final sign-off
Jun 23, 2006

phase v vendor improvement on lower level for loro piana & armani.vendor improvement on 2/f for

Open the permit page

$65,000
Jul 12, 2005Never finaled
issued Jul 2005, no final
3251 20th AvHardesty And Associatesinterior non structural demolition only. handicapped access issues to comply with administrative
Details
Permit
200507127434
Permit issued
Jul 12, 2005

interior non structural demolition only. handicapped access issues to comply with administrative

Open the permit page

$5,000
Jul 1, 2005Never finaled
issued Jul 2005, no final
2829 Mission StFisher Development Incremove (e)perimeter wall/shewing standard in retail area.remove (e)fl finish.install new perimeter
Details
Permit
200507016675
Permit issued
Jul 1, 2005

remove (e)perimeter wall/shewing standard in retail area.remove (e)fl finish.install new perimeter

Open the permit page

$45,000
Apr 7, 2005Expired or cancelled
expired Jun 2006
150 Stockton Stphase iii vendor finish work on 3rd fl for carolina herrera& chanel chanel handbags, donna karen,...
Details
Permit
200504079395
Permit issued
May 2, 2005

phase iii vendor finish work on 3rd fl for carolina herrera& chanel chanel handbags, donna karen,...

Open the permit page

$45,000
Dec 10, 2004Expired or cancelled
expired Aug 2006
100 Bush Stinterior remodel suite 1550. interior walls installation, entry door to suite instal. coabinet, **
Details
Permit
200412101158
Permit issued
Dec 10, 2004

interior remodel suite 1550. interior walls installation, entry door to suite instal. coabinet, **

Open the permit page

$60,000