Jonathan Tsao
- Listed as
- architect, authorized agent-others
- Firm
- Tsao Design Group
- Based in
- San Francisco
- On San Francisco permits
- Apr 2001 to Dec 2021
29 permits since 2000 (architect on 27 permits, authorized agent-others on 2 permits): 24 completed, 1 never finaled, 4 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 1, 2021 | Completed final sign-off Mar 2022 | 2238 Geary Bl | Kaiser Foundation Health Plan Inc | 8/f: installation of partial height modular partitions by dirtt in an (e) medical office building.Details
8/f: installation of partial height modular partitions by dirtt in an (e) medical office building. | $32,000 |
| Nov 15, 2021 | Completed final sign-off May 2022 | 401 Harrison St | Pellandini & Company | unit 32d: soft demolition of two non-structural interior walls around kitchen. closing of opening between 32c & 32d to restore separate units.Details
unit 32d: soft demolition of two non-structural interior walls around kitchen. closing of opening between 32c & 32d to restore separate units. | $10,000 |
| Nov 15, 2021 | Completed final sign-off May 2022 | 401 Harrison St | Pellandini & Company | unit 32c: closing of an interior closet door. demo non-structural walls in unit 32d. infill door to restore separation btwn 32d and 32c.Details
unit 32c: closing of an interior closet door. demo non-structural walls in unit 32d. infill door to restore separation btwn 32d and 32c. | $300 |
| Feb 24, 2020 | Expired or cancelled cancelled Jan 2026 | 2238 Geary Bl | Kaiser Foundation Health Plan Inc | 4/f: rev to pa#201908057836: partial height drywall partition added to reduce the span of a rprefabricated storefront wall.Details
4/f: rev to pa#201908057836: partial height drywall partition added to reduce the span of a rprefabricated storefront wall. | |
| Jun 12, 2013 | Never finaled issued Jun 2013, no final | 1355 Sansome St | Hathaway Dinwiddie Co. | approx 400 gross square feet on floor 1. additon of new non stuctural partitons, new security gates at entry, millwork. no work to exterior of buildingDetails
approx 400 gross square feet on floor 1. additon of new non stuctural partitons, new security gates at entry, millwork. no work to exterior of building | $86,573 |
| Aug 31, 2012 | Completed final sign-off Nov 2012 | 2728 Hyde St | 2nd fl-t.i work includes demolition of non load bearing walls, new interior glazing in (e) walls, new ceiling tiles, 4 new motion controled faucets, wall hung sinks at men's restroom, sound proof at (e) restrooms. painting & install carpet. t.i does not involve a change of occupancy/use.Details
2nd fl-t.i work includes demolition of non load bearing walls, new interior glazing in (e) walls, new ceiling tiles, 4 new motion controled faucets, wall hung sinks at men's restroom, sound proof at (e) restrooms. painting & install carpet. t.i does not involve a change of occupancy/use. | $75,000 | |
| Aug 31, 2012 | Completed final sign-off Nov 2012 | 2728 Hyde St | 1st fl-t.i work includes demolition of non load bearing walls, new interior glazing in (e) walls, new ceiling tiles, 4 new motion controled faucets, wall hung sinks at men's restroom, sound proof at (e) restrooms. new millwork exteriosion to match (e). t.i does not involve a change of occupancy/useDetails
1st fl-t.i work includes demolition of non load bearing walls, new interior glazing in (e) walls, new ceiling tiles, 4 new motion controled faucets, wall hung sinks at men's restroom, sound proof at (e) restrooms. new millwork exteriosion to match (e). t.i does not involve a change of occupancy/use | $31,500 | |
| May 11, 2012 | Completed final sign-off Nov 2012 | 1355 Sansome St | Hathaway Dinwiddie Co. | 1st floor-approx 239 sq ft remodel-office t.i to include new glass partitions & door changing office to reading library. there is no work to the exterior of the building. there is no modification to the (e) egress systems, no change in lighting & hvac.Details
1st floor-approx 239 sq ft remodel-office t.i to include new glass partitions & door changing office to reading library. there is no work to the exterior of the building. there is no modification to the (e) egress systems, no change in lighting & hvac. | $32,000 |
| Feb 21, 2012 | Completed final sign-off Jan 2013 | 525 Market St | Skyline Construction | 1st floor revision to pa #2010.08.31.9911 - relocated light fixtures, new mop sink, changes in finisheses. ref pa#2010.08.31.9931.Details
1st floor revision to pa #2010.08.31.9911 - relocated light fixtures, new mop sink, changes in finisheses. ref pa#2010.08.31.9931. | |
| Feb 7, 2012 | Completed final sign-off Nov 2012 | 211 Main St | Swinerton Builders | 17th floor tenant improvement of (e) interior space. (single tenant floor). no sturctural work, relocation mechanical diffusers, new partitions, finishes & ceiling includes minor electrical work. fire/life safety under separate permit.Details
17th floor tenant improvement of (e) interior space. (single tenant floor). no sturctural work, relocation mechanical diffusers, new partitions, finishes & ceiling includes minor electrical work. fire/life safety under separate permit. | $119,000 |
| Jun 10, 2011 | Completed final sign-off Jan 2014 | 185 Berry St | Bcci Construction Company | office ti on the 2nd fl, suite#220. no ext.work, no struc.work. remodel partitions, doors,interior glazing, millwork,act ceiling and grid. mep, fire ls and sprinklers under separate permitDetails
office ti on the 2nd fl, suite#220. no ext.work, no struc.work. remodel partitions, doors,interior glazing, millwork,act ceiling and grid. mep, fire ls and sprinklers under separate permit | $103,000 |
| Oct 26, 2010 | Completed final sign-off Aug 2011 | 77 Van Ness Av | Dome Construction Corp | physcian owned: medical offices and exam rooms. 2476 sf. tenant improvment to include architectural, mech, elec, plumbing. no exterior work. suite 301 under separate permitDetails
physcian owned: medical offices and exam rooms. 2476 sf. tenant improvment to include architectural, mech, elec, plumbing. no exterior work. suite 301 under separate permit | $400,000 |
| Jul 28, 2010 | Completed final sign-off Mar 2011 | 525 Market St | Hathaway Dinwiddie Co. | 31st floor new elevator lobby fire doors, new demising partitions, office tenant improvements, kitchen millwork. fire/life safety, mechanical & electrical under separate permit.Details
31st floor new elevator lobby fire doors, new demising partitions, office tenant improvements, kitchen millwork. fire/life safety, mechanical & electrical under separate permit. | $60,000 |
| Mar 3, 2010 | Completed final sign-off Aug 2011 | 1355 Sansome St | Hathaway Dinwiddie Co. | 1st floor. mechanical, electrical and plumbing work. tenant improvement. architectural under separate permit 201003027378.Details
1st floor. mechanical, electrical and plumbing work. tenant improvement. architectural under separate permit 201003027378. | $500,000 |
| Dec 16, 2009 | Completed final sign-off Feb 2010 | 185 Berry St | Dfi Construction Company | suite 5300: tenant improvement of existing space to include new partitions, doors, and fixtures. fire/life safety under separate permit.Details
suite 5300: tenant improvement of existing space to include new partitions, doors, and fixtures. fire/life safety under separate permit. | $30,000 |
| Jun 10, 2009 | Completed final sign-off Oct 2009 | 770 Golden Gate Av | Newground International Inc | expanding existing parking lot, new signage, update ada parking, retaining wall, bike racks.Details
expanding existing parking lot, new signage, update ada parking, retaining wall, bike racks. | $60,000 |
| Jan 27, 2009 | Completed final sign-off Jul 2009 | 44 Montgomery St | Rudolph Commercial Interiors Inc, Rci | 3rd & 4th floors-women's restrooms-new floor plan to meet code, removal of 1 stall to enlarge accessible stall to meet code, relocate lights. mens restrooms-new floor plan to meet code & new finishes in bathroom per plan. mep,ls &sp separate permit.Details
3rd & 4th floors-women's restrooms-new floor plan to meet code, removal of 1 stall to enlarge accessible stall to meet code, relocate lights. mens restrooms-new floor plan to meet code & new finishes in bathroom per plan. mep,ls &sp separate permit. | $180,000 |
| Nov 21, 2008 | Completed final sign-off Feb 2009 | 525 Market St | Hathaway Dinwiddie Co. | interior t.i. on 31st floor. includes new office partition, door & finishes. modifications to fire sprinkler, fire alarm, electrical & mechanical under separate permit.Details
interior t.i. on 31st floor. includes new office partition, door & finishes. modifications to fire sprinkler, fire alarm, electrical & mechanical under separate permit. | $20,000 |
| Jun 1, 2007 | Completed final sign-off Jan 2008 | 44 Montgomery St | Rudolph Commercial Interiors Inc, Rci | oti-1, seagate properties, 28th floor, ls.Details
oti-1, seagate properties, 28th floor, ls. | $46,000 |
| Jun 1, 2007 | Completed final sign-off Oct 2007 | 44 Montgomery St | Rudolph Commercial Interiors Inc, Rci | oti-1, seagate properties, 27th floor, ls.Details
oti-1, seagate properties, 27th floor, ls. | $46,000 |
| Jun 1, 2007 | Completed final sign-off Dec 2007 | 44 Montgomery St | Rudolph Commercial Interiors Inc, Rci | oti-1, seagate properties, 26th floor, ls.Details
oti-1, seagate properties, 26th floor, ls. | $46,000 |
| Oct 19, 2006 | Expired or cancelled expired Apr 2007 | 44 Montgomery St | Rudolph Commercial Interiors Inc, Rci | renew pa# 200309084086, 200309164877, 200309094208 for final inspection.Details
renew pa# 200309084086, 200309164877, 200309094208 for final inspection. | |
| Aug 23, 2005 | Completed final sign-off Sep 2005 | 101 Montgomery St | Novo Construction Inc | tenant improvement, subdivide 1 large office into 2 offices carpet and paint entire floor replaceDetails
tenant improvement, subdivide 1 large office into 2 offices carpet and paint entire floor replace | $105,000 |
| Jun 2, 2005 | Completed final sign-off Feb 2006 | 101 Montgomery St | Novo Construction Inc | oti-2, 10th floor, el, me.Details
oti-2, 10th floor, el, me. | $47,000 |
| Jun 2, 2005 | Completed final sign-off Feb 2006 | 101 Montgomery St | Novo Construction Inc | oti-1, 9th floor, el, me, ls, sp.Details
oti-1, 9th floor, el, me, ls, sp. | $100,000 |
| Jun 2, 2005 | Completed final sign-off Feb 2006 | 101 Montgomery St | Novo Construction Inc | oti-1,10th floor, el, me, ls, sp.Details
oti-1,10th floor, el, me, ls, sp. | $40,000 |
| Jun 2, 2005 | Completed final sign-off Feb 2006 | 101 Montgomery St | Novo Construction Inc | oti-2, 9th fl - el,me.Details
oti-2, 9th fl - el,me. | $163,000 |
| Jun 15, 2001 | Expired or cancelled expired Jun 2003 | 120 Stockton St | retrail tenant improvementDetails
retrail tenant improvement | $120,000 | |
| Apr 23, 2001 | Expired or cancelled expired Feb 2002 | 1975 Market St | handi cap revision signageDetails
handi cap revision signage | $2,000 |