John Talbot
- Listed as
- authorized agent-others, contractor
- Firm
- Mastec Network Solutions Inc
- Based in
- Sacramento
- On San Francisco permits
- Feb 2011 to Sep 2026
178 permits since 2000 (contractor on 178 permits, authorized agent-others on 10 permits): 128 completed, 27 in progress, 15 never finaled, 8 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. Their ranked record as a contractor is on their contractor page. How to read these records
Most recent permits
Showing the 100 most recent of 178.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 3, 2026 | In progress filed Sep 2026, not yet issued | 1525 Market St | Mastec Network Solutions Inc | t-mobile remove & replace 1 e) mirco wave dish, cable & equipment mw dish,Details
t-mobile remove & replace 1 e) mirco wave dish, cable & equipment mw dish, | $45,000 |
| Sep 3, 2026 | In progress filed Sep 2026, not yet issued | 770 Golden Gate Av | Mastec Network Solutions Inc | t-mobile: replace 1 (e) microwave dish on (e) cell tower. install 1 new mount for microwave dish; new jumpers, dc power cables and radios.Details
t-mobile: replace 1 (e) microwave dish on (e) cell tower. install 1 new mount for microwave dish; new jumpers, dc power cables and radios. | $25,000 |
| Sep 1, 2026 | In progress issued Sep 2026 | 450 Harrison St | Mastec Network Solutions Inc | to obtain final inspection for work approved under pa# 202405293191 all work completedDetails
to obtain final inspection for work approved under pa# 202405293191 all work completed | |
| Jul 15, 2026 | In progress issued Aug 2026 | 2000 Van Ness Av | Mastec Network Solutions Inc | to obtain final inspection for work approved under pa# 201904168079. all work is complete.Details
to obtain final inspection for work approved under pa# 201904168079. all work is complete. | |
| Jul 15, 2026 | In progress filed Jul 2026, not yet issued | 2000 Van Ness Av | Mastec Network Solutions Inc | at&t e) tower @ +/-107', remove 1 vhlpx4-11wa microwave dish, remove 4 ericsson mini-link rau2 odus, remove 2 cnt-400 coax cables, install 1 shpx4-11w microwave dish, install 2 ericsson mini-link 6365 odus, e) 2 lmr-400 coax cable to remainDetails
at&t e) tower @ +/-107', remove 1 vhlpx4-11wa microwave dish, remove 4 ericsson mini-link rau2 odus, remove 2 cnt-400 coax cables, install 1 shpx4-11w microwave dish, install 2 ericsson mini-link 6365 odus, e) 2 lmr-400 coax cable to remain | $20,000 |
| Jun 17, 2026 | In progress issued Jun 2026 | 1701 Balboa St | Mastec Network Solutions Inc | revision to bpa#202507301918. revise structural roof framing planDetails
revision to bpa#202507301918. revise structural roof framing plan | |
| Jun 15, 2026 | In progress issued Jul 2026 | 601 Market St | Mastec Network Solutions Inc | tmobile: revision to bpa#: 202409060273. revise electrical sc diagram. no change to antennas or batteries already approved.Details
tmobile: revision to bpa#: 202409060273. revise electrical sc diagram. no change to antennas or batteries already approved. | |
| Jun 5, 2026 | In progress issued Jul 2026 | 5 The Embarcadero | Mastec Network Solutions Inc | basement - remove 25kva transformer and add 50kva transformer install conduit and conductors from trasnformer to ppc existing ref 202010096268Details
basement - remove 25kva transformer and add 50kva transformer install conduit and conductors from trasnformer to ppc existing ref 202010096268 | $10,000 |
| Jun 2, 2026 | In progress filed Jun 2026, not yet issued | 2099 Market St | Mastec Network Solutions Inc | renew permit 200005109584Details
renew permit 200005109584 | |
| Apr 8, 2026 | In progress issued Jul 2026 | 10 Bernal Heights Bl | Mastec Network Solutions Inc | remove 3 rru's from tower; install 3 new rrus and 1 hybride cable on tower; install 1 rp 6672 on ground.Details
remove 3 rru's from tower; install 3 new rrus and 1 hybride cable on tower; install 1 rp 6672 on ground. | $30,000 |
| Mar 16, 2026 | Completed final sign-off May 2026 | 3250 19th Av | Mastec Network Solutions Inc | t-mobile decommission antennas, cables, beam. remove panel antennas and mounting pipes, all apxvfww24x-c-na20 (hex); all 1-5/8 coax; air32krd901146/1_b66_b2a (octo); all coax jumpers; all compsocpe twin style 3cx-tmat1921xb68-21a;all rfs twin syle 1a1900d-1a20 -comscope twin 700/pcs; all cab-steelDetails
t-mobile decommission antennas, cables, beam. remove panel antennas and mounting pipes, all apxvfww24x-c-na20 (hex); all 1-5/8 coax; air32krd901146/1_b66_b2a (octo); all coax jumpers; all compsocpe twin style 3cx-tmat1921xb68-21a;all rfs twin syle 1a1900d-1a20 -comscope twin 700/pcs; all cab-steel | $5,000 |
| Dec 11, 2025 | In progress issued Aug 2026 | 985 Geneva Av | Mastec Network Solutions Inc | t-mobile: remove 1 (e) antenna. install 6 new antennas inside 6 new radomes. remove 1 (e) cabinet. install 2 new cabinets. install 12 new batteries. install new 200amp panel.Details
t-mobile: remove 1 (e) antenna. install 6 new antennas inside 6 new radomes. remove 1 (e) cabinet. install 2 new cabinets. install 12 new batteries. install new 200amp panel. | $65,000 |
| Nov 24, 2025 | Completed final sign-off Mar 2026 | 550 15th St | Mastec Network Solutions Inc | t-mobile: modification to an existing wireless facility: 3 new antannas, 2 new raised foot curbs + masts, 1 new antenna wall mount, 3 new cable tray screens, painting/wrapping antennas/antenna mounts/masts/exposed cables to match building eligible facility request.Details
t-mobile: modification to an existing wireless facility: 3 new antannas, 2 new raised foot curbs + masts, 1 new antenna wall mount, 3 new cable tray screens, painting/wrapping antennas/antenna mounts/masts/exposed cables to match building eligible facility request. | $50,000 |
| Nov 13, 2025 | Completed final sign-off Dec 2025 | 5024 03rd St | Mastec Network Solutions Inc | revision to pa # 2025-0707-0232: revise sheets t-1, e-1, e-2 & e-3. changes to panel schedule, single line diagram, title 24.Details
revision to pa # 2025-0707-0232: revise sheets t-1, e-1, e-2 & e-3. changes to panel schedule, single line diagram, title 24. | $10 |
| Nov 6, 2025 | Completed final sign-off Jan 2026 | 650 Gilman Av | Mastec Network Solutions Inc | to obtain final inspection for work approved under pa #201607273542. all work is complete.Details
to obtain final inspection for work approved under pa #201607273542. all work is complete. | |
| Sep 23, 2025 | Completed final sign-off Dec 2025 | 211 Sutter St | Mastec Network Solutions Inc | revision to 202412237338 to document the relocation of rf cabinet 6160 and battery cabinet b160 and fiber winder box. remove rbs 6102 existing cabinet.Details
revision to 202412237338 to document the relocation of rf cabinet 6160 and battery cabinet b160 and fiber winder box. remove rbs 6102 existing cabinet. | |
| Sep 17, 2025 | In progress issued Nov 2025 | 5 Thomas Mellon Dr | Mastec Network Solutions Inc | t-mobile remove and replace 6 e antennas, remove and replace 2 e cabinets, install 6 new rrus, install 1 new 2 batteriesDetails
t-mobile remove and replace 6 e antennas, remove and replace 2 e cabinets, install 6 new rrus, install 1 new 2 batteries | $125,000 |
| Aug 8, 2025 | Completed final sign-off Nov 2025 | 1525 Ocean Av | Mastec Network Solutions Inc | revision 202504104168- to relocate vents on roofDetails
revision 202504104168- to relocate vents on roof | $2,000 |
| Jul 30, 2025 | In progress issued Nov 2025 | 1701 Balboa St | Mastec Network Solutions Inc | t-mobile: remove 1 (e) antenna and 1 (e) faux vents. install 6 new antennas within 6 new frp faux vents. remove and replace 1 (e) cabinet with 1 new cabinet. install new meter. install 16 new batteries.Details
t-mobile: remove 1 (e) antenna and 1 (e) faux vents. install 6 new antennas within 6 new frp faux vents. remove and replace 1 (e) cabinet with 1 new cabinet. install new meter. install 16 new batteries. | $78,000 |
| Jul 28, 2025 | In progress issued Jan 2026 | 599 Monterey Bl | Mastec Network Solutions Inc | t-mobile: install 6 new antennas 2 per sector. install 6 radios (3 x 3). add 2 cabinets. remove 1 cabinet.Details
t-mobile: install 6 new antennas 2 per sector. install 6 radios (3 x 3). add 2 cabinets. remove 1 cabinet. | $25,000 |
| Jul 22, 2025 | Completed final sign-off Sep 2026 | 2525 Alemany Bl | Mastec Network Solutions Inc | t-mobile remove 1 (e) antenna, install 6 (n) antennas, remove 1(e) cabinet, install 1 (n) cabinet, install (n) batteries, install (n) electric conduitDetails
t-mobile remove 1 (e) antenna, install 6 (n) antennas, remove 1(e) cabinet, install 1 (n) cabinet, install (n) batteries, install (n) electric conduit | $150,000 |
| Jul 7, 2025 | Completed final sign-off Dec 2025 | 5024 03rd St | Mastec Network Solutions Inc | remove 2 existing antennas and 3 existing cabinets; install 6 new antennas within 6 new radomes, 3 new cabinets, electrical upgrade; install new batteries.Details
remove 2 existing antennas and 3 existing cabinets; install 6 new antennas within 6 new radomes, 3 new cabinets, electrical upgrade; install new batteries. | $150,000 |
| May 1, 2025 | Completed final sign-off Oct 2025 | 888 Innes Av | Mastec Network Solutions Inc | revision to pa #202410293963. remove and replace existing dog house and cable tray with new dog house and cable tray. there is no proposed electrical, battery, or antenna with revision.Details
revision to pa #202410293963. remove and replace existing dog house and cable tray with new dog house and cable tray. there is no proposed electrical, battery, or antenna with revision. | $6,000 |
| May 1, 2025 | Completed final sign-off Jun 2025 | 1200 Mason St | Mastec Network Solutions Inc | revision to pa 202409100427 revise platform connection details per inspection. no proposed revision to antennas, batteries, rf report, or electricalDetails
revision to pa 202409100427 revise platform connection details per inspection. no proposed revision to antennas, batteries, rf report, or electrical | $3,000 |
| Apr 10, 2025 | Completed final sign-off Nov 2025 | 1525 Ocean Av | Mastec Network Solutions Inc | t-mobile: remove (2) (e) antennas, remove (2) (e) cabinets,; install (6)(n) antennas; install (2)(n) cabinets; install (2)(n) randomes; install (1) (n) frp screen; install (12) (n) batteries; install (n) elec breakers.Details
t-mobile: remove (2) (e) antennas, remove (2) (e) cabinets,; install (6)(n) antennas; install (2)(n) cabinets; install (2)(n) randomes; install (1) (n) frp screen; install (12) (n) batteries; install (n) elec breakers. | $130,000 |
| Feb 26, 2025 | In progress issued Jun 2025 | 1398 Bryant St | Mastec Network Solutions Inc | revision to pa# 202210063841: install n) safety guarrail. no other changes to equipment, batteries, antennasDetails
revision to pa# 202210063841: install n) safety guarrail. no other changes to equipment, batteries, antennas | $800 |
| Feb 7, 2025 | In progress issued Jun 2025 | 1625 Post St | Cabre Tech Solutions Inc, Mastec Network Solutions Inc | front of the building t-mobile: remove 3(e) antennas + 1(e) cabinet, install 6(n) antennas within 3(n) frp screens, instal 2(n), install 12(n) batteries <70kwh + <50 gallons electrolytes, relocate (e) elec tric panel , install (n) meter.Details
front of the building t-mobile: remove 3(e) antennas + 1(e) cabinet, install 6(n) antennas within 3(n) frp screens, instal 2(n), install 12(n) batteries <70kwh + <50 gallons electrolytes, relocate (e) elec tric panel , install (n) meter. | $125,000 |
| Jan 22, 2025 | Completed final sign-off Jun 2025 | 1135 Evans Av | Mastec Network Solutions Inc | t-mobile: remove & replace 2 (e) antennas w/ 2 (n) antennas; 2 (e) cabinets w/ 2 (n) cabinets, install batteries, install (n) 125a breaker.Details
t-mobile: remove & replace 2 (e) antennas w/ 2 (n) antennas; 2 (e) cabinets w/ 2 (n) cabinets, install batteries, install (n) 125a breaker. | $35,000 |
| Jan 14, 2025 | Completed final sign-off May 2026 | 2000 Chestnut St | Mastec Network Solutions Inc | t mobile remove 2 (e) antennas; install 6 (n) antennas, remove micro cell cabinets and install 2 (n) cabinets; install (n) batteries; relocated electrical panelDetails
t mobile remove 2 (e) antennas; install 6 (n) antennas, remove micro cell cabinets and install 2 (n) cabinets; install (n) batteries; relocated electrical panel | $115,000 |
| Jan 10, 2025 | Completed final sign-off May 2026 | 4000 Irving St | Mastec Network Solutions Inc | t-mobile - remove 1(e) antenna; install 6 (n) antennas behind frp screens; install (12) (n) batteries; remove 1 (e) cabinet; install 2 (n) cabinets; install (n) breakers in (e) elec panel.Details
t-mobile - remove 1(e) antenna; install 6 (n) antennas behind frp screens; install (12) (n) batteries; remove 1 (e) cabinet; install 2 (n) cabinets; install (n) breakers in (e) elec panel. | $135,000 |
| Jan 8, 2025 | Completed final sign-off Jul 2025 | 501 06th St | Mastec Network Solutions Inc | t-mobile: removing 2-antennas, all tmas, all diplexers, 1-cabinet and cabling from side of building. installing 6-antennas, 6-rrus, 2-cabinets and cabling within 6-new radomes. sow will not change or modify existing structure.Details
t-mobile: removing 2-antennas, all tmas, all diplexers, 1-cabinet and cabling from side of building. installing 6-antennas, 6-rrus, 2-cabinets and cabling within 6-new radomes. sow will not change or modify existing structure. | $80,000 |
| Dec 23, 2024 | Completed final sign-off Dec 2025 | 211 Sutter St | Mastec Network Solutions Inc | t-mobile: remove (4) (e) antennas. install (6) (n) antennas. remove (1) (e) cabinet and install (2) (n) cabinets. install (n) electrical panel. install (12) (n) batteries.Details
t-mobile: remove (4) (e) antennas. install (6) (n) antennas. remove (1) (e) cabinet and install (2) (n) cabinets. install (n) electrical panel. install (12) (n) batteries. | $95,000 |
| Dec 18, 2024 | In progress issued Jan 2026 | 1465 25th St | Mastec Network Solutions Inc | install (n) cabinet with (12) n batteries, install (n) 19"rack, remove 3(e) antennas and radomes and install 6(n) antennas with randomes and install (n) breakers located on roofDetails
install (n) cabinet with (12) n batteries, install (n) 19"rack, remove 3(e) antennas and radomes and install 6(n) antennas with randomes and install (n) breakers located on roof | $85,000 |
| Dec 10, 2024 | Completed final sign-off Apr 2025 | 2270 Folsom St | Mastec Network Solutions Inc | revision to pa# 202406265270, install 1-new steel beam at equipment platform. no electrical or mechanical revision. no change to approved antennas or batteries.Details
revision to pa# 202406265270, install 1-new steel beam at equipment platform. no electrical or mechanical revision. no change to approved antennas or batteries. | |
| Dec 3, 2024 | Completed final sign-off May 2025 | 890 Taraval St | Mastec Network Solutions Inc | t-mobile: to comply with nov 202419181. rebuild (e) frp screen supports and provide new support framing and connections to (e) building framing.Details
t-mobile: to comply with nov 202419181. rebuild (e) frp screen supports and provide new support framing and connections to (e) building framing. | $25,000 |
| Dec 3, 2024 | Completed final sign-off May 2025 | 590 Bosworth St | Mastec Network Solutions Inc | t-mobile: remove 1 (e) antenna and install 2 new antennas. install new 100a service disconnect. no change to (e) batteries.Details
t-mobile: remove 1 (e) antenna and install 2 new antennas. install new 100a service disconnect. no change to (e) batteries. | $35,000 |
| Nov 19, 2024 | Completed final sign-off Mar 2025 | 2601 Mission St | Mastec Network Solutions Inc | ref pa # 2023-1117-1043 tmobile antenna mount detail at sector b + c @ 134'-7" rad only; no change to approved electrical; no change to approved batteriesDetails
ref pa # 2023-1117-1043 tmobile antenna mount detail at sector b + c @ 134'-7" rad only; no change to approved electrical; no change to approved batteries | |
| Nov 12, 2024 | In progress issued Nov 2025 | 5630 Mission St | Mastec Network Solutions Inc | t-mobile: remove 2 (e) antennas & install 6 (n) antennas, construct new frp screen box/penthouse, relocate 1 (e) cabinet, install 2 (n) cabinets; install 12 (n) batteries; install (n) elec. grounding.Details
t-mobile: remove 2 (e) antennas & install 6 (n) antennas, construct new frp screen box/penthouse, relocate 1 (e) cabinet, install 2 (n) cabinets; install 12 (n) batteries; install (n) elec. grounding. | $115,000 |
| Nov 7, 2024 | Completed final sign-off Jun 2025 | 99 Green St | Mastec Network Solutions Inc | t-mobile: removing (2)antennas, all tmas, all diplexers, (1)cabinet and cabling from side of building. install (4)antennas, (4)rrus, (2)cabinets within (4)new radomes.Details
t-mobile: removing (2)antennas, all tmas, all diplexers, (1)cabinet and cabling from side of building. install (4)antennas, (4)rrus, (2)cabinets within (4)new radomes. | $80,000 |
| Nov 7, 2024 | Completed final sign-off Jul 2025 | 501 Laguna Honda Bl | Mastec Network Solutions Inc | remove 3 (e) antennas from steeple replace w/ 3 (n) antennas. remove 3 (e) cabinets and replace w/ 2 (n) cabinets.Details
remove 3 (e) antennas from steeple replace w/ 3 (n) antennas. remove 3 (e) cabinets and replace w/ 2 (n) cabinets. | $25,000 |
| Nov 4, 2024 | Completed final sign-off Jun 2026 | 3001 Mission St | Mastec Network Solutions Inc | t-mobile- remove 2 (e) antennas & 1 (e) cabinet; install 4 (n) antennas & 2 (n) batteries; upgrade 70a electrical feed w/ (n) 200a electrical feedDetails
t-mobile- remove 2 (e) antennas & 1 (e) cabinet; install 4 (n) antennas & 2 (n) batteries; upgrade 70a electrical feed w/ (n) 200a electrical feed | $75,000 |
| Oct 29, 2024 | Completed final sign-off Oct 2025 | 888 Innes Av | Mastec Network Solutions Inc | remove 3 (e) antennas, install 6 (n) antennas, remove 3 (e) cabinets, install 2 (n) cabinets, install 12 (n) batteries, install (n) breakers inside (e) panelDetails
remove 3 (e) antennas, install 6 (n) antennas, remove 3 (e) cabinets, install 2 (n) cabinets, install 12 (n) batteries, install (n) breakers inside (e) panel | $85,000 |
| Oct 21, 2024 | Completed final sign-off Jan 2025 | 221 Main St | Mastec Network Solutions Inc | removeing antennas, rrus , coas and hard lines. removing cabinets, meter and electrical cans with assoicated h frames. returing site to original condition. patching with (e) wall materialDetails
removeing antennas, rrus , coas and hard lines. removing cabinets, meter and electrical cans with assoicated h frames. returing site to original condition. patching with (e) wall material | $20,000 |
| Oct 18, 2024 | Completed final sign-off Mar 2025 | 1520 Geneva Av | Mastec Network Solutions Inc | remove (e) antenna; install 6 (n) antennas in 6 (n) radomes; remove 1(e) cabinet w batteries & install 1 (n) cabinet w/12 (n) batteries; (n) breaker inside (e) electrical panelDetails
remove (e) antenna; install 6 (n) antennas in 6 (n) radomes; remove 1(e) cabinet w batteries & install 1 (n) cabinet w/12 (n) batteries; (n) breaker inside (e) electrical panel | $75,000 |
| Sep 20, 2024 | Completed final sign-off Feb 2026 | 550 California St | Mastec Network Solutions Inc | t-mobile remove (e) antennas from (e) sign and all equipment in the basement; install 6(n) antennas behind (n) screening; install (n) platform on rooftop w/equipment; install (n) 200 a panel; install 12(n) batteriesDetails
t-mobile remove (e) antennas from (e) sign and all equipment in the basement; install 6(n) antennas behind (n) screening; install (n) platform on rooftop w/equipment; install (n) 200 a panel; install 12(n) batteries | $150,000 |
| Sep 10, 2024 | Completed final sign-off Jun 2025 | 1200 Mason St | Mastec Network Solutions Inc | t-mobile remove (e) antennas and install (6) (n) antennas behind 6 (n) radomes. remove and replace (e) battery cabinet w/(n) cabinet, install (n) 200amps panel and meter.Details
t-mobile remove (e) antennas and install (6) (n) antennas behind 6 (n) radomes. remove and replace (e) battery cabinet w/(n) cabinet, install (n) 200amps panel and meter. | $65,000 |
| Sep 10, 2024 | Completed final sign-off Apr 2026 | 1 La Avanzada | Mastec Network Solutions Inc | modification to e tmobile installation on sutro tower. at tower level 2 , remove e e antennas and replace w 6 new antennas on new mounts. remove 3 e rrus and replace w 6 new rrus. remove 2 e cabinets on level 2 and install 2 new cabinets in gr fl equp room 214. remove all e coax cables and installDetails
modification to e tmobile installation on sutro tower. at tower level 2 , remove e e antennas and replace w 6 new antennas on new mounts. remove 3 e rrus and replace w 6 new rrus. remove 2 e cabinets on level 2 and install 2 new cabinets in gr fl equp room 214. remove all e coax cables and install | $400,000 |
| Sep 6, 2024 | In progress issued Apr 2025 | 601 Market St | Mastec Network Solutions Inc | t-mobile: remove 2 existing antennas and 3 existing rru's, install 4 new antennas + 12 new rru's, install new battery cabinets with 12 new batteries, remove existing 100a breaker and install new 200 a breaker.Details
t-mobile: remove 2 existing antennas and 3 existing rru's, install 4 new antennas + 12 new rru's, install new battery cabinets with 12 new batteries, remove existing 100a breaker and install new 200 a breaker. | $70,000 |
| Sep 4, 2024 | Completed final sign-off Mar 2025 | 301 South Van Ness Av | Mastec Network Solutions Inc | t-mobile remove & replace 3(e) antennas & radomes; remove & replace 2(e) cabinets with 2 (n) data racks; install 4 (n) 25a breakers; install 12 (n) cabinetsDetails
t-mobile remove & replace 3(e) antennas & radomes; remove & replace 2(e) cabinets with 2 (n) data racks; install 4 (n) 25a breakers; install 12 (n) cabinets | $50,000 |
| Aug 13, 2024 | Completed final sign-off Mar 2025 | 1111 Junipero Serra Bl | Mastec Network Solutions Inc | t-mobile remove (3) (e) antennas all rrvs (e) cabinet. istall 6(n) antennas 6(n) rrvbs , 2(n) cabinets, 12 (n) batteries, (n) 125a and 15a breaker.Details
t-mobile remove (3) (e) antennas all rrvs (e) cabinet. istall 6(n) antennas 6(n) rrvbs , 2(n) cabinets, 12 (n) batteries, (n) 125a and 15a breaker. | $65,000 |
| Aug 5, 2024 | Completed final sign-off Feb 2025 | 890 Taraval St | Mastec Network Solutions Inc | emergency removal of frp screens on roof for engineer to perform evaluation of screen anchoring system. a separate building permit is required to reinstall the screen after evaluation. nov 202419181Details
emergency removal of frp screens on roof for engineer to perform evaluation of screen anchoring system. a separate building permit is required to reinstall the screen after evaluation. nov 202419181 | $2,000 |
| Jul 26, 2024 | In progress issued Jul 2025 | 1701 Jerrold Av | Mastec Network Solutions Inc | removing and replacing 6 antennas vvu's as well as cabinet upgrades witin existing lease areaDetails
removing and replacing 6 antennas vvu's as well as cabinet upgrades witin existing lease area | $50,000 |
| Jul 15, 2024 | Completed final sign-off Jan 2025 | 260 Stockton St | Mastec Network Solutions Inc | tmobile remove 1 e antenna and intall 1 new antenna install 3 n rru no new batteries, install new conduitDetails
tmobile remove 1 e antenna and intall 1 new antenna install 3 n rru no new batteries, install new conduit | $25,000 |
| Jun 26, 2024 | In progress issued Jul 2024 | 2270 Folsom St | Mastec Network Solutions Inc | tmobile: remove (6) (e) antennas and install (6) (n) antennas; remove (2) (e) cabinets and install (2) (n) cabinets; remove all (e) batteries and install (12) (n) batteries.Details
tmobile: remove (6) (e) antennas and install (6) (n) antennas; remove (2) (e) cabinets and install (2) (n) cabinets; remove all (e) batteries and install (12) (n) batteries. | $45,000 |
| Jun 18, 2024 | Completed final sign-off Feb 2025 | 1435 San Bruno Av | Mastec Network Solutions Inc | t-mobile: remove 3 (e) antennas and install 6 new antennas. remove and replace 2 cabinets. install new batteries. install new conduit.Details
t-mobile: remove 3 (e) antennas and install 6 new antennas. remove and replace 2 cabinets. install new batteries. install new conduit. | $50,000 |
| May 29, 2024 | In progress issued May 2025 | 450 Harrison St | Mastec Network Solutions Inc | t-mobile: remove (4)(e) antennas; install (3)(n) antennas; remove (2)(e) cabinets; install (2)(n) cabinets; isntall (12)(n) batteries; install (n) electrical ppc.Details
t-mobile: remove (4)(e) antennas; install (3)(n) antennas; remove (2)(e) cabinets; install (2)(n) cabinets; isntall (12)(n) batteries; install (n) electrical ppc. | $55,000 |
| Apr 16, 2024 | In progress issued Sep 2024 | 669 Portola Dr | Mastec Network Solutions Inc | t-mobile remove & replace 3 antennas, remove/replace 3)rrus, install 12) n batteries, 1) n cabinet, install n 15a breake & n conduitDetails
t-mobile remove & replace 3 antennas, remove/replace 3)rrus, install 12) n batteries, 1) n cabinet, install n 15a breake & n conduit | $45,000 |
| Feb 28, 2024 | In progress issued Sep 2024 | 4501 Irving St | Mastec Network Solutions Inc | tmobile: remove (1)(e) antenna; install (6)(n) antennas within (n) screening; remove (e) equipment from (e) cabinet; no change to (e) electrical panel; no change to (e) batteries.Details
tmobile: remove (1)(e) antenna; install (6)(n) antennas within (n) screening; remove (e) equipment from (e) cabinet; no change to (e) electrical panel; no change to (e) batteries. | $90,000 |
| Feb 28, 2024 | Completed final sign-off Jan 2025 | 1111 California St | Endeavor Wireless Construction Inc, Mastec Network Solutions Inc | t-mobile: remove (2) (e) antennas and (4) (e) rrus; remove (1) (e) cabinet; install (4) (n) antennas, (n) frp screen, (2) (n) cabinets; remove and replace (e) elec panel; install (12) (n) batteries in (n) cabinet.Details
t-mobile: remove (2) (e) antennas and (4) (e) rrus; remove (1) (e) cabinet; install (4) (n) antennas, (n) frp screen, (2) (n) cabinets; remove and replace (e) elec panel; install (12) (n) batteries in (n) cabinet. | $60,000 |
| Feb 13, 2024 | Completed final sign-off Nov 2024 | 185 Berry St | Mastec Network Solutions Inc | revision to tmobile site pa# 2021-0129-3677. revise electrical scope only. no change to antennas or batteries.Details
revision to tmobile site pa# 2021-0129-3677. revise electrical scope only. no change to antennas or batteries. | |
| Jan 25, 2024 | In progress issued Feb 2024 | 959 Peralta Av | Mastec Network Solutions Inc | t-mobile: revision to bpa# 202308245114 - retain (e) cabinet and batteries, revice electrical panel schedule to match.Details
t-mobile: revision to bpa# 202308245114 - retain (e) cabinet and batteries, revice electrical panel schedule to match. | |
| Dec 21, 2023 | Completed final sign-off Jul 2025 | 550 15th St | Mastec Network Solutions Inc | t-mobile: remoce 3 (e) antennas & install 3 (n) antennas; remove 2 (e) cabinets & install 2 (n) cabinets; install 6 (n) rrus; install 12 (n) batteries.Details
t-mobile: remoce 3 (e) antennas & install 3 (n) antennas; remove 2 (e) cabinets & install 2 (n) cabinets; install 6 (n) rrus; install 12 (n) batteries. | $30,000 |
| Dec 8, 2023 | Completed final sign-off May 2024 | 1398 Bryant St | Mastec Network Solutions Inc | revision to pa202210063841. revise sector a to remain in current location. no relocation. (n) rf report to account for revision. no change to aproved batteries.Details
revision to pa202210063841. revise sector a to remain in current location. no relocation. (n) rf report to account for revision. no change to aproved batteries. | |
| Nov 17, 2023 | Completed final sign-off Mar 2025 | 2601 Mission St | Mastec Network Solutions Inc | remove 3-(e) antenna, install 7-new antennas, 1-new radome on rooftop; remove/replace 2-(e) radomes, remove 3-(e) rrus/replace w/7-new rrus; remove (4) cabinet, install new 19" rack w/batteriesDetails
remove 3-(e) antenna, install 7-new antennas, 1-new radome on rooftop; remove/replace 2-(e) radomes, remove 3-(e) rrus/replace w/7-new rrus; remove (4) cabinet, install new 19" rack w/batteries | $45,000 |
| Nov 17, 2023 | Completed final sign-off May 2024 | 1744 Armstrong Av | Mastec Network Solutions Inc | revision to 20203071837. revise cabinet attachement details, revise antenna mounting detail. no change to previous approved antennnas, batteries, electricalDetails
revision to 20203071837. revise cabinet attachement details, revise antenna mounting detail. no change to previous approved antennnas, batteries, electrical | |
| Oct 30, 2023 | Completed final sign-off Jan 2025 | 1200 Folsom St | Mastec Network Solutions Inc | rev to pa# 2022-0512-4168: t-moble install (n) fiber box at equpiment platform (n0t visible; no change to antennas, 6 batteries, rf report, or electricalDetails
rev to pa# 2022-0512-4168: t-moble install (n) fiber box at equpiment platform (n0t visible; no change to antennas, 6 batteries, rf report, or electrical | |
| Oct 25, 2023 | Completed final sign-off Jan 2025 | 213 Ofarrell St | Mastec Network Solutions Inc | revision to pa# 202301240635, t-mobile, remove rbs 6201 cabinet, show (n) cable tray, no change to eme & antennas, no revised electrical work.Details
revision to pa# 202301240635, t-mobile, remove rbs 6201 cabinet, show (n) cable tray, no change to eme & antennas, no revised electrical work. | |
| Oct 2, 2023 | Completed final sign-off Sep 2024 | 770 Golden Gate Av | Mastec Network Solutions Inc | (t-mobile) - remove (1) (e) omni antenna; install (6) (n) antennas and (2) (n) frp screen enclosures; remove (3) (e) rrvs and install (6) (n) rrvs; install (2) (n) cabinets, install (n) batteries.Details
(t-mobile) - remove (1) (e) omni antenna; install (6) (n) antennas and (2) (n) frp screen enclosures; remove (3) (e) rrvs and install (6) (n) rrvs; install (2) (n) cabinets, install (n) batteries. | $125,000 |
| Sep 26, 2023 | In progress issued Oct 2023 | 945 Bryant St | Mastec Network Solutions Inc | install (6) (n) radios on mounts; install (6) (n) antenas on mounts, remove (1) antenna, install (2) (n) cabinets, install (2) (n) frp boxesDetails
install (6) (n) radios on mounts; install (6) (n) antenas on mounts, remove (1) antenna, install (2) (n) cabinets, install (2) (n) frp boxes | $30,000 |
| Sep 26, 2023 | In progress issued Jan 2024 | 888 Brannan St | Mastec Network Solutions Inc | run(n) 2" inner-duct from mpoe to the existing 4"conduit chute at the basement level,run(n) 2"conduit run from the penthouse telco room to the proposed (n)ciena.Details
run(n) 2" inner-duct from mpoe to the existing 4"conduit chute at the basement level,run(n) 2"conduit run from the penthouse telco room to the proposed (n)ciena. | $25,000 |
| Sep 19, 2023 | Completed final sign-off Sep 2026 | 3830 California St | Mastec Network Solutions Inc | tmobile remove e sprint antennas and cabinets, install 6 new antennas and 2 new cabinets, install 1 new frp enclosure, install 12 new batteriesDetails
tmobile remove e sprint antennas and cabinets, install 6 new antennas and 2 new cabinets, install 1 new frp enclosure, install 12 new batteries | $120,000 |
| Aug 30, 2023 | Completed final sign-off May 2024 | 1398 Bryant St | Mastec Network Solutions Inc | rev to pa# 2022-1006-3841; revise antenna model from air 6449 to air 6419 revise rru from model 4424 to 4460 install baseband 6630 and rp 6651 inside (e) cabinetDetails
rev to pa# 2022-1006-3841; revise antenna model from air 6449 to air 6419 revise rru from model 4424 to 4460 install baseband 6630 and rp 6651 inside (e) cabinet | |
| Aug 24, 2023 | Completed final sign-off Apr 2024 | 959 Peralta Av | Mastec Network Solutions Inc | -t-mobile- remove (3) antennas; six tmas existing mounts, remove 4 cabinets and 6 radios. install (6) antennas, (6) radios, new frp enclosure. install (2) new cabinets for batteries and equipment.Details
-t-mobile- remove (3) antennas; six tmas existing mounts, remove 4 cabinets and 6 radios. install (6) antennas, (6) radios, new frp enclosure. install (2) new cabinets for batteries and equipment. | $35,000 |
| Jul 25, 2023 | Completed final sign-off Oct 2024 | 2270 Folsom St | Diablo Telecom & Construction Inc, Mastec Network Solutions Inc | (e) at&t wireless facility modification: remove: 6 at&t ant. install: 3 new at&t ant in (e) footprint. install: 3 new nema dc6, 3 pwr trunks, 1 dc12, 1 batt string, 2 rectifiers, 1 6648 in (e) equip. area. new ant tops not to exceed bldg walls - no change to rad centers & overall height of bldgDetails
(e) at&t wireless facility modification: remove: 6 at&t ant. install: 3 new at&t ant in (e) footprint. install: 3 new nema dc6, 3 pwr trunks, 1 dc12, 1 batt string, 2 rectifiers, 1 6648 in (e) equip. area. new ant tops not to exceed bldg walls - no change to rad centers & overall height of bldg | $60,000 |
| Jul 11, 2023 | Completed final sign-off May 2024 | 1744 Armstrong Av | Mastec Network Solutions Inc | t-mobile: rr 3 rru in equipment room, install 3 new antennas, install 2 new cabinets, install 100a circuit in cabinetDetails
t-mobile: rr 3 rru in equipment room, install 3 new antennas, install 2 new cabinets, install 100a circuit in cabinet | $30,000 |
| Jun 7, 2023 | Never finaled filed Jun 2023, never issued | 4150 Clement St | Mastec Network Solutions Inc | decommission sprint site - remove all sprint and clearwire equipment from rooftop installation and restore site.Details
decommission sprint site - remove all sprint and clearwire equipment from rooftop installation and restore site. | $20,000 |
| May 24, 2023 | Completed final sign-off Jan 2025 | 3252 Pierce St | Mastec Network Solutions Inc | decomission sprint rooftop facility - garage light pole. remove sprint antennas and ground space equipments. all areas to be patched and painted to match surrounding materials.Details
decomission sprint rooftop facility - garage light pole. remove sprint antennas and ground space equipments. all areas to be patched and painted to match surrounding materials. | $20,000 |
| May 18, 2023 | Completed final sign-off May 2024 | 1135 Evans Av | Mastec Network Solutions Inc | t-mobile: remove existing mounts, cables & tmas, install 2 new h-frame mounts, install 2 new antennas & rrus, remove & replace baseband units from existing cabinetsDetails
t-mobile: remove existing mounts, cables & tmas, install 2 new h-frame mounts, install 2 new antennas & rrus, remove & replace baseband units from existing cabinets | $35,000 |
| May 11, 2023 | Completed final sign-off Dec 2023 | 765 Morse St | Mastec Network Solutions Inc | install 3 new antennas; install 3 new radios; remove 1 antenna; remove & replace faux vent; install 3 new hybrid cables. no changes to (e) batteries.Details
install 3 new antennas; install 3 new radios; remove 1 antenna; remove & replace faux vent; install 3 new hybrid cables. no changes to (e) batteries. | $35,000 |
| Apr 6, 2023 | Completed final sign-off Jan 2024 | 1400 Lombard St | Mastec Network Solutions Inc | remove 4 antennas & replace with 4 antennas & add 2 antennas. total 6 antennas. install 6 radios and remove 6 tnas and 12 coax cables. in equipment area, remove (1) 2106 cabinet and install (2) 6160 cabinet and one of them will have (2) psu vand (1) ixre.Details
remove 4 antennas & replace with 4 antennas & add 2 antennas. total 6 antennas. install 6 radios and remove 6 tnas and 12 coax cables. in equipment area, remove (1) 2106 cabinet and install (2) 6160 cabinet and one of them will have (2) psu vand (1) ixre. | $25,000 |
| Feb 27, 2023 | Completed final sign-off Aug 2023 | 1485 Bush St | Mastec Network Solutions Inc | revision to pa 2022-0520-4684: electrical panel 4 breaker 25 amps (n) 200amp panel. all work is interior at the basement for cell site on roof.Details
revision to pa 2022-0520-4684: electrical panel 4 breaker 25 amps (n) 200amp panel. all work is interior at the basement for cell site on roof. | |
| Jan 31, 2023 | Completed final sign-off Mar 2023 | 2412 14th Av | Mastec Network Solutions Inc | revision to 202202238498: change to cabinet installation. changed to 6160, new 100 amp 2 pole breaker and 15 amp for gfci.Details
revision to 202202238498: change to cabinet installation. changed to 6160, new 100 amp 2 pole breaker and 15 amp for gfci. | |
| Jan 26, 2023 | Completed final sign-off Nov 2023 | 1278 Market St | Mastec Network Solutions Inc | t-mobile install (n) wood joist, remove sleeper and install (n) sleepers; relocate 3 (e) antennas, add 3 (n) antennas; 6 total. remove and replace 6 radios; install (n) battery and equipment cabinets; install 100a breaker, (n) hybrid cablesDetails
t-mobile install (n) wood joist, remove sleeper and install (n) sleepers; relocate 3 (e) antennas, add 3 (n) antennas; 6 total. remove and replace 6 radios; install (n) battery and equipment cabinets; install 100a breaker, (n) hybrid cables | $30,000 |
| Jan 24, 2023 | Completed final sign-off Apr 2024 | 213 Ofarrell St | Mastec Network Solutions Inc | t-mobile remove (e) 60"radome & replace 2/2 (n) screen enclosures; remove 3 (e) antennas & replace w/5 (n) antennas; remove 6 (e) rrus' insall 3 (n) rrus; relocate 2 (e) rrus; remove (e) battery cabinet & batteries; install 1 (n) cabinets & 1 (n) batter cabinet w/12 (n) lead/acid batteriesDetails
t-mobile remove (e) 60"radome & replace 2/2 (n) screen enclosures; remove 3 (e) antennas & replace w/5 (n) antennas; remove 6 (e) rrus' insall 3 (n) rrus; relocate 2 (e) rrus; remove (e) battery cabinet & batteries; install 1 (n) cabinets & 1 (n) batter cabinet w/12 (n) lead/acid batteries | $62,000 |
| Jan 3, 2023 | Completed final sign-off Jan 2023 | 959 Peralta Av | Mastec Network Solutions Inc | to obtain final inspection for work approved under pa#201512306123Details
to obtain final inspection for work approved under pa#201512306123 | |
| Dec 29, 2022 | Completed final sign-off Jun 2025 | 121 Spear St | Mastec Network Solutions Inc | decommission & removal of sprint site, returning to original condition.Details
decommission & removal of sprint site, returning to original condition. | $20,000 |
| Dec 12, 2022 | Expired or cancelled cancelled Jan 2026 | 530 Bush St | Mastec Network Solutions Inc | revision to pa#202106253247. (e-1) breaker panel schedule to match installDetails
revision to pa#202106253247. (e-1) breaker panel schedule to match install | |
| Nov 29, 2022 | Completed final sign-off Oct 2024 | 2001 Union St | Mastec Network Solutions Inc, Velex Inc | sprint has contracted velex to remove existing equipment, including electrical connections, off of the exiting rooftop telecommunications site. repair/patch all finishes in kind.Details
sprint has contracted velex to remove existing equipment, including electrical connections, off of the exiting rooftop telecommunications site. repair/patch all finishes in kind. | $12,000 |
| Nov 1, 2022 | Completed final sign-off Mar 2024 | 988 Howard St | Mastec Network Solutions Inc | sprint/t-mobile decommission and removal. removing coax and cables, ice bridge, antennas, rru's, cabinets.Details
sprint/t-mobile decommission and removal. removing coax and cables, ice bridge, antennas, rru's, cabinets. | $20,000 |
| Oct 18, 2022 | Completed final sign-off Oct 2022 | 1520 Stockton St | Mastec Network Solutions Inc | to obtain final inspection for work approved under permit application no# 9920444. all work is complete.Details
to obtain final inspection for work approved under permit application no# 9920444. all work is complete. | |
| Oct 17, 2022 | Completed final sign-off Aug 2024 | 601 California St | Mastec Network Solutions Inc | decommission and removal of sprint site, returning to original condition. removing the following: coax and jumpers, frp if necessary, 5 cabinets - mmbs, bbu, pwr.ppc, sub-panel, e-mon meter with assoc h-frame/conduits, (16) batteries, (5) rectifiers.Details
decommission and removal of sprint site, returning to original condition. removing the following: coax and jumpers, frp if necessary, 5 cabinets - mmbs, bbu, pwr.ppc, sub-panel, e-mon meter with assoc h-frame/conduits, (16) batteries, (5) rectifiers. | $20,000 |
| Oct 6, 2022 | Never finaled issued Jan 2023, no final | 1398 Bryant St | Mastec Network Solutions Inc | t-mobile: remove (6) (e) antennas, install (3) antennas, swap (3) (e) antennas, install (2) (n) cabinets, relocate (1) (e) screen box, install (12) (n) batteries.Details
t-mobile: remove (6) (e) antennas, install (3) antennas, swap (3) (e) antennas, install (2) (n) cabinets, relocate (1) (e) screen box, install (12) (n) batteries. | $53,000 |
| Sep 12, 2022 | Never finaled issued Jan 2023, no final | 1465 25th St | Mastec Network Solutions Inc | t-mobile: remove 3 (e) antnnas and randomes and install 6 (n) antennas and 6 (n) radynesm renive 3 (e) rrus install 3 (n) rrvs remove 1 (e) battery rock and install 1 (n) battery cabinet, swap 12(e) batteries, install 1 (n) 100 amp breakerDetails
t-mobile: remove 3 (e) antnnas and randomes and install 6 (n) antennas and 6 (n) radynesm renive 3 (e) rrus install 3 (n) rrvs remove 1 (e) battery rock and install 1 (n) battery cabinet, swap 12(e) batteries, install 1 (n) 100 amp breaker | $65,000 |
| Sep 1, 2022 | Completed final sign-off Aug 2024 | 888 Brannan St | Mastec Network Solutions Inc | remove/replace 6 (e) antenna w/ 6 new antennas. remove/replace three (3) existing rru radios w/3 new radios; install three (3) new rrus, diplexers + hybrid cables. install two (2) new battery and euipment cabinets (4) total; remove/repacle 50a breaker w/ new 100 amp break panel inside electrical rmDetails
remove/replace 6 (e) antenna w/ 6 new antennas. remove/replace three (3) existing rru radios w/3 new radios; install three (3) new rrus, diplexers + hybrid cables. install two (2) new battery and euipment cabinets (4) total; remove/repacle 50a breaker w/ new 100 amp break panel inside electrical rm | $40,000 |
| Aug 19, 2022 | Never finaled issued May 2023, no final | 3595 Taraval St | Mastec Network Solutions Inc | sprint - cell site remove existing equipment, including electrical connections, off of the existing rooftop telecommunications site. repair/patch all finishes in kind.Details
sprint - cell site remove existing equipment, including electrical connections, off of the existing rooftop telecommunications site. repair/patch all finishes in kind. | $12,000 |
| Aug 18, 2022 | Completed final sign-off Apr 2024 | 5226 Mission St | Mastec Network Solutions Inc | sprint - remove existing cell site equipment, including electrical connections, off the existing rooftop telecommunications site.Details
sprint - remove existing cell site equipment, including electrical connections, off the existing rooftop telecommunications site. | $12,000 |
| Aug 10, 2022 | Expired or cancelled cancelled Nov 2023 | 417 31st Av | Mastec Network Solutions Inc | modification an (e) unmanned telecommunications facility. decommission and removal. removing steel platform;removing (3) hybrids and jumpers. removing (3) panel antennas & (9) rrus, removing fiber and equipment. removing mmbs, bbu, pwr, telco ppc cabs & assoc h-frames and conduits.Details
modification an (e) unmanned telecommunications facility. decommission and removal. removing steel platform;removing (3) hybrids and jumpers. removing (3) panel antennas & (9) rrus, removing fiber and equipment. removing mmbs, bbu, pwr, telco ppc cabs & assoc h-frames and conduits. | $2,000 |
| Jul 20, 2022 | Completed final sign-off May 2023 | 1520 Stockton St | Mastec Network Solutions Inc | install two radomes per section - 6 total roof level; remove and replace six (6) antennas; remove (9) (e) radios and replace in (6) new rru radios; install (2) new cabinets; remove existing 100a ppc reaplace w/ new 200a ppcDetails
install two radomes per section - 6 total roof level; remove and replace six (6) antennas; remove (9) (e) radios and replace in (6) new rru radios; install (2) new cabinets; remove existing 100a ppc reaplace w/ new 200a ppc | $35,000 |
| Jul 18, 2022 | Completed final sign-off Oct 2024 | 1100 Oak St | Endeavor Wireless Construction Inc, Mastec Network Solutions Inc, Velex Inc | sprint has contracted velex to remove existing equipment, including electrical connections, off of the exiting rooftop telecommunications site. including antennas, mounts, cabinets, panels, and batteries. after removal of equipment, the rooftop will be stored to pre-project conditions.Details
sprint has contracted velex to remove existing equipment, including electrical connections, off of the exiting rooftop telecommunications site. including antennas, mounts, cabinets, panels, and batteries. after removal of equipment, the rooftop will be stored to pre-project conditions. | $12,000 |
| Jul 14, 2022 | Completed final sign-off Jul 2023 | 1485 Bay Shore Bl | Mastec Network Solutions Inc | remove 3 existing sprint antenna, remove 3 e sprint radios, install 6 new antennas, 6 new mounts, 6 new rrus, remove and replace 2 cabinetsDetails
remove 3 existing sprint antenna, remove 3 e sprint radios, install 6 new antennas, 6 new mounts, 6 new rrus, remove and replace 2 cabinets | $35,000 |