Kathryn Briggs
- Listed as
- architect, engineer
- Firm
- Base Design
- Based in
- San Francisco
- On San Francisco permits
- Sep 2016 to Oct 2026
120 permits since 2000 (engineer on 117 permits, architect on 3 permits): 61 completed, 40 in progress, 12 never finaled, 7 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 120.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 1, 2026 | In progress issued Oct 2026 | 271 09th Av | A2z Construction Co | revision to pa 202607014458 provide geogrouting at adjacent property in lieu of installing replacement footing @ property line in sectionsDetails
revision to pa 202607014458 provide geogrouting at adjacent property in lieu of installing replacement footing @ property line in sections | |
| Sep 30, 2026 | In progress issued Oct 2026 | 267 09th Av | A2z Construction Co | geogrouting requested by inspector. provide geogrouting along south property line for replacment of footing @ 271 9th ave per 202607014458Details
geogrouting requested by inspector. provide geogrouting along south property line for replacment of footing @ 271 9th ave per 202607014458 | $3,500 |
| Sep 29, 2026 | In progress filed Sep 2026, not yet issued | 554 Mangels Av | replacement of existing retaining walls at rear yardDetails
replacement of existing retaining walls at rear yard | $6,000 | |
| Jul 27, 2026 | In progress issued Jul 2026 | 2677 California St | Fay Construction & Restoration Inc | interior remodel at kitchen and bathrooms: converting (e) bath and toilet rooms into 2 full baths, kitchen in new location (n) opening at kitchen wall, in kind windows replacements (not street visible) and new bath #3Details
interior remodel at kitchen and bathrooms: converting (e) bath and toilet rooms into 2 full baths, kitchen in new location (n) opening at kitchen wall, in kind windows replacements (not street visible) and new bath #3 | $240,000 |
| Jul 21, 2026 | In progress issued Jul 2026 | 1262 46th Av | Actually Design Build Inc | revision to bpa:202510207736- at rear southeast corner, step in south and west exterior walls in 6" @ 1st floor and add 1 skylight.Details
revision to bpa:202510207736- at rear southeast corner, step in south and west exterior walls in 6" @ 1st floor and add 1 skylight. | $1,500 |
| Jun 2, 2026 | In progress filed Jun 2026, not yet issued | 3950 Clay St | floor 1, renovate (e) gameroom, utility and bathroom. add powder room (no exterior work).Details
floor 1, renovate (e) gameroom, utility and bathroom. add powder room (no exterior work). | $65,000 | |
| Jun 1, 2026 | In progress filed Jun 2026, not yet issued | 329 Eureka St | Concannon Construction Inc | interior remodel and rear horizontal extension. new deck over rear extension.Details
interior remodel and rear horizontal extension. new deck over rear extension. | $200,000 |
| May 21, 2026 | In progress issued Jun 2026 | 1858 Union St | Zack De Vito Inc | revision to 202604239938, new framing of bathroom floor and wallsDetails
revision to 202604239938, new framing of bathroom floor and walls | $10,000 |
| May 18, 2026 | In progress filed May 2026, not yet issued | 1333 Columbus Av | erect 4-story, type 3a, mixed-use building, 3-residential units and 1-commercial.Details
erect 4-story, type 3a, mixed-use building, 3-residential units and 1-commercial. | $1,875,000 | |
| Mar 18, 2026 | In progress issued Aug 2026 | 260 Avila St | Noni Homes Inc | interior renovation - relocate kitchen and bathrooms, new skylights, replace windows, new front door and garage door. no change to height or bulk.Details
interior renovation - relocate kitchen and bathrooms, new skylights, replace windows, new front door and garage door. no change to height or bulk. | $300,000 |
| Mar 17, 2026 | In progress issued Sep 2026 | 2124 Green St | Sonoma Build Group Inc | vertical & horizontal addition to (e) two unit building. excavation & expansion of basement.Details
vertical & horizontal addition to (e) two unit building. excavation & expansion of basement. | $125,000 |
| Mar 12, 2026 | In progress issued Mar 2026 | 2020 Green St | C L & Y Construction Inc. | revision to pa #202506149364 to address exisiting conditions. revision include shifting beam along grid d between line 4&6 on 2/s2.0 to grid f; shift beam along grid d between 2 &4 on 2/s2.0 to line c; remove beam along line 4 between c & f. posts updated with (n) beam locations. (n) reinforced ftgDetails
revision to pa #202506149364 to address exisiting conditions. revision include shifting beam along grid d between line 4&6 on 2/s2.0 to grid f; shift beam along grid d between 2 &4 on 2/s2.0 to line c; remove beam along line 4 between c & f. posts updated with (n) beam locations. (n) reinforced ftg | |
| Mar 11, 2026 | In progress issued Apr 2026 | 1424 Alabama St | Inspiration Construction Inc | reconfigure (e) bedroom doors and closets. remodel (e) kitchen. add (2) new skylights. convert unconditioned space on ground floor to media room, wet bar, and full bathroom, add interior stair to 2nd floor.Details
reconfigure (e) bedroom doors and closets. remodel (e) kitchen. add (2) new skylights. convert unconditioned space on ground floor to media room, wet bar, and full bathroom, add interior stair to 2nd floor. | $100,000 |
| Mar 9, 2026 | In progress issued Sep 2026 | 1382 10th Av | revision to pa # 2022-1128-7200: replace 2 glulam beams with hss beamsDetails
revision to pa # 2022-1128-7200: replace 2 glulam beams with hss beams | $500 | |
| Mar 5, 2026 | In progress issued Apr 2026 | 265 Divisadero St | Actually Design Build Inc | demo and rebuild laundry room and rear exterior staircase in-kind, replace 4 rear windows and 1 door each on l1,l2,l3. add 2 sky lights at l3 roof. demo and remodel kitchen and barhroom at l3.Details
demo and rebuild laundry room and rear exterior staircase in-kind, replace 4 rear windows and 1 door each on l1,l2,l3. add 2 sky lights at l3 roof. demo and remodel kitchen and barhroom at l3. | $150,000 |
| Mar 2, 2026 | In progress issued May 2026 | 563 18th Av | Dunros Construction | rebuild (e) deteriorating exterior stair at rear of the building for life/safety purposes. rebuild (e) decks at each of the 3 floor levels in a revised configuration.Details
rebuild (e) deteriorating exterior stair at rear of the building for life/safety purposes. rebuild (e) decks at each of the 3 floor levels in a revised configuration. | $50,000 |
| Jan 22, 2026 | Completed final sign-off Jun 2026 | 3349 Divisadero St | Build Group Inc. | new drywall, new sliding door at storage, new storage windows, new lighting and electrical. replacmeent facade windows in kind localized voluntary structural strengthening at gridline b and c. mandatory seismic strenghting at gridline a. new garage storage.Details
new drywall, new sliding door at storage, new storage windows, new lighting and electrical. replacmeent facade windows in kind localized voluntary structural strengthening at gridline b and c. mandatory seismic strenghting at gridline a. new garage storage. | $35,000 |
| Jan 13, 2026 | Completed final sign-off May 2026 | 271 Castro St | Keaveney Construction | strengthen existing brick retaining wallDetails
strengthen existing brick retaining wall | $5,000 |
| Dec 23, 2025 | Completed final sign-off Sep 2026 | 33 Mountain Spring Av | Nima Construction | revision to 202505297535, revise addition at 2nd fl from 89 sf to 245 sfw, interior remodel to remainDetails
revision to 202505297535, revise addition at 2nd fl from 89 sf to 245 sfw, interior remodel to remain | $60,000 |
| Dec 8, 2025 | In progress issued Dec 2025 | 2627 16th Av | Mission Home Remodeling Inc, Soto Fernando | revision to permits 2025-02251029 & 2025-0731-2075. replace approximately 17'-0" of existing footing at north property lineDetails
revision to permits 2025-02251029 & 2025-0731-2075. replace approximately 17'-0" of existing footing at north property line | $20,000 |
| Dec 3, 2025 | Completed final sign-off Jun 2026 | 1262 46th Av | Actually Design Build Inc | demolish existing type 5, 2-story 1-bedroom single family home.Details
demolish existing type 5, 2-story 1-bedroom single family home. | $30,000 |
| Dec 3, 2025 | In progress issued Apr 2026 | 1262 46th Av | Actually Design Build Inc | erect a (n) type v-b, 3-story building with 2 residential units.Details
erect a (n) type v-b, 3-story building with 2 residential units. | $620,000 |
| Nov 18, 2025 | Completed final sign-off Sep 2026 | 562 40th Av | 40' add 4' to existing fence, not to exceed 10' in heightDetails
40' add 4' to existing fence, not to exceed 10' in height | $1,900 | |
| Sep 12, 2025 | In progress filed Sep 2025, not yet issued | 2237 Mason St | addition of 2 common bathrooms and 37 bathrooms including 4 ada compliant bathrooms. removal of existing common bathrooms and reconfiguration of guest rooms on 2nd & 3rd floor. no change to room count. new elevator shaft.Details
addition of 2 common bathrooms and 37 bathrooms including 4 ada compliant bathrooms. removal of existing common bathrooms and reconfiguration of guest rooms on 2nd & 3rd floor. no change to room count. new elevator shaft. | $1,300,000 | |
| Aug 26, 2025 | Completed final sign-off Aug 2026 | 2083 29th Av | Cht Properties Development | enclose entryway and stairwell. add bathroom and office at gr fl. rebuild interior staircase. new window and door at rear wall.Details
enclose entryway and stairwell. add bathroom and office at gr fl. rebuild interior staircase. new window and door at rear wall. | $150,000 |
| Aug 13, 2025 | In progress issued Feb 2026 | 1006 Carolina St | Rico's General Construction | reconfiguration of lower unit interior- 1/f and 2/f, reconfiguration of upper unit interior- 3/f. removal of (e) rear decks and addition of (n) cantilevered deck @ 3/f. front and rear facade alteration. addition of (n) exterior staris connecting (e) rear yard to ground flr. reroofing.Details
reconfiguration of lower unit interior- 1/f and 2/f, reconfiguration of upper unit interior- 3/f. removal of (e) rear decks and addition of (n) cantilevered deck @ 3/f. front and rear facade alteration. addition of (n) exterior staris connecting (e) rear yard to ground flr. reroofing. | $770,047 |
| Aug 12, 2025 | In progress issued Feb 2026 | 663 44th Av | Hunter Dale Builders Inc. | horizontal addition at 1st floor below (e) 2nd floor cantilever to create a new sun room at level 1. convert part of garage to condition space for primary bedroom suite. new windows & doors on the 1st floor level facing the rear yard.Details
horizontal addition at 1st floor below (e) 2nd floor cantilever to create a new sun room at level 1. convert part of garage to condition space for primary bedroom suite. new windows & doors on the 1st floor level facing the rear yard. | $125,000 |
| Aug 11, 2025 | In progress issued Dec 2025 | 3713 Lawton St | A-1 Dynamic Builders Inc., Apex General Builder Inc | addition new adu; add roof decks along east and west w/interior space created within the new barrel vault roof. new barrel vault roof will exceed 35ft height limit by measurement equal to 50% said height limit to finihsed floor; add rear bump outs to 2/f & 3/f; add rear decks. move front door.Details
addition new adu; add roof decks along east and west w/interior space created within the new barrel vault roof. new barrel vault roof will exceed 35ft height limit by measurement equal to 50% said height limit to finihsed floor; add rear bump outs to 2/f & 3/f; add rear decks. move front door. | $450,000 |
| Jul 31, 2025 | In progress issued Aug 2025 | 2627 16th Av | Mission Home Remodeling Inc, Soto Fernando | revision to 202502251029: level 2: remove center courtyard. add 2 skylights at kitchen, 2 skylights at office, 1 skylight at hallway. structural work included.Details
revision to 202502251029: level 2: remove center courtyard. add 2 skylights at kitchen, 2 skylights at office, 1 skylight at hallway. structural work included. | $25,000 |
| Jul 18, 2025 | In progress issued Sep 2025 | 2339 39th Av | F C Company | rear deck and stair. replace two windows at front elevation. replace two rear windows with doors.Details
rear deck and stair. replace two windows at front elevation. replace two rear windows with doors. | $25,000 |
| Jul 16, 2025 | Completed final sign-off Aug 2026 | 1250 42nd Av | Actually Design Build Inc | at first floor: reconfigure existing bathroom and bedroom, add one bedroom. at second floor: extend primary bedroom and relocate powder room. adding 435 sf conditioned area. new windows and door at rear walls.Details
at first floor: reconfigure existing bathroom and bedroom, add one bedroom. at second floor: extend primary bedroom and relocate powder room. adding 435 sf conditioned area. new windows and door at rear walls. | $130,000 |
| May 14, 2025 | In progress issued Oct 2025 | 7 Bennington St | Rico's General Construction | remodel & vertical expansion of an (e)single family dwelling structure,including a modification of a small portion of the ground fl,modification of the (e)2nd fl,addition of a new 3rd fl and a small roof deck,modification of front & rear facades,& addition of a small rear deckDetails
remodel & vertical expansion of an (e)single family dwelling structure,including a modification of a small portion of the ground fl,modification of the (e)2nd fl,addition of a new 3rd fl and a small roof deck,modification of front & rear facades,& addition of a small rear deck | $558,000 |
| Apr 25, 2025 | Completed final sign-off Jun 2026 | 1747 Broadway | Cbs Construction Inc. | interior remodel of e) condo unit. total bedrooms changing from 4 to 2. add 1 bath. minor reconfiguration of inteior walls & doors. remodel 1 kitchen, 1 full bath, & 1 half bath. replace all non st facing windowsDetails
interior remodel of e) condo unit. total bedrooms changing from 4 to 2. add 1 bath. minor reconfiguration of inteior walls & doors. remodel 1 kitchen, 1 full bath, & 1 half bath. replace all non st facing windows | $40,000 |
| Mar 12, 2025 | In progress filed Mar 2025, not yet issued | 62 Jordan Av | replace (e) exterior front entry steps in-like kind + 3'0' landingDetails
replace (e) exterior front entry steps in-like kind + 3'0' landing | $16,000 | |
| Feb 26, 2025 | In progress filed Feb 2025, not yet issued | 2322 Lombard St | altered site permit to 2014/1217/3954: converting parking (17 spaces) to 14 new guest rooms and 3/f converting storage to 1 new guest room. increasing total guestrooms count from 60 to 75. addition of a fire wall for area increase. new flr opening to above lightwells, reconfigure lobby add laundry.Details
altered site permit to 2014/1217/3954: converting parking (17 spaces) to 14 new guest rooms and 3/f converting storage to 1 new guest room. increasing total guestrooms count from 60 to 75. addition of a fire wall for area increase. new flr opening to above lightwells, reconfigure lobby add laundry. | $200,000 | |
| Feb 25, 2025 | Completed final sign-off Feb 2026 | 217 Holly Park Cr | replacement/modification of existing rear exterior stair and existing patio for improved egress and access per variance case #2024-000042var. structural updates for stair support, new patio door and windows to replace existing updated to egress plan rescue criteria alternative 3:Details
replacement/modification of existing rear exterior stair and existing patio for improved egress and access per variance case #2024-000042var. structural updates for stair support, new patio door and windows to replace existing updated to egress plan rescue criteria alternative 3: | $20,000 | |
| Feb 25, 2025 | In progress issued Jul 2025 | 2627 16th Av | Mission Home Remodeling Inc, Soto Fernando | level 2- remodel kitchen, remodel bathroom, add bathroom, new windows at atruium and lightwell and rear wall. all new siding and waterproofing at rear wall and lightwell level 1- add bathroom, office and bedroom, two new sliding doors to rear yard. add concrete retaining wall and patio at rear yardDetails
level 2- remodel kitchen, remodel bathroom, add bathroom, new windows at atruium and lightwell and rear wall. all new siding and waterproofing at rear wall and lightwell level 1- add bathroom, office and bedroom, two new sliding doors to rear yard. add concrete retaining wall and patio at rear yard | $250,000 |
| Nov 20, 2024 | Completed final sign-off Apr 2026 | 1916 Great Hy | Mc Gowan Builders | revision to permit #202108065980.reduce size of primary bed with small job in wall near top of stairs.swap locations for primary bath & closet.change door to primary bed to pocket door.remove skylight in primary closet.revise stairs & reduce number of stair risers to 16 instead of 17.Details
revision to permit #202108065980.reduce size of primary bed with small job in wall near top of stairs.swap locations for primary bath & closet.change door to primary bed to pocket door.remove skylight in primary closet.revise stairs & reduce number of stair risers to 16 instead of 17. | $5,000 |
| Nov 19, 2024 | In progress issued Nov 2025 | 2434 43rd Av | to erect 1 story, no basement, type v, detached adu at rear of house.Details
to erect 1 story, no basement, type v, detached adu at rear of house. | $120,000 | |
| Nov 15, 2024 | Completed final sign-off Feb 2025 | 75 Elgin Pk | Red White & Blue Construction Inc. | rev to pa 202405172403 to address (e) conditions.Details
rev to pa 202405172403 to address (e) conditions. | $20,000 |
| Oct 25, 2024 | Completed final sign-off Mar 2025 | 650 46th Av | Actually Design Build Inc | revision to pa# 202312112256, remove 1 skylight, add 2 skylights over stairs, remove 2 windows at rear wall. change window to sliding door at rear wall.Details
revision to pa# 202312112256, remove 1 skylight, add 2 skylights over stairs, remove 2 windows at rear wall. change window to sliding door at rear wall. | |
| Aug 29, 2024 | Completed final sign-off Jun 2025 | 1643 44th Av | Actually Design Build Inc | revision to pa # 2023-0627-0938 structural framing revisionsDetails
revision to pa # 2023-0627-0938 structural framing revisions | $1,000 |
| Aug 15, 2024 | Expired or cancelled expired Sep 2026 | 2542 Great Hy | Chl Construction Company | remove wall betweek kitchen/dining on 2nd flrDetails
remove wall betweek kitchen/dining on 2nd flr | $30,000 |
| May 20, 2024 | Expired or cancelled expired Feb 2026 | 4454 17th St | remodel of kitchen. work to include relocating of structural wall, new plumbing fixtures, lighting, finishes & millwork/cabinetry to be addedDetails
remodel of kitchen. work to include relocating of structural wall, new plumbing fixtures, lighting, finishes & millwork/cabinetry to be added | $50,000 | |
| May 14, 2024 | In progress issued Jun 2024 | 217 Randall St | Paul K Vou | replace existing foundaton with slab on gradeDetails
replace existing foundaton with slab on grade | $80,000 |
| Apr 12, 2024 | Completed final sign-off Sep 2024 | 219 Paris St | Actually Design Build Inc | relocate existing bathroom, add a powder room, add new interior staircase, structural work included. no exterior work.Details
relocate existing bathroom, add a powder room, add new interior staircase, structural work included. no exterior work. | $75,000 |
| Mar 14, 2024 | Completed final sign-off Feb 2025 | 64 Crags Ct | Baldenebro Construction | replace hardwood floors throughout. relocate washer & dryer to kitchen. alter bedroom hallway. skim coat plaster walls. provde fire rated sheet rock at garage. upgrade electrical lighting and outletsDetails
replace hardwood floors throughout. relocate washer & dryer to kitchen. alter bedroom hallway. skim coat plaster walls. provde fire rated sheet rock at garage. upgrade electrical lighting and outlets | $30,000 |
| Mar 12, 2024 | Completed final sign-off Jun 2024 | 2912 Hawes St | Associated Builders | revision to pa #201907024993 to replace an extg cripple wall at grid line d with concrete and to account for ppreviosly unknown higher elevation at the neighbor's grade at 2020 hawes.Details
revision to pa #201907024993 to replace an extg cripple wall at grid line d with concrete and to account for ppreviosly unknown higher elevation at the neighbor's grade at 2020 hawes. | $1,500 |
| Dec 22, 2023 | Completed final sign-off Nov 2024 | 2610 Greenwich St | Ayala Builder's And Company Inc | the scope of work involves infilling space at rear on the basement level under (e) first fl. abitable space acess and stair from 1st fl. to basement level to be modifiedDetails
the scope of work involves infilling space at rear on the basement level under (e) first fl. abitable space acess and stair from 1st fl. to basement level to be modified | $59,000 |
| Nov 9, 2023 | In progress issued Nov 2023 | 112 Day St | revision to pa# 202205244829 & 202112164572. add 3 skylights. increase size of openings between kitchens & living rooms on 2nd & 3rd fl. replace (e) windows at rear facing living room on 3rd fl. expand 2nd fl bathroom into pantry area. change patio to concrete pavers.Details
revision to pa# 202205244829 & 202112164572. add 3 skylights. increase size of openings between kitchens & living rooms on 2nd & 3rd fl. replace (e) windows at rear facing living room on 3rd fl. expand 2nd fl bathroom into pantry area. change patio to concrete pavers. | ||
| Nov 6, 2023 | In progress issued Jul 2025 | 915 Haight St | J 1 Construction | remove portion of (e) roof and rpelace with new shed roofs to increase headroom. install new deck at rear of 4/f level. convert attice space to habitable space connected to (e) third floor.Details
remove portion of (e) roof and rpelace with new shed roofs to increase headroom. install new deck at rear of 4/f level. convert attice space to habitable space connected to (e) third floor. | $200,000 |
| Oct 24, 2023 | Completed final sign-off Apr 2024 | 491 27th St | Actually Design Build Inc | widen garage door opening 12". replace one wood window at front elevation. install new garage door. structural work included.Details
widen garage door opening 12". replace one wood window at front elevation. install new garage door. structural work included. | $30,000 |
| Oct 10, 2023 | Completed final sign-off Mar 2025 | 1824 Jackson St | North Bay Construction | remodel kitchen, primary bath. work to include relocating structural wall. new plumbing fixtures, lighting, finishes, milllwork cabinetry to be added. no additinal sq footage. no horizontal or vertical expansions.Details
remodel kitchen, primary bath. work to include relocating structural wall. new plumbing fixtures, lighting, finishes, milllwork cabinetry to be added. no additinal sq footage. no horizontal or vertical expansions. | $350,000 |
| Sep 28, 2023 | Completed final sign-off May 2025 | 326 Lawton St | Sft Construction Corp | enlarge 3rd floor bedroom & add bathroom by raising (e) roofline. new construction to cover (e) lightwell at 2nd floor. no change in building footprint of overall building height.Details
enlarge 3rd floor bedroom & add bathroom by raising (e) roofline. new construction to cover (e) lightwell at 2nd floor. no change in building footprint of overall building height. | $90,000 |
| Sep 14, 2023 | Completed final sign-off May 2025 | 436 Gold Mine Dr | American Builders | remodel kitchen, partial structural wall removal, entry extension inside courtyard at 2nd fl. structural wall removal, remodel e bath, new laundry, new sauna, new storage at 1st flDetails
remodel kitchen, partial structural wall removal, entry extension inside courtyard at 2nd fl. structural wall removal, remodel e bath, new laundry, new sauna, new storage at 1st fl | $175,000 |
| Aug 24, 2023 | Completed final sign-off Dec 2024 | 1662 47th Av | Kingfish Construction Llc. | new office and bathroom at 1st fl. new doors and windows at rearDetails
new office and bathroom at 1st fl. new doors and windows at rear | $65,000 |
| Aug 10, 2023 | Completed final sign-off Apr 2024 | 2608 Diamond St | Actually Design Build Inc | conversion one bedroom and remodel one bathroom at ground floor. replace windows on rear exterior at ground floor. remove exterior door and replace with window on level 2 at rear wall.Details
conversion one bedroom and remodel one bathroom at ground floor. replace windows on rear exterior at ground floor. remove exterior door and replace with window on level 2 at rear wall. | $80,000 |
| Aug 9, 2023 | Never finaled filed Aug 2023, never issued | 1107 Gilman Av | rebuild entry steps to residence.Details
rebuild entry steps to residence. | $3,500 | |
| Jul 17, 2023 | Completed final sign-off Feb 2026 | 217 Holly Park Cr | Bradford Construction | interior renovation of 2-unit bldg. excavation at basement level for structural enhancements for (e) support (n) fixtures, finishes & windows. in-kind window + door replacement. excavation >50 y, does not exceed 8 vertical ft soil disturbance. no work outside exterior envelope. no work outside prow.Details
interior renovation of 2-unit bldg. excavation at basement level for structural enhancements for (e) support (n) fixtures, finishes & windows. in-kind window + door replacement. excavation >50 y, does not exceed 8 vertical ft soil disturbance. no work outside exterior envelope. no work outside prow. | $842,000 |
| Jun 22, 2023 | Completed final sign-off Apr 2024 | 478 Hoffman Av | Robert Kennedy Construction | new dormer and roof extension at 3rd level bedroom, scope of work includes new rated property line wall and parapetm new skylight, new rear facing window, no increase in gsf, new electrical, lighting and finishes in bedroom.Details
new dormer and roof extension at 3rd level bedroom, scope of work includes new rated property line wall and parapetm new skylight, new rear facing window, no increase in gsf, new electrical, lighting and finishes in bedroom. | $50,000 |
| Jun 8, 2023 | Completed final sign-off Feb 2024 | 171 Robinhood Dr | Hunter Dale Builders Inc. | renovation of the principal batroom and kitchem of an (e) single family home, the project adds conditionded space behind the (e) garage and relocates the stair from the lower to mid levels, no new square footae added, 261 sf of condidioned space addedDetails
renovation of the principal batroom and kitchem of an (e) single family home, the project adds conditionded space behind the (e) garage and relocates the stair from the lower to mid levels, no new square footae added, 261 sf of condidioned space added | $125,000 |
| May 10, 2023 | Completed final sign-off Apr 2024 | 866 Brussels St | Triond Remodeling Inc | rev to pa# 2021-0428-9490: to add 10" interior concrete wallDetails
rev to pa# 2021-0428-9490: to add 10" interior concrete wall | $5,000 |
| Apr 21, 2023 | In progress issued Sep 2024 | 1701 Broderick St | Seamus Melaugh Construction | foundation update for lvel 1 addition (unit 1701): (n) bath , kitchenette, bedroom. level 2 & 3 (unit 1703): renovation to (e) floor plan layouts. (n) level 3 interior stair to roof deck. (n) roof deck w/ pop up stair & trellis. 2nd fl rear deckDetails
foundation update for lvel 1 addition (unit 1701): (n) bath , kitchenette, bedroom. level 2 & 3 (unit 1703): renovation to (e) floor plan layouts. (n) level 3 interior stair to roof deck. (n) roof deck w/ pop up stair & trellis. 2nd fl rear deck | $150,000 |
| Jan 13, 2023 | In progress issued Apr 2024 | 1447 Thomas Av | 1st fl. reconfig.(e) living and garage, add a full bath, a kitchen, bedroom, office, and (1) sliding glass door at the rear of building not visable from a street or other public right-of-way), convert 1st floor into an adu per state program & legalization of all unpermitted work as shown on plans.Details
1st fl. reconfig.(e) living and garage, add a full bath, a kitchen, bedroom, office, and (1) sliding glass door at the rear of building not visable from a street or other public right-of-way), convert 1st floor into an adu per state program & legalization of all unpermitted work as shown on plans. | $42,000 | |
| Dec 21, 2022 | Completed final sign-off Apr 2024 | 5 Starview Wy | A L Martin Construction | remove existing metal cladding, repair existing plaster, replace w/ synthetic wood cladding & plaster, replace existing vinyl & aluminum windows in e opening front visible, street windows remain. new deck at 2/f in rear yard.Details
remove existing metal cladding, repair existing plaster, replace w/ synthetic wood cladding & plaster, replace existing vinyl & aluminum windows in e opening front visible, street windows remain. new deck at 2/f in rear yard. | $180,000 |
| Dec 8, 2022 | Never finaled filed Dec 2022, never issued | 1107 Gilman Av | erect a 1-story garage with storage loft at front of lot, type vb (u-occupancy).Details
erect a 1-story garage with storage loft at front of lot, type vb (u-occupancy). | $180,000 | |
| Dec 1, 2022 | Never finaled issued Dec 2022, no final | 1 Loma Vista Tr | Bergquist Builders | 1st fl: remodel kitchen, living, dining. create powder room. new doors to (e) deck. add gas fire place. 2nd fl: remodel (e) bathroom. create 2nd bath & utility room.Details
1st fl: remodel kitchen, living, dining. create powder room. new doors to (e) deck. add gas fire place. 2nd fl: remodel (e) bathroom. create 2nd bath & utility room. | $160,000 |
| Nov 18, 2022 | Never finaled filed Nov 2022, never issued | 438 44th Av | level 2: remodel of (e) kitchen and bathroom and remove (1) bedroom and addition of (1) new bathroom. level 1: partial (e) garage conversion to maintain (1)(e) parking space and include a new 560sf dwelling unit.Details
level 2: remodel of (e) kitchen and bathroom and remove (1) bedroom and addition of (1) new bathroom. level 1: partial (e) garage conversion to maintain (1)(e) parking space and include a new 560sf dwelling unit. | $200,000 | |
| Nov 4, 2022 | In progress issued Apr 2024 | 38 Mars St | Eastwood Development Incorporated | vertical addition. renovate facade. create (n) entry on ground floor, with (n) stair connection to all 3 levels. create 4 bedrooms, 2 bathrooms, & laundry on 2nd fl. create (n) living room, dining room, powder room & kitchen on 3rd fl. (n) decks over living spaces below. (n) terracing at rear yard.Details
vertical addition. renovate facade. create (n) entry on ground floor, with (n) stair connection to all 3 levels. create 4 bedrooms, 2 bathrooms, & laundry on 2nd fl. create (n) living room, dining room, powder room & kitchen on 3rd fl. (n) decks over living spaces below. (n) terracing at rear yard. | $620,253 |
| Oct 26, 2022 | Expired or cancelled withdrawn Aug 2024 | 2542 Great Hy | remove wall between kitchen/dining rm. remodel kitchen, new cabinetry, appliances, finishes. remodel bath, replace finishes and plumbing fixtures. no exterior changes.Details
remove wall between kitchen/dining rm. remodel kitchen, new cabinetry, appliances, finishes. remodel bath, replace finishes and plumbing fixtures. no exterior changes. | $35,000 | |
| Aug 29, 2022 | Never finaled issued Jun 2023, no final | 284 Page St | Hunter Dale Builders Inc. | interior remodel to (e) bathrooms & kitchen. convert unconditioned ground floor into conditioned space: new cabinets, lighting, fixtures, finishes. 2 new patio doors on rear elevation, 1 new skylight. no change to lily st apts.Details
interior remodel to (e) bathrooms & kitchen. convert unconditioned ground floor into conditioned space: new cabinets, lighting, fixtures, finishes. 2 new patio doors on rear elevation, 1 new skylight. no change to lily st apts. | $785,000 |
| Aug 11, 2022 | Completed final sign-off Sep 2023 | 1550 45th Av | Actually Design Build Inc | revision to pa# 202012080507. replace front exterior stair and north retaining wall.Details
revision to pa# 202012080507. replace front exterior stair and north retaining wall. | $10,000 |
| Aug 8, 2022 | Expired or cancelled cancelled Jan 2026 | 494 Fair Oaks St | demo of exterior stairs and deck installing new spiral stairsDetails
demo of exterior stairs and deck installing new spiral stairs | $12,000 | |
| Aug 2, 2022 | Completed final sign-off Nov 2025 | 469 Fair Oaks St | Barker-O'donoghue Master Bldrs | remodel and addition to (e) 2-story 2-family dwelling including: interior and exterior alterations throughout. rear, front and 1-story vertical addition. alter front facade, setback and entries. new garage and curb cut. full foundation replacement. bldg will be fully sprinklered under sep. permit.Details
remodel and addition to (e) 2-story 2-family dwelling including: interior and exterior alterations throughout. rear, front and 1-story vertical addition. alter front facade, setback and entries. new garage and curb cut. full foundation replacement. bldg will be fully sprinklered under sep. permit. | $600,000 |
| Jul 15, 2022 | Completed final sign-off Nov 2023 | 1 South Park | Delgado Construction | unit 401: convert bedroom 2 and bedroom 3 into master bedroom, extend the bathroom 3 and add a free-standing bathrtub convert bathroom 2 to a walk-in closet convert living rom to office with neew metal window wall, change (e) stair guardrails to new glass guard railsDetails
unit 401: convert bedroom 2 and bedroom 3 into master bedroom, extend the bathroom 3 and add a free-standing bathrtub convert bathroom 2 to a walk-in closet convert living rom to office with neew metal window wall, change (e) stair guardrails to new glass guard rails | $35,000 |
| Jul 15, 2022 | Never finaled issued Jul 2022, no final | 566 20th Av | Actually Design Build Inc | revision to 202102044033: add exterior stair from 2nd fl deck to rear yard. remove and replace brick at front facadeDetails
revision to 202102044033: add exterior stair from 2nd fl deck to rear yard. remove and replace brick at front facade | $15,000 |
| Jul 13, 2022 | In progress issued May 2024 | 88 Castenada Av | Rico's General Construction | renovation & vertical expansion. alteration to interior comprises of reconfiguration of interior stair. modification of ground fl and l2 floor plans & windows. exterior modifications include front & rear facades, exterior entry area landscaping, and addition of stair penthouse.Details
renovation & vertical expansion. alteration to interior comprises of reconfiguration of interior stair. modification of ground fl and l2 floor plans & windows. exterior modifications include front & rear facades, exterior entry area landscaping, and addition of stair penthouse. | $550,000 |
| Jun 16, 2022 | Completed final sign-off Sep 2024 | 418 Pacheco St | remodel kitchen. remove wall btw dining & kitchen, remove ceiling & dining & kitchen and replace w/ sloped ceiling. new windows @ kitchen and dining.Details
remodel kitchen. remove wall btw dining & kitchen, remove ceiling & dining & kitchen and replace w/ sloped ceiling. new windows @ kitchen and dining. | $40,000 | |
| May 24, 2022 | Never finaled issued May 2023, no final | 112 Day St | 2 story horizontal addition & consisting of home office, dining & roof deck @ 3rd floor. 1 story horizontal addition less than 10' high to the rear of (e) building & extend 12' & consist of 1 new bedroom & rood deck @ 2nd floor. replace (e) wood sairs with spiral stair from 3rd floor to 2nd floor.Details
2 story horizontal addition & consisting of home office, dining & roof deck @ 3rd floor. 1 story horizontal addition less than 10' high to the rear of (e) building & extend 12' & consist of 1 new bedroom & rood deck @ 2nd floor. replace (e) wood sairs with spiral stair from 3rd floor to 2nd floor. | $175,000 | |
| May 3, 2022 | Never finaled issued May 2022, no final | 2179 44th Av | Actually Design Build Inc | revision to pa# 202204132110. structural detail updated to show accurate location of new footing in relation to existing footings.Details
revision to pa# 202204132110. structural detail updated to show accurate location of new footing in relation to existing footings. | $500 |
| Apr 13, 2022 | Never finaled issued Apr 2022, no final | 2179 44th Av | Actually Design Build Inc | structural upgrade to current code. new rear openings. new interior partitions. upgrade of elec/plumb. insulate. new finishes/ fixtures throughout. no increase in gross area / height.Details
structural upgrade to current code. new rear openings. new interior partitions. upgrade of elec/plumb. insulate. new finishes/ fixtures throughout. no increase in gross area / height. | $500,000 |
| Apr 8, 2022 | Expired or cancelled withdrawn Jan 2025 | 1547 43rd Av | ist fl kitchen & powder room work to include demolition and (n) construction (n) plumbing (n) cabinetry (n) lighting and (n) finishes. rear deck under seperated permit.Details
ist fl kitchen & powder room work to include demolition and (n) construction (n) plumbing (n) cabinetry (n) lighting and (n) finishes. rear deck under seperated permit. | $212,000 | |
| Mar 23, 2022 | Completed final sign-off Apr 2023 | 172 Denslowe Dr | Design Max Construction | remodel kitchen & 2 baths. add one new bath. relocate w/d, add d.v. fireplace, replace 2 doors, add/relocate recepticles, new lighting throughout.Details
remodel kitchen & 2 baths. add one new bath. relocate w/d, add d.v. fireplace, replace 2 doors, add/relocate recepticles, new lighting throughout. | $90,000 |
| Mar 8, 2022 | Completed final sign-off Oct 2022 | 2267 25th Av | Perez Construction Llc. | revision to pa# 202202147905. locate washer / dryer under interior stairway. add wet bar on 1st fl. add footing for interior stair landing.Details
revision to pa# 202202147905. locate washer / dryer under interior stairway. add wet bar on 1st fl. add footing for interior stair landing. | $500 |
| Feb 17, 2022 | Never finaled issued Nov 2022, no final | 1946 California St | revision to issued permit#202104138442. extend elevator to flr"4" for unit accessibility.add solar thrells over rear roof deck @ flr"4".Details
revision to issued permit#202104138442. extend elevator to flr"4" for unit accessibility.add solar thrells over rear roof deck @ flr"4". | $30,000 | |
| Feb 14, 2022 | Completed final sign-off Oct 2022 | 2267 25th Av | Perez Construction Llc. | revision to pa 2022-0111-5737 add 305 sf in (e) family rm; remodel (e) bathroom & add half bath on 1st fl; upgrade (e) interior stair; add 4'6x19" skylight & 30" high 1 hr er parapet @ north side lightwellDetails
revision to pa 2022-0111-5737 add 305 sf in (e) family rm; remodel (e) bathroom & add half bath on 1st fl; upgrade (e) interior stair; add 4'6x19" skylight & 30" high 1 hr er parapet @ north side lightwell | $150,000 |
| Jan 13, 2022 | Completed final sign-off Jul 2022 | 226 Moraga St | Actually Design Build Inc | revision to pa# 202010196890. replace slab on grade, replace (e) post and (e) beam with bearing wall & cont ftg, and eliminate at a + 2.Details
revision to pa# 202010196890. replace slab on grade, replace (e) post and (e) beam with bearing wall & cont ftg, and eliminate at a + 2. | $10,000 |
| Jan 4, 2022 | Completed final sign-off Feb 2023 | 1108 Tennessee St | D N S Construction | add new apartment unit, kitchen and bath; add 2 gas heating units; raise ceiling height at breezeway; add fire sprinklers at entire ground fl in accordance with nfpa 13r under a separate permitDetails
add new apartment unit, kitchen and bath; add 2 gas heating units; raise ceiling height at breezeway; add fire sprinklers at entire ground fl in accordance with nfpa 13r under a separate permit | $103,000 |
| Jan 3, 2022 | In progress issued Feb 2026 | 266 Connecticut St | Galaxy Building Construction | rear horizontal & vertical addition. remodel/reconfig (e) sdf to add 1 new unit. add new 6 bathrms. remove (e) kitchen & replace w/new for lower unit. add kitchen & living spaces for upper unit. expand garage. add roof deck. alter front & rear of bldg w/new facade. n flat roof. upgrade foundation.Details
rear horizontal & vertical addition. remodel/reconfig (e) sdf to add 1 new unit. add new 6 bathrms. remove (e) kitchen & replace w/new for lower unit. add kitchen & living spaces for upper unit. expand garage. add roof deck. alter front & rear of bldg w/new facade. n flat roof. upgrade foundation. | $1,168,850 |
| Dec 28, 2021 | Completed final sign-off Jan 2023 | 283 29th Av | A L Martin Construction | remodel: repair and replace wood siding on west and south elevations. replace door and windows on west and south elevations in kind. replace existing deck in rear yard in kind. new partial concrete retaining wall.Details
remodel: repair and replace wood siding on west and south elevations. replace door and windows on west and south elevations in kind. replace existing deck in rear yard in kind. new partial concrete retaining wall. | $100,000 |
| Dec 16, 2021 | Completed final sign-off May 2025 | 112 Day St | convert unoccupied space at ground floor to habitable space. infill at rear of ground floor below (e) 2nd floor. (n) interior stair to connect (n) space to (e) 2nd floor unit. (n) rooms to include media room, 2 home offices, 2 full bathrooms. 26 cy excavationDetails
convert unoccupied space at ground floor to habitable space. infill at rear of ground floor below (e) 2nd floor. (n) interior stair to connect (n) space to (e) 2nd floor unit. (n) rooms to include media room, 2 home offices, 2 full bathrooms. 26 cy excavation | $200,000 | |
| Nov 15, 2021 | Completed final sign-off Jul 2023 | 1954 48th Av | new 2nd floor deck at rear of house with stairs down to 1st floor backyard and 3 new exterior doors at the rear facade of the house.Details
new 2nd floor deck at rear of house with stairs down to 1st floor backyard and 3 new exterior doors at the rear facade of the house. | $20,000 | |
| Sep 2, 2021 | Completed final sign-off Jan 2022 | 1307 Francisco St | Robert Bernhard Coatings/Rbc Inc | 1 wall to be removed to make 2 closets an office. replace (e) window in-kind.Details
1 wall to be removed to make 2 closets an office. replace (e) window in-kind. | $165,000 |
| Aug 11, 2021 | Completed final sign-off Jan 2022 | 85 Central Av | Excelsior Building Group | remove interior columns & walls to increase width & depth of garage parking area; replace interior beams. install doors at ground level at rear of buildingDetails
remove interior columns & walls to increase width & depth of garage parking area; replace interior beams. install doors at ground level at rear of building | $75,000 |
| Jul 7, 2021 | Completed final sign-off Jun 2023 | 255 Silliman St | mudroom addition to signle family residenceDetails
mudroom addition to signle family residence | $30,000 | |
| Feb 17, 2021 | In progress issued May 2025 | 249 Texas St | Hunter Dale Builders Inc. | erect a four story + basement type 5-b construction two family dwelling unitsDetails
erect a four story + basement type 5-b construction two family dwelling units | $810,000 |
| Feb 3, 2021 | Completed final sign-off Mar 2022 | 915 Haight St | J 1 Construction | emergency roof repair to replace remove portion of roof in original configuration in respose to complaint 202061201. legalize (e) iron security gate at front & tradesman alleyDetails
emergency roof repair to replace remove portion of roof in original configuration in respose to complaint 202061201. legalize (e) iron security gate at front & tradesman alley | $50,000 |
| Sep 19, 2020 | Completed final sign-off Apr 2021 | 4450 24th St | interior remodel of first floor (main) including partial demo of bearing wall and demo of non-structural walls. no work to exterior of building.Details
interior remodel of first floor (main) including partial demo of bearing wall and demo of non-structural walls. no work to exterior of building. | $10,000 | |
| Sep 18, 2020 | Completed final sign-off Oct 2022 | 203 Carl St | De Brus Construction Inc | revision to pa# 201902072327. modifications to ground fl framing, 3rd fl framing, shearwall layout & moment frame bracing members.Details
revision to pa# 201902072327. modifications to ground fl framing, 3rd fl framing, shearwall layout & moment frame bracing members. | $30,000 |
| Sep 9, 2020 | Completed final sign-off Dec 2021 | 2075 Mission St | Hasz Construction Inc | per cua 2019-004451prj tenant build out cannabis retail consumption lounge, mill work, storage, locker, shower rooms, office, existing restroom to be ada compliant, relocate doors at entry, new finishes, lighting.Details
per cua 2019-004451prj tenant build out cannabis retail consumption lounge, mill work, storage, locker, shower rooms, office, existing restroom to be ada compliant, relocate doors at entry, new finishes, lighting. | $420,000 |