31 permits since 2000: 20 completed, 6 in progress, 5 expired or cancelled.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 28, 2026 | Completed final sign-off Sep 2026 | 600 Wisconsin St | to obtain final inspection for work approved under pa# 202111192835, 202202087532, 202209072030. all work is completeDetails
to obtain final inspection for work approved under pa# 202111192835, 202202087532, 202209072030. all work is complete | |
| Aug 17, 2026 | Completed final sign-off Sep 2026 | 33 Mountain Spring Av | revision to bpa: 202505297535: add in unit washer and dryer. ref pa# 2025-1223-2564Details
revision to bpa: 202505297535: add in unit washer and dryer. ref pa# 2025-1223-2564 | |
| Apr 20, 2026 | Completed final sign-off Apr 2026 | 1819 20th St | recommencement and completion of work under pa# 2024-0403-9209Details
recommencement and completion of work under pa# 2024-0403-9209 | $2,000 |
| Feb 25, 2026 | In progress issued Mar 2026 | 35 Moulton St | upper unit (3rd & 4th fl)- replace & repair (2) aluminum windows and (5) skylights in-kind; remodel/update (2) bathrooms & (1) kitchen in-kind; replace furnace and water heater and replace lighting in-kind; no structural work.Details
upper unit (3rd & 4th fl)- replace & repair (2) aluminum windows and (5) skylights in-kind; remodel/update (2) bathrooms & (1) kitchen in-kind; replace furnace and water heater and replace lighting in-kind; no structural work. | $492,079 |
| Dec 23, 2025 | Completed final sign-off Sep 2026 | 33 Mountain Spring Av | revision to 202505297535, revise addition at 2nd fl from 89 sf to 245 sfw, interior remodel to remainDetails
revision to 202505297535, revise addition at 2nd fl from 89 sf to 245 sfw, interior remodel to remain | $60,000 |
| May 30, 2025 | In progress issued Jun 2025 | 585 Connecticut St | revision to pa 202103166680 extension of existing rear deck; extend rear deck @ level 1 an additional 3'-6". deck is less than 10'-0" above existing grade and is an allowed obstruction per sf planning code sec 136.c,25.b.iiDetails
revision to pa 202103166680 extension of existing rear deck; extend rear deck @ level 1 an additional 3'-6". deck is less than 10'-0" above existing grade and is an allowed obstruction per sf planning code sec 136.c,25.b.ii | $5,000 |
| May 29, 2025 | Completed final sign-off Sep 2026 | 33 Mountain Spring Av | single family residence interior remodel and minor 89 sq ft addition.Details
single family residence interior remodel and minor 89 sq ft addition. | $140,000 |
| May 21, 2025 | In progress issued May 2025 | 585 Connecticut St | revision to pa # 202103166680: update the property line retaining wall detail at gridline 1.Details
revision to pa # 202103166680: update the property line retaining wall detail at gridline 1. | |
| Feb 27, 2025 | In progress issued May 2025 | 585 Connecticut St | shoring plans for pa 202103166680 & pa 202505216981Details
shoring plans for pa 202103166680 & pa 202505216981 | $50,000 |
| Dec 30, 2024 | Completed final sign-off Oct 2025 | 155 Connecticut St | prop h:change of occupancy from b to e. remove non structural patitions, add ext door, replace windows inkind new toilets, sinks, kitchenette, partitions, deck & ramp (outdoor) new luxury vynil throughout, paint, interior & exteriorDetails
prop h:change of occupancy from b to e. remove non structural patitions, add ext door, replace windows inkind new toilets, sinks, kitchenette, partitions, deck & ramp (outdoor) new luxury vynil throughout, paint, interior & exterior | $250,000 |
| Apr 3, 2024 | Expired or cancelled expired Apr 2026 | 1819 20th St | exterior renovation of rear structure (1819 20th st) removal/ replace of exterior stucco in kind. new roof parapet of 18". replace entry door in kind. patch & repair exterior (e) stair treadsDetails
exterior renovation of rear structure (1819 20th st) removal/ replace of exterior stucco in kind. new roof parapet of 18". replace entry door in kind. patch & repair exterior (e) stair treads | $20,000 |
| May 3, 2023 | Completed final sign-off Feb 2024 | 1045 Sansome St | construction of 2 non load bearing partitions. demolition of e light fixtures, new light fixtures, installation of kitchenette with sink and dishwasherDetails
construction of 2 non load bearing partitions. demolition of e light fixtures, new light fixtures, installation of kitchenette with sink and dishwasher | $15,000 |
| Sep 7, 2022 | Expired or cancelled expired Sep 2026 | 600 Wisconsin St | rev to pa202111192835: structural updates to foundation design, architectural updates to interior plan, no change to scope. no change to demo calculations, interior work only.Details
rev to pa202111192835: structural updates to foundation design, architectural updates to interior plan, no change to scope. no change to demo calculations, interior work only. | |
| Jul 28, 2022 | In progress issued Mar 2024 | 1422 Douglass St | horizontal addition @ front both floors. horizontal addition @ rear @ 1st floor. interior reconfiguration throughout. (e) 2nd floor plate to be raised approx 22". new finish, windows & doors throuthout with a new gable roof form matching (e) roof slope. fully automatic sprinkler system throuthout.Details
horizontal addition @ front both floors. horizontal addition @ rear @ 1st floor. interior reconfiguration throughout. (e) 2nd floor plate to be raised approx 22". new finish, windows & doors throuthout with a new gable roof form matching (e) roof slope. fully automatic sprinkler system throuthout. | $450,000 |
| Jun 24, 2022 | Completed final sign-off Sep 2024 | 600 Wisconsin St | shoring engineering permit to approved building permit 202111192835.Details
shoring engineering permit to approved building permit 202111192835. | |
| Dec 8, 2021 | Completed final sign-off Sep 2026 | 600 Wisconsin St | renov per plans, add 1,021 sq. ft. 3/f, unconditioned decks, office/ bedrm w/closet, bathrm, (n) stucco finish parapet/roof @ 3/f add, raise ceiling height l2, replace/reconfig ext envelope/stucco/wd siding, modification to (e) bay window to accommodate (n) 3/f additionDetails
renov per plans, add 1,021 sq. ft. 3/f, unconditioned decks, office/ bedrm w/closet, bathrm, (n) stucco finish parapet/roof @ 3/f add, raise ceiling height l2, replace/reconfig ext envelope/stucco/wd siding, modification to (e) bay window to accommodate (n) 3/f addition | $500,000 |
| Nov 29, 2021 | In progress issued Nov 2024 | 744 Rhode Island St | add a 3rd fl w/ roof deck. upgrade all structure & foundation to meet/ exceed current code. complete partially excavated 1st fl basement/garage. upgrade m.e.p. to code. increase permeable area of sidewalk. increase area of solar panels & add gray water system. install sprinkler system per nfpa13r.Details
add a 3rd fl w/ roof deck. upgrade all structure & foundation to meet/ exceed current code. complete partially excavated 1st fl basement/garage. upgrade m.e.p. to code. increase permeable area of sidewalk. increase area of solar panels & add gray water system. install sprinkler system per nfpa13r. | $1,200,000 |
| Nov 19, 2021 | Expired or cancelled expired Sep 2026 | 600 Wisconsin St | revision to 202103196927: replace and reconfigure 1st and 2nd fl interior to include: (n) elevator shaft (n)interior stais, replace & reconfigure kitchen and replace (e) bathrooms and laundry. no exterior workDetails
revision to 202103196927: replace and reconfigure 1st and 2nd fl interior to include: (n) elevator shaft (n)interior stais, replace & reconfigure kitchen and replace (e) bathrooms and laundry. no exterior work | $300,000 |
| Mar 19, 2021 | Expired or cancelled cancelled Feb 2022 | 600 Wisconsin St | interior renovation of an extg single family dwelling. replace and reconfigure kitchen and master suite. replace and reconfigure main interior stair.Details
interior renovation of an extg single family dwelling. replace and reconfigure kitchen and master suite. replace and reconfigure main interior stair. | $100,000 |
| Mar 16, 2021 | Expired or cancelled suspend Mar 2026 | 585 Connecticut St | remodel of (e) sfh w/ (n) horizontal addition at rear. the house will be lifted vertically 5'-10". upgrade of mechanical, electtical, & structural systems to the current codes. addition of new nfpa 13r sprinkler systems per cbc 903.3.1.3 under separate permit.Details
remodel of (e) sfh w/ (n) horizontal addition at rear. the house will be lifted vertically 5'-10". upgrade of mechanical, electtical, & structural systems to the current codes. addition of new nfpa 13r sprinkler systems per cbc 903.3.1.3 under separate permit. | $200,000 |
| Nov 14, 2018 | Completed final sign-off Sep 2019 | 709 York St | rev to pa# 201809180650; repair & replace door/windows, update stair interior. design, replace sidingDetails
rev to pa# 201809180650; repair & replace door/windows, update stair interior. design, replace siding | |
| Sep 18, 2018 | Completed final sign-off Sep 2019 | 709 York St | revision to 201807124393 repair stair surface & replace door/windows where required demo rear deck maher naDetails
revision to 201807124393 repair stair surface & replace door/windows where required demo rear deck maher na | $50,000 |
| Jul 12, 2018 | Completed final sign-off Sep 2019 | 709 York St | renovate room layout on upper and lower level/ no exterior work.Details
renovate room layout on upper and lower level/ no exterior work. | $200,000 |
| Jun 22, 2018 | Completed final sign-off Sep 2018 | 104 Molimo Dr | 2nd floor bathroom remodel in kind, replace fanDetails
2nd floor bathroom remodel in kind, replace fan | $5,000 |
| May 29, 2018 | Completed final sign-off Sep 2018 | 104 Molimo Dr | 1)remove bearing wall, provide new posts and footings. 2) renovate kitchen, dining room and living room.Details
1)remove bearing wall, provide new posts and footings. 2) renovate kitchen, dining room and living room. | $10,000 |
| Jan 12, 2018 | Completed final sign-off May 2018 | 3470 19th St | add one full bath and a closet at third floor (within (e) sf). new door at third floor (with sf)Details
add one full bath and a closet at third floor (within (e) sf). new door at third floor (with sf) | $20,000 |
| Jun 27, 2017 | Completed final sign-off Mar 2018 | 600 Wisconsin St | remodel (e) courtyard to include new deck,hottub, fire pit, remodel (e) family room 1st fl to include new gas fireplace. remodel (e) living room on 2/f to include (n) gas fireplace and built-in furniture. (n) deck not to exceed 30in from (e) grade at any point.Details
remodel (e) courtyard to include new deck,hottub, fire pit, remodel (e) family room 1st fl to include new gas fireplace. remodel (e) living room on 2/f to include (n) gas fireplace and built-in furniture. (n) deck not to exceed 30in from (e) grade at any point. | $30,000 |
| May 5, 2017 | Completed final sign-off Jan 2018 | 310 Santa Ana Av | interior renovation & finish upgrade. maintain (e) area with new wall layout for lower floor including family room, media room, office, wine room, game room & full bath. adjust walls for master bedroom, bathroom, guest bathroom to make spaces functional. enlarge connecting stair to meet codeDetails
interior renovation & finish upgrade. maintain (e) area with new wall layout for lower floor including family room, media room, office, wine room, game room & full bath. adjust walls for master bedroom, bathroom, guest bathroom to make spaces functional. enlarge connecting stair to meet code | $80,000 |
| Aug 16, 2016 | Completed final sign-off Sep 2019 | 495 Chapman St | to erect 3 stories, no basement, single family dwelling building.Details
to erect 3 stories, no basement, single family dwelling building. | $120,000 |
| Feb 26, 2016 | Completed final sign-off Jul 2016 | 1819 20th St | stucco repair in-kind stair less than 50% work.Details
stucco repair in-kind stair less than 50% work. | $3,000 |
| Jun 24, 2015 | Completed final sign-off Jul 2016 | 1819 20th St | remodel (e) kitchen, (e) bathroom, and (e) living room, new skylight, and new gas burning stoveDetails
remodel (e) kitchen, (e) bathroom, and (e) living room, new skylight, and new gas burning stove | $40,000 |